Document #9C.1

Board of Library Trustees MeetingSeptember 25, 2013

The District of Columbia Public Library

Capital Construction and FacilitiesManagement Report

September 25, 2013

Active Capital Projects Report

Completed Projects

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 2/12

2

Active Capital Projects

Northeast Library  – Design-Build Renovations Contacts Progress

Councilmember Tommy Wells

Design work is complete

Contract approved by DC Council

Selective demolition work is complete

Vertical Circulation Addition Steel Work 

Complete

Addition is complete

Interior finish work is underway

Ward 6 202.724.8072

ArchitectBell/Vines

Architects

David Bell

Victor Vines

Project

Manager Chris Wright

202.727.4913

Design-Builder Whiting-Turner 

Andrew Easter 

West End Library – Mixed Use Development  Contacts Progress

Councilmember Jack Evans

New ground floor library will be part of mixed use

development

Library designs have been approved

Project has received preliminary PUD approval

from DC Zoning Commission on February 13,

2012

Litigation against project was dismissed 

Ward 2 202.724.8058

Architect Ten Arquitectos

Erik Lang

Project

Manager Kim Fuller 

202.442.6069

Developer EastBanc

Gareth Eckmann

202.737.1000

This project is a major interior renovation of the 1930’s era

library. Renovations will create a 21st

Century library while

maintaining the historic integrity of the building’s interior.

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 3/12

3

West End Interim Library  Contacts Progress

Councilmember Jack Evans

DC Department of General Services (DGS) is in

lease negotiations on a potential storefront space

Library’s design-build team has completed the

design for the interim space

Lease has been executed.

Permitting process is underway 

Ward 2 202.724.8058

Architect Franck and Lohsen

Art Lohsen

Project

Manager Chris Wright

202.727.4792

Contractor GCS/Sigal

Taryn Morgan

202-944-6634

Woodridge Library  – Design Contacts Progress

Councilmember Kenyen McDuffie

CFA approved conceptual plan

Mentor-Protégé Construction Manager selected:

Coakley-Williams and Blue Skye

GMP pricing proposal received & negotiated

Contract package for Board approval underway

Ward 5 (202) 724-8028

Architect Wiencek + Assoc

Bing Thom Arch

Project

Manager Kim Fuller 

202.442.6069

Contractor Coakley-Williams

Terrance Caulfield

301.693.5000

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 4/12

4

Woodridge Modular Interim Library  Contacts Progress

Councilmember Kenyen McDuffie

Modular Units will be utilized at 1790 Douglass

Avenue NE (District controlled parcel)

MOU signed between Library and DGS

Modular building is in manufacturing

Targeting a late Fall opening. 

Ward 5 (202) 724-8028

Architect GDG

Mokhless Alhariri

202.857.0060Project

Manager Chris Wright

202.727.4913

Contractor Modular Genius

Gregg Bichell

410.676.3424

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 5/12

5

Completed Capital ProjectsAnacostia Library – New Building Construction Contacts Progress

Councilmember 

Opened to the public - April 26, 2010 

Ward 7 YvetteAlexander 

202.724.8068

Architect Freelon Group

Philip Freelon919.941.9790

Project

Manager Dedric Boyd

202.727.1127

Contractor Forrester 

Construction

Tom Willerton

301.816.1700

DCPL PM

Firm Hill International

Benning Library – New Building Design Contacts Progress

Councilmember 

Opened to the public - April 5, 2010 

Ward 7 YvetteAlexander 

202.724.8068

ArchitectDavis, Brody,

Bond &Aedas

Peter Cook 

202.449.1190

Project

Manager Kim Fuller 

202.442.6069

Contractor Forrester 

Jon McGee

301.255.1750

DCPL PM

FirmA-1 Consulting

 New State of the Art Library on Good Hope Road SE is open.

 New State of the Art Library located at 3935 Benning Road NE

is open.

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 6/12

6

William O. Lockridge Bellevue Library Contacts Progress

Councilmember 

Library opened – June 13, 2012

Ward 8 Marion Barry

202.724.8045

Architect Wiencek/Adjaye

Scott Knudson

301.948.6220

Project

Manager Lisa Deanes

202.727.5181

Contractor  Coakley-Williams

DCPL PM

Firm

Jair Lynch

Development

Partners

ClevelandPark  –   New Ceiling and Lighting Contacts Progress

Councilmember 

Project complete

Ward 3 Mary Cheh

202.724.8062

Architect  N/A

Project

Manager Ed Hampton

202.442.6067

Contractor Eagle

Construction

Project consists of installing a new ceiling and lighting system.

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 7/12

7

The Library has received Federal Stimulus Money for energy

enhancements. Projects will take place at the above locations,

focusing on window replacements, energy efficient lighting,

and automated building heating and cooling controls

Deanwood – New Community Center and Library Contacts Progress

Councilmember 

Opened to the public on June 25, 2010  

Ward 7 YvetteAlexander 

202.724.8068

Architect EEK 

Sean O’Donnell 

Project

Manager 

Contractor 

Energy Enhancement Projects – Various Locations  Contacts Progress

Capitol View, Cleveland Park,

Shepherd Park, Lamond Riggs, Palisades, Southwest, West

End and Woodridge 

Councilmember 

Energy efficient lighting projects are completed

Window and roof work is completed 

Various

Architect T.B.D

Project

Manager Ed Hampton

202.442.6067

Contractor 

DCPL PM

Firm

Project is a partnership with the Department of Parks and

Recreation to co-locate a 10,000 square foot library within a

54,000 square foot aquatic center and community center.

Library and Community Center would share such space as

computer lab, senior rooms, tutor rooms and community

meeting rooms. Project location is 49

th

and Quarles St. NE 

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 8/12

8

Francis A. Gregory Library – New Library Contacts Progress

Councilmember 

Library opened – June 19, 2012

Ward 7 YvetteAlexander 

202.724.8068

Architect Wiencek/Adjaye

Scott Knudson

301.948.6220

Project

Manager Lisa Deanes

202.727.5181

Contractor Hess Construction

Jair Lynch

Development

PartnersDCPL PM

Firm

Georgetown Library –  Building Renovation Contacts Progress

Councilmember 

Opened to the public on October 18, 2010 

Ward 2 Jack Evans

202.724.8058

Architect Martinez & Johnson

Tom Johnson

202.333.4480

ProjectManager 

Chris Wright

202.272.4913

Contractor N/A

DCPL PM

Firm

Smoot

Construction

Renovation complete and Library open to the public.

Design of the new Francis Gregory Library will include

community input on planning and programming phase. Project

is fully funded.

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 9/12

9

MLK Jr. Library  –  Renovations to Great Hall & Digital Commons  Contacts Progress

Councilmember 

Complete.

Opened to the public on July 17, 2013

Ward 2 Jack Evans

202.724.8058

Architect The Freelon Group

Derek Jones

919-941-9790

Project

Manager Kim Fuller 

202-442-6069

Contractor MCN Build

Joseph Kourney

202.333.3424

Mount Pleasant  –  Interior Restoration Contacts Progress

Councilmember Jim Graham

Opened to public on September 12, 2012

Ward 1 202.724.8181

Architect Core Architects

Dale Stewart

202.466.6116

ProjectManager 

Chris Wright

202.727.4913

Contractor T.B.D

DCPL Project

Management

Smoot

Construction

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 10/12

10

Northeast Library  –  Exterior Restoration Contacts Progress

Councilmember Tommy Wells

Substantial completion of construction on May 15,

2010 

Ward 6 202.724.8072

Architect Bell Architects

David Bell

202.548.7570

Project

Manager Chris Wright

202.727.4913

Contractor Monarc

Construction

C. McDermott,

703.201.1747

Northwest One  –   New Co-location Facility  Contacts Progress

Councilmember Tommy Wells

Library openedon December 7, 2009 to the public

Ward 6

Architect HordCort Plan

ProjectManager 

Reagan Assoc

Contractor Forrester 

Project consists of Exterior Improvements to windows,

doors, security lighting, masonry restoration, landscaping

and signage.

Project consists of 6,500 SQ FT Library facility as part of 

Elementary School and RecreationCenter. This facility replaces

the Sursum Corda kiosk.

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 11/12

11

Parklands-Turner  –   New Storefront Library  Contacts Progress

Councilmember Marion Barry

Ribbon cutting held on October 5, 2009 and

opened to the public 

Ward 8 202.724.8045 

Architect Mood Nolan - DC

Patrick Williams

202.244.

Project

Manager Dedric Boyd

202.727.1129

Contractor Lexx Group

Ken Postell

202.393.

Petworth –  Interior Renovations Contacts Progress

Councilmember 

Opened on February 28, 2011 

Councilmember MurielBowser 

Ward 4 202.724.8052

Architect Frank and Loshen

Fletcher Farr 

Anoyte

Project

Manager Chris Wright

202.727.4913

Contractor Sigal Construction

Sarah Norman

DCPL PM

Firm

McKissack and

McKissack 

Project updates the interior of the Petworth Library to be a

fully functional state of the art 21st

Century Library, while

still being respectful of the buildings historic character.

Project to fit out approximately 5,000 Sq Ft of storefront space

to replace the existing Parklands-Turner kiosk. The storefront

library is similar in size, scope, computers, and collections to the

Georgetown Interim and Tenley-Friendship Interim Libraries.

7/29/2019 Document #9C.1 - Capital Projects Report

http://slidepdf.com/reader/full/document-9c1-capital-projects-report 12/12

12

Tenley Friendship – New Building Contacts Progress

Councilmember 

Opened on January 24, 2011 

Ward 3 Mary Cheh

202.724.8062

Architect Freelon Group

Philip Freelon

919.941.9790

Project

Manager Dedric Boyd

202.727.1113

Contractor Forrester.

Joe Ockershausen

301.255.1794

DCPL PM

FirmHill International

Martin Luther King Jr. Library  –   New Teen Spot andCollegeInformationCenter  

Contacts Progress

Councilmember 

Project complete 

Ward 2 Jack Evans

202.724.8058

Architect Sorg Associates

SumanSorg

Project

Manager Kim Fuller 

202.442.6070

Contractor Bennett Group

Kolar Bowen

202. 625.3330

Design of the new Tenley Branch Library will include

community input on planning and programming phase. Design

and construction is fully funded.

 New Teen Spot and CollegeInformationCenter is a destination

for teens.It provides stimulating learning opportunities that

support their success in life. This destination provides