document 3 014 545c-np, summary equipment ...non-proprietary psi ptvas pul pu2 qa qts rad rfi rg rh...

128
NON-PROPRIETARY D Rolls-Royce D6signation du document Document name Affalre [xI Product Equipement Ex Equipment Sous-ensemble E Subassembly Classi IE ou 6quiv. Safety classification Summary Equipment Qualification Test Report SPIMLINE 3 NRC Qualification Qualification Test Specimen 1E Document contractuel (pour le cilent) Contractual document (for customer) oui ED] non [III yes no Nbrede pages 128 Number of pages Code projet Project code Diffusion Interne: Internaldistribution Diffusion exteme: External distribution JE.REOl J17.00 ICC. BEE; KLI FNRC I Tampon archivage / Atzhiye stamp I I Version franpalse R6dig6 par vWrIfM6 par Approuv4 par Written by Checked by Approved by Nom: Nom: Nom Nameame Name Visa :Vsa Visa: Signatuee Date jae-Dt Englishversion R6dig6 ou traduit par Vdrifl6 pat Approuv, par Wdtten or translated by Checked by Approved by Nom : M. BURZYNSKI Nom: M. LNAND Nom: M. P. Durand Name Neme,< 2 Name Visa :./ , / 1. . ' Visa 11 1 Visa / Signal.e2 , igna rb.- , Stgna Date: Date " Date:j D V Da 7O o os- qte Date Date The doe-o1n coo~oins jqoloooo00 -Aich Is propfltnt.y -od oecndvnWo to Rol!-Royve CIA Nud.or SAS w~ch ovy not, velout "e dor Hfton -2~o of RAýtn.oyco CAA Node., SAS, b. used .n .,.~dced, 1. WfO. .tto Pelt, onior ntnotad t. ery pors"n not eo.toyed by Rotlos-Royce CIA Nod-o SAS'. CR.b-Royn. pl. 2009 Lo doonnn content des ionnorndotons corldentialtov 61 propnt6li do Rolts-Royoo~totl Nudootn SAS ot no pout. ans racmod W0t protniouo do Rotls-Royce CMot Nnotoo SAtS, 6tr Witt, ou rponojnin en tnofli6 ono pontlo. ow 61n, nonnnonquiIton Vent. Rollo.Royoo pto2009 Impdrm6 n' 8 303 090 F 3 014 545C-NP Page 1

Upload: others

Post on 19-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARYD Rolls-Royce

D6signation du documentDocument name

Affalre [xIProduct

Equipement ExEquipment

Sous-ensemble ESubassembly

Classi IE ou 6quiv.Safety classification

Summary Equipment QualificationTest Report

SPIMLINE 3 NRC Qualification

Qualification Test Specimen

1E

Document contractuel (pour le cilent)Contractual document (for customer)

oui ED] non [IIIyes no

Nbrede pages 128Number of pages

Code projetProject code

Diffusion Interne:Internal distribution

Diffusion exteme:External distribution

JE.REOl J17.00

ICC. BEE; KLI

FNRC

I Tampon archivage / Atzhiye stamp I IVersion franpalse

R6dig6 par vWrIfM6 par Approuv4 parWritten by Checked by Approved by

Nom: Nom: NomNameame NameVisa :Vsa Visa:SignatueeDate jae-Dt

English version

R6dig6 ou traduit par Vdrifl6 pat Approuv, parWdtten or translated by Checked by Approved by

Nom : M. BURZYNSKI Nom: M. LNAND Nom: M. P. DurandName Neme,< 2 NameVisa :./ , / 1. . ' Visa 11 1 Visa /Signal.e2 , igna rb.- , StgnaDate: Date " Date:j D VDa 7O o os- qte Date Date

The doe-o1n coo~oins jqoloooo00 -Aich Is propfltnt.y -od oecndvnWo to Rol!-Royve CIA Nud.or SAS w~ch ovy not, velout "e dor Hfton -2~o of RAýtn.oyco CAANode., SAS, b. used .n .,.~dced, 1. WfO. .tto Pelt, onior ntnotad t. ery pors"n not eo.toyed by Rotlos-Royce CIA Nod-o SAS'. CR.b-Royn. pl. 2009Lo doonnn content des ionnorndotons corldentialtov 61 propnt6li do Rolts-Royoo~totl Nudootn SAS ot no pout. ans racmod W0t protniouo do Rotls-Royce CMot Nnotoo SAtS, 6trWitt, ou rponojnin en tnofli6 ono pontlo. ow 61n, nonnnonqui Iton Vent. Rollo.Royoo pto 2009

Impdrm6 n' 8 303 090 F 3 014 545C-NPPage 1

Page 2: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

IRolls-Royce

TABLEAU DEMISE A JOURRecord of revisions

Indice /dateR6dig6 par Pages modifi6es Origine et d6signation de la modification

Revision letter/date Modified pages Origin and designation of the modificationWritten by

A/ 11/15/11Michel BELNAND

B / 05/12/12Mark Burzynski

C / 11/16/12Mark Burzynski

All

Sections 1, 7, 8, 11, 12, 13, 14, 15, and16.Appendix A Sections A.5 and A.8.Appendix B Sections B.6, B.11, andB.12.Appendix E Sections E.4, E.6, E.8, E.9,E.11, E.12, and E.13.Appendix F Sections F.2, F.4, F.6, F.8,F.10, F.11, and F.12.Appendix K Sections K.11 and K.12.

First issue

Updated to reflect completion of test eventevaluations.

Updated to reflect completion of 2012 testresults.

Identification des moyens de production de ce document

Identification of document production means

Outils: Microsoft Word Fichier: SummaryEQTestReport_3014545C-NP

Tools File

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page 2

Page 3: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY Rol- ycLL]Rolls-Royce

TABLE DES MATIERESTable of contents

1 P u rp o s e .................................................................................................................................. 4

2 Abbreviations and Acronyms ............................................................................................ 4

3 Scope of EQ Testing ...................................................................................................... 7

4 Equipment Tested .......................................................................................................... 7

5 T e st S yste m ........................................................................................................................... 8

6 Test Requirements and Acceptance Criteria ..................................................................... 9

7 Test Plan and Test Procedures ....................................................................................... 10

8 Test Responsibilities ....................................................................................................... 11

9 T e st C o n tro l ......................................................................................................................... 1 2

10 Measurement and Test Equipment ................................................................................. 12

1 1 T e st S c h e d u le ...................................................................................................................... 12

12 T e st D o cu m e ntatio n ............................................................................................................. 17

13 Evaluation of Test Results .............................................................................................. 19

14 As-tested Equipment Qualification Envelope .................................................................. 19

1 5 S u m m a ry .............................................................................................................................. 2 5

16 R e fe re n c e s ........................................................................................................................... 2 6

Appendix A: Factory Acceptance Test Summary ................................................................. A-1

Appendix B: Pre-Qualification Acceptance Test Summary ................................................... B-1

Appendix C: Radiation Exposure W ithstand Test Summary ................................................. C-1

Appendix D: Environmental Test Summary .............................................................................. D-1

Appendix E: Seismic Test Summary .......................................................................................... E-1

Appendix F: EMI/RFI Test Summary ..................................................................................... F-1

Appendix G: Electrical Fast Transient Test Summary ......................................................... G-1

Appendix H: Surge W ithstand Test Summary ........................................................................ H-1

Appendix I: Electrostatic Discharge Test Summary ............. .................................................... I-1

Summary EQ Test Report 3 014 545C-NP

Impdm6 n' 8 303 090 F

Page 3

Page 4: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY Rol- ycR~olls-Royce

Appendix J: Class 1E to Non-lE Isolation Test Summary ......................................................... J-1

Appendix K: Performance Proof Test Summary ..... ........................... K-1

1 Purpose

This document provides a summary of the equipment qualification (EQ) testing performed in accordance withthe EQ Test Plan (Reference 1) on the Rolls-Royce SPINLINE3 Qualification Test Specimen (QTS,Reference 2). The SPINLINE 3 QTS includes all of the generic safety-related components of the Rolls-RoyceSPINLINE 3 digital safety instrumentation and control (I&C) platform described in the SPINLINE 3 LicensingTopical Report (LTR, Reference 3). The generic SPINLINE 3 platform is intended for use in mildenvironments as defined in the LTR and the EQ Test Plan.

This document is the summary report of EQ test results required by the U.S. Nuclear RegulatoryCommission (NRC) Interim Staff Guide DI&C-ISG-06 (Reference 4), item 2.12, including the QTS factoryacceptance test (FAT) results, which correspond to DI&C-ISG-06 items 2.5 and 2.6.

The test results reported herein define the as-tested EQ envelope within which the hardware and software ofthe generic SPINLINE3 digital safety I&C platform are expected to be able to perform intended safetyfunctions without experiencing environmentally induced common-cause failures during normal environmentalconditions and anticipated operational occurrences. The document has been updated to reflect the post-testanalysis of the reported test deficiencies.In this document, double brackets ("[[ ]]") denote proprietary information. In the proprietary document, thetwo brackets denoting the end of a proprietary segment may appear one or more pages following the bracketindicating the start of the proprietary segment. In the nonproprietary edition of this document, the materialwithin the brackets is removed.

2 Abbreviations and Acronyms

A Ampere

AC Alternating Current

Al Analog Input

AIOTB Analog Input Output Terminal BlockANSI American National Standards Institute

AO Analog Output

ASOA Application Software Objects Acceptance

C Celsius

CFAS Cooling Fan Assembly System

CFR Code of Federal Regulations

DAS Data Acquisition System

dB Decibel

DC Direct Current

DI Digital Input

DITB Digital Input Terminal Block

DO Digital Output

EFT Electrical Fast Transient

Summary EQ Test Report 3 014 545C-NP

1mpdm6 n* 8 303 090 F

Page 4

Page 5: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

EMC

EMI

EPRI

EQ

ESD

F

FAT

gG1 to G5

GHz

HCAS

hPa

Hz

HMI

I&CIEC

IEEE

ICTO

I/O

ISG

ISO

kA

kHz

kV

LDU

LTR

M

M&TE

mA

MCL

MHz

MIL-STD

msec

mV

NCSL

NERVIA+ DaughterNET

NIST

NRC

NTS

OBE

PC

PLC

PSi

PS2

PSAS

LRolls-RoyceElectromagnetic Compatibility

Electromagnetic Interference

Electric Power Research Institute

Equipment qualification

Electrostatic Discharge

Fahrenheit

Factory Acceptance Test

Gravity

Converters DC/DC located in the PSi rack

GigahertzHubs and Converters Assembly System

Hectopascal

Hertz

Human-Machine Interface

Instrumentation and Control

International Electrotechnical Commission

Institute of Electrical and Electronics Engineers

Count rate Interface Board

Input/Output

Interim Staff Guidance

International Standards Organization

Kiloampere

Kilohertz

Kilovolt

Local Display Unit

Licensing Topical Report

meter

Measurement and Test Equipment

Milliamp

Master Configuration List

Megahertz

Military Standard

Millisecond

Millivolt

National Conference of Standards Laboratories

UC25 N+ daughter board (constitutes the NERVIA+ network electronic part)Network

National Institute of Standards and Technology

Nuclear Regulatory Commission

National Technical Systems

Operating Basis Earthquake

Personal Computer

Programmable Logic Controller

Power Supply rack type 1 (48 VDC / 24 VDC)

Power Supply rack type 2 (120 VAC /48 VDC)

Power Supply Assembly System

Summary EQ Test Report

Impdm6 n° 8 303 090 F

3 014 545C-NP

Page 5

Page 6: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

PSI

PTVAS

PulPU2

QA

QTS

Rad

RFI

RG

RH

RTD

RMS

RO

Rolls-Royce

ROTB

RRS

SER

SIN

SSE

Temp

TP/FL

TR

TSAP

UC25 N+

VI

V

ZPA

pV

16E.ANA ISO

32ACT

32ETOR

Rolls-RoycePounds per Square Inch

Periodic Test and Vote Modules Assembly System

SPINLINE 3 Equipment Cabinet with test specimen modules except RTD modules

SPINLINE 3 Equipment Cabinet with RTD module test specimens

Quality Assurance

Qualification Test Specimen

Radiation Absorbed Dose

Radio-Frequency Interference

Regulatory Guide

Relative Humidity

Resistance Temperature Detector

Root Mean Square

Relay Output

Rolls-Royce Civil Nuclear SAS (Societ6 Anonyme Simplifie)

Relay Output Terminal Block

Required Response Spectrum

Safety Evaluation Report

Serial Number

Safe Shutdown Earthquake

Temperature

Copper link to Optical fiber link

Technical Report

Test Specimen Application ProgramBoard that leads processing and control unit function

Voltage Input

Volt

Zero Period Acceleration

Microvolt

Analog signals acquisition and analog to digital conversion board

Actuator Drive Board

Digital Input isolated acquisition board

Summary EQ Test Report

Impdm5 n* 8 303 090 F

3 014 545C-NP

Page 6

Page 7: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY * Rolls-Royce

3 Scope of EQ Testing

The EQ testing of the SPINLINE 3 QTS was performed in accordance with the requirements of RegulatoryGuide (RG) 1.89 (Reference 5) and requirements of Institute of Electrical and Electronics Engineers (IEEE)Standard 323-2003 (Reference 6). This standard is subject to the enhancements and exceptions listed inSection C, "Regulatory Position" of RG 1.209 (Reference 7).

The environmental qualification testing of the SPINLINE3 QTS also was performed in accordance with therequirements for qualifying digital computers in IEEE Standard 7-4.3.2-2003 (Reference 8) and RG 1.152,Revision 3 (Reference 9).

Electric Power Research Institute (EPRI) Technical Report TR-107330 (Reference 10) describes anapproach for generically qualifying commercial Programmable Logic Controllers (PLCs) for safety-relatedapplications. This approach was found acceptable by the NRC as documented in its Safety EvaluationReport (SER) Letter dated July 30, 1998 to Mr. J. Naser of the EPRI (Reference 11). The generic hardwarequalification testing approach described in the EQ Plan uses guidance from EPRI TR-107330 as applicableto meet the requirements of IEEE Standard 323-2003 and other NRC guidance.RG 1.180, Revision 1 (Reference 12) describes methods acceptable to the NRC for complying withregulations on testing practices to address the effects of electromagnetic and radio-frequency interference(EMI/RFI) and power surges on safety-related I&C systems. The qualification testing approach described inthe EQ Plan uses guidance from RG 1.180, Revision 1 as applicable to meet the requirements of IEEEStandard 323-2003.RG 1.100, Revision 2 (Reference 13) states that the procedures described in IEEE Standard 344-1987(Reference 14) are acceptable to the NRC for complying with regulations on testing practices to address theeffects of seismic qualification of electric equipment. Seismic testing based on EPRI TR-107330 guidance isperformed in accordance with IEEE Standard 344-1987. The qualification testing approach described in theEQ Plan uses guidance from EPRI TR-107330 to meet the requirements of RG 1.100 and IEEE Standard344-1987.

The EQ Plan appendices are the test design specifications for EQ testing required by DI&C-ISG-06, Item2.4.

4 Equipment Tested

The equipment under test was known as the SPINLINE3 QTS. In accordance with EPRI TR-107330, theequipment tested included a representative sample of the SPINLINE 3 platform components. The QTS wascomprised of the following types of hardware modules and components:

o Chassis (PU1 and PU2)

o Power Supply Modules (PS1, PS2/1 to PS2/3)

o Digital Processing Modules (PTVAS)

o Communication Modules (HCAS)

o Signal Input Modules

o Signal Output Modules

o Signal Conditioning Modules

o Terminal Blocks (DITB, AIOTB and ROTB)

o Cable and Wire Sets

o Fan Cooling Hardware (CFAS)

o Power Distribution Hardware (PSAS)

Summary EQ Test Report 3 014 545C-NP

Imprim6 n° 8 303 090 F

Page 7

Page 8: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceA detailed description of the SPINLINE 3 QTS is provided in the document, "System Specification for theQualification Test Specimen and Data Acquisition System". Test specimen and test system arrangement andwiring drawings (References 15 to 18) provide additional hardware configuration information. The MasterConfiguration List (MCL, Reference 19) provides detailed SPINLINE3 QTS configuration information suchas component serial numbers and software version numbers. The QTS is shown in Figure 1.

QTS (front view) QTS (rear view)Figure 1: Qualification Test Specimen

5 Test System

The QTS was exercised during qualification testing by a test system comprised of an industrial-grade dataacquisition system (DAS) and a test specimen application program (TSAP), both of which are described inthe "System Specification for the Qualification Test Specimen and Data Acquisition System". This testsystem is a non-qualified system whose sole purposes were to: (1) generate a series of known inputs to theQTS, and (2) monitor the corresponding outputs of the QTS. Correct correspondence between input andoutput during and after qualification tests and lack of spurious behavior are the key results that demonstratethe predictable behavior of SPINLINE 3 hardware during normal and abnormal plant operating conditions.The DAS is shown in Figure 2.The DAS is composed of the following equipment:

* A cabinet, with terminal blocks* Power supplies0

a

0

0

Hubs and Fiber optic converterConditioning boards, which provide protection to digital and analog inputsthe DAS-PC,the DAS-RT (Real Time), including a PXI (PCI bus eXtended for Instrumentation) system

Summary EQ Test Report

Imprim6 n° 8 303 090 F

3 014 545C-NP

Page 8

Page 9: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

1Rolls-Royce

IDAS (front view) DAS (Rear view)

Figure 2: Data Acquisition System

6 Test Requirements and Acceptance Criteria

As discussed in Section 3, the generic hardware qualification testing approach defined in the EQ Plan usedguidance from EPRI TR-107330 to meet the requirements of IEEE Standard 323-2003, IEEE Standard 7-4.3.2-2003, and other NRC guidance applicable to qualifying safety-related digital I&C systems intended forinstallation in a mild plant environment.The basic test acceptance criteria applied to the SPINLINE 3 QTS are the following:

o The SPINLINE3 QTS will continue to function correctly during and/or after exposure to abnormalenvironmental conditions (incident gamma radiation, temperature, and humidity).

o The SPINLINE 3 QTS will continue to function correctly during and after exposure to Operating BasisEarthquake (OBE) and Safe Shutdown Earthquake (SSE) seismic events.

o The SPINLINE 3 QTS will continue to function correctly during and after exposure to EMI/RFI, voltagesurges, electrical fast transients, and electrostatic discharges.

o The SPINLINE 3 QTS will continue to function correctly during and after exposure to electrical faultsapplied to selected external interface points.

Correct functioning of the SPINLINE 3 QTS during normal and abnormal plant operating conditions wasdetermined by the behavior or the performance of operational parameters identified in the respective testprocedures. Correct functioning includes:

o Proper response of inputs to applied input signals,o Proper response of outputs to application program control,

Summary EQ Test Report 3 014 545C-NP

Imprim6 n° 8 303 090 F

Page 9

Page 10: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royceo Proper control of connected output devices,

o Proper operation of communication interfaces,

o Acceptable input/output (1/O) accuracy,

o Acceptable response time,

o Proper response to momentary interruption of input power,

o Proper response to loss of input power,

o Proper response to input power quality (voltage and frequency) variations,

o Proper failover to redundant components.

7 Test Plan and Test Procedures

The EQ Plan defines the qualification testing program for the generic SPINLINE 3 digital safety I&C platform.As listed in Table 7-1, Appendices A through M of the EQ Plan are the detailed Test Plans for each of thetests performed on the SPINLINE 3 QTS. These individual Test Plans constitute the qualification test designspecifications required by DI&C-ISG-06, Item 2.4.

Table 7-1. SPINLINE 3 EQ Test Plans

Reference 1EQ Test Plan Appendix

Appendix

Factory Acceptance Test Plan Appendix APre-qualification Acceptance Test Plan Appendix B

Radiation Exposure Test Plan Appendix CEnvironmental Test Plan Appendix DSeismic Test Plan Appendix EEMI / RFI Test Plan Appendix F

Electrical Fast Transient Test Plan Appendix GSurge Withstand Test Plan Appendix HElectrostatic Discharge Test Plan Appendix IClass 1 E to Non-Class 1 E Isolation Plan Appendix JSystem Setup and Checkout Test Plan Appendix KOperability Test Plan Appendix LPrudency Test Plan Appendix M2012 Additional Seismic Test Plan Appendix N2012 EMI / RFI Test Plan Appendix 0

Each individual Test Plan addresses the specific test approach, equipment tested, sequence of testing, testprocedures, test specimen mounting, service conditions, test levels, performance monitoring, acceptancecriteria and documentation. The Test Plans provide references to the specific qualification test requirementsand guidance obtained from IEEE Standard 323-2003, IEEE Standard 344-1987, IEEE Standard 7-4.3.2-2003, EPRI TR-107330, RG 1.100 Revision 2, RG 1.152 Revision 3, RG 1.180 Revision 1, and RG 1.209.

The Test Plans are implemented by the following set of test procedures that are executed as defined in theTest Plans.

Summary EQ Test Report

Imprim6 n' 8 303 090 F

3 014 545C-NP

Page 10

Page 11: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY j Rolls-RoyceTable 7-2. SPINLINE 3 EQ Test Procedures

EQ Test Procedures Document # Reference2010 Factory Acceptance Test Procedure and Report 3 010 783 B 202012 Factory Acceptance Test Procedure and Report 3 022 951 A 21System Setup and Checkout Test Procedure 3 010 294 E 22Radiation Exposure Test Procedure 3 010 286 C 23Environmental Test Procedure 3 010 287 C 24Seismic Test Procedure 3 010 288 D 25EMI / RFI Test Procedure 3 010 289 C 26Electrical Fast Transient Test Procedure 3 010 290 B 27Surge Withstand Test Procedure 3 010 291 A 28Electrostatic Discharge Test Procedure 3 010 292 A 29Class 1 E to Non-Class 1 E Isolation Test Procedure 3 010 293 A 30Operability Test Procedure 3 010 295 E 31Prudency Test Procedure 3 010 296 D 32

These test procedures are the detailed qualification test methodologies required by DI&C-ISG-06, Item 2.11.The completed test procedures are the "completed test procedures and reports" required by DI&C-ISG-06,Item 3.5.

8 Test Responsibilities

Rolls-Royce is both the manufacturer and the qualifier of the generic SPINLINE 3 platform, as those termsare defined in Section 1.3 of EPRI TR-107330.In Section 7.2 of EPRI TR-107330, there is a requirement that generic qualification activities shall beperformed under a 10 CFR Part 50 Appendix B (Reference 33) compliant Quality Assurance (QA) Program.The qualification testing and analyses activities summarized in this report were performed in accordance withthe Rolls-Royce Quality Manual (Reference 34), which defines a nuclear quality program that is incompliance with 10 CFR Part 50 Appendix B. Procurement, receipt and acceptance of the test laboratoryservices was done in accordance with Rolls-Royce quality procedures for procurement, receipt andacceptance of nuclear grade services, including preparation of a services procurement specification.Rolls-Royce subcontracted with the test laboratory NTS (National Technical Systems) located in Acton,Massachusetts to provide qualification testing services in 2011 and 2012. Laboratory testing services wereperformed in accordance with the Rolls-Royce procurement specification, which invoked the NTS QAProgram, which is in compliance with 10 CFR Part 50 Appendix B. Rolls-Royce subcontracted with Wylelaboratory located in Huntsville, Alabama to provide qualification testing services in 2010. Laboratory testingservices were performed in accordance with the Rolls-Royce procurement specification, which invoked theWyle QA Program, which is in compliance with 10 CFR Part 50 Appendix B.Appendices A through K of this report identify the division of responsibilities between each organization forperformance and documentation of the qualification testing and analysis activities. This division ofresponsibilities is identified by the indicated preparers of the qualification testing procedures and the testdocumentation.

Summary EQ Test Report

Impdmd n° 8 303 090 F

3 014 545C-NP

Page 11

Page 12: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

.NON-PROPRIETARY Rolls-Royce

9 Test Control

Rolls-Royce personnel were present to perform test setup and oversee all hardware -qualification testingperformed by the test laboratory. Rolls-Royce activities were performed according to the quality proceduresfor test control. All testing activities performed by Rolls-Royce and the test laboratory were accomplishedaccording to Rolls-Royce test procedures.

Rolls-Royce completed the procedures, recorded any deviation relating to the sequence of testing, the testspecimen mounting, service conditions, test levels, test results and any exception, deficiency or field changewhich occurred during these tests. The results are summarized in the following appendices A to K.

All test exceptions, deficiencies, and field changes resulting from discrepancies or deficiencies in testdocumentation or unacceptable test specimen hardware or software performance during qualification testingare identified in Appendices A through K of this summary report and have been processed in accordancewith Rolls-Royce quality procedures.

10 Measurement and Test Equipment

All measurement and test equipment (M&TE) used in the SPINLINE 3 QTS qualification testing project toacquire data according to the qualification test procedures were calibrated to the requirements of AmericanNational Standards Institute / National Conference of Standards Laboratories (ANSI/NCSL) Z540-1(Reference 35) and/or International Standards Organization (ISO) 10012-1 (Reference 36). Standards usedfor calibration were traceable to the National Institute of Standards and Technology (NIST).

Rolls-Royce provided all required M&TE for simulating inputs to and monitoring performance of the testspecimen during hardware qualification testing. Calibration of this equipment was done by Rolls-Royceapproved suppliers.NTS provided all required calibrated M&TE for monitoring the applied qualification test conditions and forrecording the SPINLINE 3 QTS response to the applied test conditions.

As part of the SPINLINE3 QTS qualification testing project, Rolls-Royce specified, procured, andprogrammed a software based data acquisition system for use during pre-qualification and qualificationtesting. The data acquisition system was calibrated for use in the qualification project. Calibration wasperformed by a Rolls-Royce approved supplier.

11 Test Schedule

The originally planned sequence of testing is defined in Figure 1 of the EQ Plan. The actual test sequencefor the 2010/2011 SPINLINE3 QTS qualification testing sequence is shown in Figure 3. The actual testsequence for the 2012 SPINLINE3 QTS qualification testing sequence is shown in Figure 4. The actualtesting sequence is summarized in Table 11-1. The basis for making changes to the original test sequenceis included as comments in Table 11-1.

Summary EQ Test Report 3 014 545C-NP

Imprim6 n* 8 303 090 F

Page 12

Page 13: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[Rolls-Royce2010/2011 SPINLINE 3 QTS QUALIFICATION SEQUENCE

MANUFACTURING

Test Specimen and Test SystemManufacture and Assembly

0

FACTORY ACCEPTANCE TESTING

Test Specimen and Test System Factory Acceptance Testing

PRE-QUALIFICATION ACCEPTANCE TESTING

VI

Pre-Oualifcation Testing Pre-Oualitication Testing Pre-Oualiication TestingSystem Setup and Checkout Testing Operability Testing Prudency Testing

QUALIFICATION TESTING

Radiation Exposure Environmental Testing Post-Radiation Exposure Testing Post-Radiation Exposure TestingWithstand Testing System Setup and Checkout Testing Operability Testing Prudency Testing

Environmental Testing WiWth Operability Testing at High Temp/RH, Lom Temp, Lom RH and ambient Temp/RHF niomna TetnWiith Prudency Testing at High TemplRH

Seeismic Testing SeismicTestng Seismc TestingSystem Setup and Checkout Testing First configuration - stage one Second confguration

Post-emi Post-SeismiOperability Testing Prudency Testing

EMI/RFI Testing S Ei Elertro smat ic Dshr [11I si EMT/RFIe gS y s t e _ m S e tu p a n d C h e c k o u t T e s t~in gl l et i n g I l c r c l F s r n Ie n e t n E m is s io n s T e s t in g

[ EMI/RFI Susceptibility Testing - [ SugWihtnTetn 1 las1t...1EIotonetng - ]

S Post-EMo __ Post-YEWo }Operability Testn Prdency T.sting

System Setup and Checkout Testing First configuration - stage Iwo

PERFORMANCE PROOF TESTING

VPerformance Proof Testing J J Performance Proof Testing Performance Proof Testing

System Setup and Checkout Testing• Operability Te sting ~ r Prudency Testing

:T-I.

Figure 3: 2010/2011 SPINLINE 3 QTS Qualification Testing Sequence

Summary EQ Test Report

ImpIm• n° 8 303 090 F

3 014 545C-NP

Page 13

Page 14: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce2012 SPINLINE 3 QTS QUALIFICATION SEQUENCE

MANUFACTURING

L,UI

Post-EMC Post-EMCOperability Testing Prudency Testing

U

LUJ

Radiated SusceptibilityMIL-STD-461 E RS1 03 (up to 5.8 GHz)

Figure 4:2012 SPINLINE 3 QTS Qualification Testing Sequence

Summary EQ Test Report 3 014 545C-NP

Imprim6 n° 8 303 090 F

Page 14

Page 15: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Table 11-1: Sequence of SPINLINE 3 EQ Testing

Originally-Planned Test Sequence F Actual Test Test Start Test End CommentsSequence Date Date

FACTORY ACCEPTANCE TESTING1 Test Specimen and 2010 campaign 03/10/10 04/20/10

Test SystemFactory AcceptanceTesting, including 2012 campaign 07/05/12 07/17/12Operability andPrudency Testing

PRE-QUALIFICATION ACCEPTANCE TESTING

2 Pre-Qualification 2010 campaign 04/21/10 04/21/10Testing System 2012 campaign 09/15/12 09/18/12Setup and CheckoutTesting

3 Pre-Qualification 2010 campaign 04/22/10 04/27/10Testing 2012 campaign 09/18/12 09/20/12Operability Testing

4 Pre-Qualification 2010 campaign 04/26/10 04/26/10Testing 2012 campaign 09/20/12 09/21/12Prudency Testing

QUALIFICATION TESTING5 Radiation Exposure Group 1 05/19/10 05/19/10 QTS parts

Withstand Testing (2010 campaign)Group 2 03/17/11 03/22/11 Spare parts(2011 campaign)

6 Environmental (2010 campaign) 06/05/2010 06/07/2010Testing System (2011 campaign) 03/27111 03/28/11Setup and CheckoutTesting

7 Post-Radiation (2010 campaign) 06/07/2010 06/09/2010Exposure (2011 campaign) 03/29/11 03/30/11Testing OperabilityTesting

8 Post-Radiation (2010 campaign) 06/09/2010 06/09/2010Exposure (2011 campaign) 03/30/11 03/30/11Prudency Testing

9 Environmental (2010 campaign) 06/11/2010 06/13/2010Testing (2011 campaign) 03/29/11 04/07/11

10 Operability Testing 04/03/11 04/07/11at HighTemperature(Temp)/RelativeHumidity (RH), LowTemp/RH andAmbient Temp/RH

11 Prudency Testing at 04/03/11 04/03/11High Temp/RH

12 Seismic Testing First Stage 04/18/11 04/19/11 Configuration 1System 04/26/11 04/27/11Setup and Checkout First Stage Configuration 2Testing I I

Summary EQ Test Report

Impdm6 n' 8 303 090 F

3 014 545C-NP

PageS 5

Page 16: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-RoyceOriginally-Planned Test Sequence Actual Test Test Start Test End CommentsOriginaly-Plane TSequence Date Date

13 Seismic Testing 2011 First Stage 04/18/11 04/20/11 Configuration 1(with HCAS)

OBE Runs 1 -6

2011 First Stage 04/20/11 04/22/11 Configuration 1(without HCAS)OBE Runs 7 -

92011 First Stage 04/26/11 05/02/11 Configuration 2

OBE Runs 10-11

SSE Runs 1 - 32011 Second 06/21/11 06/23/11 Configuration 1

Stage (without HCAS)SSE

2012 Campaign 09/21/12 09/21/12 PUlOBE Runs

09/21/12 09/21/12 PUlSSE Run

(4.9 g ZPA)09/24/12 09/24/12 HCAS

OBE Runs09/24/12 09/24/12 HCAS

SSE Run(4.9 g ZPA)

09/25/12 09/25/12 HCASSSE Run(7 g ZPA)

09/26/12 09/26/12 PUlSSE Run(7 g ZPA)

14 Post Seismic 2011 Campaign 05/02/11 05/03/11 Note: For theOperability Testing Second Stage

thePerformanceProof Testsseries wasused.

2012 Campaign 09/25/12 09/25/12 4.9 g ZPA SSE09/27/12 09/27/12 7 g ZPA SSE

15 Post Seismic 2011 Campaign 05/03/11 05/03/11 Note: For thePrudency Testing Second Stage

thePerformanceProof Testsseries wasused.

2012 Campaign 09/25/12 09/25/12 4.9 g ZPA SSE09/27/12 09/27/12 7 g ZPA SSE

16 EMI/RFI Testing 2011 Campaign 05/09/11 05/09/11System Setup and 2012 Campaign 10/09/12 10/09/12Checkout Testing

17 EMI/RFI Emissions 05/19/11 05/23/11Testing

Summary EQ Test Report

Impdm6 n* 8 303 090 F

3 014 545C-NP

Page 16

Page 17: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

ERolls-RoyceOriginally-Planned Test Sequence Actual Test Test Start Test End Comments

Sequence Date Date18 EMI/RFI 2011 Campaign 05/13/11 06/14/11

Susceptibility 2012 Campaign 10/10/12 10/16/12Testing

19 Electrical Fast 05/12/11 05/13/11Transient Testing

20 Surge Withstand 06/07/11 06/10/11Testing

21 Electrostatic 05/10/11 05/11/11Discharge Testing

22 Class 1 E to Non-1 E 06/15/11 06/23/11Isolation Testing

23 Post EMC 2011 Campaign 06/16/11 06/17/11 Note: AddedOperability Testing based on

addition ofSecond Stage

seismic test.2012 Campaign 10/12/12 10/12/12

(1 - 3 GHz)2012 Campaign 10/15/12 10/16/12

(3 - 5.8 GHz)2012 Campaign 10/16/12 10/17/12 Note:

(5.8 - 8 GHz) PerformanceProof Testsseries wasused.

24 Post EMC Prudency 2011 Campaign 06/17/11 06/17/11 Note: AddedTesting based on

addition ofSecond Stageseismic test.

2012 Campaign 10/12/12 10/12/12(1 - 3 GHZ)

2012 Campaign 10/16/12 10/16/12(3 - 5.8 GHZ)

2012 Campaign 10/17/12 10/17/12 Note:(5.8 - 8 GHZ) Performance

Proof Testsseries wasused.

PERFORMANCE PROOF TESTING25 Performance Proof 2011 Campaign 06/24/11 06/24/11

Testing SystemSetup and CheckoutTesting

26 Performance Proof 2011 Campaign 06/24/11 06/24/11Testing 2012 Campaign 10/16/12 10/17/12Operability Testing

27 Performance Proof 2011 Campaign 06/24/11 06/24/11 tTesting 2012 Campaign 10/17/12 10/17/12Prudency Testing

12 Test Documentation

Summary EQ Test Report

Impdm6 n° 8 303 090 F

3 014 545C-NP

Page 17

Page 18: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

MRolls-Royce

This document is the summary report of EQ test results required by the NRC Interim Staff Guide DI&C-ISG-06, item 2.12, including the QTS FAT results associated with DI&C-ISG-06 items 2.5 and 2.6.Appendices A through K of this summary report provide a synopsis of each test and identify the supportingdocumentation that serves as the detailed record of the qualification testing and analysis of the SPINLINE 3QTS.

The Test Summaries describe the results obtained from the implementation of the test procedures that wereexecuted in accordance with the Test Plans.

The following terminology is used in the Appendices to describe the results of the qualification testing:

* Passed - Test acceptance criteria were met and no events encountered during testing.* Satisfactory - Test acceptance criteria were met. However; some events encountered were

encountered during testing that did not affect qualification.* Unsatisfactory - Some test acceptance criteria were not met and required additional technical

evaluation or analysis to demonstrate qualification.* Failed - Some test acceptance criteria were not met and additional testing will be required to

demonstrate qualification.

I The Rolls-Royce test reports issued to document the 2010 - 2012 SPINLINE 3 qualification test campaignare listed in Table 12-1.

Summary EQ Test Report

Impdm6 n° 8 303 090 F

3 014 545C-NP

Page 18

Page 19: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceTable 12-1. SPINLINE 3 EQ Test Reports

EQ Test Plan Document # ReferenceFactory Acceptance Test Report 3 010 783 B Reference 20

3 022 951 A Reference 21Pre-qualification Acceptance Test Report 3 013 350 A Reference 56

3 013 308 A Reference 64Radiation Exposure Test Report 3 018 588 A Reference 68

3 013 309 A Reference 71Environmental Test Report 3 018 589 A Reference 80Seismic Test Report 3 018 590 A Reference 89

3 020 948 A Reference 903 018 591 A Reference 100

EMI / RFI Test Report 3 020 951 A Reference 105Electrical Fast Transient Test Report 3 018 592 A Reference 109Surge Withstand Test Report 3 018 593 A Reference 111Electrostatic Discharge Test Report 3 018 594 A Reference 113Class 1 E to Non-Class 1 E Isolation Test Report 3 018 595 A Reference 115Performance Proof Test Report 3 018 596 A Reference 121

3 020 949 A Reference 125

13 Evaluation of Test Results

Rolls-Royce evaluated the test results from the 2011 and 2012 test campaigns and performed engineeringevaluations of all reported test events. The results of the engineering evaluations for the 2011 test campaignare documented in Rolls-Royce document "Investigations Results of 2011 NRC Qualification Tests"(Reference 126). The results of the engineering evaluations have been incorporated into the as-testedqualification envelope summarized in Section 14 below. The results of the evaluation for each event are alsosummarized in the summary discussion for each qualification test found in the Appendices.

As a result of the testing, Rolls-Royce conducted a supplemental test campaign in 2012 to validate thesolutions for the problems noted during the seismic tests and to extend the EMI/RFI radiated susceptibilityqualification envelope.

14 As-tested Equipment Qualification Envelope

Successful execution of the EQ tests defined in the Test Plans is intended to qualify the generic SPINLINE 3digital safety I&C platform for a qualification envelope substantiated by the actual test levels. The as-testedequipment qualification envelope is summarized in Table 14-1.

Summary EQ Test Report

Impdm6 n° 8 303 090 F

3 014 545C-NP

Page 19

Page 20: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

Table i4-1. As-tested Generic Qualification Envelope for the SPINLINE 3 Digital Safety I&C Platform

Equipment EQ Plan it R Source of Qualification Test Asested Quaifiation Envelope Qualification Test AccptanceQualification Appendix egulato Requiremen Specification Criteria

Category

Radiation Appendix C RG 1.89 and IEEE Standard 323- Section 4.3.6 of EPRI TR-107330 [[ Section 4.3.6 of EPRI TR-1 07330Exposure 2003

Environmental Appendix D RG 1.89 and IEEE 323, subject to Section 4.3.6 of EPRI TR-107330, Section 4.3.6 of EPRI TR-107330(Temperature & enhancements and exceptions listed modifiedHumidity) in Section C of RG 1.209.

Seismic Appendices RG 1.100 and IEEE Standard 344 Section 4.3.9 of EPRI TR-107330. The [[ Section 4.3.9 of EPRI TR-1 07330.E and N OBE and SSE tests shall follow the RRS Limitations on the qualification

curve given as Figure 4-5 in EPRI TR- envelope are described in Appendix E.107330 within the limits of the seismic testtable, with the exception that the minimumZPA requirements are met.

EMI/RFI Appendices RG 1.180, Revision 1 EMI/RFI Emissions TestsF and 0

MIL-STD-461E, CE101 (Reference 39): Section 4.3.7 of EPRI TR-1 07330 andConducted Emissions, Low Frequency, RG 1.180, Revision 1AC and DC Power Leads Emission limit: RG 1.180, Revision 1:

Figure 3-1

MIL-STD-461E, CE102 (Reference 39): Section 4.3.7 of EPRI TR-1 07330 andConducted Emissions, High Frequency, RG 1.180, Revision 1AC and DC Power Leads Emission limit: RG 1.180, Revision 1:

Figure 3-2

MIL-STD-461E, RE101 (Reference 39): Section 4.3.7 of EPRI TR-107330 andRadiated Emissions, Magnetic Field, QTS RG 1.180, Revision 1Surfaces and Leads Emission limit: RG 1.180, Revision 1:

Figure 3-3

Summary EQ Test Report

lmprim6 n' 8 303 090 F

3 014 545C-NP

Page-20

Page 21: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

EQ Table 14-1. Astse eei ulfcto Envelope for the SPINLIXE 3 Digital Safety I&C Platform__

EQualificeint E Plan RgltrReuemnsSource of Qualification Test As- tested Qualification Envelope1> ~Qualification Test AcceptaniceQualeiaieo .Appendix Regulatory Requirements Specification .. Criteria

MIL-STD-461E, RE102 (Reference 39): Section 4.3.7 of EPRI TR-107330 andRadiated Emissions, Electric Field, RG 1.180, Revision 1Antenna Measurement Emission limit: RG 1.180, Revision 1:

Figure 3-4

ýEMIIUIRFI Susceptibility Tests ..

IEC 61000-4-6 (Reference 40): Conducted Section 4.3.7 of EPRI TR-107330 andSusceptibility, Induced RF Fields, RG 1.180, Revision 1

Power/Signal Leads Susceptibility test level - power leads:

140 dBpV

Section 4.3.7 of EPRI TR-107330 andRG 1.180, Revision 1

Susceptibility test level - signal leads:130 dBpV

IEC 61000-4-13 (Reference 41): Section 4.3.7 of EPRI TR-107330 andConducted Susceptibility, RG 1.180, Revision 1Harmonics/Interharmonics, Power Leads Susceptibility test level: RG 1.180:

Table 10

IEC 61000-4-16 (Reference 42): Section 4.3.7 of EPRI TR-1 07330 andConducted Susceptibility, Common Mode RG 1.180, Revision 1Disturbance, Power/Signal Leads Susceptibility test level - power/signal

leads: RG 1.180: Table 11

Section 4.3.7 of EPRI TR-107330 andRG 1.180, Revision 1

Susceptibility test level - signal leads:RG 1.180: Table 15

Summary EQ Test Report

Imprimd n' 8 303 090 F

3 014 545C-NP

Page 21

Page 22: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

iRolls-Royce

Table 14-1. As-tested Generic Qualification Envelope for the SPINLINE 3 Digital Safety I&C Platform

... RguqoyueureetiA-etepuliiaioeetncetactEquipment EQ Plan Source of Qualification Test Qualification Test Acceptance

Qualification Appendix Regulatory Requirements Specification As-tested Qualification Envelope CriteriaCategory

IEC 61000-4-8 (Reference 43): Radiated ]] Section 4.3.7 of EPRI TR-1 07330 andSusceptibility, Magnetic Field, Helmholtz RG 1.180, Revision 1Coil Exposure Susceptibility test level - continuous:

30 NmSection 4.3.7 of EPRI TR-1 07330 and

RG 1.180, Revision 1

Susceptibility test level - shortduration: 300 Nm

IEC 61000-4-9 (Reference 44): Radiated Section 4.3.7 of EPRI TR-107330 andSusceptibility, Magnetic Field, Pulsed RG 1.180, Revision 1

Susceptibility test level: 300 Nm

IEC 61000-4-10 (Reference 45): Radiated Section 4.3.7 of EPRI TR-1 07330 andSusceptibility, Magnetic Field, Damped RG 1.180, Revision 1Oscillatory Susceptibility test level: 30 A/m

IEC 61000-4-3 (Reference 46): Radiated Section 4.3.7 of EPRI TR-1 07330 andSusceptibility, High Frequency, Antenna RG 1.180, Revision 1Exposure Susceptibility test level: 10V/m

Appendix 0 RG 1.180, Revision 1 MIL-STD-461IE, RS103 (Reference 39): [[ RG 1.180, Revision 1Radiated Susceptibility, High Frequency, Susceptibility test level: 10V/mAntenna Exposure

Summary EQ Test Report

lmprim6 n° 8 303 090 F

3 014 545C-NP

Page 22

Page 23: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

1]Electrical Fast Appendix G RG 1.180, Revision 1 IEC 61000-4-4, "Electromagnetic Sections 4.6.2 and 4.3.7 of EPRI TR-Transient (EFT) Compatibility (EMC), Part 4-4: Testing and 107330 and RG 1.180, Revision 1

Measurement Techniques, Electrical FastTransient/Burst Immunity Test,"(Reference 48). ]

Surge Withstand Appendix H RG 1.180, Revision 1 Table 22 of RG 1.180, Revision 1 defines [[ Section 4.6.2 of EPRI TR-107330 andthe IEC 61000-4-12 Ring Wave and IEC RG 1.180, Revision 161000 4-5 Combination Wave surgewithstand levels for power suppliesinstalled in Category B locations with

surge waveform Low Exposure levels.

Table 15 of RG 1.180, Revision 1 definesthe IEC 61000-4-12 Ring Wave and IEC61000 4-5 Combination Wave surgewithstand levels for signal leads in LowExposure locations with Level 2 surgewaveforms.

IEC 61000-4-5, "ElectromagneticCompatibility (EMC), Part 4-5: Testing andMeasurement Techniques, SurgeImmunity Test," (Reference 49).

IEC 61000-4-12, 'ElectromagneticCompatibility (EMC), Part 4-12: Testingand Measurement Techniques, OscillatoryWaves Immunity Test," (Reference 50).

Summary EQ Test Report 3 014 545C-NP

Impdm& n* 8 303 090 F

Page 23

Page 24: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

Table 14-1. As-tested Generic Qualification Envelope for the SPINLINE 3 Digital Safety I&C Platform

Equipment EQ Plan Sourc Ie of Qualification Test Eneoe Qualification Test Acceptance::Qualification~qim n :: Q: Pln I :: :....:Regulatory: Requirements: : ..... . .. .. . . . ..:: So re..ofQ ifiat nTst: As-tested: Qualification: Envelope:: ao etA cpa c

Category Appendix , id .Requirements Specification AteQaftoCriteria

Electrostatic Appendix I EPRI TR-1 07330, Section 4.3.8, IEC 61000-4-2 "Electromagnetic Sections 4.3.8 of EPRI TR-107330Discharge (ESD) requires that the test specimen under Compatibility (EMC), Part 4-2: Testing and

qualification be tested for ESD Measurement Techniques, Electrostaticwithstand capability in accordance Discharge Immunity Test" (Reference 51).with the requirements of EPRI TR-102323, Revision 1 (Reference 38).RG 1.180, Revision 1 provides noguidance or requirements for ESDTesting.

Class 1E to Non- Appendix J IEEE Standard 384 (Reference 52). Sections 4.6.4 of EPRI TR-1 07330 Sections 4.6.4 of EPRI TR-1 07330Class 1E EPRI TR-107330, Section 6.3.6,Isolation requires that the test specimen under

qualification be tested for Class 1E tonon-Class 1E isolation capability inaccordance with the requirements ofEPRI TR-107330, Section 4.6.4.

Summary EQ Test Report 3 014 545C-NP

Impdm& n* 8 303 090 F

Page 24

Page 25: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

15 Summary

The SPINLINE 3 equipment is considered to have passed successfully the following qualification tests:

a Factory Acceptance Test

* Pre-qualification Acceptance Test

* Radiation Exposure Test

* Environmental Test

* Electrical Fast Transient Test

• Surge Withstand Test

* Class 1E to Non-Class 1E Isolation Test

* Performance Proof Test

The SPINLINE 3 equipment is considered to have passed successfully the Electrostatic Discharge Testqualification test with the following limitation:

The SPINLINE 3 equipment is considered to have passed successfully the EMI/RFI Test qualification testwith the following limitations:

* [[

The SPINLINE 3 equipment in Configuration 2 passed the Seismic Test. The SPINLINE 3 equipment inConfiguration 1 is considered to have passed the Seismic Test except for the following limitation:

1]

Summary EQ Test Report 3 014 545C-NP

Imprim6 n* 8 303 090 F

Page 25

Page 26: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY* Rol- yc.o.j Rolls-o c

16 References

1. Rolls-Royce Document 3 006 501 E, "Equipment Qualification Plan."

2. Rolls-Royce Document 3 006 404 E, "System Specification of the Qualification Test Specimenand Data Acquisition System."

3. Rolls-Royce Document 3 008 503 D, "Licensing Topical Report."

4. Interim Staff Guidance - Task Working Group #6: Licensing Process, DI&C-ISG-06, Revision 1,U.S. Nuclear Regulatory Commission, January 19, 2011

5. Regulatory Guide 1.89, "Environmental Qualification of Certain Electric Equipment Important toSafety for Nuclear Power Plants", June 1984

6. IEEE Standard 323-2003, "Standard for Qualifying Class 1E Equipment for Nuclear PowerGenerating Stations," Institute of Electrical and Electronics Engineers

7. Regulatory Guide 1.209, "Guidelines for Environmental Qualification of Safety-RelatedComputer-Based Instrumentation and Control Systems in Nuclear Power Plants", March 2007.

8. IEEE Standard 7-4.3.2-2003, "Standard Criteria for Digital Computers in Safety Systems ofNuclear Power Generating Stations," Institute of Electrical and Electronics Engineers

9. Regulatory Guide 1.152, Revision 3, "Criteria for Use of Computers in Safety Systems of NuclearPower Plants", July 2011.

10. EPRI TR-107330, "Generic Requirements Specification for Qualifying a Commercially AvailablePLC for Safety-Related Applications in Nuclear Power Plants", December 1996.

11. NRC Letter dated July 30, 1998 to Mr. J. Naser (EPRI), "Safety Evaluation by the Office ofNuclear Reactor Regulation Electric Power Research Institute Topical Report, TR-107330, FinalReport, Generic Requirements Specification for Qualifying a Commercially Available PLC forSafety-Related Applications in Nuclear Power Plants."

12. Regulatory Guide 1.180, Revision 1, "Guidelines for Evaluating Electromagnetic and Radio-Frequency Interference in Safety-Related Instrumentation and Control System", October 2003.

13. Regulatory Guide 1.100, Revision 2, "Seismic Qualification of Electric and MechanicalEquipment for Nuclear Power Plants", June 1988

14. IEEE Standard 344-1987 "Recommended Practice for Seismic Qualification of Class 1EEquipment for Nuclear Power Generating Stations," Institute of Electrical and ElectronicsEngineers

15. Rolls-Royce Document 3 008 630 F, "Qualification Test Specimen wiring diagrams."

16. Rolls-Royce Document 3 010 140 G, "Data Acquisition System wiring diagrams."

17. Rolls-Royce Document 3 009 634 D, "Equipment Mounting Details for Seismic Testing."

18. Rolls-Royce Document 3 010 520 F, "Interconnection of Qualification Test Specimen and DataAcquisition System."

19. Rolls-Royce Document 3 010 612 G, "QTS Master Configuration List."

20. Rolls-Royce Document 3 010 783 B, "Factory Acceptance Test Procedure and Report."

21. Rolls-Royce Document 3 022 951 A, "Factory Acceptance Test Procedure and Report."(Procedure 3 019 950 A completed)

22. Rolls-Royce Document 3 010 294 E, "System Setup and Checkout Test Procedure."

23.. Rolls-Royce Document 3 010 286 C, "Radiation Exposure Test Procedure."

24. Rolls-Royce Document 3 010 287 C, "Environmental Test Procedure."

25. Rolls-Royce Document 3 010 288 D, "Seismic Test Procedure."

26. Rolls-Royce Document 3 010 289 C, "EMI / RFI Test Procedure."

27. Rolls-Royce Document 3 010 290 B. "Electrical Fast Transient Test Procedure."

Summary EQ Test Report 3 014 545C-NP

Imprims n° 8 303 090 F

Page 26

Page 27: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY * Rols-oyc~Rolls-Royce

28. Rolls-Royce Document 3 010 291 A, "Surge Withstand Test Procedure."

29. Rolls-Royce Document 3 010 292 A, "Electrostatic Discharge Test Procedure."

30. Rolls-Royce Document 3 010 293 A, "Class 1 E to Non-Class 1 E Isolation Test Procedure."

31. Rolls-Royce Document 3 010 295 E, "Operability Test Procedure."

32. Rolls-Royce Document 3 010 296 D, "Prudency Test Procedure."

33. Title 10 to the Code of Federal Regulation, Part 50, Appendix B, "Quality Assurance Criteria forNuclear Power Plants and Fuel Reprocessing Plants".

34. Rolls-Royce Document 8 303 186 P, "Rolls-Royce Civil Nuclear SAS Quality Manual."

35. ANSI / NCSL Z540.1-1994 (R2002) - Calibration & Measurement & Test Equipment - GeneralRequirements, American National Standards Institute,

36. ISO 10012-1-1992: Quality Assurance Requirements for Measuring Equipment, InternationalOrganization for Standardization

37. EPRI TR-100516, "Nuclear Power Plant Equipment Qualification Reference Manual", 1992.

38. EPRI TR-102323, Revision 1, "Guidelines for Electromagnetic Interference Testing in PowerPlants", January 1997.

39. Military Standard 461E, "Requirements for the Control of Electromagnetic InterferenceCharacteristics of Subsystems and Equipment", August 20, 1999.

40. IEC 61000-4-6, "Testing and Measurement Techniques, Immunity to Conducted DisturbancesInduced by Radio-Frequency Fields," May 2006.

41. IEC 61000-4-13, "Testing and Measurement Techniques, Harmonics and InterharmonicsIncluding Mains Signaling at A.C. Power Ports, Low Frequency Immunity Tests," March 2002.

42. IEC 61000-4-16, "Testing and Measurement Techniques, Tests for Immunity to Conducted,Common Mode Disturbances in the Frequency Range 0 Hz to 150 kHz," July 2002.

43. IEC 61000-4-8, "Testing and Measurement Techniques, Power Frequency Magnetic FieldImmunity Test," March 2001.

44. IEC 61000-4-9, "Testing and Measurement Techniques, Pulse Magnetic Field Immunity Test,"March 2001.

45. IEC 61000-4-10, "Testing and Measurement Techniques, Damped Oscillatory Magnetic FieldImmunity Test," March 2001.

46. IEC 61000-4-3, "Testing and Measurement Techniques, Radiated, Radio-Frequency,Electromagnetic Field Immunity Test," February 2006.

47. IEEE Standard 1050-1989, "Guide for Instrumentation and Control Equipment Grounding inGenerating Stations."

48. IEC 61000-4-4, "Testing and Measurement Techniques, Section 4: Electrical FastTransient/Burst Immunity Test," July 2004.

49. IEC 61000-4-5, "Testing and Measurement Techniques, Section 5: Surge Immunity Test,"November 2005.

50. IEC 61000-4-12, "Testing and Measurement Techniques, Section 12: Oscillatory WavesImmunity Tests," September 2006.

51. IEC 61000-4-2, "Testing and Measurement Techniques, Section 2: Electrostatic DischargeImmunity Test," April 2001.

52. IEEE Standard 384-1981, "Standard Criteria for Independence of Class 1E Equipment andCircuits."

53. Rolls-Royce Document 3 012 995 A, "Pre-Qualification Testing System Setup and Checkout TestProcedure -Completed."

54. Rolls-Royce Document 3 013 008 A, "Pre-Qualification Acceptance Testing Operability TestProcedure -Completed."

55. Rolls-Royce Document 3 012 997 A "Pre-Qualification Acceptance Testing Prudency TestProcedure -Completed."

56. Rolls-Royce Document 3 013 350 A, "Pre-Qualification Acceptance Testing Report."

Summary EQ Test Report 3 014 545C-NP

Impdm6 n° 8 303 090 F

Page 27

Page 28: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY * Rolls-Royce57. Rolls-Royce Document 3 022 953 A, "2012 Pre-Qualification Testing System Setup and

Checkout Test Procedure -Completed."58. Rolls-Royce Document 3 022 954 A, "2012 Pre-Qualification Acceptance Testing Operability

Test Procedure -Completed."

59. Rolls-Royce Document 3 022 955 A "2012 Pre-Qualification Acceptance Testing Prudency TestProcedure -Completed."

60. Rolls-Royce Document 3 020 950 A, "2012 Pre-Qualification Acceptance Testing Report."

61. Rolls-Royce Document 3 013 393 A, "SPINLINE 3 Nuclear Qualification Project, CompletedRadiation Exposure Withstand Test Procedure."

62. Rolls-Royce Document 3 013 462 A, "SPINLINE 3 Nuclear Qualification Project, Post-RadiationWithstand Testing Operability Test Procedure (Completed)."

63. Rolls-Royce Document 3 013 468 A, "SPINLINE 3 Nuclear Qualification Project, Post-RadiationWithstand Testing Prudency Test Procedure (Completed)."

64. Rolls-Royce Document 3 013 308 A, "Radiation Exposure Withstand Test Report."65. Rolls-Royce Document 3015 117 A, "SPINLINE 3 Nuclear Qualification Project, Radiation

Exposure Withstand Testing (Procedure 3 010 286 C completed)."

66. Rolls-Royce Document 3 015 115 A, "SPINLINE 3 Nuclear Qualification Project, OperabilityProcedure after Radiation Exposure Withstand Testing (Procedure 3 010 295 C completed)."

67. Rolls-Royce Document 3 015 116 A, "SPINLINE 3 Nuclear Qualification Project, PrudencyProcedure after Radiation Exposure Withstand Testing (Procedure 3 010 296 B completed)."

68. Rolls-Royce Document 3 018 588 A, "SPINLINE 3 Nuclear Qualification Project, RadiationExposure Withstand Test Report."

69. Wyle Laboratories Document No. T56766-2, "Test Report for Radiation Exposure of aSPINLINE 3 Qualification Test Specimen," Revision A (Rolls-Royce Document 3 023 443 A).

70. NTS Laboratories Document No. TP63560-12N-RAD, "Test Report for Radiation Exposure of theSPINLINE 3 Digital Safety I&C Platform Spare Parts for the Qualification Test Specimen,"Revision 1 (Rolls-Royce Document 3 018 635 A).

71. Rolls-Royce Document 3 013 309 A, "Environmental Test Report."72. Wyle Laboratories Document No. T56766-1, "Test Report for Environmental Testing of a

SPINLINE 3 Qualification Test Specimen," Revision A (Rolls-Royce Document 3 023 444 A).73. Rolls-Royce Document 3 015 118 A, "SPINLINE 3 Nuclear Qualification Project, Environmental

Testing (Procedure 3 010 287 C completed)."74. Rolls-Royce Document 3 018 370 A, "SPINLINE 3 Nuclear Qualification Project, Environmental

Testing System Setup & Checkout Testing (Procedure 3 010 294 C completed)."75. Rolls-Royce Document 3 018 270 A, "SPINLINE 3 Nuclear Qualification Project, High

Temperature and High Humidity Operability Testing (Procedure 3 010 295 C completed)."76. Rolls-Royce Document 3 018 271 A, "SPINLINE 3 Nuclear Qualification Project, High

Temperature and High Humidity Prudency Testing (Procedure 3 010 296 B completed)."77. Rolls-Royce Document 3 018 294 A, "SPINLINE 3 Nuclear Qualification Project, Low

Temperature Operability Testing (Procedure 3 010 295 C completed)."78. Rolls-Royce Document 3 018 295 A, "SPINLINE 3 Nuclear Qualification Project, Low Humidity

Operability Testing (Procedure 3 010 295 C completed)."79. Rolls-Royce Document 3 018 296 A, "SPINLINE 3 Nuclear Qualification Project, Ambient

Temperature and Ambient Humidity Operability Testing (Procedure 3 010 295 C completed)."80. Rolls-Royce Document 3 018 589 A, "SPINLINE 3 Nuclear Qualification Project, Environmental

Test Report."81. NTS Laboratories Document No. TR63560-12N-ENV, "Test Report for Environmental

Qualification of the SPINLINE 3 Digital Safety I&C Platform for the Qualification Test Specimen,"Revision 1 (Rolls-Royce Document 3 018 636 A).

82. Rolls-Royce Document 3 011 606 A, "Instruction for QTS mounting and setup."83. Rolls-Royce Document 3 018 430 A, "SPINLINE 3 Nuclear Qualification Project, Seismic Testing

- Phase 1 (Procedure 3 010 288 C completed)."84. Rolls-Royce Document 3 018 428 A, "SPINLINE 3 Nuclear Qualification Project, Seismic Testing

System Setup & Checkout Testing - Run 1 (Procedure 3 010 294 C completed)."

Summary EQ Test Report 3 014 545C-NP

Impdm6 n' 8 303 090 F

Page 28

Page 29: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARYRollsRoyce

85. Rolls-Royce Document 3 018 429 A, "SPINLINE 3 Nuclear Qualification Project, Seismic TestingSystem Setup & Checkout Testing - Run 2 (Procedure 3 010 294 C completed)."

86. Rolls-Royce Document 3 018 327 A, "SPINLINE 3 Nuclear Qualification Project, Post Seismic-Operability Testing (Procedure 3 010 295 C completed)."

87. Rolls-Royce Document 3 018 431 A, "SPINLINE 3 Nuclear Qualification Project, Post Seismic -Prudency Testing (Procedure 3 010 296 B completed)."

88. Rolls-Royce Document 3 018 586 A, "SPINLINE 3 Nuclear Qualification Project, SeismicTesting - Phase 2 (Procedure 3 010 288 C completed)"

89. Rolls-Royce Document 3 018 590 A, "SPINLINE 3 Nuclear Qualification Project, Seismic TestReport."

90. Rolls-Royce Document 3 022 984 A, "SPINLINE 3 Nuclear Qualification Project, Seismic TestingSystem Setup & Checkout Testing - HCAS Before 3.5 g."

91. Rolls-Royce Document 3 022 985 A, "SPINLINE 3 Nuclear Qualification Project, Seismic TestingSystem Setup & Checkout Testing - PU1 Before 7 g."

92. Rolls-Royce Document 3 022 956 A, "SPINLINE 3 Nuclear Qualification Project, Post Seismic -Operability Testing."

93. Rolls-Royce Document 3 022 957 A, "SPINLINE 3 Nuclear Qualification Project, Post Seismic -Prudency Testing."

94. Rolls-Royce Document 3 022 958 A, "SPINLINE 3 Nuclear Qualification Project, SeismicTesting."

95. Rolls-Royce Document 3 020 948 A, "2012 SPINLINE 3 Nuclear Qualification Project, SeismicTest Report."

96. NTS Laboratories Document No. TR63560-12N-SEI, "Test.Report for Seismic Qualification ofthe SPINLINE 3 Digital Safety I&C Platform for the Qualification Test Specimen," Revision 1(Rolls-Royce Document 3 018 637 A).

97. NTS Laboratories Document No. TR016813-13N-SEI, "Test Report for Seismic Qualification ofthe SPINLINE 3 Digital Safety I&C Platform for the Qualification Test Specimen," Revision 0(Rolls-Royce Document 3 023 630 A).

98. Rolls-Royce Document 3 018 580 A, "SPINLINE3 Nuclear Qualification Project, EMI-RFITesting System Setup & Checkout Testing (Procedure 3 010 294 C completed)."

99. Rolls-Royce Document 3 018 584 A, "SPINLINE 3 Nuclear Qualification Project, EMI-RFITesting (Procedure 3 010 289 A completed)."

100. Rolls-Royce Document 3 018 591 A, "SPINLINE 3 Nuclear Qualification Project, EMI-RFI TestReport."

101. Rolls-Royce Document 3 022 965 A, "SPINLINE 3 Nuclear Qualification Project, EMC TestingSystem Setup & Checkout Testing."

102. Rolls-Royce Document 3 022 966 A, "SPINLINE 3 Nuclear Qualification Project, EMC Testing."103. Rolls-Royce Document 3 022 967 A, "SPINLINE 3 Nuclear Qualification Project, Post EMC -

Operability Testing."104. Rolls-Royce Document 3 022 968 A, "SPINLINE 3 Nuclear Qualification Project, Post EMC -

Prudency Testing."105. Rolls-Royce Document 3 020 951 B, "2012 SPINLINE 3 Nuclear Qualification Project, EMI-RFI

Test Report."106. NTS Laboratories Document No. TR63560-12N-EMI, "Test Report for EMI/RFI Qualification of

the SPINLINE 3 Digital Safety I&C Platform for the Qualification Test Specimen," Revision 1(Rolls-Royce Document 3 018 642 A).

107. NTS Laboratories Document No. TR016813-13N-EMI, "Test Report for EMI/RFI Qualification ofthe SPINLINE 3 Digital Safety I&C Platform for the Qualification Test Specimen," Revision 0(Rolls-Royce Document 3 023 631 A).

108. Rolls-Royce Document 3 018 583 A, "SPINLINE 3 Nuclear Qualification Project, Electrical FastTransient Testing (Procedure 3 010 290 B completed)."

109. Rolls-Royce Document 3 018 592 A, "SPINLINE3 Nuclear Qualification Project, Electrical FastTransient Test Report."

110. Rolls-Royce Document 3 018 585 A, "SPINLINE 3 Nuclear Qualification Project, SurgeWithstand Testing (Procedure 3 010 291 A completed)."

111. Rolls-Royce Document 3 018 593 A, "SPINLINE 3 Nuclear Qualification Project, SurgeWithstand Test Report."

Summary EQ Test Report 3 014 545C-NP

Imprirm n* 8 303 090 F

Page 29

Page 30: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY jRolls-Royce112. Rolls-Royce Document 3 018 582 A, "SPINLINE 3 Nuclear Qualification Project, Electrostatic

Discharge Testing (Procedure 3 010 292 A completed)."113. Rolls-Royce Document 3 018 594 A, "SPINLINE 3 Nuclear Qualification Project, Electrostatic

Discharge Test Report."114. Rolls-Royce Document 3 018 641 A, "SPINLINE 3 Nuclear Qualification Project, Class 1E to

Non-lE Isolation Testing (Procedure 3 010 293 A completed)."115. Rolls-Royce Document 3 018 595 A, "SPINLINE 3 Nuclear Qualification Project, Class 1 E to

Non-IE Isolation Test Report."116. Rolls-Royce Document 3 018 328 A, "SPINLINE 3 Nuclear Qualification Project, Post EMI/RFI -

Operability Testing (Procedure 3 010 295 C completed)."117. Rolls-Royce Document 3 018 329 A, "SPINLINE 3 Nuclear Qualification Project, Post EMI/RFI -

Prudency Testing (Procedure 3 010 296 B completed)."118. Rolls-Royce Document 3 018 330 A, "SPINLINE 3 Nuclear Qualification Project, Performance

Proof Testing System Setup & Checkout Testing (Procedure 3 010 294 C completed)."119. Rolls-Royce Document 3 018 331 A, "SPINLINE 3 Nuclear Qualification Project, Proof Testing -

Operability Testing (Procedure 3 010 295 C completed)."120. Rolls-Royce Document 3 018 587 A, "SPINLINE 3 Nuclear Qualification Project, Proof Testing -

Prudency Testing (Procedure 3 010 296 B completed)."121. Rolls-Royce Document 3 018 596 A, "SPINLINE 3 Nuclear Qualification Project, Performance

Proof Test Report."122. Rolls-Royce Document 3 022 969 A, "SPINLINE 3 Nuclear Qualification Project, Performance

Proof Testing System Setup & Checkout Testing."123. Rolls-Royce Document 3 022 970 A, "SPINLINE 3 Nuclear Qualification Project, Proof Testing -

Operability Testing."124. Rolls-Royce Document 3 022 971 A, "SPINLINE 3 Nuclear Qualification Project, Proof Testing -

Prudency Testing."125. Rolls-Royce Document 3 020 949 A, "2012 SPINLINE 3 Nuclear Qualification Project,

Performance Proof Test Report."126. Rolls-Royce Document 3 018 630 A, "Investigations Results of 2011 NRC Qualification Tests."

127. Rolls-Royce Document 3 002 603 B, Regles de c~blage dans les 6quipements type SPINLINE

Summary EQ Test Report

Imprimd n* 8 303 090 F

3 014 545C-NP

Page 30

Page 31: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY "Rolls-Royce

Appendix A: Factory Acceptance Test Summary

A.1 Purpose

This test summary describes the FAT of the SPINLINE 3 QTS and Test System and presents the results ofthis test.

A.2 Objective

FAT was performed at the end of the manufacturing and assembly phase to demonstrate compliance of theSPINLINE 3 QTS and Test System with, "System Specification of the Qualification Test Specimen and DataAcquisition System".

A.3 Equipment Tested

The equipment tested were the SPINLINE3 QTS (hardware and software) and the Test System. The MCLidentifies the specific hardware and firmware items that are part of the QTS.

A.4 Sequence of Testing

The FAT is the first test performed on the QTS and Test System. The FAT was performed at the Rolls-Royce facilities in Grenoble, France.

A.5 Procedures

The applicable test procedures are "Factory Acceptance Test Procedure and Report" (References 20 and21), which include instructions and checklists for performing the following tests:

1. Perform the system startup testsa. Power startup of DAS hardware testb. Power startup of QTS hardware testc. Inputs / Outputs Addressing Tests (to confirm the correct interface between DAS and QTS

hardwired inputs / outputs)2. Perform FAT functional tests

a. Perform system setup and checkout testsb. Perform the Operability Test, including

i. Analog Input And Output Accuracy Testii. Response Time Test

iii. Discrete Input Operation Tests

Summary EQ Test ReportImprime n* 8 303 090 F

3 014 545C-NP

Page A-1

Page 32: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royceiv. Discrete Output Operation Testv. Timer Function Accuracy Test

vi. Failover Performance Testvii. Loss of Power Performance Test

viii. Power Interrupt Performance Testix. Power Quality Tolerance TestPerform the Prudency TestPerform environmental mode testPerform seismic mode testPerform hardware failure tests (from the normal state configuration, a hardware failure isgenerated manually. The verification of the correct detection and reporting is made via the HMIof the DAS)

C.

d.e.f.

A.6 Test Specimen Mounting

The SPINLINE3 QTS was mounted in open mounting frames for the FAT. The configuration of theSPINLINE 3 QTS components and interconnecting cabling was similar to the configuration if the hardwarewere installed in a cabinet. The QTS cooling fans were installed on the open mounting frames and providedcooling to the other SPINLINE 3 QTS components.

A.7 Service Conditions

1]

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page A-2

Page 33: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceA.8 Test Results

The test results are reported in the completed copy of the "Factory Acceptance Test Procedure and Report"(Reference 20) and are summarized below.[f

.]]

Summary EQ Test Reportlmprim n' 8 303 090 F

3 014 545C-NP

Page A-3

Page 34: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARYW Rol- yc~Rolls-Royce

Appendix B: Pre-Qualification Acceptance Test Summary

B.1 Purpose

This test summary describes the Pre-Qualification Acceptance Testing of the Rolls-Royce SPINLINE 3 QTSand presents the results of this test. Pre Qualification Acceptance Testing of the SPINLINE3 QTS wasperformed as part of qualification testing to demonstrate compliance with the applicable Pre-QualificationAcceptance Tests requirements of EPRI TR-107330, Section 5.2.

B.2 Objective

The Pre-Qualification Acceptance Testing was performed to demonstrate that the SPINLINE3 QTShardware and the TSAP operated as intended prior to start of qualification testing, and to provide baselineacceptance data for qualification testing implementation of the Operability and Prudency Tests. Section 5.2of EPRI TR-1 07330 provides guidance for implementation of Pre-Qualification Acceptance Testing.

B.3 Equipment Tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

B.4 Sequence of Testing

Pre-Qualification Acceptance Testing was performed after FAT of the SPINLINE 3 QTS and Test System,and prior to the start of the qualification testing. The Pre-Qualification Acceptance Testing was performed atthe Rolls-Royce facilities in Grenoble, France. The following describes the Pre-Qualification AcceptanceTesting sequence:

1. Perform the Pre-Qualification Acceptance Testing System Setup and Checkout Test.2. Perform Pre-Qualification Acceptance (baseline) Operability Testing.3. Perform Pre-Qualification Acceptance (baseline) Prudency Testing.4. Disassemble the SPINLINE 3 QTS and test system for transport to the qualification test facility.

The sequence of testing did not include Application Software Objects Acceptance (ASOA) Testing, as listedin Section 5.2.A of EPRI TR-107330. As described in LTR, Section 6.2.9, the generic SPINLINE 3 platformsoftware includes an application-oriented library of re-usable software components that has been subject toverification and validation and is available for use in developing future application software for SPINLINE 3plant-specific systems. The equipment qualification testing program was not intended to qualify applicationsoftware.

The sequence of testing did not include Burn-In Testing as listed in Section 5.2.F of EPRI TR-107330. TheRolls-Royce SPINLINE 3 platform manufacturing process includes routine burn-in of SPINLINE 3 platformhardware. This process is documented in Rolls-Royce manufacturing procedures. Manufacturing burn-in ofthe SPINLINE3 QTS hardware is considered sufficient to meet the intent of the EPRI TR-107330requirement to detect early life failures during Pre-Qualification Testing through performance of Burn-inTesting.

Summary EQ Test Report 3 014 545C-NPImprim6 n° 8 303 090 F

Page B-1

Page 35: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY Rolls-Royce

B.5 Procedures

The following procedures were used during Pre-Qualification Acceptance Testing:

a) System Setup and Checkout Test Procedure (Reference 22): Through this procedure, initialSPINLINE 3 QTS calibration was addressed and the correct operation of the SPINLINE 3 QTS andtest system was verified.

b) Operability Test Procedure (Reference 31): This procedure includes a series of tests defined inSection 5.3 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE3 platform. The PreQualificationTesting run of this procedure established baseline performance of the SPINLINE 3 QTSfor use in performance of the Operability Test Procedure throughout qualification testing.

c) Prudency Test Procedure (Reference 32): This procedure included a series of tests defined inSection 5.4 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE 3 platform. The Pre-Qualification Testing run of this procedure established baseline performance of the SPINLINE 3 QTSfor use in performance of the Prudency Test Procedure throughout qualification testing.

All procedures above include instructions and checklists for performing the Pre-Qualification AcceptanceTest as follows:

a. Perform system setup and checkout testsb. Perform the Operability Test, including

i. Analog Input And Output Accuracy Testii. Response Time Test

iii. Discrete Input Operation Testsiv. Discrete Output Operation Testv. Timer Function Accuracy Test

vi. Failover Performance Testvii. Loss of Power Performance Test

viii. Power Interrupt Performance Testix. Power Quality Tolerance Test

c. Perform the Prudency Test

B.6 Test Specimen Mounting

EPRI TR-107330 provides no requirements or guidance for mounting of the test specimen during PreQualification Acceptance Testing.

The SPINLINE3 2011 QTS was mounted in open mounting frame(s) for Pre-Qualification AcceptanceTesting. The configuration of the SPINLINE3 QTS components and interconnecting cabling is similar toexpected in-cabinet applications. The test specimen cooling fans were installed on the open mountingframes and operated in such a manner that they provided cooling to the other SPINLINE3 QTScomponents. For the SPINLINE3 2012 campaign, PU1 was mounted on tri-axial table for Pre-QualificationAcceptance Testing. The HCAS was mounted in an open mounting frame for the 2012 Pre-QualificationAcceptance Testing.

Summary EQ Test Report 3 014 545C-NPImpdim6 n' 8 303 090 F

Page B-2

Page 36: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

B.7 Service Conditions

LRolls-Royce

EPRI TR-107330 provides no requirements or guidance for operation of the test specimen during Pre-Qualification Acceptance Testing. During Pre-Qualification Acceptance Testing, the SPINLINE 3 QTS waspowered with the I/Os operating under control of the TSAP and the connected test system simulationdevices.[[

I]

EPRI TR-107330 provides no requirements or guidance for control of ambient conditions (temperature,pressure, and humidity) during Pre-Qualification Acceptance Testing. During Pre Qualification AcceptanceTesting, the test space conditions of temperature and humidity were maintained within the normal operatingrange of the SPINLINE 3 QTS.

EPRI TR-107330 provides no requirements or guidance for configuration of the test PLC power supplysources during Pre-Qualification Acceptance Testing. [

B.8 Test Levels

The test levels (supply power and I/O signal and load levels) applied to the SPINLINE 3 QTS during Pre-Qualification Acceptance Testing were set as specified in the System Setup and Checkout, Operability andPrudency Test procedures.

B.9 Performance Monitoring

Performance monitoring of the SPINLINE 3 QTS during Pre-Qualification Acceptance Testing were set asspecified in the System Setup and Checkout, Operability and Prudency Test procedures.

B.10Acceptance Criteria

Acceptance criteria for performance monitoring of the SPINLINE 3 QTS during Pre Qualification AcceptanceTesting were set as specified in the System Setup and Checkout, Operability and Prudency Test procedures.

B.11 Documentation

The following records were prepared by Rolls-Royce to document the results of Pre-Qualification AcceptanceTesting:

1. 2010 Pre-Qualification Testing System Setup and Checkout Test Procedure -Completed(Reference 53)

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page B-3

Page 37: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

IRolls-Royce2.

3.

4.

5.

6.

7.

8.

2010 Pre-Qualification Acceptance Testing Operability Test Procedure -Completed (Reference 54)2010 Pre-Qualification Acceptance Testing Prudency Test Procedure -Completed (Reference 55)2010 Pre-Qualification Acceptance Testing Report (Reference 56)

2012 Pre-Qualification Testing System Setup and Checkout Test Procedure -Completed(Reference 57)

2012 Pre-Qualification Acceptance Testing Operability Test Procedure -Completed (Reference 58)

2012 Pre-Qualification Acceptance Testing Prudency Test Procedure -Completed (Reference 59)2012 Pre-Qualification Acceptance Testing Report (Reference 60)

B.12Test Results

The test results are reported in the completed copies of the following procedures:

* the "System Setup and Checkout Test Procedure"

* the "Operability Test Procedure"

* the "Prudency Test Procedure"

The results are summarized below.[[

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page B-4

Page 38: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY ra _M M-)I IIIIIJAI

1mi Rolls-Royce=MM

Appendix C: Radiation Exposure Withstand Test Summary

CA1 Purpose

This test summary describes the Radiation Exposure Withstand Testing of the Rolls-Royce SPINLINE 3QTS. Radiation Exposure Withstand Testing of the QTS was performed as part of qualification testing todemonstrate compliance with'the applicable environmental requirements of EPRI TR-107330, Section 4.3.6.

C.2 Objective

The objective of Radiation Exposure Withstand Testing was to demonstrate the SPINLINE 3 QTS did notexperience failures or unacceptable degradation due to expected radiation exposure arising from normal andabnormal service conditions as required by RG 1.89 and IEEE 323-2003. Section 4.3.6 of EPRI TR-107330defines the normal and abnormal radiation exposure levels the test specimen must withstand (i.e., the testspecimen must continue to meet the manufacturer specified performance levels). [[]]

C.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

C.4 Sequence of Testing

As stated in Table 11-1, Radiation Exposure Withstand Testing was performed in two groups aftercompletion of the Pre-Qualification Testing Baseline Operability and Prudency Test runs. The QTS wasirradiated in one group and the spare parts were irradiated in a second group. The test for the first groupwas performed by Wyle at the Southwest Research Institute in San Antonio, Texas. The test for the secondgroup was performed by NTS at the University of Massachusetts Lowell Radiation Laboratory in Lowell,Massachusetts.

C.5 Procedures

The following procedure was used during Radiation Exposure Withstand Testing:

a) Radiation Exposure Withstand Test Procedure (Reference 23): Through this procedure, theSPINLINE 3 QTS was configured in the test chamber for irradiation, and the condition of theSPINLINE 3 QTS was determined on completion of testing.This procedure has been performed two times: one for SPINLINE 3 QTS components (Campaign2010) and another one for SPINLINE 3 QTS spare parts (Campaign 2011).

Summary EQ Test ReportImpdrme no 8 303 090 F

3 014 545C-NP

Page C-1

Page 39: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceC.6 Test Specimen Mounting

EPRI TR-107330 provides no requirements or guidance for mounting of the test specimen during RadiationExposure Withstand Testing.[[:

C.7 Service Conditions

EPRI TR-107330 provides no requirements or guidance for operation of the test specimen during RadiationExposure Withstand Testing.

I]EPRI TR-107330 provides no requirements or guidance for control of ambient conditions (temperature,pressure, and humidity) during Radiation Exposure Withstand Testing. [[

11

C.8 Test Levels

As stated in Section 4.1 of EPRI TR-107330, the normal and abnormal environmental radiation exposurelevels (1000 Rads) given in Section 4.3.6 of the TR are characteristic of "mild" plant operating environments(i.e., plant environments that are not exposed to harsh environmental conditions during design basis events).Section 6.3 (Table 6.6) of EPRI TR-100516 (Reference 37), provides a basis for the specified 1000 Rads

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page C-2

Page 40: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royceradiation exposure level. Section 6.3 further defines the 1000 Rads exposure as the gamma 40-year dosefrom normal/abnormal service (related to approximately 2.9 millirems per hour).

RG 1.209 identifies that one significant difference between digital and analog equipment is the radiationtolerance. The radiation exposure level (1000 Rads) as required in EPRI TR-107330 is compliant with thesensitivity of digital equipment as discussed in section B bf RG 1.209.IEEE Standard 323-2003 imposes an additional margin of 10% on the qualification test level.

[[]

C.9 Performance Monitoring

EPRI TR-107330 provides no requirements or guidance for performance monitoring of the test specimenduring Radiation Exposure Withstand Testing.

]] Also, theSPINLINE 3 QTS was visually inspected for exterior damage or degradation following Radiation ExposureWithstand Testing.

C.10Acceptance Criteria

The following Radiation Exposure Withstand Test acceptance criteria were based on Section 4.3.6 of EPRITR-107330.

a) The SPINLINE 3 QTS components and SPINLINE 3 QTS spare parts shall not exhibit any exteriordamage or degradation as a result of gamma radiation exposure based on visual examinationsperformed following Radiation Exposure Withstand Testing.

b) The SPINLINE 3 QTS shall meet all acceptance criteria of the Operability and Prudency Tests to beperformed following Radiation Exposure Withstand Testing. Subsequently, this criteria shall be metby all spare parts which are used to replace any SPINLINE 3 QTS components

C.1 I Documentation

The following records were prepared by Rolls-Royce to document the results of Radiation ExposureWithstand Testing:

Summary EQ Test ReportImpim6 n' 8 303 090 F

3 014 545C-NP

Page C-3

Page 41: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce1. Two completed Radiation Exposure Withstand Test Procedures (References 57 and 65): One filled

during the first campaign in 2010 (SPINLINE3 QTS components and additional components) andanother one for the second campaign in 2011 (SPINLINE 3 QTS spare parts)

2. Two completed Post Radiation Exposure Withstand Testing Operability Test Procedures(References 62 and 66): One was performed after subjecting SPINLINE3 QTS components andadditional components to the Radiation Exposure and another one was performed after subjectingSPINLINE 3 QTS spare parts to the Radiation Exposure.

3. Two completed Post Radiation Exposure Withstand Testing Prudency Test Procedures (References63 and 67): One was performed after subjecting SPINLINE3 QTS components and additionalcomponents to the Radiation Exposure and another one was performed after subjecting SPINLINE 3QTS spare parts to the Radiation Exposure.

4. Two Rolls-Royce Radiation Exposure Withstand Test Reports (References 64 and 68): One linked tothe campaign 2010 and another one linked to the campaign 2011.

The following records were prepared by the test laboratories to document the results of Radiation ExposureWithstand Testing:

1. Wyle Laboratories Document No. T56766-2, "Test Report for Radiation Exposure of a SPINLINE 3Qualification Test Specimen (QTS)," Revision A (Reference 69 for Campaign 2010)

2. NTS Laboratories Document No. TP63560-12N-RAD, "Test Report for Radiation Exposure of theSPINLINE 3 Digital Safety I&C Platform Spare Parts for the Qualification Test Specimen," Revision 1(Reference 70 for Campaign 2011)

C.12Test Results

The test results are reported in the completed copies of the following procedures (two copies for eachprocedure):

0

0

"System Setup and Checkout Test Procedure"

"Operability Test Procedure"

* "Prudency Test Procedure"The results are summarized below.

Summary EQ Test ReportImpftmC n* 8 303 090 F

3 014 545C-NP

Page C-4

Page 42: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

I .Rolls-Royce

C.13Resolution of Test Discrepancies

Summary EQ Test Report 3 014 545C-NPImpdm6 n' 8 303 090 F

Page C-5

Page 43: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

MRolls-Royce

I]The SPINLINE 3 equipment is considered to have passed the Radiation Exposure Withstand Testsuccessfully (either in Campaign 2010 or Campaign 2011).

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page C-6

Page 44: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

rRolls-Royce

Appendix D: Environmental Test Summary

D.1 Purpose

This test summary describes the Environmental Testing of the Rolls-Royce SPINLINE 3 QTS. EnvironmentalTesting of the SPINLINE 3 QTS was performed as part of qualification testing to demonstrate compliancewith the applicable environmental requirements of EPRI TR-107330, Sections 4.3.6 and 6.4.4.

D.2 Objective

The objective of Environmental Testing was to demonstrate the SPINLINE 3 QTS did not experience failuresdue to abnormal service conditions of temperature and humidity, as required by RG 1.89 and IEEE 323-2003, subject to enhancements and exceptions listed in Section C of RG 1.209. Section 4.3.6 of EPRI TR-107330 defines the recommended normal and abnormal temperature and humidity exposure levels the testspecimen must withstand (i.e., the test specimen must continue to meet the manufacturer specifiedperformance levels). [[ 1]]

D.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

D.4 Sequence of Testing

During the first SPINLINE 3 qualification campaign in 2010, environmental testing was performed at the Wylelaboratory in Huntsville, Alabama. This campaign was stopped before finishing the planned testing due toproblems at the test facility. All results from this testing were reported in References 71 and 72. Rolls-Roycemade the decision to re-perform the environmental testing at a different test facility.The SPINLINE 3 qualification campaign was restarted in 2011 at the NTS laboratories in Boxborough,Massachusetts. As shown in Table 11-1, Environmental Testing was performed after completion ofRadiation Exposure Withstand Testing and included performance of the post Radiation Exposure WithstandTesting Operability and Prudency Tests. Environmental Testing Operability and Prudency Testing wereperformed at the times identified in the Environmental Testing procedures.

D.5 Procedures

The following procedures were used during Environmental Testing:

Summary EQ Test Report"Impdmd n* 8 303 090 F

3 014 545C-NP

Page D-1

Page 45: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY* Rol- yc~Rolls-Royce

a) System Setup and Checkout Test Procedure (Reference 22): Through this procedure, theSPINLINE3 QTS was configured in the test chamber for Environmental Testing and the correctoperation of the SPINLINE 3 QTS and test system was verified.

b) Environmental Test Procedure (Reference 24): Through this procedure, the SPINLINE3 QTSreceived additional configuration in the test chamber for Environmental Testing. The performance ofthe SPINLINE 3 QTS was monitored throughout application of the Environmental Test conditions.

c) Operability Test Procedure (Reference 31): This procedure included a series of tests defined inSection 5.3 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications and with baseline performance for theSPINLINE 3 platform. The Post Radiation Exposure Withstand Testing run of this procedure wasperformed following completion of the Setup and Checkout Test procedure and prior to application ofthe Environmental Test conditions. This procedure was also performed at various times duringapplication of the Environmental Test conditions, as listed in Table 5-1 of EPRI TR-107330.

d) Prudency Test Procedure (Reference 32): This procedure included a series of tests defined inSection 5.4 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE 3 platform. The Post RadiationExposure Withstand Testing run of this procedure was performed following completion of the Setupand Checkout Test procedure and prior to application of the Environmental Test conditions. Thisprocedure was also performed one time during application of the Environmental Test conditions, aslisted in Table 5-1 of EPRI TR-107330.

D.6 Test Specimen Mounting

As required by EPRI TR-107330, Section 6.3.3.1, the test specimen was mounted on a simple structure thatdoes not enclose the test specimen chassis during Environmental Testing. No additional cooling fans shallbe included in the Environmental Test chamber other than those normally included with the SPINLINE3QTS.

The SPINLINE 3 QTS was installed in the environmental test chamber in accordance with the requirementsof EPRI TR-107330, Section 6.3.3.1. The SPINLINE 3 QTS includes cabinet cooling fans which would be apart of actual plant applications and therefore are subject to qualification testing. During environmentalqualification of the SPINLINE3 QTS, the cabinet cooling fans were installed on the SPINLINE 3 QTSmounting frame and operated in such a manner that they provided cooling of the other SPINLINE 3 QTScomponents. The cabinet cooling fans were powered from the output of the SPINLINE 3 QTS cabinet powersupply assembly.

EPRI TR-107330, Section 6.2.1.1 required that during Environmental Testing the test specimen modules bearranged to simulate the maximum expected temperature rise across the test specimen chassis for anyreasonable arrangement of the modules included for qualification. The SPINLINE3 QTS modules werearranged to meet the intent of this requirement.

The QTS and DAS arrangements during the environmental testing are shown in Figure D-1.

Summary EQ Test Report 3 014 545C-NPImpdm6 n° 8 303 090 F

Page D-2

Page 46: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

QTS inside the chamber - Cables from QTS to DAS DAS outside the chamber

Figure D-1: Equipment Arrangements During Environmental Testing

D.7 Service Conditions

As required by EPRI TR-107330, Section 6.3.3, the test specimen was powered with its TSAP operatingduring Environmental Testing, with one half of the discrete and relay outputs on and loaded to their ratedcurrent. In addition, all analog outputs were set to between one half and two thirds of full scale.

EPRI TR-107330, Section 6.3.3, required that Environmental Testing be performed with the power supplysources set to values that maximize heat dissipation in the test specimen. [[

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page D-3

Page 47: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

I]EPRI TR-107330, Section 6.2.1, required that additional resistive loads be placed on each test specimenmain power supply output so that nominal current draws at nominal power supply output voltages are equalto the power supply rating. Section 6.3.3.1 required that these additional resistive loads be placed in theEnvironmental Test chamber. [[

I]EPRI TR-107330, Section 6.2.1, required that additional resistive loads be placed on each test specimenloop power supply output so that nominal current draws at nominal power supply output voltages are equalto the power supply rating. Section 6.3.3.1 required that these additional resistive loads be placed in theEnvironmental Test chamber. [[

a

11Figure D-2: Equipment Layout in Environmental Test Chamber (NTS)

Summary EQ Test ReportImprime n' 8 303 090 F

3 014 545C-NP

Page D-4

Page 48: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

URolls-Royce

D.8 Test Levels

EPRI TR-107330, Section 4.3.6, required that the test specimen meet its performance requirements duringand following exposure to abnormal environmental conditions of 40'F (4.4'C) to 120'F (48.90C) and 10% to95% relative humidity (non-condensing). Figure 4-4 of EPRI TR-107330 shows a profile of temperature andhumidity versus time which can be used during Environmental Testing to demonstrate the environmentalwithstand requirements. The profile includes margin on maximum temperature to address potentialincreased temperature effects of in-cabinet installations. The Figure 4-4 minimum and maximum conditionsof temperature and humidity are 40'F (4.4°C) to 140'F (600C) and 5% to 90% relative humidity (non-condensing).

[[]

Figure D-3: Actual Test Conditions for Temperature and Humidity Versus Time.

Summary EQ Test Report 3 014 545C-NPImpdm& n' 8 303 090 F

Page D-5

Page 49: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceD.9 Performance Monitoring

EPRI TR-107330, Section 6.3.3.1, required that air temperature be monitored near the fan inlet if any testspecimen power supply contains fans, or at the bottom of each test specimen chassis, for test specimensthat use natural circulation cooling. [[

]]EPRI TR-1 07330, Section 4.3.6.3, required that the test specimen operate as intended during and followingexposure to the temperature and humidity profile given in Figure 4-4 of EPRI TR-107330. [[

D.10Acceptance Criteria

The following Environmental Test acceptance criteria were based on Section 4.3.6 of EPRI TR-107330.

a) The SPINLINE 3 QTS shall operate as intended during and after exposure to the Environmental Testconditions given in Section 0.8. Evaluation of normal operating performance data (inputs, outputs,and fault/diagnostic indicators) collected during testing shall demonstrate operation as intended.

b) The SPINLINE3 QTS shall meet the applicable acceptance criteria of the Operability Testsperformed during Environmental Testing.

c) The SPINLINE 3 QTS shall meet the applicable acceptance criteria of the Prudency Test performedduring Environmental Testing.

D.11 Documentation

The following records were prepared by Rolls-Royce to document the results of Environmental Testing:

1. Completed Environmental Testing Procedure (Reference 73)2. Completed Environmental Testing System Setup and Checkout Test Procedure (Reference 74)

3. Completed High Temperature, High Humidity Environmental Testing Operability Test Procedure(Reference 75)

4. Completed High Temperature, High Humidity Environmental Testing Prudency Test Procedure(Reference 76)

5. Completed Low Temperature Environmental Testing Operability Test Procedure (Reference 77)

6. Completed Low Humidity Environmental Testing Operability Test Procedure (Reference 78)7. Ambient Temperature, Ambient Humidity Environmental Testing Operability Test Procedure

(Reference 79)

8. Rolls-Royce Environmental Test Report (Reference 80)

The following records were prepared by NTS to document the results of Environmental Testing:

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page D-6

Page 50: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

1. Test Facility Environmental Test Report (Reference 81)

D.12Test Results

The test results are reported and summarized below:

Rolls-Royce

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page D-7

Page 51: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

1]

D.13Resolution of Test Discrepancies

Summary EQ Test ReportImprim6 n' 8 303 090 F

3 014 545C-NP

Page D-8

Page 52: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test ReportImpmdrn no 8 303 090 F

3 014 545C-NP

Page D-9

Page 53: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

S ummary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page D-10

Page 54: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test ReportImprimd n' 8 303 090 F

3 014 545C-NP

Page D-11

Page 55: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

The SPINLINE 3 equipment is considered to have passed the 2011 Environmental Tests successfully.

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page D-12

Page 56: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[Rolls-Royce

Appendix E: Seismic Test Summary

E.1 Purpose

This test summary describes the Seismic Testing of the Rolls-Royce SPINLINE 3 QTS. Seismic Testing ofthe SPINLINE3 QTS was performed as part of qualification testing to demonstrate compliance with RG1.100 and IEEE Standard 344-1987. It used guidance from EPRI TR-107330 which is compliant with theserequirements.

E.2 Objective

The objective of Seismic Testing was to demonstrate the suitability of the SPINLINE3 platform forqualification as a Category 1 seismic device based on seismic withstand testing performed on theSPINLINE3 QTS in accordance with RG 1.100 and IEEE 344-1987. Section 4.3.9 of EPRI TR-107330defines the recommended seismic test levels the test specimen is expected to withstand (i.e., the testspecimen must continue to meet the manufacturer specified performance levels). These tests establishedthe qualification envelope for SPINLINE 3 seismic withstand.

E.3 Equipment tested

The MCL documents the SPINLINE3 QTS hardware and firmware to be tested. The first configurationtested (Configuration 1) consisted of five subassemblies: PU2 rack, PU1 rack, HCAS, AIOTB, DITB. Thesecond configuration tested (Configuration 2) consisted of seven subassemblies: Power Supply racks PS1and PS2, Fan-Assembly, Power Supply-Assembly, Periodic Test-Assembly, ROTB type 1 and ROTB type 2.

E.4 Sequence of Testing

As shown in Table 11-1, the 2011 Seismic Testing was performed [[

I]

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page E-1

Page 57: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-RoyceStage 2 seismic testing was performed to complete the SSE testing performed on Configuration 1 (withoutthe HCAS subassembly). The following test sequence was performed: an OBE, a SSE, another OBE, andtwo SSEs. This testing was performed just before to the Performance Proof Testing. The PerformanceProof Testing served as the Post Seismic Testing Operability and Prudency Testing for the SSE testsequence for Configuration 1.

As shown in Table 11-1, the 2012 Seismic Testing was performed [[

The equipment layout for the seismic testing is shown in Figure E-1.

Figure E-1: Equipment Layout in Seismic Test Room

E.5 Procedures

The following procedures were used during Seismic Testing:

a) System Setup and Checkout Test Procedure (Reference 22): Through this procedure, theSPINLINE 3 QTS was configured on the test table for Seismic Testing, and the correct operation ofthe SPINLINE 3 QTS and test system was verified.

b) Seismic Test Procedure (Reference 25): Through this procedure, the SPINLINE 3 QTS wassubjected to resonance search testing and received additional configuration on the test table for

Summary EQ Test ReportImprim5 n° 8 303 090 F

3 014 545C-NP

Page E-2

Page 58: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY r Roll-RoycLL]Rolls-Royce

Seismic Testing. This procedure required monitoring the performance of the SPINLINE3 QTSthroughout application of the Seismic Test conditions.

c) Operability Test Procedure (Reference 31): This procedure included a series of tests defined inSection 5.3 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE 3 platform. This procedure wasperformed at the completion of Seismic Testing, as listed in Table 5-1 of EPRI TR-107330. [[

]]d) Prudency Test Procedure (Reference 32): This procedure included a series of tests defined in

Section 5.4 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE3 platform. Although notrequired by Table 5-1 of EPRI TR-107330, this procedure was performed at the completion ofSeismic Testing. [[

E.6 Test Specimen Mounting

As required by EPRI TR-107330, Section 6.3.4.1, the test specimen should be mounted on a structurewhose configuration meets the manufacturer's mounting requirements during Seismic Testing. The seismictests were performed with the test specimen mounting most susceptible to seismic vibrations. The mountingused manufacturer required hardware. All threaded fasteners used for mounting were tightened with a torquewrench and the torque values recorded.

The SPINLINE 3 QTS was mounted to the Seismic Test table in accordance with Rolls-Royce specifiedmounting instructions for seismic applications. The Seismic Test mounting simulated a typical 19" rack mountconfiguration using standard Rolls-Royce chassis mounting brackets and fastener hardware. Resonancesearch testing was performed to demonstrate that the simulated mounting configuration was stiff enough toensure that there were no resonances below 100 Hz. The first analysis of the 2011 NTS report indicates thatthe fixture had two resonance frequencies below 100 Hz (74 Hz side-to-side and 43 Hz front-to-back). The2012 fixture had no resonances below 100 Hz.

All mounting hardware fasteners were tightened using calibrated tightening torque devices, and torquevalues were recorded.

EPRI TR-107330, Section 6.2.1.1 requires that during Seismic Testing the test specimen modules andassociated cabling be arranged to cause a total stress on the chassis and its mounting hardware that isequal to the maximum that could result from any reasonable arrangement of the modules, cabling, and anyother devices included in the qualification program. Dummy weights were added.

The SPINLINE 3 QTS was configured, mounted, and equipped with dummy weight loadings as necessary tomeet these requirements within the confines of the manufacturer's instructions for configuration andmounting for seismic applications. The details about where the dummy loads were added are described inReference 82.

Several modules installed in the SPINLINE3 QTS main chassis were located as close together as thechassis design allows to demonstrate interaction effects during the Seismic Testing.

The equipment arrangement for the 2011 seismic test Configuration 1 is shown in Figure E-2.

Summary EQ Test Report 3 014 545C-NPImpdmt n° 8 303 090 F

Page E-3

Page 59: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

Part of QTS not mounted on the test fixture - Parts on the test fixture (Configuration 1)

Figure E-2: Equipment Arrangement for Seismic Test Configuration I

The modified test fixture used for the 2012 seismic tests is shown in Figure E-3.

Summary EQ Test ReportImpdm6 n* 8 303 090 F

3 014 545C-NP

Page E-4

Page 60: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

Figure E-3: Modified Test Fixture Used for 2012 Seismic Test

E.7 Service Conditions

As required by EPRI TR-107330, Section 6.3.4.2, the test specimen was powered with its TSAP operatingduring Seismic Testing, with one half of its solid-state discrete outputs ON and loaded to their rated current,one half of its relay outputs ON, and one half of its relay outputs OFF. In addition, one quarter of its relayoutputs transitioned from OFF to ON and one quarter transitioned from ON to OFF during the OBE and SSEtests.

1]]EPRI TR-107330, Section 6.3.4.2, requires that Seismic Testing be performed with the power sources to thetest specimen power supply modules set to operate at the following minimum AC and DC source voltagesand frequencies given in Section 4.6.1.1 of the EPRI TR:

a) Power supply modules fed from AC sources shall remain operable at a minimum source voltage of90 VAC and a minimum source frequency of 57 Hz.

Summary EQ Test Report 3 014 545C-NPImpdm6 n° 8 303 090 F

Page E-5

Page 61: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY * Rolls-Royce

b) Power supply modules fed from DC sources shall remain operable at a minimum source voltage of20.4 VDC.

I]EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each test specimenmain power supply output so that nominal current draws at nominal power supply output voltages are equalto the power supply rating. [[

1]EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each test specimenloop power supply output so that nominal current draws at nominal power supply output voltages are equalto the power supply rating. [[

E.8 Test Levels

EPRI TR-107330, Sections 4.3.9 and 6.3.4, required that the test specimen be seismically tested inaccordance with IEEE Standard 344. The testing included a resonance search followed by five simulatedOBEs to the level shown in.Figure 4 5 of EPRI TR-107330, and one simulated SSE to the level shown inFigure 4 5 of EPRI TR-107330. The test vibrations were applied triaxially (in three orthogonal directions), andwere random and multifrequency in content.

2011 Seismic TestsThe maximum SSE and OBE acceleration levels for the 2011 seismic tests shown in Figure 4-5 are 14 gmaximum 7 g ZPA and 9.75 g maximum /4.9 g ZPA respectively, based on 5% damping.

]] Figures E-4 through E-6 show the results for the OBE testing forConfiguration 1. Figures E-7 through E-9 show the results for SSE testing for Configuration 1. Figures E-10through E-12 show the results for the OBE testing for Configuration 2. Figures E-13 through E-15 show theresults for SSE testing for Configuration 2.

[II

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page E-6

Page 62: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImpdm6 n° 8 303 090 F

Page E-7

Page 63: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

jRolls-Royce

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page E-8

Page 64: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

j Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImprim6 n* 8 303 090 F

Page E-9

Page 65: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

WRolls-Royce

Summary EQ Test ReportImpdm& n° 8 303 090 F

3 014 545C-NP

Page E-IO

Page 66: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImpdmd n° 8 303 090 F

Page E-11

Page 67: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[Rolls-Royce

2012 Seismic Tests

The maximum SSE and OBE acceleration levels for the 2012 seismic tests are 14 g maximum / 7 g ZPA and7 g maximum / 3.5 g ZPA respectively, based on 5% damping.

[[

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page E-12

Page 68: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

]] Figures E-16 through E-21 show the results for the OBE testing for the OBEtesting. Figures E-22 through E-27 show the results for SSE testing at 4.9 g ZPA. Figures E-28 throughE-33 show the results for SSE testing at 7 g ZPA.

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page E-13

Page 69: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test ReportImpdm6 n* 8 303 090 F

3 014 545C-NP

Page E-14

Page 70: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test ReportImpdms n* 8 303 090 F

3 014 545C-NP

Page E-15

Page 71: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

* Rolls-Royce

Summary EQ Test ReportImpdrm6 no 8 303 090 F

3 014 545C-NP

Page E-16

Page 72: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

i

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page E-17

Page 73: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

MRolls-Royce

Summary EQ Test ReportImprime no 8 303 090 F

3 014 545C-NP

Page E-18

Page 74: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY j Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImprimd n* 8 303 090 F

Page E-19

Page 75: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test ReportImpdmL n° 8 303 090 F

3 014 545C-NP

Page E-20

Page 76: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

jRolls-Royce

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page E-21

Page 77: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY* Rol- yc10Rolls-Royce

E.9 Performance Monitoring

As required by EPRI TR-107330, Section 6.3.4.1, the test specimen should be mounted on a structurewhose configuration meets the manufacturer's mounting requirements during Seismic Testing. Resonancesearch testing was performed to demonstrate that the simulated mounting configuration was stiff enough toensure that there were no resonances below 100 Hz. The first analysis of the 2011 NTS report indicates thatthe fixture had two resonance frequencies below 100 Hz (74 Hz side-to-side and 43 Hz front-to-back). The2012 fixture had no resonances below 100 Hz.

As required by EPRI TR-107330, Section 6.3.4.2, the Seismic Test table was instrumented with a controlaccelerometer and that each chassis of the test specimen was instrumented with one or more responseaccelerometers located to establish maximum chassis accelerations.

]]EPRI TR-107330, Section 4.3.9, required that the test specimen operate as intended during and followingthe application of an SSE, all connections and parts remain intact and in place, and relay output contacts notchatter. Relay contact chatter is defined as a spurious change of state that exceeds 2 milliseconds induration.

I]Following each simulated OBE and SSE test, the SPINLINE3 QTS components mounted on the SeismicTest table were inspected for damage or degradation.

E.1OAcceptance Criteria

The following Seismic Test acceptance criteria were based on Section 4.3.9 of EPRI TR-107330.

a) The SPINLINE 3 QTS mounting fixtures shall be stiff enough so that there are no resonances below100 Hz detected during resonance search testing.

b) The SPINLINE 3 QTS shall operate as intended during and after application of the OBE and SSEvibrations given in Section E.8. Evaluation of normal operating performance data (inputs, outputs,and fault/diagnostic indicators) collected during testing shall demonstrate operation as intended.

c) During and after application of the OBE and SSE vibrations:

o All connections on the SPINLINE 3 QTS shall remain intact,

o All modules installed in the SPINLINE 3 QTS shall remain fully inserted,

o No functional or non-functional parts of the SPINLINE 3 QTS shall fall off.

d) During application of the OBE and SSE vibrations, the relay output module contacts shall bedemonstrated to change state from energized to de-energized and de-energized to energized inaccordance with execution of the TSAP.

e) During application of the OBE and SSE vibrations, any spurious change of state of the relay outputmodule contacts shall not exceed 2 milliseconds in duration for both energized and de-energizedcontact states.

Summary EQ Test Report 3 014 545C-NPImpdm6 n' 8 303 090 F

Page E-22

Page 78: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY Ro l- yc.o. Rolls-Royce

f) The SPINLINE 3 QTS shall meet the applicable acceptance criteria of the Operability Testsperformed on completion of Seismic Testing.

g) The SPINLINE 3 QTS shall meet the applicable acceptance criteria of the Prudency Test performedon completion of Seismic Testing.

E.11 Documentation

The following records have been prepared by Rolls-Royce to document the results of 2011 Seismic Testing:

1. Completed Seismic Testing Procedure for Stage 1 (Reference 83)2. Completed Seismic Testing Setup and Checkout Test Procedure for Configuration 1 (Reference 84)3. Completed Seismic Testing Setup and Checkout Test Procedure for Configuration 2 (Reference 85)4. Post Seismic Testing Operability Test Procedure for Stage 1 (Reference 86)5. Post Seismic Testing Prudency Test Procedure for Stage 1 (Reference 87)6. Completed Seismic Testing Procedure for Stage 2 (Reference 88)

7. Completed Performance Proof Testing Operability Test Procedure (Reference 119)8. Completed Performance Proof Testing Prudency Test Procedure (Reference 1209. Rolls-Royce Seismic Test Report (Reference 89)

The following records have been prepared by Rolls-Royce to document the results of 2012 Seismic Testing:

1. Completed Seismic Testing Setup and Checkout Test Procedure for HCAS before 3.5 g ZPATest(Reference 90)

2. Completed Seismic Testing Setup and Checkout Test Procedure for PU1 before 7 g ZPATest(Reference 91)

3. Post Seismic Testing Operability Test Procedure (Reference 92)

4. Post Seismic Testing Prudency Test Procedure (Reference 93)5. Completed Seismic Testing Procedure (Reference 94)

6. Rolls-Royce Seismic Test Report (Reference 95)

The following record was prepared by NTS to document the results of Seismic Testing:

1. 2011 Test Facility Seismic Test Report (Reference 96)

2. 2012 Test Facility Seismic Test Report (Reference 97)

E.12 Test Results

The test results are reported and summarized below:[r

Summary EQ Test Report 3 014 545C-NPImpdm6 n* 8 303 090 F

Page E-23

Page 79: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

Summary EQ Test ReportImprimd n° 8 303 090 F

3 014 545C-NP

Page E-24

Page 80: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

* Rolls-Royce

1]

E.13 Resolution of Test Discrepancies

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page E-25

Page 81: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

MRolls-Royce

Summary EQ Test Report 3 014 545C-NPImprim6 n* 8 303 090 F

Page E-26

Page 82: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY jRolls-Royce

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page E-27

Page 83: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

L Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImpdimi n* 8 303 090 F

Page E-28

Page 84: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[Rolls-Royce

Summary EQ Test ReportImprim6 n* 8 303 090 F

3 014 545C-NP

Page E-29

Page 85: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

* Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImpdm6 n' 8 303 090 F

Page E-30

Page 86: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Summary EQ Test ReportImprim6 n* 8 303 090 F

3 014 545C-NP

Page E-31

Page 87: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royce

Summary EQ Test Report 3 014 545C-NPImpdm6 n' 8 303 090 F

Page E-32

Page 88: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

0Rolls-Royce

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page E-33

Page 89: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[Rolls-Royce

]]Two subassemblies of the SPINLINE 3 equipment in Configuration 1 were successfully retested in the 2012test campaign.

The SPINLINE 3 equipment in Configuration 2 passed the Seismic Test. The SPINLINE 3 equipment inConfiguration 1 is considered to have passed the Seismic Test except for the following limitation:

•* [

Summary EQ Test ReportImpdmo n° 8 303 090 F

3 014 545C-NP

Page E-34

Page 90: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

* Rolls-Royce

Appendix F: EMI/RFI Test Summary

F.1 Purpose

This test summary describes the EMI/RFI Testing performed on the Rolls-Royce SPINLINE 3 QTS. EMI/RFITesting of the SPINLINE 3 QTS was performed as part of qualification testing to demonstrate compliance withthe applicable EMI/RFI emissions and susceptibility requirements of RG 1.180, Revision 1 and EPRI TR-107330.

F.2 Objective

The objective of EMI/RFI testing was to demonstrate the suitability of the SPINLINE 3 platform for qualificationas a safety-related device with respect to EMI/RFI emissions measurements and susceptibility test levels.EMI/RFI testing of the SPINLINE3 QTS was performed in accordance with RG 1.180, Revision 1, usingadditional guidance from EPRI TR-107330 as applicable. The specific EMI/RFI tests performed include:EMI/RFI Emissions Tests" MIL-STD-461E, CE1 01: Conducted Emissions, Low Frequency, AC and DC Power Leads" MIL-STD-461E, CE1 02: Conducted Emissions, High Frequency, AC and DC Power Leads" MIL-STD-461E, RE101: Radiated Emissions, Magnetic Field, QTS Surfaces and Leads* MIL-STD-461E, RE102: Radiated Emissions, Electric Field, Antenna MeasurementEMI/RFI Susceptibility TestsS

S

S

S

S

S

IEC 61000-4-6:IEC 61000-4-13:IEC 61000-4-16:IEC 61000-4-8:IEC 61000-4-9:IEC 61000-4-10:IEC 61000-4-3:MIL-STD-461 E:

1]

Conducted Susceptibility, Induced RF Fields, Power/Signal LeadsConducted Susceptibility, Harmonics/Interharmonics, Power LeadsConducted Susceptibility, Common Mode Disturbance, Power/Signal LeadsRadiated Susceptibility, Magnetic Field, Helmholtz Coil ExposureRadiated Susceptibility, Magnetic Field, PulsedRadiated Susceptibility, Magnetic Field, Damped OscillatoryRadiated Susceptibility, High Frequency, Antenna ExposureRS103, Radiated Susceptibility, High Frequency, Antenna Exposure (from [[

These tests established the qualification envelope for SPINLINE 3 EMI/RFI emissions and susceptibility.

Summary EQ Test ReportImprim6 n' 8 303 090 F

3 014 545C-NP

Page F-1

Page 91: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

1Rolls-RoyceF.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

F.4 Sequence of Testing

As shown in Table 11-1, 2011 EMI/RFI Testing was performed after completion of the ESD and EFT Testing andthe 2012 EMI/RFI Testing was performed after completion of the Seismic Test.

F.5 Procedures

The following procedures were used during EMI/RFI Testing:a) System Setup and Checkout Test Procedure (Reference 22): Through this procedure, the SPINLINE 3

QTS was configured in the EMI/RFI test chamber for EMI/RFI Testing, and the correct operation of theSPINLINE 3 QTS and test system was verified.

b) EMI/RFI Test Procedure (Reference 26): Through this procedure, the SPINLINE3 QTS receivedadditional configuration in the EMI/RFI test chamber for EMI/RFI Testing, and the performance of theSPINLINE 3 QTS was monitored throughout application of the EMI/RFI Test conditions.

c) Test Facility EMI/RFI Test Procedure: This procedure is prepared and implemented by the selectedqualification test facility. Through this procedure, the SPINLINE 3 QTS received additional configurationand instrumentation in the EMI/RFI test chamber for EMI/RFI Testing, and the specified EMI/RFI Testconditions were applied to the SPINLINE 3 QTS and monitored.

F.6 Test Specimen Mounting

EPRI TR-107330, Section 6.3.2.1 requires that the test specimen be mounted on a non-metallic vertical surfaceat a height of at least six feet to the bottom of the test specimen chassis, with no secondary enclosure. The testspecimen shall be connected to a ground bus located at the base of the mounting surface using themanufacturer's recommended grounding conductor. Grounding and shielding shall meet the requirements ofIEEE Standard 1050 (Reference 47) and EPRI TR-102323, Revision 1.The SPINLINE 3 OTS was installed in the EMI/RFI test chamber mounted in metal frame instrument cabinetswith all sides removed. Due to restraints imposed by the size of the SPINLINE 3 QTS, the requirement to mountthe test specimen six feet above the floor of the test chamber could not practicably be met. The test specimenmounting frames were mounted on non-conductive (i.e., wooden) supports approximately 4 inches above thefloor of the test chamber. This was done to prevent the EMI/RFI Test results from being affected by beneficialground paths that might exist through the test specimen mounting frames. [[

]]Grounding of the SPINLINE 3 QTS was in accordance with the manufacturer's recommendations. TheSPINLINE 3 QTS grounds were passed across the gap created by the mounting frame non-conductive supports

Summary EQ Test ReportImprim6 n' 8 303 090 F

3 014 545C-NP

Page F-2

Page 92: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

*Rolls-Royceand bonded to the EMI/RFI test chamber conductive floor. This grounding configuration met the applicable EPRITR-1 07330 requirements for grounding during EMI/RFI Testing.Emissions Tests (CE101, CE102, RE101 and RE102) and some Susceptibility Tests (IEC 61000-4-6, IEC61000-4-16, IEC 61000-4-3, and MIL-STD-461E RS103) were performed inside the EMC Chamber.The arrangement of the QTS in the EMC Test Chamber is shown in Figure F-1.

Figure F-I: Arrangement of QTS in EMC Test Chamber

F.7 Service Conditions

EPRI TR-107330 does not include specific requirements for operation of the test specimen during EMI/RFITesting. [[

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page F-3

Page 93: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

wRolls-Royce

I]Figure F-2: Approach to Cabling Through the Penetration Plate

]]EPRI TR-107330 provides no requirements or guidance for control of ambient conditions (temperature,pressure, and humidity) during EMI/RFI Testing. [[

]]

Summary EQ Test ReportImprim& no 8 303 090 F

3 014 545C-NP

Page F-4

Page 94: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-RoyceEPRI TR-107330 does not include specific requirements for configuration of the test specimen power suppliesduring EMI/RFI Testing. [[

]] EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each testspecimen main power supply output so that nominal current draws at nominal power supply output voltages areequal to the power supply rating. [[

]] Neither EPRI TR-107330 nor the industry EMI/RFI test standards used required therelay output points to be operating at rated currents during EMI/RFI Testing.EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each test specimen looppower supply output so that nominal current draws at nominal power supply output voltages are equal to thepower supply rating. [[

]] The equipment layout in the EMC test chamber is shown in Figure F-3.

11Figure F-3: Equipment Layout in the EMC Test Chamber

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page F-5

Page 95: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceF.8 Test Levels

EMI/RFI Testing of the SPINLINE 3 QTS were performed inside a shielded (anechoic or semi-anechoic) testchamber. The following table summarizes the specific EMI/RFI emissions and susceptibility testingaccomplished per RG 1.180, Revision 1, and the specified test levels (frequency ranges) to be used. Testacceptance criteria, including applied susceptibility test levels (dBmV, %V, Vrms, A/m, and V/m) are listed inSection F.10 of this Appendix).

Test Type Test Method Frequency Range

Conducted Emissions, Low Frequency, AC and DC MIL-STD-461E, [[ ]Power Leads CE101

Conducted Emissions, High Frequency, AC and DC MIL-STD-461E, [[ ]Power Leads CE102

Radiated Emissions, Magnetic Field, Surfaces and Leads MIL-STD-461E, [[ ]RE101

Radiated Emissions, Electric Field, Antenna MIL-STD-461E, [[ ]Measurement RE102

Conducted Susceptibility, Disturbances Induced by IEC 61000-4-6 [[ ]Radio-Frequency Fields

Conducted Susceptibility, Harmonics/Interharmonics, IEC 61000-4-13 [[Power Leads

Conducted Susceptibility., Common Mode Disturbances, IEC 61000-4-16 [[ ]Power/Signal Leads

Radiated Susceptibility, Magnetic Field, Helmholtz Coil IEC 61000-4-8 ]Exposure

Radiated Susceptibility, Magnetic Field, Pulsed IEC 61000-4-9 ]

Radiated Susceptibility, Magnetic Field, Damped IEC 61000-4-10 [[ ]]Oscillatory

Radiated Susceptibility, High Frequency, Antenna IEC 61000-4-3 [[ ]Exposure MIL-STD-461E, [[ ]

RS103

ri

F.9 Performance Monitoring

EPRI TR-107330, Section 4.3.7, requires that the test specimen under qualification withstand the appliedEMI/RFI susceptibility test levels.

Specifically, when subjected to the EMI/RFI test levels, the test specimen modules shall perform as follows:

Summary EQ Test ReportImprim6 n' 8 303 090 F

3 014 545C-NP

Page F-6

Page 96: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

CRolls-Roycea) The main processors and coprocessors shall continue to function.b) The transfer of I/O data shall not be interrupted.

c) The emissions shall not causethe discrete I/O to change state.d) Analog I/O levels shall not vary more than 3% (of full scale).

In addition, EPRI TR-107330 requires that a portion of the Operability and Prudency Tests be performed duringthe EMI/RFI testing.

F e C

F.1 0 Acceptance Criteria

Summary EQ Test Report 3 014 545C-NPImprime n' 8 303 090 F

Page F-7

Page 97: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY jRolls-Royce

11

F.11 Documentation

The following records were prepared by Rolls-Royce to document the results of EMI/RFI Testing:1. 2011 Completed EMI/RFI Testing Setup and Checkout Test Procedure (Reference 98)2. 2011 Completed EMI/RFI Testing Procedure (Reference 99)3. 2011 Rolls-Royce EMI/RFI Test Report (Reference 100)4. 2012 Completed EMC Testing Setup and Checkout Test Procedure (Reference 101)5. 2012 Completed EMC Testing Procedure (Reference 102)

6. 2012 Completed Post-EMC Operability Testing Procedure (Reference 103)7. 2012 Completed Post-EMC Prudency Testing Procedure (Reference 104)8. 2012 Rolls-Royce EMI/RFI Test Report (Reference 105)

Summary EQ Test ReportImprim6 n* 8 303 090 F

3 014 545C-NP

Page F-8

Page 98: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

* Rolls-RoyceThe following record was prepared by NTS to document the results of EMI/RFI Testing:

1. 2011 Test Facility EMI/RFI Test Report (Reference 106)2. 2012 Test Facility EMI/RFI Test Report (Reference 107)

F.12 Test Results

The test results are reported and summarized below:

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page F-9

Page 99: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[Rolls-Royce

11

F.13 Resolution of Test Discrepancies

Summary EQ Test ReportImprim6 no 8 303 090 F

3 014 545C-NP

Page F-10

Page 100: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page F-11

Page 101: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

* Rolls-Royce

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page F-12

Page 102: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

]]The SPINLINE 3 equipment is considered to have passed the EMI/RFI Test with the limitations noted above.

Summary EQ Test ReportImprim6 n' 8 303 090 F

3 014 545C-NP

Page F-13

Page 103: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

0Rolls-Royce

Appendix G: Electrical Fast Transient Test Summary

G.1 Purpose

This test summary describes the EFT Testing performed on the Rolls-Royce SPINLINE 3 QTS. EFT Testingof the SPINLINE3 QTS was performed as part of qualification testing to demonstrate compliance with theapplicable EFT susceptibility requirements of RG 1.180, Revision 1.

G.2 Objective

The objective of EFT testing was to demonstrate the suitability of the SPINLINE 3 platform for qualificationas a safety-related device with respect to EFT susceptibility levels. EFT testing of the SPINLINE 3 QTS wasperformed in accordance with RG 1.180, Revision 1, using additional guidance from EPRI TR-107330, asapplicable. The specific EFT test performed was IEC 61000-4-4, "Electromagnetic Compatibility (EMC), Part4-4: Testing and Measurement Techniques, Electrical Fast Transient/Burst Immunity Test". This testestablished the qualification envelope for SPINLINE 3 for EFT susceptibility.

G.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

G.4 Sequence of Testing

As shown in Table 11-1, EFT Testing was performed after completion of ESD Testing and uses the sameSPINLINE 3 QTS and test system setup as the EMI/RFI Testing. The EFT test was performed in the EMCchamber at the NTS facilities in Boxborough, Massachusetts.

G.5 Procedures

The following procedures were used during EFT Testing:

a) EFT Test Procedure (Reference 27): Through this procedure, the SPINLINE3 QTS receivedadditional configuration in the test chamber for EFT Testing, and the performance of the SPINLINE 3QTS was monitored throughout application of the EFT Test conditions.

b) Test Facility EFT Test Procedure: Through this procedure, the SPINLINE 3 QTS received additionalconfiguration and instrumentation in the test chamber for EFT Testing, and the specified EFT Testconditions were applied to the SPINLINE 3 QTS and monitored.

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page G-1

Page 104: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

ERolls-RoyceG.6 Test Specimen Mounting

EPRI TR-107330, Section 6.3.2.1 requires that during EMI/RFI testing the test specimen be mounted on anon-metallic vertical surface at a height of at least six feet to the bottom of the test specimen chassis, with nosecondary enclosure. The test specimen shall be connected to a ground bus located at the base of themounting surface using the manufacturer's recommended grounding conductor. Grounding and shieldingshall meet the requirements of IEEE Standard 1050 and EPRI TR-102323, Revision 1.

For EFT Testing, the SPINLINE3 QTS was installed in the EMI/RFI test chamber mounted in metal frameinstrument cabinets with all sides removed. Due to restraints imposed by the size of the SPINLINE 3 QTS,the requirement to mount the SPINLINE3 QTS six feet above the floor of the test chamber could notpracticably be met. The SPINLINE 3 QTS mounting frames were mounted on non-conductive (i.e., wooden)supports approximately 4 inches above the floor of the test chamber. This was done to prevent the EFT Testresults from being affected by beneficial ground paths that might exist through the SPINLINE 3 QTSmounting frames if the frames were placed directly on the floor of the EMI/RFI test chamber. [[

]]Grounding of the SPINLINE3 QTS was in accordance with the manufacturer's recommendations. TheSPINLINE 3 QTS grounds passed across the gap created by the mounting frame non-conductive supportsand bonded to the EMI/RFI test chamber floor. This grounding configuration met the applicable EPRI TR-107330 requirements for grounding during EMI/RFI Testing.

G.7 Service Conditions

EPRI TR-107330 does not include specific requirements for operation of the test specimen during EFTTesting. [[

]]EPRI TR-107330 provides no requirements or guidancepressure, and humidity) during EFT Testing. [[

for control of ambient conditions (temperature,

]]EPRI TR-107330 does not include specific requirements for configuration of the test specimen powersupplies during EFT Testing. [[

Summary EQ Test ReportImprim6 n' 8 303 090 F

3 014 545C-NP

Page G-2

Page 105: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

WRolls-Royce]] EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each test

specimen main power supply output so that nominal current draws at nominal power supply output voltagesare equal to the power supply rating. [[

]] Neither EPRI TR-107330 nor the industry EFT test standard usedrequire the relay output points to be operating at rated currents during EFT Testing.EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each test specimenloop power supply output so that nominal current draws at nominal power supply output voltages are equalto the power supply rating. [[

I]

G.8 Test Levels

Table 22 of RG 1.180, Revision 1 defines the IEC 61000-4-4 EFT withstand levels for the AC and DC powersupplies of safety related instrumentation installed in various plant locations. [[

]]Table 15 of RG 1.180, Revision 1 defines the IEC 61000-4-4 EFT withstand levels for the signal leads ofsafety related instrumentation installed in various plant locations. [[

G.9 Performance Monitoring

EPRI TR-107330, Section 4.3.7, discusses performance of the test specimen under qualification duringEMI/RFI Testing. This discussion was assumed to apply to EFT Testing as well. EPRI TR-107330, Section4.3.7, requires that the test specimen under qualification withstand the applied EMI/RFI susceptibility testlevels. Specifically, when subjected to the EMI/RFI test levels, the test specimen modules shall perform asfollows:

a) The main processors and coprocessors shall continue to function.

.b) The transfer of I/O data shall not be interrupted.

c) The emissions shall not cause the discrete I/O to change state.

d) Analog I/O levels shall not vary more than 3% (of full scale).In addition, the EPRI TR requires that a portion of the Operability and Prudency Tests be performed duringthe EMI/RFI testing.

Summary EQ Test ReportImprim6 n° 8 303 090 F

3 014 545C-NP

Page G-3

Page 106: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

[r

Rolls-Royce

11

G.10 Acceptance Criteria

Section 4.3.7 of EPRI TR-107330 discusses the acceptance criteria for EMI/RFI Testing of the test specimenunder qualification. Section 4.6.2 of EPRI TR-107330 discusses the acceptance criteria for Surge WithstandTesting of the test specimen under qualification. These discussions are assumed to apply to EFT Testing aswell.

The following EFT Test acceptance criteria were based on Sections 4.3.7 and 4.6.2 of EPRI TR-107330 andRG 1.180, Revision 1.

[[I

G.11 Documentation

The following records were prepared by Rolls-Royce to document the results of EFT Testing:1. Completed EFT Testing Procedure (Reference 107)

2. Rolls-Royce EFT Test Report (Reference 109)

Summary EQ Test ReportImpdmL n* 8 303 090 F

3 014 545C-NP

Page G-4

Page 107: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

The following record was prepared by NTS to document the results of EFT Testing:

1. Test Facility EFT Test Report (Reference 106)

G.12 Test Results

The test results are reported and summarized below:

1]

G.13 Resolution of Test Discrepancies

The SPINLINE 3 equipment is considered to have passed the EFT Test.

Summary EQ Test ReportImprimL n° 8 303 090 F

3 014 545C-NP

Page G-5

Page 108: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

Appendix H: Surge Withstand Test Summary

H.1 Purpose

This test summary describes the Surge Withstand Testing performed on the Rolls-Royce SPINLINE 3 QTS.Surge Withstand Testing of the SPINLINE3 QTS was performed as part of qualification testing todemonstrate compliance with the applicable Surge Withstand requirements of RG (RG) 1.180, Revision 1.

H.2 Objective

The objective of Surge Withstand Testing was to demonstrate the suitability of the SPINLINE 3 platform forqualification as a safety-related device with respect to Surge Withstand levels. The Surge Withstand testingof the SPINLINE3 QTS will be performed in accordance with RG 1.180, Revision 1, using additionalguidance from EPRI TR-107330, as applicable. The specific Surge Withstand Tests performed include:

" IEC 61000-4-5, "Electromagnetic Compatibility (EMC), Part 4-5: Testing and Measurement Techniques,Surge Immunity Test" and

* IEC 61000-4-12, "Electromagnetic Compatibility (EMC), Part 4-12: Testing and MeasurementTechniques, Oscillatory Waves Immunity Test".

This test established the qualification envelope for SPINLINE 3 Surge Withstand.

H.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

H.4 Sequence of Testing

As shown in Table 11-1, Surge Withstand Testing is performed after completion of EMI/RFI Testing and usesthe same SPINLINE 3 QTS and test system setup as the EMI/RFI Testing. The Surge Withstand Tests wereperformed at the NTS facilities in Boxborough, Massachusetts.

H.5 Procedures

The following procedures were used during Surge Withstand Testing:

a) Surge Withstand Test Procedure (Reference 28): Through this procedure, the SPINLINE3 QTSreceived additional configuration in the test chamber for Surge Withstand Testing, and theperformance of the SPINLINE 3 QTS was monitored throughout application of the Surge WithstandTest conditions.

Summary EQ Test ReportImpdm6 n* 8 303 090 F

3 014 545C-NP

Page H-1

Page 109: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

4Rolls-Royce

b) Test Facility Surge Withstand Test Procedure: This procedure was prepared and implemented byNTS (qualification test facility). Through this procedure, the SPINLINE3 QTS received additionalconfiguration and instrumentation in the test chamber for Surge Withstand Testing and the specifiedSurge Withstand Test conditions were applied to the SPINLINE 3 QTS and monitored.

H.6 Test Specimen Mounting

EPRI TR-107330, Section 6.3.5.1 requires that during Surge Withstand testing the test specimen bemounted on a non-metallic vertical surface at a height of at least six feet to the bottom of the test specimenchassis, with no secondary enclosure. The test specimen shall be connected to a ground bus located at thebase of the mounting surface using the manufacturer's recommended grounding conductor. Grounding andshielding shall meet the requirements of IEEE Standard 1050 and EPRI TR-102323, Revision 1.For Surge Withstand Testing, the SPINLINE 3 QTS was installed in the EMI/RFI test chamber mounted inmetal frame instrument cabinets with all sides removed. Due to restraints imposed by the size of theSPINLINE3 QTS, the requirement to mount the SPINLINE3 QTS six feet above the floor of the testchamber could not practicably be met. The SPINLINE3 QTS mounting frames were mounted on non-conductive (i.e., wooden) supports approximately 4 inches above the floor of the test chamber. This wasdone to prevent the Surge Withstand Test results from being affected by beneficial ground paths that mightexist through the SPINLINE 3 QTS mounting frames if the frames were placed directly on the floor of theEMI/RFI test chamber. [[

1]

Grounding of the SPINLINE 3 QTS was in accordance with the manufacturer's recommendations. TheSPINLINE 3 QTS grounds passed across the gap created by the mounting frame non-conductive supportsand bonded to the EMI/RFI test chamber floor. This grounding configuration met the applicable EPRI TR-107330 requirements for grounding during Surge Withstand Testing.

H.7 Service Conditions

EPRI TR-107330 does not include specific requirements for operation of the test specimen during SurgeWithstand Testing. [[

]]EPRI TR-107330 provides no requirements or guidance for control of ambient conditions (temperature,pressure, and humidity) during Surge Withstand Testing. [[

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page H-2

Page 110: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

]]EPRI TR-107330 does not include specific requirements for configuration of the test specimen powersupplies during Surge Withstand Testing. [[

]] EPRI TR-107330, Section 6.2.1, requires that additionalresistive loads be placed on each test specimen main power supply output so that nominal current draws atnominal power supply output voltages are equal to the power supply rating. [[

]] Neither EPRI TR-107330 nor the industry Surge Withstandtest standards used require the relay output points to be operating at rated currents during Surge WithstandTesting.

EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each test specimenloop power supply output so that nominal current draws at nominal power supply output voltages are equalto the power supply rating. [[

H.8 Test Levels

Table 22 of RG 1.180, Revision 1 defines the IEC 61000-4-12 Ring Wave and IEC 61000 4-5 CombinationWave surge withstand levels for the power supplies of safety related instrumentation installed in variousplant locations. [[

I]Table 15 of RG 1.180, Revision 1 defines the IEC 61000-4-12 Ring Wave and IEC 61000 4-5 CombinationWave surge withstand levels for the signal leads of safety related instrumentation installed in various plantlocations. [[

I]Section 5 of IEC 61000-4-5 states that all voltages of the lower tests levels shall be satisfied (i.e., the surgevoltage should be applied as a series of steps from a lower range value up to the maximum required testvalue). For equipment that contains surge protective devices, this approach can reveal "blind spots" in theequipment (applied surge test voltage levels where the protective devices perform less effectively than at

Summary EQ Test ReportImprim6 no 8 303 090 F

3 014 545C-NP

Page H-3

Page 111: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Roycehigher test voltage levels). [[

]]EPRI TR-107330, Section 4.3.4.3, Item E requires Surge Withstand Testing of any devices required forconnecting the main chassis to other types of chassis. [[

]]Section 6.3.5 of EPRI TR-107330 states that Surge Withstand Testing should be performed on a

representative sample of points for each type of I/O module. [[

H.9 Performance Monitoring

EPRI TR-107330, Section 4.6.2, requires that the test specimen under qualification continue to operatefollowing application of the Surge Withstand Test voltages.

Applying the specified level of surge to the specified points:

a) Shall not damage any other module or device in the test specimen.

b) Shall not cause a disruption of the specimen backplane signals that could result in a loss of theability to generate a trip.

c) Shall not cause a disruption of any other data acquisition signals that could result in a loss of theability to generate a trip.

During Surge Withstand Testing, NTS was responsible for generating and exposing the SPINLINE 3 QTS tothe required levels of surge voltages given in Tables 15 and 22 of RG 1.180, Revision 1. During SurgeWithstand Testing, Rolls-Royce was responsible for monitoring operation of the SPINLINE3 QTS anddetermining the SPINLINE 3 QTS surge withstand capability.

[[

Summary EQ Test ReportImpdmd n° 8 303 090 F

3 014 545C-NP

Page H-4

Page 112: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY j Rolls-RoyceH.1OAcceptance Criteria

The following Surge Withstand Test acceptance criteria were based on Section 4.6.2 of EPRI TR-107330and RG 1.180, Revision 1. [[

H.1 I Documentation

The following records were prepared by Rolls-Royce to document the results of Surge Withstand Testing:

1. Completed Surge Withstand Testing Procedure (Reference 110)

2. Rolls-Royce Surge Withstand Test Report (Reference 111)The following record was prepared by NTS to document the results of Surge Withstand Testing:

1. Test Facility Surge Withstand Test Report (Reference 106)

H.12Test Results

The test results are reported and summarized below:[[:

Summary EQ Test ReportImprimd n° 8 303 090 F

3 014 545C-NP

Page H-5

Page 113: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

0Rolls-RoyceH.13Resolution of Test Discrepancies

11

11The SPINLINE 3 equipment is considered to have passed the Surge Withstand Test.

Summary EQ Test ReportImpdm& n' 8 303 090 F

3 014 545C-NP

Page H-6

Page 114: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

IRolls-Royce

Appendix I: Electrostatic Discharge Test Summary

1.1 Purpose

This test summary describes the Electrostatic Discharge (ESD) Testing performed on the Rolls-RoyceSPINLINE 3 QTS. ESD Testing of the SPINLINE 3 QTS was performed as part of qualification testing todemonstrate compliance with the applicable ESD requirements of EPRI TR-107330, Section 4.3.8.

1.2 Objective

The objective of ESD testing was to demonstrate the suitability of the SPINLINE 3 platform for qualificationas a safety-related device with respect to ESD withstand levels. EPRI TR-107330, Section 4.3.8, requiresthat the test specimen under qualification be tested for ESD withstand capability in accordance with therequirements of EPRI TR-102323, Revision 1. In accordance with EPRI TR-102323, Revision 1, the specificESD Test to be performed is IEC 61000-4-2 "Electromagnetic Compatibility (EMC), Part 4-2: Testing andMeasurement Techniques, Electrostatic Discharge Immunity Test". This test will establish the qualificationenvelope for SPINLINE3 ESD withstand. RG 1.180, Revision 1 provides no guidance for ESD Testing.

1.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

1.4 Sequence of Testing

As shown in Table 11-1, ESD Testing was performed after completion of Seismic OBE Testing and uses thesame SPINLINE 3 QTS and test system setup as the EMI/RFI Testing. The ESD Testing was performed inthe EMC chamber at the NTS facilities in Boxborough, Massachusetts.

1.5 Procedures

The following procedures were used during ESD Testing:

a) Electrostatic Discharge Test Procedure (Reference 29): Through this procedure, the SPINLINE3QTS received additional configuration in the test chamber for ESD Testing, and the performance ofthe SPINLINE 3 QTS was monitored throughout application of the ESD Test conditions.

b) Test Facility Electrostatic Discharge Test Procedure: This procedure was prepared andimplemented by NTS (qualification test facility): Through this procedure, the SPINLINE3 QTSreceived additional configuration and instrumentation in the test chamber for ESD Testing and thespecified ESD Test conditions were applied to the SPINLINE 3 QTS and monitored.

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page I-1

Page 115: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce1.6 Test Specimen Mounting

EPRI TR-107330, Section 6.3.2.1 requires that during EMI/RFI testing the test specimen be mounted on anon-metallic vertical surface at a height of at least six feet to the bottom of the test specimen chassis, with nosecondary enclosure. The test specimen shall be connected to a ground bus located at the base of themounting surface using the manufacturer's recommended grounding conductor. Grounding and shieldingshall meet the requirements of IEEE Standard 1050 and EPRI TR-102323, Revision 1.For ESD Testing, the SPINLINE3 QTS was installed in the EMI/RFI test chamber mounted in metal frameinstrument cabinets with all sides removed. Due to restraints imposed by the size of the SPINLINE 3 QTS,the requirement to mount the SPINLINE3 QTS six feet above the floor of the test chamber could notpracticably be met. The SPINLINE 3 QTS mounting frames were mounted on non-conductive (i.e., wooden)supports approximately 4 inches above the floor of the test chamber. This was done to prevent the ESDTest results from being affected by beneficial ground paths that might exist through the test specimenmounting frames if the frames were placed directly on the floor of the EMI/RFI test chamber. [[

]]Grounding of the SPINLINE3 QTS was in accordance with the manufacturer's recommendations. TheSPINLINE3 QTS grounds were passed across the gap created by the mounting frame non-conductivesupports and bonded to the EMI/RFI test chamber floor. This grounding configuration met the applicableEPRI TR-107330 requirements for grounding during EMI/RFI Testing.

1.7 Service Conditions

EPRI TR-107330 does not include specific requirements for operation of the test specimen during ESDTesting. [[

]]EPRI TR-107330 provides no requirements or guidance forpressure, and humidity) during ESD Testing. [[

control of ambient conditions (temperature,

I]EPRI TR-107330 does not include specific requirements for configuration of the test specimen powersupplies during ESD Testing. [[

Summary EQ Test ReportImprim n° 8 303 090 F

3 014 545C-NP

Page 1-2

Page 116: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

. ]] EPRI TR-107330, Section 6.2.1, requires that additional resistive loads be placed on each testspecimen main power supply output so that nominal current draws at nominal power supply output voltagesare equal to the power supply rating. [[

1.8 Test Levels

Appendix B, Section 3.5 of EPRI TR-102323, Revision 1 recommends maximum ESD test levels of 15 kV forair discharges and 8 kV for contact discharges for safety-related instrumentation to be installed in a nuclearplant control room. These levels correspond to IEC 61000-4-2 Level 4 installations. Section 5 of IEC 61000-4-2 further requires that ESD testing of instrumentation at a specific test level also satisfy all lower levels.

[[]

1.9 Performance Monitoring

EPRI TR-107330, Section 4.3.8, requires that the test specimen under qualification continue to operatefollowing application of the ESD Test voltages. Applying the specified level of electrostatic discharges to thespecified points:

1. Shall not disrupt operation of the test specimen.2. Shall not cause a disruption of the test specimen backplane signals that could result in a loss of the

ability to generate a trip.3. Shall not cause a disruption of any other data acquisition signals that could result in a loss of the

ability to generate a trip.

Summary EQ Test ReportImpdmd n* 8 303 090 F

3 014 545C-NP

Page 1-3

Page 117: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

ERolls-Royce4. Shall not cause damage to or failure of any components of the test specimen. This criterion does

not apply to redundant components given that the test specimen continues to operate as intendedfollowing damage to or failure of a redundant component.

1.10 Acceptance Criteria

The following ESD Test acceptance criteria were based on Section 4.3.8 of EPRI TR-107330. [[

1.11 Documentation

The following records were prepared by Rolls-Royce to document the results of ESD Testing:

1. Completed Electrostatic Discharge Testing Procedure (Reference 112)2. Rolls-Royce Electrostatic Discharge Test Report (Reference 113)

The following record was prepared by NTS to document the results of ESD Testing:1. Test Facility Electrostatic Discharge Test Report (Reference 106)

Summary EQ Test ReportImpdm6 n* 8 303 090 F

3 014 545C-NP

Page 1-4

Page 118: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

MRolls-Royce1.12 Test Results

The test results are reported and summarized below:

1]

1.13 Resolution of Test Discrepancies

]]The SPINLINE 3 equipment is considered to have passed the ESD Test with the limitation noted above.

Summary EQ Test ReportImpdmd n' 8 303 090 F

3 014 545C-NP

Page 1-5

Page 119: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY *'Rolls-Royce

Appendix J: Class 1E to Non-lE Isolation Test Summary

J.1 Purpose

This test summary describes the Class 1E to Non-lE Isolation Testing performed on the Rolls-RoyceSPINLINE 3 QTS. Class 1 E to Non-i E Isolation Testing of the SPINLINE 3 QTS was performed as part ofqualification testing to demonstrate compliance with the applicable Class 1E to Non-lE Isolationrequirements of EPRI TR-107330, Section 6.3.6.

J.2 Objective

The objective of Class 1 E to Non-i E Isolation Testing was to demonstrate the suitability of the SPINLINE 3platform for qualification as a safety-related device with respect to providing electrical isolation at Non-iEfield connections, as required by IEEE 384. EPRI TR-107330, Section 6.3.6, requires that the test specimenunder qualification be tested for Class 1 E to Non-i E Isolation capability in accordance with the requirementsof EPRI TR-107330, Section 4.6.4. This test established the qualification envelope for SPINLINE 3 Class 1Eto Non-i E Isolation

J.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware that was tested.

J.4 Sequence of Testing

As shown in Table 11-1, Class 1E to Non-lE Isolation Testing was performed after completion of the lastEMI/RFI Test and used the same SPINLINE 3 QTS and test system setup as the Surge Withstand Testing.The Class 1 E to Non-1 E Isolation Testing was performed at the NTS facilities in Acton, Massachusetts.

The post EMI/RFI Operability and Prudency tests were added into the test sequence after the Class 1E toNon-1 E Isolation Testing when the decision was made to perform the Stage 2 Seismic Tests.

J.5 Procedures

The following procedures were used during Class 1 E to Non-1 E Isolation Testing:

a) Class 1E to Non-lE Isolation Test Procedure (Reference 30): Through this procedure, theSPINLINE3 QTS received additional configuration in the test chamber for Class 1E to Non-iEIsolation Testing, and the performance of the SPINLINE3 QTS was monitored throughoutapplication of the Class 1 E to Non-i E Isolation Test conditions.

b) Operability Test Procedure (Reference 31): This procedure included a series of tests defined inSection 5.3 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS in

Summary EQ Test ReportImpdm6 n° 8 303 090 F

3 014 545C-NP

Page J-1

Page 120: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY LW Rol-Royce~,]Rolls-oc

accordance with the manufacturer's specifications for the SPINLINE 3 platform. The PerformanceProof Testing run of this procedure demonstrated performance of the SPINLINE3 QTS at thecompletion of all hardware qualification testing.

c) Prudency Test Procedure (Reference 32): This procedure included a series of tests defined inSection 5.4 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE 3 platform. The PerformanceProof Testing run of this procedure demonstrated performance of the SPINLINE3 QTS at thecompletion of all hardware qualification testing.

d) Test Facility Class 1E to Non-lE Isolation Test Procedure: This procedure is prepared andimplemented by NTS. Through this procedure, the NTS Test Equipment was connected toSPINLINE3 QTS for Class 1E to Non-lE Isolation Testing, and the specified Class 1E to Non-lEIsolation Test conditions were applied to the SPINLINE 3 QTS and monitored.

This Test was performed outside the EMC Chamber.

J.6 Test Specimen Mounting

As required by EPRI TR-107330, Section 6.3.6, the Class 1E to Non-lE Isolation test specimen wasmounted on a non-metallic vertical surface at a height of at least six feet to the bottom of the test specimenchassis, with no secondary enclosure. The test specimen was connected to a ground bus located at thebase of the mounting surface using the manufacturer's recommended grounding conductor. Grounding andshielding met the requirements of IEEE Standard 1050 and EPRI TR-102323, Revision 1.

For Class 1E to Non-lE Isolation Testing, the SPINLINE 3 QTS was installed in the EMI/RFI test chambermounted in metal frame instrument cabinet(s) with all sides removed. Due to restraints imposed by the sizeof the SPINLINE 3 QTS, the requirement to mount the SPINLINE 3 QTS six feet above the floor of the testchamber could not practicably be met. The SPINLINE3 QTS mounting frames were mounted on non-conductive (i.e., wooden) supports approximately 4 inches above the floor of the test chamber. This wasdone to prevent the Class 1 E to Non-I E Isolation Test results from being affected by beneficial ground pathsthat might exist through the SPINLINE 3 QTS mounting frames if the frames were placed directly on the floorof the EMI/RFI test chamber. [[

I]Grounding of the SPINLINE 3 QTS was done in accordance with the manufacturer's recommendations. TheSPINLINE3 QTS grounds were passed across the gap created by the mounting frame non-conductivesupports and bonded to the EMI/RFI test chamber floor. This grounding configuration met the applicableEPRI TR-1 07330 requirements for grounding during Class 1 E to Non-1 E Isolation Testing.

J.7 Service Conditions

EPRI TR-107330 does not include specific requirements for operation of the test specimen during Class 1Eto Non-iE Isolation Testing. [[

Summary EQ Test Report 3 014 545C-NPImprime n* 8 303 090 F

Page J-2

Page 121: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

WRolls-Royce

EPRI TR-107330 provides no requirements or guidance for control of ambient conditions (temperature,pressure, and humidity) during Class 1E to Non-lE Isolation Testing. During Class 1E to Non-lE IsolationTesting, the test chamber conditions of temperature and humidity were maintained within the normaloperating range of the SPINLINE 3 QTS. The test chamber barometric pressure was allowed to assume thebarometric pressure conditions local to the test facility.

EPRI TR-107330 does not include specific requirements for configuration of the test specimen powersupplies during Class 1E to Non-lE Isolation Testing. [[

J.8 Test Levels

EPRI TR-107330, Section 4.6.4, specifies that Class 1E to Non-lE Isolation Testing of the test specimenunder qualification demonstrate that the isolation features conform to the instrumentation and controlrequirements for Class 1E to Non-lE connections given in IEEE Standard 384-1981

Section 7.2.2.1 of IEEE Standard 384 requires that:

a) The isolation device prevents shorts, grounds and open circuits on the Non-lE side from degradingunacceptably the operation of the circuits on the 1 E side and,

b) The isolation device prevents application of the maximum credible voltage on the Non-i E side fromdegrading unacceptably the operation of the circuits on the 1 E side.

Summary EQ Test ReportImprimd n* 8 303 090 F

3 014 545C-NP

Page J-3

Page 122: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

LRolls-Royce

EPRI TR-107330, Section 4.6.4, requires that the test specimen modules under qualification provideelectrical isolation capability of at least 600 VAC and 250 VDC applied for 30 seconds. Per Section 7.2.2.1of IEEE Standard 384, the highest voltage to which an isolation device Non 1E side is exposed determinedthe minimum voltage level that the device must withstand across the Non-i E side terminals and between theNon-lE terminals and ground. [[

J.9 Performance Monitoring

Per EPRI TR-107330, Section 4.6.4, applying the specified levels of Class 1E to Non-lE Isolation Testvoltage to relay output module points shall not disrupt the operation of any other modules in the testspecimen, or cause disruption of the test specimen backplane signals. Per EPRI TR-107330, Section 4.6.4,applying the specified levels of Class 1E to Non-lE Isolation Test voltage to analog output module pointsshall not cause more than a 5% change to any other channel on the module, disrupt the operation of anyother modules in the test specimen, or cause disruption of the test specimen backplane signals

[[

Summary EQ Test ReportImprim6 no 8 303 090 F

3 014 545C-NP

Page J-4

Page 123: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

11

J.10 Acceptance Criteria

The following Class I1E to Non-l E Isolation Test acceptance criteria were based on Section 4.6.4 of EPRITR-107330. [[

I]

J.11 Documentation

The following records were prepared by Rolls-Royce to document the results of Class 1 E to Non-1 E IsolationTesting:

1. Completed Class 1E to Non-iE Isolation Testing Procedure (Reference 114)

2. Rolls-Royce Class 1E to Non-iE Isolation Test Report (Reference 115)

3. Completed Post EMI/RFI Operability Test Procedure (Reference 116)

4. Completed Post EMI/RFI Prudency Test Procedure (Reference 117)

The following record was prepared by NTS to document the results of Class 1 E to Non-1 E Isolation Testing:

1. Test Facility Class 1E to Non-lE Isolation Test Report (Reference 106)

Summary EQ Test ReportImpim6 n° 8 303 090 F

3 014 545C-NP

Page J-5

Page 124: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceJ.12 Test Results

The test results are reported and summarized below:

1]

J.13 Resolution of Test Discrepancies

1]The SPINLINE 3 equipment is considered to have passed the Class 1 E to Non-1 E Isolation Test.

Summary EQ Test ReportImprimd n* 8 303 090 F

3 014 545C-NP

Page J-6

Page 125: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

Appendix K: Performance Proof Test Summary

K.1 Purpose

This test summary describes the Performance Proof Testing that was performed on the Rolls-RoyceSPINLINE 3 QTS. Performance Proof Testing of the SPINLINE3 QTS was performed as part ofqualification testing to meet the intent of the applicable requirements of EPRI TR-1 07330, Section 5.5.

K.2 Objective

The objective of Performance Proof Testing was to demonstrate the continuing acceptable operation andperformance of the SPINLINE3 QTS following completion of all hardware qualification testing. EPRI TR-107330, Section 5.5 requires a final performance of the Operability Test procedure on completion ofElectrostatic Discharge Testing. As an alternative to this requirement, Performance Proof Testing included afinal performance of both the Operability and Prudency Test procedures following completion of all hardwarequalification testing, and comparison of the test results to the results for all previous performances of theOperability and Prudency Test procedures.

K.3 Equipment tested

The MCL documents the SPINLINE 3 QTS hardware and firmware to be tested.

K.4 Sequence of Testing

The Performance Proof Testing sequence was:* Perform system setup and checkout tests* Perform the Operability Test, including

o Analog Input And Output Accuracy Testo Response Time Testo Discrete Input Operation Testso Discrete Output Operation Testo Timer Function Accuracy Testo Failover Performance Testo Loss of Power Performance Testo Power Interrupt Performance Testo Power Quality Tolerance Test

* Perform the Prudency Test

The 2011 Performance Proof Testing was performed after completion of Seismic SSE Testing (Configuration1 Stage 2) at the NTS facilities in Acton, Massachusetts. The 2012 Performance Proof Testing wasperformed after completion of EMC Testing at the NTS facilities in Boxborough, Massachusetts.

Summary EQ Test ReportImprim6 n* 8 303 090 F

3 014 545C-NP

Page K-I

Page 126: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceK.5 Procedures

The following procedures were used during Performance Proof Testing:

a) System Setup and Checkout Test Procedure (Reference 22): Through this procedure, theSPINLINE 3 QTS was configured for Performance Proof Testing, and the correct operation of theSPINLINE 3 QTS and test system was verified.

b) Operability Test Procedure (Reference 31): This procedure included a series of tests defined inSection 5.3 of EPRI TR-107330 that verified acceptable performance of the SPINLINE3 QTS inaccordance with the manufacturer's specifications for the SPINLINE 3 platform. The PerformanceProof Testing run of this procedure demonstrated performance of the SPINLINE3 QTS at thecompletion of all hardware qualification testing.

c) Prudency Test Procedure (Reference 32): This procedure included a series of tests defined inSection 5.4 of EPRI TR-1 07330 that verified acceptable performance of the SPINLINE 3 QTS inaccordance with the manufacturer's specifications for the SPINLINE 3 platform. The PerformanceProof Testing run of this procedure demonstrated performance of the SPINLINE 3 QTS at thecompletion of all hardware qualification testing.

K.6 Test Specimen Mounting

EPRI TR-107330 provides no requirements or guidance for mounting of the test specimen duringPerformance Proof Testing. The SPINLINE 3 QTS was mounted in open mounting frame(s) for PerformanceProof Testing. The configuration of the SPINLINE 3 QTS components and interconnecting cabling wassimilar to expected in-cabinet applications. The SPINLINE 3 QTS cooling fans were installed on the openmounting frame(s) and operated to provide cooling of the other SPINLINE 3 QTS components.

K.7 Service Conditions

EPRI TR-107330 provides no requirements or guidance for operation of the test specimen duringPerformance Proof Testing. [[

]]EPRI TR-107330 provides no requirements or guidance for control of ambient conditions (temperature,pressure, and humidity) during Performance Proof Testing. [[

I]EPRI TR-107330 provides no requirements or guidance for configuration of the test specimen power supplysources during Performance Proof Testing. [[

Summary EQ Test Report 3 014 545C-NPImpdmd n' 8 303 090 F

Page K-2

Page 127: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-RoyceK.8 Test Levels

The test levels (supply power, input signals, output signals and loads) applied to the SPINLINE 3 QTS duringPerformance Proof Testing were as specified in the System Setup and Checkout, Operability and PrudencyTest procedures.

K.9 Performance Monitoring

Performance monitoring of the SPINLINE3 OTS during Performance Proof Testing was performed asspecified in the System Setup and Checkout, Operability and Prudiency Test procedures.

K.10Acceptance Criteria

Acceptance criteria for performance monitoring of the SPINLINE 3 QTS during Performance Proof Testingwill be as specified in the System Setup and Checkout, Operability and Prudency Test procedures. Inaddition, comparison of the Performance Proof Testing Operability and Prudency Test data to all otherOperability and Prudency test data shall not indicate an unacceptable change in performance of theSPINLINE 3 QTS hardware.

K.11I Documentation

I The following records were prepared by Rolls-Royce to document the results of 2011 Performance ProofTesting:

7. Completed Performance Proof Testing System Setup and Checkout Test Procedure (Reference118)

8. Completed Performance Proof Testing Operability Test Procedure (Reference 119)

9. Completed Performance Proof Testing Prudency Test Procedure (Reference 102)

10. Performance Proof Testing Report (Reference 121)

The following records were prepared by Rolls-Royce to document the results of 2012 Performance ProofTesting:

1. Completed Performance Proof Testing System Setup and Checkout Test Procedure (Reference122)

2. Completed Performance Proof Testing Operability Test Procedure (Reference 123)

3. Completed Performance Proof Testing Prudency Test Procedure (Reference 124)

4. Performance Proof Testing Report (Reference 125)

K.12Test Results

The test results are reported and summarized below:

Summary EQ Test ReportImprim• n° 8 303 090 F

3 014 545C-NP

Page K-3

Page 128: Document 3 014 545C-NP, Summary Equipment ...NON-PROPRIETARY PSI PTVAS Pul PU2 QA QTS Rad RFI RG RH RTD RMS RO Rolls-Royce ROTB RRS SER SIN SSE Temp TP/FL TR TSAP UC25 N+ VI V ZPA

NON-PROPRIETARY

Rolls-Royce

1]

K.13 Resolution of Test Discrepancies

11The SPINLINE 3 equipment is considered to have passed the Performance Proof Test.

Summary EQ Test ReportImpdm6 n' 8 303 090 F

3 014 545C-NP

Page K-4