do not use the first task to define the project start date project always calculates from project...

31
Anaheim, CA | February 2-5, 2014

Upload: devan-grave

Post on 11-Dec-2015

219 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Anaheim, CA | February 2-5, 2014

Page 2: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Steffen ReisterSenior Consultant, Book AuthorThe Project Group

10 Golden Rules for working with MS Project

Page 3: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Question

Who has ever heard the phrase:

“MS Project calculates wrong!”

Page 4: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

The 10 Golden Rules• Rule 1: Define Project Start in “Project - Project

Information“• Rule 2: Define Task Type in “File - Options”• Rule 3: Follow Black-Box-Principle• Rule 4: Let Project calculate - Do not edit Dates!• Rule 5: Use Milestones for specific Events and Dates• Rule 6: Use “Deadlines” instead of Constraints• Rule 7: Avoid open ends for Summary Tasks• Rule 8: “Highlander“ Principle – one Task, one Resource• Rule 9: No Work Resource Assignments on Summary Task

level• Rule 10: Update Project at Status Date

Page 5: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Handout

Page 6: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #1 Define Project Start Date

Do not use the first Task to define the Project Start Date

Project always calculates from Project Start (Finish) Date

Schedule from Project Finish Date

Option in an early planning phase:

Page 7: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Project Start Date – Demo #1

Page 8: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #2 Define Task TypeWork = Duration * Units * Hours/Day

Task entry= variable

ResourceAssignment= variable

Calendar Setting= fixed

Page 9: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #2 Define Task TypePlanning focus is fundamental

When you assignResources

CostorDates

Project calculates according to Task Type

More in Rule #8

Page 10: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #2 Define Task Type

Work

Work

Peak Units

Work

Duration

Duration

Peak Units

Duration

Duration

Duration Units Work

If you change one of these variables:

Fixed Duration

Fixed Units

Fixed Work

Task is set to: Project then calculates:

How Project calculates

Page 11: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #3 The Black-Box Principle

Phase 2

Phase 3Phase 1

Project Black Box

Project Start Project EndEach Box is independent

One path in One path out

Each Box acts like a small Project

Page 12: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #3 The Black-Box Principle

Collapse Phases and still see the logical structure of the Project

Page 13: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #3 The Black-Box Principle

Start Structure on Phase level

Summary or Taskon one level - never both

Each Black Box has a defined End

How to define Black Boxes?

Each Task has a Summary

How to set up Dependencies?

Connect Tasks within a Summary never across Summaries

Never connect to a higher or lower level

A Summary can be connected to a Milestone

Short Overview

Page 14: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

The Black-Box Principle – Demo #2

Page 15: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #4 Let Project calculate

Date Columns allow editing

Editing Dates produces Constraints

Start and Finish are Calculated Fields

Hidden side effects for Project calculation

Page 16: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #4 Let Project calculate

Constraints produce Planning Wizard Messages

Beware of simply clicking “OK”

Recommendation

Do NOT edit Start and Finish!

Instead follow Rule #5 and #6

Page 17: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Let Project calculate – Demo #3

Page 18: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #5 Use Milestones for specific Dates

Enter a separate Line for each Milestone

Entering “0” in Durationcreates a Milestone

This highlights a Specific Date

Milestone appears with a special shape

Page 19: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #6 Deadlines instead of Constraints

Project shows a graphical Indicator

Messages in Indicator column

Total Slack shows exact delay to Deadline

Page 20: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Milestones & Deadlines- Demo #4

Page 21: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #7 Control open end in Schedule

Outline Project to Level 1

First & Last item in Plan should be a Milestone

Every item in Plan should have a Successor

Only End Milestone has no Successor

Page 22: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Control open end in Schedule – Demo #5

Page 23: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #8 Highlander Principle

Who knows the movie „Highlander“ with Christopher Lambert?

There can be only One!

One Task – One Resource!

Page 24: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Highlander Principle – Demo #6

Page 25: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #8 Highlander Principle

Always a 1:1 relationship between Task and Resource

Assigned Resource and Work on Task belong together

Avoid very strange Work calculation for Tasks

Task Type is no longer as important to know

Key Takeaways

Page 26: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #9 No Resources on Summary

Version 2: 9 days * 200% * 8 hrs = 144 Hours

2 methods2 different results

Work = Duration * Units * Hours/Day

Version 1: 3 days * 100% * 8 hrs = 24 Hours

2 days * 100% * 8 hrs = 16 Hours

6 days * 100% * 8 hrs = 48 Hours

Summary:88 Hours

Page 27: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

No Work Resource on Summary – Demo #7

Page 28: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Rule #10 Update Project at Status Date

Update the Project to know the truth about your Dates

Uncompleted work has to be in the future

Page 29: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Update Project at Status Date – Demo #8

Page 30: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

Resources

• For Germany, Switzerland, Austria and everyone else who speaks German:http://amzn.to/LHfeXP

• For demo files or Print Template of [email protected]

Page 31: Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish

© 2014 Microsoft Corporation. All rights reserved. Microsoft, Windows and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries.The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.