ALJ/ANG/avs DRAFT Agenda ID #11225 (Rev.1) Ratesetting 5/24/12 Decision PROPOSED DECISION OF ALJ MINKIN (Mailed 4/3/2012) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of The Nevada Hydro Company for a Certificate of Public Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500 kV Interconnect Project. Application 10-07-001 (Filed July 6, 2010) DECISION DISMISSING APPLICATION AND DENYING PETITION TO MODIFY DECISION 11-07-036 581435 - 1 -

Upload: others

Post on 17-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

ALJ/ANG/avs DRAFT Agenda ID #11225 (Rev.1)Ratesetting

5/24/12

Decision PROPOSED DECISION OF ALJ MINKIN (Mailed 4/3/2012)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

In the Matter of the Application of The Nevada Hydro Company for a Certificate of Public Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500 kV Interconnect Project.

Application 10-07-001(Filed July 6, 2010)

DECISION DISMISSING APPLICATION ANDDENYING PETITION TO MODIFY DECISION 11-07-036

581435 - 1 -

Page 2: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

TABLE OF CONTENTS

Title Page

DECISION DISMISSING APPLICATION AND......................................2DENYING PETITION TO MODIFY DECISION 11-07-036.....................2

Summary............................................................................................21. Background...................................................................................22. Should the Application be Dismissed?..........................................5

2.1. The Parties’ Positions.............................................................52.2. Discussion.............................................................................10

3. Should the Petition to Modify D.11-07-036 be Granted?............134. Categorization and Need for Hearings.......................................175. Comments on Proposed Decision................................................176. Assignment of Proceeding..........................................................19

Findings of Fact..................................................................................19Conclusions of Law.............................................................................20ORDER................................................................................................23

- i -

Page 3: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

DECISION DISMISSING APPLICATION ANDDENYING PETITION TO MODIFY DECISION 11-07-036

SummaryIn this decision, we dismiss The Nevada Hydro Company’s

(Nevada Hydro) Application (A.) 10-07-001 for a Certificate of Public Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500 kilovolt Interconnect Project. We take this action because, despite over 18 months of work, the application is not complete and does not conform to our requirements. We cannot continue to expend Commission or party resources on A.10-07-001. Although we dismiss this application without prejudice, we impose a series of conditions that must be met if we are to consider an application for this project (or similar projects) in the future. We also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements specified by Ordering Paragraph 2 of D.11-07-036.1. Background

In this application, The Nevada Hydro Company (Nevada Hydro) requests a Certificate of Public Convenience and Necessity (CPCN) for the Talega-Escondido/Valley-Serrano (TE/VS) 500 kilovolt Interconnect Project.

Nevada Hydro previously filed Application (A.) 07-10-005 and A.09-02-012 seeking the same authorization. These applications were dismissed without prejudice by Decision (D.) 09-04-006, because Nevada Hydro failed to prepare a complete Proponent’s Environmental Assessment (PEA), as required by the California Environmental Quality Act (CEQA).

- 2 -

Page 4: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

On July 6, 2010, the instant revised application was accepted for filing. On August 5, 2010, Commission staff determined that the PEA was complete for purposes of CEQA. At the request of Commission Staff, Nevada Hydro amended its PEA on February 25, 2011. The Notice of Preparation was filed on March 14, 2011 at the Governor’s Office of Planning and Research. By this action, Commission staff began an independent evaluation of the proposed project, including public scoping meetings to develop alternatives to the proposed project, and the potential environmental impacts of the proposed project and alternatives, as required by CEQA.

Timely protests were filed by the Division of Ratepayer Advocates (DRA), Southern California Edison Company (SCE), San Diego Gas & Electric Company (SDG&E), John Pecora (Pecora), Forest Residents Opposing New Transmission Lines (FRONTLINES), Fresian Focus, LLC, Linda Lou and Martin Ridenour, the Elsinore Valley Municipal Water District (EVMWD), and jointly by the Center for Biological Diversity, Friends of the Forest (Trabuco District) and the Santa Rosa Plateau, and Santa Ana Mountains Task Force of the Sierra Club. We refer to these intervenors as Joint Intervenors. Nevada Hydro filed its reply on August 16, 2010.

We issued D.11-07-036 on July 28, 2011 to address several threshold issues in Phase 1 of this proceeding. In D.11-07-036, we determined that, consistent with precedent, Nevada Hydro would become a public utility under Pub. Util. Code §§ 216 and 218, if a CPCN were to be issued in Phase 2 of this proceeding. In addition, because it was not certain that a CPCN would be issued for this project and because we must harmonize the various statutes that are incorporated in the Pub. Util. Code, we ordered Nevada Hydro to

- 3 -

Page 5: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

guarantee payment for those intervenors who meet the requirements of Pub. Util. Code §§ 1801 et seq. and for consultants hired by DRA, regardless of the outcome of this application. Therefore, we directed Nevada Hydro to post a surety bond or performance bond in the amount of $550,000 to cover the anticipated costs of eligible intervenors who make a substantial contribution to this proceeding, consistent with the requirements of the Pub. Util. Code. We also ordered Nevada Hydro to enter into a reimbursable contract arrangement that would cover the costs of DRA’s expert consultants, approximately $450,000, assuming Phase 2 went forward. We concluded that these are reasonable costs of doing business for an entity proposing to be certified as a public utility and proposing to build a project originally estimated to cost $353 million (in 2007 dollars), and now anticipated to cost $684 million.

Pursuant to Rule 16.6, on August 22, 2011, Nevada Hydro requested an extension of time from the Executive Director to comply with Ordering Paragraphs 2 and 3 of D.11-07-036. On August 25, 2011, the Executive Director granted a 60-day extension and required Nevada Hydro to provide the appropriate bond by October 28, 2011. On October 28, 2011, Nevada Hydro filed a motion for acceptance of a bond and cashiers check made payable to the California Public Utilities Commission. On November 9, 2011, as directed by the assigned Administrative Law Judge (ALJ), Nevada Hydro filed a petition for modification of D.11-07-036 to request that a letter of credit with cash backing be accepted in lieu of the bond. FRONTLINES and Joint Intervenors filed timely responses to the petition.

- 4 -

Page 6: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

On November 10, 2011, the assigned ALJ convened a prehearing conference in Phase 2 of this proceeding. On December 1, 2011, the assigned ALJ issued a ruling that required the parties to file and serve comments on whether or not the Commission should dismiss A.10-07-001 and, if it is dismissed, whether or not the application should be dismissed with prejudice.

Nevada Hydro, DRA, SCE, SDG&E, EVMWD, Joint Intervenors, Pecora, and FRONTLINES filed and served timely comments on the ruling. No reply comments were accepted. On January 3, 2012, Nevada Hydro filed a motion requesting leave to file reply comments and January 4, 2012, SCE filed a motion to strike portions of Nevada Hydro’s comments.2. Should the Application be Dismissed?

2.1. The Parties’ PositionsAt the prehearing conference held on November 10, 2011, in

response to the ALJ’s questions regarding financial viability, Nevada Hydro explained that the witnesses associated with the Siemens Company are no longer available and requested a 90-day stay in the proceeding in order to prepare and submit new, replacement testimony. The testimony that must be replaced addresses costs and reliability and therefore feeds into the testimony of other Nevada Hydro witnesses who relied on the previously-submitted testimony. DRA raised additional concerns regarding the cost calculations in the previously-submitted testimony and requested that calculations of costs and benefits be done on a stand-alone basis, i.e., not associated with the Lake Elsinore Advanced Pumped Storage (LEAPS) Project. DRA also raised questions regarding Nevada Hydro’s modeling assumptions.

- 5 -

Page 7: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

SDG&E stated that the application is still deficient and that Nevada Hydro has not complied with Rules 2.3 and 3.1(g), in particular. SCE raised concerns regarding the collection of the Transmission Access Charge (TAC), whether the California Independent System Operator (CAISO) approval is required in order for Nevada Hydro to collect such a charge, and suggested that Nevada Hydro file a compliance filing to prove that it has the financial wherewithal to go forward. EVWMD concurred with this suggestion and agreed with DRA’s statements regarding costs and benefits.

The Center for Biological Diversity agreed that the application remains deficient and stated that the application should be dismissed with prejudice. The Santa Ana Mountains Task Force of the Sierra Club and the Friends of the Forest (Trabuco District) and the Santa Rosa Plateau pointed out that the issue of the Southern terminus remains an open question, and that this issue was a key reason the previous applications were dismissed. FRONTLINES suggested that a technical workshop be convened in the impacted area to discuss modeling and cost issues. Several parties concurred with this recommendation.

In its response to the ALJ’s Ruling, Nevada Hydro argues that many, many years of work have gone into this project and the Commission should proceed with Phase 2. Nevada Hydro contends that it has embarked on “sensitive” commercial negotiations with prospective investors and has attached letters of intent from the St. Augustine Trust and First Reserve Corporation to provide development and construction financing for the proposed project. These commitments depend on regulatory approval of the project and retention of a bonded general contractor. Nevada Hydro contends

- 6 -

Page 8: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

that such letters of intent demonstrate that once a CPCN is issued, the project will have the necessary financing to become financially viable. Applicant further contends that issuance of a CPCN will lead to a reasonable expectation that the proposed project would become part of the CAISO grid and will lead to recovery of operating and investment costs.

In order to recover its costs, Nevada Hydro states that it intends to turn control over its facilities to the CAISO and to recover its costs through the TAC. Nevada Hydro states that it submitted a Participating Transmission Owner application for the project to the CAISO in February 2007, as supplemented in April 2009. Nevada Hydro maintains that the project has been evaluated and approved by the CAISO when it was proposed as the Valley Rainbow Interconnect Project (sponsored by SDG&E) and further contends that the CAISO evaluated the project as part of the Southwest Transmission Expansion Plan and the South Regional Transmission Plan. Applicant also contends that the CAISO’s actions in 2006 regarding the South Regional transmission Plan led to a conclusion that the project will ensure reliability and will achieve cost savings. However, Nevada Hydro acknowledges that the CAISO has not acted on these findings.

Nevada Hydro explains that the TE/VS project was originally planned as a tie-line with the LEAPS project, which was being considered at the Federal Energy Regulatory Commission (FERC). Nevada Hydro states that the FERC proceedings resulted in a Final Environmental Impact Statement that also considered the stand-alone project. Applicant also cites to FERC’s approval of rate incentives and states that this approval “is the driver of inducing commercial funding sources to provide capital for the development and construction of

- 7 -

Page 9: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

innovative, non-utility transmission projects such as the TE/VS interconnect.”1 Nevada Hydro also maintains that the viability of the project is proven because in the environmental review of SDG&E’s Sunrise Project, the Final Environmental Impact Report ranked the LEAPS Transmission-Only Alternative as one of the preferred alternatives.

While Nevada Hydro recognizes that Siemens is no longer financially involved in this project and that key aspects of its testimony must be replaced, Nevada Hydro contends that it has identified a substitute construction manager and is ready to proceed to correct cost and modeling assumptions that will result in lower costs to ratepayers. Thus, Nevada Hydro states that it is premature to dismiss the application; that need and economics must be determined based on the development of a complete record, and that dismissal of the application, particularly dismissal with prejudice would be “catastrophic” to the owners and investors who have invested $25 million in the endeavor thus far.2 In addition, Nevada Hydro contends that such actions would have a chilling effect on the independently developed projects of all kinds in California.

Nearly all other parties assert that the application should be dismissed. FRONTLINES states that this application should go forward “to ensure the ongoing TEVS CPSN application is the last TEVS CPCN application from Nevada Hydro that the Commission ever considers.”3 FRONTLINES therefore suggests that the Commission convene a workshop to establish appropriate modeling assumptions

1 Nevada Hydro’s December 16, 2011, Comments at 12.2 Id. at 22.3 FRONTLINES’ December 16, 2011, Comments at 2.

- 8 -

Page 10: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

and cost/benefit parameters and that Nevada Hydro prepare new expert witness testimony based on the workshop findings. Alternatively, FRONTLINES agrees that the application could be dismissed with prejudice but only if the Commission precluded Nevada Hydro from submitting any future application for any transmission line project which interconnects the Talega-Escondido line with the Valley-Serrano line.

DRA supports dismissal of the application because Nevada Hydro has failed to submit a complete application despite ample time and opportunity to do so. DRA explains that Nevada Hydro’s failure to submit a complete application has lead to wasted resources for parties and for the Commission. DRA suggests that the application be dismissed without prejudice but states that the Commission should require a complete and thorough application including testimony sponsored by witnesses who will be available for hearings and cross-examination. DRA correctly observes that Nevada Hydro is obligated to pay all of DRA’s costs incurred with hiring an expert witness in this proceeding, pursuant to D.11-07-036.

SDG&E, SCE, EVWMD, and Pecora all agree that the application should be dismissed, and either state that the application should be dismissed without prejudice or defer to the Commission to make this determination. SCE and SDG&E maintain that should Nevada Hydro be allowed to refile an application, that application must be complete in all ways, must comply with the Rules of Practice and Procedure, must demonstrate that a viable Southern terminus exists for the project, and must show that Nevada Hydro is actively seeking approval from the CAISO for the required interconnection and ability to implement a TAC. EVWMD contends that Nevada Hydro has

- 9 -

Page 11: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

not honored certain obligations to pay for all LEAPS Project development costs, including all necessary permits and entitlements and represents that this failure is evidence of Nevada Hydro’s inability to obtain necessary financing for the TE/VS project. Joint Intervenors argue that the application should be dismissed with prejudice because the application fails to comply with Commission rules and fails to provide the needed experts and witnesses to ensure that the parties can fully assess the project.

2.2. DiscussionWithout assessing the contentions and representations

regarding Nevada Hydro’s failure to pay certain obligations, we conclude that this application is procedurally deficient and should be dismissed. At this late date, we decline to stay this proceeding while Nevada Hydro seeks expert witnesses to prepare testimony that is critical to the consideration of whether this project is viable, feasible, economic, and whether there is a need for the project. The Commission cannot afford to squander its resources on applications that, despite over 18 months of work, remain vague and speculative as to financing plan and indeed the project description itself. Nevada Hydro has had ample opportunity in this application and in previous applications to develop its project description and financing plan appropriately, and to confirm that it can present its case-in-chief that includes with specificity how it will interconnect with both SDG&E and SCE’s systems and that the CAISO will accept control as the grid operator. This has not occurred. In sum, despite months of work and resources expended by this Commission, the parties, and the project proponent itself, Nevada Hydro has not yet provided the Commission with a full and complete application that would allow us to assess the

- 10 -

Page 12: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

economics and need of the proposed project. Because its financial wherewithal to proceed with the project is not readily apparent, we dismiss this application.

Intervenors that have been found eligible for intervenor compensation may file and serve requests for intervenor compensation, which the Commission will consider in due course. Consistent with the requirements of D.11-07-036, we direct Nevada Hydro to honor authorized intervenor compensation requests and to ensure that the reimbursable contracts with the Commission’s Energy Division consultants for environmental review of the project and with DRA for expert consultants are paid in full.

However, we also take this opportunity to confirm that the Commission supports the concept of independent transmission owners and operators. On the one hand, we acknowledge that Nevada Hydro has had multiple opportunities to prepare a complete and sufficient application. On the other hand, there may be savings for ratepayers if competent independent transmission owners receive a CPCN. In this particular case, we set a series of conditions that Nevada Hydro, its principals, or any other proponent of this project (or similar projects) must meet before an application will be accepted for filing at the Commission. We concur with the Joint Intervenors’ recommendations that any subsequent application must meet the following requirements:

1. To be considered complete, any application must comply fully with the requirements of the Pub. Util. Code §§ 1001 et seq., General Order 131, the Rules of Practice and Procedure, must fully demonstrate the proposed project’s need, and must comply with the detailed requirements to

- 11 -

Page 13: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

provide a cost control plan, implementation plan, and project management plan;

2. Any subsequent application must ensure that the financial viability of the project is clear and that any financial partner’s participation is transparent, as well as the financial viability of the project and proponent’s ability to support the project;

3. Any subsequent application must include complete testimony from expert witnesses. Because the application must be complete, parties must be able to rely on the proffered experts and their testimony;

4. Any subsequent application must provide an accurate and stable project description and location and the Energy Division must not accept the PEA as complete without such a description; and

5. Any subsequent application must explain how the CAISO is currently considering the project and must include a full discussion of how revenue requirements will be calculated and recovered through the TAC, as well as the impact on California ratepayers.

To the extent that the project proponents consider filing a future application, we agree with Joint Intervenors and FRONTLINES that a technical workshop should be convened before any application is filed. The technical workshop should be held in the location of the proposed project. To the extent that a future project of this type is considered, Nevada Hydro (or any subsequent project proponent) is responsible for convening and properly noticing such a workshop, which will be held at Nevada Hydro’s expense. Nevada Hydro must also maintain a list of workshop attendees. The technical workshop should focus, at a minimum, on the proposed project description as a stand-alone project, the proposed route, costs, benefits, and modeling

- 12 -

Page 14: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

assumptions. The workshops must be widely-noticed and held well before any application is submitted to the Commission. Nevada Hydro must supply a thorough description of the workshop and must explicitly demonstrate in any subsequent application how it has considered and incorporated the input from such a workshop. Nevada Hydro must serve any subsequent application on the workshop attendees, as well as on the service list to this proceeding. In addition, Energy Division Staff must review a preliminary application and must agree that the application is complete, pursuant to the requirements of this decision, before applicant files formally. We also require Nevada Hydro to demonstrate that all approved reimbursable contract invoices have been paid in full before a new application tendered by either Nevada Hydro or its principals will be accepted for filing.

Because we are dismissing this application, all pending motions are dismissed as moot.3. Should the Petition to Modify

D.11-07-036 be Granted?In D.11-07-036, among other things, we determined that the

Nevada Hydro is subject to the mandates of Pub. Util. Code §§ 1801 et seq., whether or not the proposed transmission line is not certificated by this Commission. We reasoned that: “A transmission line proceeding often has many interested parties and intervenors who ‘have a stake’ in the outcome of this matter.

It would have a chilling effect on effective participation, if there is not some guarantee that funding will be available to pay those eligible intervenors who are determined to have made a substantial contribution to this proceeding, whether or not a CPCN is issued to Nevada Hydro. In

- 13 -

Page 15: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

addition, this approach treats all applicants for a transmission CPCN similarly; to hold otherwise would be to impose more stringent requirements on utility CPCN applicants than on non-utility applicants without any justification for this differential treatment.”4

We concluded that the costs of providing a performance or surety bond and entering into a progressive invoicing and reimbursable contract arrangement with DRA are reasonable costs of doing business for an entity proposing to be certified as a public utility and proposing to build a project now estimated to cost $684 million5 and therefore ordered Nevada Hydro to post a surety or performance bond with a face value of $550,000, or approximately 1.5 times the budgets estimated by the three eligible intervenor groups in this proceeding. The bond requirement is to remain in effect until the proceeding is completed and Nevada Hydro has compensated all intervenors that the Commission determines have made a substantial contribution to the proceeding. While there is a fund within the Commission’s budget to pay intervenors in broad policy rulemakings where there are either numerous or unnamed respondents, this proceeding does not meet the requirements for paying intervenors from this fund.6

Nevada Hydro was ordered to post the bond within 30 days of the effective date of D.11-07-036. Ordering Paragraph 5 stated that

4 D.11-07-036, Conclusion of Law 8 at 18.5 November 30, 2010 Testimony of Nevada Hydro Witness Drzemiecki, Exhibit 2 indicating Gross Plant Beginning of Year. Gross plant includes costs associated with construction of physical plant, acquisition of rights-of-ways and easements, and financing costs during the construction period.6 D.00-01-020 established a fund within the Commission’s budget for intervenor awards in quasi-legislative proceedings in which there are either numerous respondents or respondents are not named.

- 14 -

Page 16: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

the application would be dismissed if Nevada Hydro did not comply with these requirements. Pursuant to Rule 16.6, On August 22, 2011, Nevada Hydro requested an extension of time from the Executive Director to comply with these requirements. On August 25, 2011, the Executive Director granted a 60-day extension and required Nevada Hydro to provide the appropriate bond by October 28, 2011. On October 28, 2011, Nevada Hydro filed a motion for acceptance of a bond and cashiers check made payable to the California Public Utilities Commission. In its motion, Nevada Hydro acknowledged its confusion regarding the intervenor compensation program and who was responsible for paying the intervenors. On November 9, 2011, as directed by the assigned ALJ, Nevada Hydro filed a petition for modification of D.11-07-036 to request that a letter of credit with cash backing be accepted in lieu of the bond. FRONTLINES and Joint Intervenors filed timely responses to the petition.

Nevada Hydro states that it understands that it is subject to the laws of the State and the Rules of Practice and Procedure, and further acknowledges its responsibility to pay intervenor compensation ultimately awarded by the Commission. Nevada Hydro contends that because the Commission did not specify the “form, language, beneficiary, conditions precedent to performance, creditworthiness of the surety, or other legal elements” of the bond, it believes the alternative proposed approach should be acceptable.7 Nevada Hydro further understands that a letter of credit is not a form of guarantee under California law, but explains that it has set aside $550,000 in cash that is on deposit with Wells Fargo to compensate intervenors. Nevada Hydro further contends that this arrangement may be more

7 Petition to Modify D.11-07-036 at 2.

- 15 -

Page 17: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

conducive to intervenor funding because the funds will be readily available and will not require the extensive paper trail that a surety or performance bond would require.

Joint Intervenors urge the Commission to reject the Petition for Modification because the intervenor compensation program requires a well-defined and well-functioning guarantee of payment, particularly if (as is the case here) the application is denied or dismissed, the CPCN is not issued, and Nevada Hydro does not become a public utility. The parties argue that a letter of credit and the revocable funds on deposit do not provide the necessary guarantee that funds will be in place to compensate intervenors. In addition, these intervenors explain that the letter of credit contain both cancellation and expiration clauses that are inapposite to the requirements of Ordering Paragraph 2 of D.11-07-036. FRONTLINES agrees with the Joint Intervenors, stating that the Letter of Credit as structured is inadequate to guarantee payment and secure intervenor compensation funds.

We agree with the intervenors: as structured, the Letter of Credit proffered by Nevada Hydro and the funds placed on deposit by Rex Waite are not a sufficient substitute for the guarantees intended to be in place by a performance or surety bond. As FRONTLINES points out, a bond cannot be arbitrarily or unilaterally cancelled by Nevada Hydro or Mr. Waite, is secured by a reliable funding source, and must clearly designate that payments must be made to eligible intervenors if Nevada Hydro defaults on its intervenor compensation obligations. Therefore, we deny Nevada Hydro’s Petition to Modify D.11-07-036 and require Nevada Hydro to post the requisite bond within 15 days of the effective date of this decision. No time extensions will be granted. We urge Nevada Hydro to work with

- 16 -

Page 18: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

appropriate outside counsel to ensure that the bond is issued expeditiously. While the bonding requirements will serve to protect the interests of the intervenors, we expect Nevada Hydro to promptly pay all approved intervenor compensation claims. Nevada Hydro must demonstrate that such payments have been made within 30 days of our decisions authorizing such payments and must include any interest payments so ordered. To the extent that payments have not been made when a new application is filed, Nevada Hydro must include a status report on the payment of any pending claims.4. Categorization and Need for Hearings

In Resolution ALJ 176-3257 dated July 8, 2010, the Commission preliminary categorized this application as Ratesetting, and preliminary determined that hearings were necessary. Because we dismiss the application based on procedural deficiencies, no hearings are required. The hearings determination is changed to state that no evidentiary hearings are necessary.5. Comments on Proposed Decision

The proposed decision of ALJ Minkin in this matter was mailed to the parties in accordance with Section 311 of the Public Utilities Code, and comments were allowed under Rule 14.3 of the Commission’s Rules of Practice and Procedure. Nevada Hydro, SCE, EVMWD, and FRONTLINES filed timely opening comments. SCE and FRONTLINES filed timely reply comments. We have considered the factual, technical, and legal concerns delineated in the comments and have made changes, as appropriate, in the decision. We have given little weight to comments that merely reiterate or reargue positions

As SCE suggests, we have clarified that we are referring to “independent” transmission owners in this decision.

- 17 -

Page 19: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

Nevada Hydro contends that the decision is in error because we require CAISO approval of the project “or efforts to obtain same as a precondition to a CPCN application.”8 Both SCE and FRONTLINES state that Nevada Hydro has mischaracterized the Large Generator Interconnection Procedure at the CAISO, among other concerns. As stated above, Nevada Hydro must explain how the CAISO is considering the project and must further demonstrate how it will recover costs and the impact of those costs on California ratepayers. This is a reasonable requirement.

Nevada Hydro disputes the need for a technical conference as a pre-condition to filing a new application. We do not need to have an open proceeding here for Nevada Hydro to convene such a workshop. Indeed, such efforts could help to both resolve technical issues prior to an application being filed and could lead to a more efficient, less contentious proceeding. While this proceeding will be closed, the service list remains accessible on our web site.

We decline to add additional requirements to the workshop process, as FRONTLINES suggests. Parties have the ability to ask specific questions of Nevada Hydro at the workshops. While FRONTLINES suggests that Nevada Hydro should provide a 45-day notice period for the workshops, we note that Rule 13.1(a) of our Rules of Practice and Procedure require proper notice of hearings to be provided “not less than 10 days before the date of hearing.” We urge Nevada Hydro to provide as much notice as possible, since such actions will recognize community values and concerns, but we will not impose further requirements.

8 Nevada Hydro Comments to Proposed Decision at 7.

- 18 -

Page 20: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

Nevada Hydro also contends that requiring the payment of authorized intervenor compensation claims before the Commission accepts a new application will unfairly delay any new application. As discussed above, we expect Nevada hydro to honor all commitments, including prompt payment of approved intervenor compensation claims. Approved claims must be paid within 30 days of our orders authorizing such payment and must include any interest payments so ordered. To the extent that claims are outstanding, Nevada Hydro must file a status report in the new docket. All reimbursable contract invoices must be paid on a timely basis and must be paid in full before a new application will be accepted for filing.6. Assignment of Proceeding

Michel Peter Florio is the assigned Commissioner and Angela K. Minkin is the assigned ALJ in this proceeding.Findings of Fact1. Nevada Hydro previously filed A.07-10-005 and A.09-02-012 seeking a CPCN for the TE/VS 500 kV Interconnect Project.2. By D.09-04-006, we dismissed A.07-10-005 and A.09-02-012 without prejudice, because Nevada Hydro failed to prepare a complete PEA, as required by CEQA.3. Without assessing the contentions and representations regarding Nevada Hydro’s failure to pay certain obligations, we conclude that A.10-07-001 is procedurally deficient and should be dismissed.4. The Commission cannot afford to squander its resources on applications that, despite more than 18 months of work, remain vague and speculative as to financing and indeed the project itself.

- 19 -

Page 21: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

5. It makes little sense to stay this proceeding while Nevada Hydro seeks expert witnesses to prepare testimony that is critical to the consideration of whether this project is viable, feasible, economic, and whether there is a need for the project.6. Nevada Hydro has had ample opportunity in A.10-07-001 and in previous applications to develop its project description and financing plan appropriately and to confirm that it can present its case-in-chief, which includes with specificity how it will interconnect with both SDG&E’s and SCE’s systems, and that the CAISO will accept control as the grid operator; however, none of these actions have occurred.7. We support the concept of independent transmission owners and operators, which may provide savings for ratepayers if competent independent transmission owners receive a CPCN.8. It is reasonable to impose a series of conditions that Nevada Hydro, its principals, or subsequent project proponents must meet before an application for this or any similar project will be accepted for formal filing by the Commission.9. The Letter of Credit and Cash Deposit approach proposed by Nevada Hydro in its Petition for Modification filed on November 9, 2011 does not provide the requisite guarantee of intervenor compensation funding ordered in D.11-07-036.

- 20 -

Page 22: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

Conclusions of Law1. Application 10-07-001 should be dismissed without prejudice.2. Nevada Hydro, its principals, or subsequent project proponents should be required to comply with a series of conditions in order to have any subsequent application accepted for filing by this Commission:

a. To be considered complete, any application must comply fully with the requirements of the Pub. Util. Code §§ 1001 et seq., General Order 131, the Rules of Practice and Procedure, must fully demonstrate the proposed project’s need, and must comply with the detailed requirements to provide a cost control plan, implementation plan, and project management plan;

b. Any subsequent application must ensure that the financial viability of the project is clear and that any financial partner’s participation is transparent, as well as the financial viability of the project and proponent’s ability to support the project;

c. Any subsequent application must include complete testimony from expert witnesses. Because the application must be complete, parties must be able to rely on the proffered experts and their testimony;

d. Any subsequent application must provide an accurate and stable project description and location and the Energy Division must not accept the PEA as complete without such a description;

e. Any subsequent application must explain how the CAISO is currently considering the project and include a full discussion of how revenue requirements will be calculated and recovered through the Transmission Access Charge, as well as the impact on California ratepayers;

f. To the extent that the project proponents (or subsequent proponents) consider filing a future application for a similar project, the project

- 21 -

Page 23: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

proponents shall convene a technical workshop before any application is filed at this Commission. The technical workshop must be held in the location of the proposed project;

g. To the extent that a future project of this type is considered, Nevada Hydro (or any subsequent project proponent) is responsible for convening and properly noticing such a workshop, which will be held at Nevada Hydro’s expense. The technical workshop must focus, at a minimum, on the proposed project description, route, costs, benefits, and modeling assumptions. The workshops must be widely-noticed and held well before any application is submitted to the Commission. Nevada Hydro must maintain a list of workshop attendees;

h. Nevada Hydro (or subsequent project proponent) must supply a thorough description of the workshop and must explicitly demonstrate in any subsequent application how it has considered and incorporated the input from such a workshop. Nevada Hydro must serve any subsequent application on workshop attendees, among others, as well as on the service list to this proceeding;

i. Prior to any subsequent application being formally filed, Energy Division Staff must review any preliminary application and agree that the application is complete, pursuant to the requirements of this decision; and

j. No subsequent application may be filed until Nevada Hydro demonstrates that it has paid in full all approved reimbursable contract invoices.

3. The Petition to Modify D.11-07-036, filed by Nevada Hydro on November 9, 2011, should be denied.4. Nevada Hydro should be required to comply with Ordering Paragraph 2 of D.11-07-036 and should be required to post the

- 22 -

Page 24: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

required performance or surety bond within 15 days of the effective date of this decision.5. As we determined in D.11-07-036, it is reasonable to require Nevada Hydro to provide a performance or surety bond in the amount of $550,000 and to require the bond to remain in effect until Nevada Hydro has fully compensated all intervenors that the Commission determines have made a substantial contribution to this matter.6. It is reasonable to require prompt payment to eligible intervenors that the Commission has determined have made a substantial contribution to this proceeding.7. It is reasonable to require Nevada Hydro or its principals to demonstrate that all approved intervenor compensation claims have been paid in full within 30 days of our orders so authorizing, including any authorized interest payments. It is reasonable to require Nevada Hydro to file a status report on pending claims in the new docket.8. Because the application is dismissed, all pending motion should be dismissed as moot.9. This proceeding should be closed, although Nevada Hydro should be ordered to post the requisite bond, to honor all intervenor compensation claims awarded by the Commission, and to ensure that the reimbursable contracts with the Commission’s Energy Division consultants for environmental review of the project and with DRA for expert consultants are paid in full.10. Hearings are not necessary.11. This decision should be effective today.

O R D E R

- 23 -

Page 25: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

IT IS ORDERED that:1. Application 10-07-001 is dismissed without prejudice. To the extent that The Nevada Hydro Company (Nevada Hydro), its principals, or subsequent project proponent chooses to pursue the proposed Talega-Escondido/Valley-Serrano Transmission Line Interconnect or other similar project, the project proponent must comply with the following explicit requirements:

a. To be considered complete, any subsequent application must comply fully with the requirements of the Pub. Util. Code §§ 1001 et seq., General Order 131, and the Rules of Practice and Procedure, must fully demonstrate the proposed project’s need, and must comply with the detailed requirements to provide a cost control plan, implementation plan, and project management plan;

b. Any subsequent application must ensure that the financial viability of the project is clear and that any financial partner’s participation is transparent, as well as the financial viability of the project and proponent’s ability to support the project;

c. Any subsequent application must include complete testimony from expert witnesses. Because the application must be complete, parties must be able to rely on the proffered experts and their testimony;

d. Any subsequent application must provide an accurate and stable project description and location and the Energy Division must not accept the Proponent’s Environmental Assessment as complete without such a description;

e. Any subsequent application must include a discussion of the California Independent System Operator’s current consideration of the project and include a full discussion of how revenue requirements will be calculated and recovered

- 24 -

Page 26: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

through the Transmission Access Charge, as well as the impact on California ratepayers;

f. To the extent that the project proponents (or subsequent proponents) consider filing a future application for a similar project, the project proponents shall convene a technical workshop, before any application is filed at this Commission. The technical workshop must be held in the location of the proposed project;

g. To the extent that a future project of this type is considered, Nevada Hydro (or any subsequent project proponent) is responsible for convening and properly noticing such a workshop, which will be held at Nevada Hydro’s expense. The technical workshop must focus, at a minimum, on the proposed project description as a stand-alone project, the proposed route, costs, benefits, and modeling assumptions,. The workshop must be widely-noticed and held well before any subsequent application is filed at the Commission. Project proponents must maintain a list of workshop attendees;

h. Nevada Hydro (or subsequent project proponent) must supply a thorough description of the workshop and must explicitly demonstrate in any subsequent application how it has considered and incorporated the input from such a workshop. Project proponents must serve any subsequent application on workshop attendees, among others, as well as on the service list to this proceeding;

i. Energy Division Staff must review any preliminary application and must agree that the application is complete, pursuant to the requirements of this decision. Nevada Hydro (or subsequent project proponents) must include a letter from the Director of the Energy Division that states the application is complete as an attachment to any subsequent application tendered for formal filing;

j. Prior to a subsequent application being accepted for filing, Nevada Hydro must demonstrate that it

- 25 -

Page 27: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

has paid in full all reimbursable contract invoices approved by the Energy Division and the Division of Ratepayer Advocates. Nevada Hydro shall include a declaration that all such approved invoices have been paid; and

k. When a new application is filed, Nevada Hydro (or subsequent project proponents) must demonstrate that all authorized intervenor compensation claims have been paid within 30 days of our authorizing decisions, and that such payments include such interest payments as are authorized in those decisions, or Nevada Hydro must file a status report on any pending claims in the new docket.

2. The Nevada Hydro Company’s Petition to Modify Decision (D.) 11-07-036 is denied. Consistent with D.11-07-036 and Ordering Paragraph 2, The Nevada Hydro Company shall provide a surety or performance bond in the amount of $550,000 that shall remain in effect until it has fully compensated all eligible intervenors determined to have made a substantial contribution to this proceeding.3. No later than 15 days after the effective date of this proceeding, The Nevada Hydro Company shall file and serve proof of the bond in this proceeding.4. This proceeding is closed. Consistent with the requirements of Decision 11-07-036, the Nevada Hydro Company must post the bond as directed in Ordering Paragraphs 2 and 3, must honor authorized intervenor compensation requests and must ensure that the reimbursable contracts with the Commission’s Energy Division consultants for environmental review of the project and with the Division of Ratepayer Advocates for expert consultants are paid in full.5. The hearing determination is changed to no hearings necessary.

- 26 -

Page 28: docs.cpuc.ca.gov€¦ · Web viewWe also deny Nevada Hydro’s Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements

A.10-07-001 ALJ/ANG/avs DRAFT (Rev. 1)

6. Application 10-07-001 is closed.This order is effective today.Dated , at Fresno, California.