document of the world bank klh komir kpiu kpmu mis moa moenv mof moha mpw mou npiu npmu nscwr nwc...

81
Document of The World Bank Report No: ICR00001861 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47110, IBRD-77570, IDA-38070, TF-52124, TF55997) ON A LOAN/CREDIT/GRANT IN THE AMOUNT OF US$45.0 MILLION (LOAN), SDR17.9 MILLION (CREDIT), US$14.0 MILLION (GOVERNMENT OF NETHERLANDS GRANT) AND EURO 9.5 MILLION (EC GRANT) RESPECTIVELY TO THE REPUBLIC OF INDONESIA FOR A WATER RESOURCES AND IRRIGATION SECTOR MANAGEMENT PROGRAM PHASE I PROJECT AND NUSA TENGGARA BARAT WATER RESOURCE MANAGEMENT PROJECT March 30, 2012 Indonesia Sustainable Development Unit Sustainable Development Department East Asia and Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: phamlien

Post on 24-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Document of

The World Bank

Report No: ICR00001861

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IBRD-47110, IBRD-77570, IDA-38070, TF-52124, TF55997)

ON A

LOAN/CREDIT/GRANT

IN THE AMOUNT OF US$45.0 MILLION (LOAN), SDR17.9 MILLION

(CREDIT), US$14.0 MILLION (GOVERNMENT OF NETHERLANDS GRANT)

AND EURO 9.5 MILLION (EC GRANT) RESPECTIVELY

TO

THE REPUBLIC OF INDONESIA

FOR A

WATER RESOURCES AND IRRIGATION SECTOR MANAGEMENT PROGRAM

PHASE I PROJECT AND

NUSA TENGGARA BARAT WATER RESOURCE MANAGEMENT PROJECT

March 30, 2012

Indonesia Sustainable Development Unit

Sustainable Development Department

East Asia and Pacific Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

CURRENCY EQUIVALENTS

(Exchange Rate Effective December 31, 2011)

Currency Unit = Indonesian Rupiah

IDR = US$0.00011236

US$* = IDR 8,900 *All $ in this document refer to US currency unless otherwise noted.

GOI FISCAL YEAR

January 1 – December 31

ABBREVIATIONS AND ACRONYMS

ADB

AMDAL

APBD(K)

APBD(P)

APBN

APL

AWP

Balai PSDA

Bangda

Bapedalda

Asian Development Bank

Full Environmental Assessment

Kabupaten Government Budget

Provincial Government Budget

Central Government Budget

Adaptable Program Loan

Annual Work Plan

Provincial River Basin Management Organization

DG Regional Development, MoHA

Local Environmental Management Office

Bappeda

Bappenas

B (B)WS

BPKP

BWRC

BWRM

BWRMP

CAS

CDD

CDP

CDMU

CPS

CSO

DA

DAS

DGWR

DGAIF

Dinas Pertanian

Dinas PUP

Dinas SDA

DPRD

DSC

EMP

FMR

GOI

GP3A/IP3A

IAIP

IBRD

ICR

IFR

IMEU

IMF

JBIC

JIWMP

Kabupaten

Local Government Development Planning Board

National Development Planning Board

National River Basin Management Organization

Central Government Audit Agency

Basin Water Resources Council (Committee)

Basin Water Resources Management

Basin Water Resources Management Plan/Planning

Country Assistance Strategy

Community-driven development

Community Development Plan

Central Dam Monitoring Unit within MPW

Country Partnership Strategy

Civil Society Organization

Designated Account

River Basin

Directorate General of Water Resources, MPW

Directorate General of Agriculture Infrastructure and Facilities

Local Government Agriculture Services

Local Government Public Works Services (Department)

Local Government Water Resources Services (Department)

Local Government Legislative Assembly

Dam Safety Commission

Environmental Management Plan

Financial Monitoring Report

Government of Indonesia

Federation/Apex Body of Water Users Associations (WUAF)

Kabupaten Irrigated Agriculture Improvement Program

International Bank for Reconstruction and Development

Implementation Completion Report

Interim Financial Reports

Impact Monitoring and Evaluation Unit

Irrigation Management Fund

Japan Bank for International Cooperation

Java Irrigation and Water Resources Management Project

District

KIIF

KLH

KOMIR

KPIU

KPMU

MIS

MoA

MoEnv

MOF

MoHA

MPW

MOU

NPIU

NPMU

NSCWR

NWC

O&M

PAD

PDO

Perda

PIM

PIU

PJT I/II

PKPI

PMU

PMM

PPISP

PPIU

PPMU

PPTPA

PTPA

PWRC

SRI

RBC

RIM

TA

UPTD

WISMP

WS

WUA

WUAF

WUR

Kabupaten Irrigation Improvement Facility (DPI-K)

State Ministry of Environment

Irrigation Commission (Committee)

Kabupaten Project Implementation Unit

Kabupaten Project Management Unit

Management Information System

Ministry of Agriculture

Ministry of Environment

Ministry of Finance

Ministry of Home Affairs

Ministry of Public Works

Memorandum of Understanding

National Project Implementation Unit

National Project Management Unit

National Steering Committee for Water Resources

National Water Council

Operation and Maintenance

Project Appraisal Document

Project Development Objectives

Local Government Regulation

Participatory Irrigation Management

Project Implementation Unit

Basin Management Corporation I/II

Irrigation Management Reform Policy

Project Management Unit

Project Management Manual

National Policy on Irrigation

Provincial Project Implementation Unit

Provincial Project Management Unit

River Basin Water Management Committee

Provincial Water Management Committee

Provincial Water Resources Management Council

System of Rice Intensification

River Basin Corporation

River Infrastructure Maintenance and Rehabilitation

Technical Assistance

An Operational Unit within Dinas PUP

Water Resources and Irrigation Sector Management Program

River Territory

Water User Associations

Water User Association Federation (GP3A/IP3A)

Water Use Right

Vice President:

Pamela Cox, EAPVP

Country Director: Stefan Koeberle, EACIF

Sector Director: John Roome, EASSD

Sector Manager: Franz Drees-Gross, EASIS

Task Team Leader: Xiaokai Li, EASIN

INDONESIA

Water Resources and Irrigation Sector Management Program Phase I Project

(WISMP1) and

Nusa Tenggara Barat Water Resource Management Project (NTB-WRMP)

CONTENTS

Water Resources and Irrigation Sector Management Program Phase I Project Data Sheet…………………………………………………………………………………….i

A. Basic Information

B. Key Dates

C. Ratings Summary D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs H. Restructuring

I. Disbursement Graph

Nusa Tenggara Barat Water Resource Management Project (NTB-WRMP)

Data Sheet…………………………………………………………………………………….xi

A. Basic Information B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design…………………………..1

2. Key Factors Affecting Implementation and Outcomes …………………………7

3. Assessment of Outcomes ………………………………………………………15

4. Assessment of Risk to Development Outcome ……………………………….. 24

5. Assessment of Bank and Borrower Performance ………………………………26

6. Lessons Learned ………………………………………………………………..29

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ….29

Annex 1. Project Costs and Financing ……………………………………………31

Annex 2. Outputs by Component …………………………………………………34

Annex 3. Economic and Financial Analysis ……………………………………...41

Annex 4. Bank Lending and Implementation Support/Supervision Processes …...45

Annex 5. Beneficiary Survey Results …………………………………………….48

Annex 6. Stakeholder Workshop Report and Results …………………………….49

Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR…………50

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ………….55

Annex 9. List of Supporting Documents ………………………………………….56

MAP: IBRD 39248

i

For WISMP 1 (Phase I of the WISMP APL):

A. Basic Information

Country: Indonesia Project Name:

Water Resources &

Irrigation Sector

Management Program

Project ID: P059931 L/C/TF Number(s):

IBRD-47110, IBRD-

77570, IDA-

38070,TF-52124

ICR Date: 03/29/2012 ICR Type: Core ICR

Lending Instrument: APL Borrower: REPUBLIC OF

INDONESIA

Original Total

Commitment: USD 84.00M Disbursed Amount: USD 86.00M

Revised Amount: USD 84.00M

Environmental Category: B

Implementing Agencies:

Directorate General Water Resources of Ministry of Public Works (DGWR-MOPW)

Directorate General Regional Development of Ministry of Home Affairs (DGRD-MOHA)

Directorate General Land and Water of Ministry of Agriculture (MOA)

Co-financiers and Other External Partners: Government of Netherlands (USD 14 Million)

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 12/17/2001 Effectiveness: 11/24/2005 11/24/2005

Appraisal: 03/17/2003 Restructuring(s):

Approval: 06/26/2003 Mid-term Review: 03/17/2008 03/28/2008

Closing: 12/31/2009 12/31/2010

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately satisfactory

Risk to Development Outcome: Moderate

Bank Performance: Moderately Satisfactory

Borrower Performance: Moderately Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

Satisfactory Government:

Moderately

Satisfactory

Quality of

Supervision: Satisfactory

Implementing

Agency/Agencies: Satisfactory

ii

Overall Bank

Performance: Moderately

Satisfactory Overall Borrower

Performance: Moderately

Satisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem

Project at any time

(Yes/No):

No Quality at Entry

(QEA): Satisfactory

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status: Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

General water, sanitation and flood protection sector 50 30

Irrigation and drainage 50 70

Theme Code (as % of total Bank financing)

Rural services and infrastructure 50 50

Water resource management 50 50

E. Bank Staff

Positions At ICR At Approval

Vice President: Pamela Cox Jemal-ud-din Kassum,

Country Director: Stefan G. Koeberle Andrew Steer

Sector Manager: Franz R. Drees-Gross Mark D. Wilson

Project Team Leader: Xiaokai Li Guy Alaerts

ICR Team Leader: Xiaokai Li

ICR Primary Author: Xueming Liu &

John Weatherhogg ( FAO/CP)

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

(a) Water allocation, water quality and water conservation improved in Project basins, and

river infrastructure better maintained, through strengthened capacity for planning and

management; and investments;

(b) Sector governance enhanced, and sector fiscal sustainability strengthened, nationally,

and in Project basins, through setting up Water Resources Councils; ensuring stakeholder‟s

iii

involvement; unbundling of operational tasks, and Private Sector Participation; and improved

cost recovery; and

(c) Increased agricultural productivity and improved performance of irrigation, based on

participatory irrigation management, through setting up and strengthening WUAFs;

strengthening restructured Dinas PUP of local government; financing rehabilitation and

improvement of existing irrigation schemes; and facilitating access to agricultural support

services and micro-credit.

The project development objective stated in the Development Credit Agreement (DCA) is as

follows: The objective of the Project is to assist the Borrower in attaining a strengthened

water resources sector by improving the performance of its water resources and irrigation

sector, and rehabilitating and upgrading the infrastructure of the said sector.

Revised Project Development Objectives (as approved by original approving authority)

There is no revision of project development objectives in the course of project

implementation. There are some discrepancies between the monitoring indicators of the DCA

and those of the PAD. As per advice of the Operations Support Team of the EAP Sustainable

Development Department, the indicators from the PAD were used for reporting below.

iv

Indicator Baseline

Value Original Target

Values Formally Revised

Target Values Actual Value

Achieved at

Completion or

Target Years

Indicator 1 Allocation of deliverable water more equitable for all competing uses and needs (incl.

environmental).

Value

quantitative

or

Qualitative

No

participatory

water allocation

planning

practiced

>75% of demand being

met in each sub-sector,

in 5 project Basins

Participatory allocation

planning was piloted in 5

river basins and is being

practiced in 9 river

basins, enabling more

equitable water

allocation for all uses.

However, no information

is available on the exact

percentage of sub-sector

water demand met.

Date

achieved

31-May-2003 31-December-2006 31-December-2010

Comments

Achievement: Virtually achieved based on the number of river basins practicing

participatory water allocation planning

Indicator 2 System of water pollution monitoring and control effective

Value

quantitative

or

Qualitative

No basin

oriented water

pollution

monitoring and

control system

in place

System of water

pollution monitoring

and control, incl.

discharge permits and

fees, effective in 1

Project Basin

Water quality monitoring

is practiced in 27

participating basins and

water quality databases

established. The data

collected was shared

with the respective

environmental agency

responsible for water

pollution control,

discharge permit, and

fees, for further action.

Date

achieved

31-May-2003 31-December-2006 31-December-2010

Comments

Achievement: partially achieved. Water quality/pollution monitoring target fully achieved

while there is no data available on the effectiveness of water pollution control (discharge

permit and fees, etc)

Indicator 3 Economic losses reduced as river infrastructure development and O&M are better geared

to regional priorities and sustained cost recovery.

Value

quantitative

or

Qualitative

River

infrastructure

development

and O&M were

carried out

without public

consultation

Economic losses

reduced as river

infrastructure

development and O&M

are better geared to

regional priorities and

sustained cost recovery.

Priority maintenance of

key river infrastructure

in 54 Balai PSDA is

based on public

consultation and

participation. O&M cost

is met through

government budget as

cost recovery through

service fees was

precluded by Law No.

7/2004.

Date

achieved

31-May-2003 31-December-2006 31 December-2010

v

Comments Achievement: largely achieved, based on the fact that river infrastructure development and

O&M are better aligned with regional priorities and needs through consultation and

participation.

Indicator 4 Balai PSDA plan basin operations and investments based on BWRMPs

Value

quantitative

or

Qualitative

BWRMP

prepared for 2

basins (Pekalen

Sampean and

Bodri Kuto)

In 3 basins the Balai

PSDAs plan basin

operations and

investments based on

Basin Water Resource

Management Plans

(BWRMPs)

In 20 project basins the

BWRMPs were prepared

and six of these plans

were legalized and are

being used as the basis

for basin operations and

investments.

Date

achieved

31-May-2003 31-December-2006 31 December-2010

Comments Achievement: over 100% by the number of basins where basin operations and investments

are based on BWRMPs.

Indicator 5 Demonstrable improvement in construction quality and contract management, annual

work programs based on cost-effectiveness, improved inter-agency coordination.

Value

quantitative

or

Qualitative

Construction

work program

was prepared

through top-

down approach,

with little inter-

agency

coordination

Demonstrable

improvement in

construction quality and

contract management;

annual work programs

based on cost-

effectiveness;

Improved inter-agency

coordination.

Construction quality and

contract management

improved through

beneficiary participation;

Work program more cost

effective because of end

user participation in

investment prioritization;

Inter-agency

coordination established

and strengthened through

river basin councils

Date

achieved

31-May-2003 31-December-2006 31 December-2010

Comments

Contract management follows established procedures but more transparent with better

quality results by involving beneficiaries. Achievement: largely achieved

Indicator 6 A National Water Council and its Secretariat develop policies for fiscal sustainability and

sector governance and resolve inter-agency conflict

Value

quantitative

or

Qualitative

There was no

dedicated

multi-

stakeholder

coordination

setup for water

sector.

A National Water

Council has appropriate

stakeholders

representation,

reflecting gender

sensitivity, and has its

Secretariat fully

established, staffed,

funded and operational

as evidenced by policy

decisions made.

Target remained the

same, and achievement

date amended to

become December 31,

2010.

A National Water

Council (NWC)

established with multi-

stakeholder

representation in 2009,

and its secretariat fully

functional with adequate

staff and funding from

National Budget

(APBN); A National

Water Resources Policy

was prepared by NWC in

2010 and enacted in

2011.

Date

achieved

31-May-2003 31-December-2006 31-December-2010 31-December-2010

Comments Achievement: 100% based on establishment of a NWC with a fully functional Secretariat

Indicator 7 Number of Participating Provinces that have established Provincial and Basin Water

vi

Resources Councils (PWRC and BWRC ) with appropriate stakeholder representation

Value

quantitative

or

Qualitative

Provincial

Water

Resources

Management

Committees

(PTPA) existed

in a small

number of

provinces,

without

stakeholder

participation.

In 12 Provinces and 15

basins multi-

stakeholder Water

Resources Councils

reflecting sensitivity

towards gender

sensitivity and

vulnerable groups are

established, and

demonstrably influence

regulations, water

allocation investments

and budgets.

50% of the Participating

Provinces establish

PWRCs with proper

stakeholder

representation, and 50%

of these provinces in

process of establishing

BWRCs.

Target achievement

date amended to be

December 31, 2010.

13 out of 14 provinces

established PWRCs, with

9 fully functional and 5

out of the 9 PWRCs

finalizing the provincial

water resources policy.

9 out of the 14 provinces

established a total of 16

BWRCs that were

engaged in basin

strategic plan review and

water use conflict

resolution.

Date

achieved

31-May-2003 31-December-2006 31-December-2010 31-December-2010

Comments

Achievement: over 100% based on the number of total PWRCs and BWRCs established

(against amended targets)

Indicator 8 Basin Water Resources Management Plans (BWRMP)adopted by the local parliament

(DPRD) and the Provincial Water Resources Council

Value

quantitative

or

Qualitative

2 Basin Water

Resources

Management

Plan are

prepared, have

not been

discussed in

PPTPA.

3 BWRMPs adopted by

DPRD and Provincial

Water Resources

Councils.

9 basin strategic plans /

BWRMP have been

reviewed and adopted by

the Provincial Water

Resources Councils/local

parliament (DPRD).

Date

achieved

31-May-2003 31-December-2006 31 December-2010

Comments

Achievement: over 100% based on the number of BWRMPs adopted

Indicator 9

Local Government (Pemda) budget allocation covers 50% of Balai PSDA operating cost;

abstraction and effluent discharge fee revenue covers 25% of operational expenditures of

a new river basin corporation (RBC)

Value

quantitative

or

Qualitative

In Balai PSDAs

established

prior to the

project, major

part of the

budget

originated

from central

government

In 3 basins, earmarked

Pemda budget

allocation covers 50%

of Balai PSDA

operating costs;

Abstraction and effluent

discharge fee revenue

covers 25% of

operational

expenditures of a new

basin organization

(RBC)

In each of the 14

Participating Provinces

for each basin under their

authority, a Balai PSDA

established in each of 14

provinces for every

provincial basin with

100% funding

(structural) from

provincial budget

(APBD). Effluent

discharge fee not

allowed by the Water

Law No. 7/2004.

Date

achieved

31-May-2003 31-December-2006 31 December-2010

Comments

Achievement: fully achieved if measured by the number of basins where the Balai PSDAs

get 50% of their operating costs from APBD.

Indicator10 Operational Framework prepared to pilot more commercial approach in APL II

Value Operational Operational Framework Operational framework

vii

quantitative

or

Qualitative

framework not

available

prepared to pilot more

commercial approach in

APLII

based on public service

corporation (BLU)

concept developed but

not yet accepted by the

National Government.

Date

achieved

31-May-2003 31-December-2006 31- December-2010

Comments

Financial administrative regulations require a full separation of management entities of

BLU and Balai WS. This issue was not resolved during WISMP2 (APLII) negotiations so

the BLU could not be officially included in WISMP2. Achievement: partially achieved

Indicator11 Public irrigation schemes in kabupaten are governed by WUAFs in partnership with

kabupaten government.

Value

quantitative

or

Qualitative

493,540 ha

irrigation area

adopted joint

management;

166,173 ha

rehabilitated

and managed

by WUAF with

technical and

matching grant

financial

support;

Irrigation

commissions

established in

50 Kabupatens

50% of public irrigation

schemes in 70

kabupaten (690,000 ha)

managed by WUAFs in

partnership with

Kabupaten government;

At least 25% of

secondary canal

services (345,000 ha)

managed by WUAFs

with technical and

matching grant financial

support;

Kabupaten Irrigation

Commissions

operational in 70

Kabupaten

A total of 1,027,194 ha

of public irrigation areas

governed by WUAFs in

partnership with

kabupaten or provincial

government agencies

(>100%);

Secondary canals serving

354,464 ha rehabilitated

and managed by WUAFs

jointly with Kabupaten

irrigation agencies

providing technical and

financial support

(>100%); and 12

Provincial and 95

Kabupaten Irrigation

Commissions operational

(>100%).

Date

Achieved

31-May-2003 31-December-2006 31- December-2010

Comments Achievement: over 100% (See above)

Indicator 12 Active participation of women farmers in WUAs and WUAFs enhanced

Value

quantitative

or

Qualitative

Women were

rarely active in

the WUAs and

WUAFs.

Active participation of

women farmers in

WUAs and WUAFs

enhanced

Women‟s participation in

WUAs and WUAFs is

stimulated through their

inclusion in training and

provision of female

community organizers or

facilitators (30%),

resulting in increased

active women

participation in many

WUA/WUAF boards,

now accounting for 5%-

7% of total board

members.

Date

achieved

31-May-2003 31-December-2006 31- December-2010

Comments Achievement: fully achieved, based on qualitative assessment of women‟s participation in

WUAs and WUAFs

Indicator 13 Capacity of 70 Kabupaten Irrigation Departments Improved

Value

quantitative

Participatory

irrigation

Capacity of 70

Kabupaten Irrigation

99 Kabupaten and 12

provinces restructured

viii

or

Qualitative

management

newly

introduced

Departments Improved their irrigation

departments, issued

Regulations on

Irrigation, and trained

their staff (about 7,000)

in participatory irrigation

management, rapid

assessments, and

supporting user

communities.

Date

achieved

31-May-2003 31-December-2006 31 December 2010

Comments: Achievement: over 100% measured by the number of Kabupaten irrigation departments the

capacity of which has been improved under the project

Indicator 14 Reduction in Government rehabilitation investment expenditures by 10% by transfer of

tasks and budgets to WUAFs

Value

quantitative

or

Qualitative

Contribution of

the WUAFs to

rehabilitation

cost piloted in

the irrigation

systems under

previous

IWIRP project.

Reduction in

Government

rehabilitation

investment expenditures

by 10% by transfer of

tasks and budgets to

WUAFs

Participatory

construction enabled

WUAF contributions in

form of labor, materials

and sometimes cash, and

related budget transfer to

them. WUAFs‟

contributions reached

10% of rehabilitation

cost, and led to better

quality and longer use

life of project works

Date

achieved

31-December-2006 31- December-2010

Comments Achievement : 100% by percentage of WUAF contribution to government system

rehabilitation investment expenditures

Indicator 15 Matching contributions from WUAFs for O&M of schemes are at least 20% of expenditure

in half of the schemes and increase in all schemes.

Value

quantitative

or

Qualitative

There was no

mechanism for

WUAF to

participate in

the O&M

activities. If

any, it was

done in an ad

hoc manner.

Matching contributions

from WUAFs for O&M

of irrigation schemes

are at least 20% of

expenditure in half of

the schemes and

increase in all schemes.

For O&M of public

systems the WUAF

contributed in form of

labor amounting to 20%

or more of the O&M

cost. In general,

WUAFs‟ contributions to

O&M of all the project

schemes have increased.

Date

Achieved

31-May-2003 31-December-2006 31- December-2010

Comments: Achievement: full achieved

Indicator 16 Irrigation O&M budgets of 11 provinces and 70 kabupaten reach a satisfactory and

sustainable level.

Value

quantitative

or

Qualitative

The local

budget (APBD)

allocated for

irrigation

system O&M is

erratic and

marginal, well

below the level

of 60,000Rp/ha

level.

Irrigation O&M budgets

of 11 provinces and 70

Kabupaten reach a

satisfactory and

sustainable level.

At least15 Participating

Kabupaten provide

from their APBD at

least Rp60,000/ha per

year for O&M over the

total irrigated areas.

Target achievement

date amended to be

December 31, 2010.

9 Provinces and

71Kabupaten,

representing a total of

1,387,000 ha of irrigated

areas, allocated O&M

budgets of over 60,000

Rp/ha(average 130,000

Rp/ha). About 30% of

these provinces and

Kabupatens in 2010

ix

matched or exceeded

150,000 Rp/ha.

Date

achieved

31-May-2003 31-December-2006 31-December-2010 31- December-2010

Comments: Achievement: 99% against original target and 500% against amended target of total

number of provinces and Kabupatens that provided satisfactory level of O&M budget

Indicator 17 No decrease in average and median farm income in 30 irrigated kabupaten, and

mechanisms in place that will increase income over WISMP2

Before the

project the

irrigation water

efficiency tends

to decline,

causing

decrease in

production and

farm income.

No decrease in average

median farm income in

30 irrigated Kabupaten,

and mechanisms in

place that will increase

income during

WISMP2

Government statistics

showed significant

increase in farm income

in all Participating

Kabupaten, especially in

18 Kabupaten where

agricultural support was

piloted, although no

project specific

monitoring data

available. Investments in

capacity building in all

99 Kabupaten

contributed to better

water management and

to increasing farm

income under WISMP

Date

Achieved

31-May-2003 31-December-2006 31- December-2010

Comments: Achievement: fully achieved, based on the qualitative assessment

Indicator 18 Increase in ERR of benefits based on income from higher rice yield and higher value

crops; and improved farm gate prices.

Crop yield was

generally

decreasing due

to declining

irrigation

system

performance.

Most farmers

sell their

products to the

mediators /

collectors at

low price for

quick cash.

Increase in ERR of

benefits based on

income from higher rice

yield and higher value

crops; and improved

farm gate prices.

Crop production

increased in project areas

due to improved

irrigation system

performance leading to

increase in both crop

intensity and

diversification, which

was reflected in a re-

calculated overall ERR

of 23% (See Annex 3).

Many WUAFs signed

farming contracts with

the private companies,

enabling better prices of

farm products although

systematic record on

farm gate prices are not

available.

Date

Achieved

31-May-2003 31-December-2006 31- December-2010

Comments: Achievement: fully achieved based on economic analysis results

x

G. Ratings of Project Performance in ISRs

No. Date ISR Archived

DO IP Actual

Disbursements (USD millions)

1 12/30/2003 Satisfactory Satisfactory 0.00

2 06/25/2004 Satisfactory Unsatisfactory 0.00

3 12/20/2004 Satisfactory Unsatisfactory 0.00

4 06/01/2005 Moderately Satisfactory Unsatisfactory 0.00

5 06/27/2005 Moderately Satisfactory Satisfactory 0.00

6 06/27/2005 Moderately Satisfactory Satisfactory 0.00

7 06/07/2006 Moderately Satisfactory Moderately Satisfactory 6.15

8 06/25/2007 Moderately Satisfactory Moderately Satisfactory 7.20

9 06/23/2008 Satisfactory Satisfactory 18.76

10 06/26/2009 Satisfactory Satisfactory 37.90

11 12/24/2009 Satisfactory Satisfactory 42.16

H. Restructuring (if any)

N/A

I. Disbursement Profile

The actual disbursement is the total of credit, loan and grant while the original and

formally revised amounts do not include the grant amount.

xi

For NTB-WRMP:

A. Basic Information

Country: Indonesia Project Name:

EC GRANT - ID

NTB-River Basin

Water Resources

Management Program

Project ID: P095128 L/C/TF Number(s): TF-55997

ICR Date: 03/29/2012 ICR Type: Core ICR

Lending Instrument: SIL Grantee: REPUBLIC OF

INDONESIA

Original Total

Commitment:

Euro 9.05 M

(USD 12.00 M

equivalent)

Disbursed Amount: N/A

Revised Amount:

Euro 9.50M

(USD 11.36M

equivalent)

Disbursed Amount

Euro 9.46M

(USD11.31M

equivalent)

Environmental Category: U

Implementing Agencies:

Directorate General Water Resources of Ministry of Public Works (DGWR-MOPW)

Directorate General Regional Development of Ministry of Home Affairs (DGRD-MOHA)

Directorate General Land and Water of Ministry of Agriculture (MOA)

Co-financiers and Other External Partners: European Commission(EC)

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: * Effectiveness: 12/27/2005 12/27/2005

Appraisal: * Restructuring(s): N/A N/A

Approval: * Mid-term Review: 03/28/2008 02/19/2008

Closing: 06/30/2011 06/30/2011

* There was no formal concept review, appraisal and Board approval.

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately satisfactory

Risk to Development Outcome: Moderate

Bank Performance: Moderately satisfactory

Grantee Performance: Moderately Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

Satisfactory Government:

Moderately

Satisfactory

xii

Quality of

Supervision: Satisfactory

Implementing

Agency/Agencies: Satisfactory

Overall Bank

Performance: Moderately

Satisfactory Overall Borrower

Performance: Moderately

Satisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem

Project at any time

(Yes/No):

No Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): No

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status: Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

General water, sanitation and flood protection sector 50 30

Irrigation and drainage 50 70

Theme Code (as % of total Bank financing)

Rural services and infrastructure 67 67

Water resource management 33 33

E. Bank Staff

Positions At ICR At Approval

Vice President: Pamela Cox Jemal-ud-din Kassum

Country Director: Stefan G. Koeberle Andrew Steer

Sector Manager: Franz R. Drees-Gross Mark D. Wilson

Project Team Leader: Xiaokai Li Guy Alaerts

ICR Team Leader: Xiaokai Li

ICR Primary Author: Xueming Liu &

John Weatherhogg ( FAO/CP)

F. Results Framework Analysis

Project Development Objectives (from Grant Agreement)

The objective of the Grant is to assist the Recipient in strengthening the water

resources and irrigation sector in the Province of Nusa Tenggara Barat and in the

Kabupatens of the said province by improving the performance of the Province's and

xiii

the Kabupatens' water resources and irrigation sector, and rehabilitating and

upgrading its infrastructure of the said sector.

Revised Project Development Objectives (as approved by original approving authority)

There is no revision of the project development objective in the course of project

implementation.

There is no PAD for this project, therefore the performance indicators in the 2005

Grant Agreement (amended in 2009) are used for the analysis.

Indicator Baseline

Value

Original Target

Values (from

approval

documents)

Formally Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1

A Provincial Water Resources Council (PWRC) with appropriate stakeholder

representation and its Secretariat established and functional.

Value

quantitative or

Qualitative

No provincial

water resources

council exists.

A PWRC, with

Secretariat,

established with

representative

stakeholder

representation,

reflecting gender

sensitivity established

and functional with

evidence

A PWRC established

with a fully staffed and

funded secretariat in

2009. PWRC includes

women and

vulnerable group

representatives. It is

functional, and has

discussed provincial

policy on climate

change adaptation, and

resolved water use

conflicts.

Date achieved 20-December-

2005 30-June-2011 30-June-2011

Comments

(incl. %

achievement)

The PWRC and its Secretariat established with appropriate representation and fully

functional. Achievement: fully achieved

Indicator 2 Basin Water Resources Councils (BWRCs) established with appropriate stakeholder

representation and functional.

Value

quantitative or

Qualitative

No provincial

basin water

resources

council exists.

All BWRCs

established covering

the whole territory of

the Province and each

BWRC has

representative

stakeholder

representation.

Two BWRCs are

established in Sumbawa

and Bima-Dompu

covering the whole

Island of the province,

each with representative

stakeholder

representation.

Two BWRCs

established with

required representation

in NTB. BWRC

Lombok established in

2009 and functional -

discussed strategic

plan and basin

management issues;

BWRC Bima -Dompu

established in 2010,

and BWRC Sumbawa

in 2011

Date achieved 20-December-

2005 30-June-2011 30-June-2011 30-June-2011

Comments

(incl. %

Achievement: 100% by number of BWRCs established (According to Water Law

No.7/2004, BWRC establishment is based on need).

xiv

achievement)

Indicator 3 Balai PSDA covering entire provincial territory established and operational with

trained staff.

Value

quantitative or

Qualitative

No formal basin

unit or Balai

PSDA exists.

All UPTD/ Balai

PSDA established,

covering the entire

Province, adequately

staffed and

operational, and at

least half of such

entities are receiving

50% of their

operational budget

form the Province

Government

Three Balai PSDAs

and one Balai ISDA

established and

functional. Necessary

training carried out

with over 100

personnel trained.

These entities are

receiving over 50% of

their budgets for

operations, from

Provincial

Government.

Date achieved 20-December-

2005 30-June-2011 30-June-2011

Comments

(incl. %

achievement)

All Balai PSDA established covering the whole territory of the Province, and

appropriately staffed and fully operational. Achievement: 100% by number of Balai

PSDA.

Indicator 4

A decree of Dinas PUP has been issued for role sharing in hydrometeorology between

the relevant Dinas PUP and UPTD or Balai PSDA, and the hydromet network is

operational.

Value

quantitative or

Qualitative

There were no

dedicated funds

for hydromet

work in the

Balai, although

limited funds

available in

Dinas for this

purpose.

A Dinas PUP Surat

Keputusan has been

issued for role

sharing in

hydrometeorology

between the relevant

Dinas PUP and

UPTD or Balai PSDA

in the Province.

Hydromet asset mgt

fully transferred from

the Dinas PUP to the

relevant UPTD or

Balai PSDA and

hydromet network

fully operational

A decree of Dinas

PUP issued, 4 Joint

Operation Agreements

between Dinas PUP

and Balai PSDA

Lombok, Balai PSDA

Sumbawa,

Balai PSDA Bima-

Dompu and Balai

ISDA signed in 2007.

Hydromet asset mgt.

transferred; and and

hydrometric data being

collected and

managed by Balai

ISDA.

Date achieved 20-December-

2005 30-June-2011 30-June-2011

Comments

(incl. %

achievement)

Achievement: largely achieved.

Indicator 5 The provincial planning unit in Dinas PUP appropriately staffed and funded, and

producing basin water resources management plans.

Value

quantitative or

Qualitative

There was no

planning unit in

the Dinas PUP.

The provincial

planning unit in

Dinas PUP

appropriately staffed

and funded, and

producing basin

water resources

management plans.

The Provincial

Planning Team in Dinas

PUP established,

appropriately staffed

and funded and capacity

developed to prepare

strategic and master

plans for river basins

under the authority of

the Province.

The planning function

integrated into the

structural functions of

Dinas PUP. A

provincial planning

team established

supervising outsourced

planning services;

strategic plans for

Lombok and Bima

xv

Dompu basins

completed and

legalized.

Date achieved 20-December-

2005

30-June-2011 30-June-2011 30-June-2011

Comments

(incl. %

achievement)

Achievement: virtually achieved based on the number of basin plans completed.

Indicator 6 : Quality assurance plans and infrastructure maintenance plans produced and being

implemented.

Value

quantitative or

Qualitative

There was no

Quality

Assurance Plans

in existence.

Quality Assurance

Plans and river

infrastructure

maintenance plans

produced and being

implemented.

Quality Assurance

Plans and irrigation

infrastructure

maintenance plans

produced and being

implemented.

Quality Assurance

Core team established,

quality assurance and

maintenance plans

produced and being

implemented, and

annual river

infrastructure

maintenance plans

prepared in

consultation with

stakeholder and

implemented.

Date achieved 20-December-

2005

30-June-2011 30-June-2011 30-June-2011

Comments

(incl. %

achievement)

Achievement: fully achieved.

Indicator 7 : Area of irrigation system is co-managed by WUAFs.

Value

quantitative or

Qualitative

There was no

co-management

arrangements

for irrigation

system

At least 60,000 ha of

irrigation system is

co-managed by

WUAFs, resulting in

demonstrable

operation and

maintenance, crop

productivity, water

use efficiency, and

reduced levels of

infrastructure

deterioration.

145,000 ha of

irrigation schemes co-

managed with

WUAFs;

crop productivity

increased 4.4% and

harvested areas

increased 24.5%; and

infrastructure

improved with longer

life expected.

Date achieved 20-December-

2005 30-June-2011 30-June-2011

Comments

(incl. %

achievement)

Achievement: 225% by number of hectare co-managed by WUAFs.

Indicator 8 Number of WUAFs established in 7 Participating Kabupatens.

Value

quantitative

or

Qualitative

No WUAF

request

mechanism

was in

At least 160

WUAFs in 7

Kabupatens

established,

presented to

respective

The Province and 7

Kabupatens issued

Perdas and

established

Irrigation

Commissions; A

xvi

existence.

Irrigation

Commissions IMF

funding proposals

endorsed by the

relevant Dinas

PUP.

total of 214 WUAFs

established;

WUAFs‟ proposals

presented to

Irrigation

Commissions.

Date

achieved

20-

December-

2005

30-June-2011 30-June-2011

Comments

(incl.%

achievement)

Achievement: 135% by number of WUAFs established.

Indicator 9 Number of IMF funding proposals received by the Irrigation Commissions from

WUAFs in the 7 Participating Kabupaten.

Value

quantitative

or

Qualitative

Neither

WUAF

request

mechanism

nor Irrigation

Commission

exists.

In 7 Participating

Kabupaten, the

Irrigation

Commissions

received, reviewed,

evaluated and

recommended at

least 100 WUAFs‟

proposals for IMF

funding endorsed

by the relevant

Dinas PUP.

The Irrigation

Commission

received and

evaluated over 100

proposals endorsed

by the Dinas PUP,

and 91 proposals

were recommended

for IMF funding.

Date

achieved

20-

December-

2005

30-June-2011 30-June-2011

Comments

(incl. %

achievement)

Achievement: 100% by number of proposals received by the Irrigation

Commissions and endorsed by Dinas PUP.

Indicator 10 Number of Participating Kabupaten that provide from APBD at least 60,000 Rp/ha

O&M budget for their project schemes.

Value

quantitative

or

Qualitative

Local budget

(APBD)

allocated for

irrigation

system O&M

was erratic

and marginal,

well below

the level of

60,000Rp/ha

level.

At least 3

Kabupaten

supplied from their

APBD, at least

60,000 Rp/ha per

year of IMF funds

over the total

irrigated area in

their respective

Kabupatens,

besides required

counterpart budget

The Province and 4

Kabupatens

allocated over

60,000 Rp/ha O&M

budget through

APBD. All 7

Participating

Kabupatens

provided required

counterparts budgets

for project

implementation.

Date

achieved

20-

December-

2005

30-June-2011 30-June-2011

Comments

(incl. %

achievement)

Achievement: 100% by number of Kabupaten providing the required O&M budget.

xvii

G. Ratings of Project Performance in ISRs

No. Date ISR Archived

DO IP Actual

Disbursements (USD millions)

1 06/25/2008 Satisfactory Moderately Satisfactory 3.79

2 06/24/2009 Satisfactory Satisfactory 5.63

3 02/13/2010 Satisfactory Satisfactory 8.97

4 06/27/2011 Satisfactory Highly Satisfactory 12.21

H. Restructuring (if any)

N/A

I. Disbursement Profile

The Grant has been fully disbursed. Disbursement Profile for NTB-WRMP is not

available in the system because it is not treated as a separate project due to its special

relation with the WISMP 1 project, although NTB-WRMP has its own project

number.

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

1.1.1 Country and sector background: Water resources and irrigation management plays an

important role in Indonesia‟s socio-economic development in terms of food security since

most grain production is from irrigated areas. Development of water resources and irrigation

between the 1970s and mid 1980s focused on achieving and maintaining self sufficiency in

rice after a period of serious food shortages. During five consecutive five-year plan periods

starting in 1969, some 2.5 million hectares of irrigation areas were rehabilitated and 1.7

million hectares of new areas were developed. River basin management was mainly seen as a

requirement for securing irrigation supply and flood protection. Such efforts were supported

by massive expansion and farm input programs leading to self sufficiency in rice in 1984.

1.1.2 However, the government could not maintain rice self-sufficiency after that. One of

the main reasons was the lack of attention to and funding for operation and maintenance

(O&M) of the newly rehabilitated and developed irrigation systems. The subsequent rapid

deterioration of the physical systems resulted in frequent and premature rehabilitation or

deferred maintenance of the infrastructure. In the late 1990s it became clear that such a supply

driven approach led to unsustainable use of water resources and poor cost recovery.

1.1.3 In response to the financial crisis, the government embarked in 1998 on a process of

democratization and decentralization. This also involved reform of the water resources and

irrigation sector aiming at devolution and unbundling of management responsibilities to

provincial and district governments. It introduced stakeholder participation to enhance

sustainable management of the resource and infrastructure, and put more emphasis on demand

responsive and decentralized service delivery.

1.1.4 These reforms were fully supported by the Bank. The Country Assistance Strategy

(CAS) (2001) had three main objectives, (a) promoting broad-based growth; (b) building

national institutions for accountable government;, and (c) delivering better public services to

the poor, including support to local governments that put reform into practice. The WISMP

program and this first phase project contributed substantially to objectives (b) and (c) of the

CAS.

1.1.5 Rationale for Bank Assistance: After the 1997/98 financial crisis, the Bank played a

leadership role through its support to the regulatory reform (Water Resources Sector

Adjustment Loan (WATSAL, Ln. 4469-IND) (1999 - 2003)) and the large-scale field pilot of

new institutional arrangements for irrigation and basin water resources management (Java

Irrigation Improvement and Water Management Project (JIWMP, Ln. 37624) (1995 - 2002)

and Indonesia Water and Irrigation Reform Implementation Project (IWIRIP, TF 29896)

(2001 - 2004) resulting in a new Law on Water Resources in 2004. Other donors were also

actively supporting the reform process, leading to the formation of the Donor Water

Resources Sector Support Group in October 2000. The Asian Development Bank (ADB) and

the Japan Bank for International Cooperation (JBIC), which both held larger water resources

portfolios than the bank, increasingly adopted the principles and concepts emerging from

JIWMP and WATSAL. As a result, both ADB and JBIC harmonized their own project

designs, culminating in the ADP Participative Irrigation Project (PISP) and participatory

approaches in JBIC loans for small-scale irrigation management projects. The Government of

Indonesia‟s intention was to implement these reforms in the decade up to 2014. Due to its

deep involvement in WATSAL and the other projects piloting the reforms, the Bank was well

positioned to support WISMP to implement and further the sector reforms. Furthermore, the

Bank‟s long-standing involvement in Indonesia‟s water sector provided a sound basis for

project design, in particular sequencing priorities and benefiting from earlier project

implementation experiences.

2

1.1.6 When GOI and the European Union (EU) decided to undertake a project with similar

institutional reform goals with more poverty focus in the province of Nusa Tenggara Barat

(NTB), it was agreed that the EU grant could best be administered by the Bank. In addition to

increasing the geographic coverage of the WISMP water sector reforms, it was in line with

the on-going Good Governance in Water Resource Management Project (GGWRMP)

financed by EU and covering three river basins (respectively in DI Yogyakarta, East Java and

Lampung).

1.2 Original Project Development Objectives and Key Indicators

1.2.1 The WISMP was designed as a twelve-year adaptable program loan (APL). The

WISMP program objectives were as follows:

(a) Sustainable and equitable management of surface water resources and their

utilization infrastructure by: (i) transparent sector governance institutions and, (ii)

more accountable and better performing sector agencies;

(b) Increased irrigation farm household incomes and improved regional food security

as a result of raising the overall productivity of irrigated agriculture and reducing its

vulnerability to natural and economic shocks through: (i) sustainable participatory

irrigation management for more reliable and equitable water provision and, (ii) better

agricultural and marketing support services for members of irrigation water user

associations; and

(c) More cost-effective and fiscally sustainable management of sector agencies.

1.2.2 Within these overall program objectives the project development objectives of the

WISMP Phase I (WISMP1) were stated as follows:

(a) Water allocation, water quality and water conservation improved in Project basins,

and river infrastructure better maintained, through strengthened capacity for planning

and management; and investments;

(b) Sector governance enhanced, and sector fiscal sustainability strengthened,

nationally, and in Project basins, through setting up Water Resources Councils

(WRCs); ensuring stakeholder involvement; unbundling of operational tasks, and

Private Sector Participation; and improved cost recovery; and

(c) Increased agricultural productivity and improved performance of irrigation, based

on participatory irrigation management, through setting up and strengthening Water

User Association Federations (WUAFs); strengthening restructured Local

Government Public Works Water Resources Departments (Dinas PUPs); financing

rehabilitation and improvement of existing irrigation schemes; and facilitating access

to agricultural support services and micro-credit.

All the triggers for WISMP to migrate to Phase II (WISMP2) were met satisfactorily and

WIMSP 2 loan was approved in 2011, and is now under implementation. This ICR covers

both the WISMP1 and NTB-WRMP projects as approved by the OPCS.

1.2.3. The NTB-WRMP had similar institutional reform objectives with a more clear focus

on poverty alleviation by being located in one of the poorest provinces of Indonesia over a

five year project period. The purpose of the Grant was to assist the Recipient in attaining a

strengthened water and irrigation sector in its Province of Nusa Tenggara Barat and in the

Kabupatens in the said province by improving the performance of the Province‟s and the

Kabupatens‟ water resources and irrigation sector, and rehabilitating and upgrading the

infrastructure of said sector.

3

1.2.4 The Key Indicators identified for the WISMP project were as follows (See details in

the Data Sheet):

Governance and Institutional Capacity-building: National Water Council (NWC)

established and focusing on implementation of the National Water Policy (as a transitional

arrangement, the National Coordination Team (of Ministers) for Water Resources

Management is upgraded). Basin policy decisions and basin agency operations are transparent

and reviewed by provincial and basin councils or committees that include stakeholders

(including representation of the interests of women and vulnerable isolated indigenous

peoples). Irrigation schemes are governed by WUAFs in partnership with kabupatens via the

Komisi Irigasi, which have stakeholder representation. Water use rights system piloted for

more rational and fair water allocation and providing for in-stream needs.

Management Performance of Sector Agencies: Management audits show that kabupaten

agency assistance to WUAFs is participatory and effective, with Management Information

System (MIS) being maintained, hydrology operations improving, and National Water

Quality Monitoring Network operational in pilot sites.

Fiscal Sustainability of Sector: Cost recovery mechanisms for river infrastructure

maintenance identified and arrangements made for its implementation. Arrangements for fees

on effluent discharges and for water abstraction were operationalized in two basins. KIIF

funds disbursement on a matching basis under way.

(Initiation of) Integrated Approach to Irrigated Agriculture Support: Farmers use extension

services more regularly, raise income (i.e. increased farm incomes).

1.2.5 The Key Indicators for NTB-WRMP were analogous to those for WISMP and were

as follows (See details in the Data Sheet):

(a) A Provincial Water Resources Council (PWRC) with appropriate stakeholder

representation and its Secretariat established and functional;

(b) Basin Water Resources Council (BWRC) established with appropriate

stakeholder representation and functional; (c) Balai PSDA covering entire provincial territory established and operational

with trained staff;

(d) A Dinas PUP Surat Keputusan has been issued for role sharing in

hydrometeorology between the relevant Dinas PUP and UPTD or Balai PSDA, and

the hydromet network operational;

(e) The provincial planning unit in Dinas PUP is established with appropriate

staffing and funding, and starts producing strategic and master plans for provincial

basins;

(f) Quality Assurance Plans and infrastructure maintenance plans produced and

being implemented;

(g) At least 60,000ha of irrigation system is co-managed by WUAFs;

(h) At least 160 WUAFs established in the 71 participating kabupaten;

(i) At least 100 IMF funding proposals received by the Irrigation Commissions

from WUAFs in the 7 Participating Kabupaten; and

(j) At least 3 Participating Kabupaten provide from their APBD at least

Rp60,000/ha O&M budget for their project schemes.

1 Originally 6 kabupaten but later Sumbawa was split into two.

4

1.3 Revised PDO and Key Indicators

1.3.1 The WISMP PDO remained the same throughout implementation. The loan/credit for

the project was negotiated but the signing and effectiveness of the loan was delayed by two

years because government wanted to ensure consistency with the new law on water

resources only issued in 2004 (Law 7/2004). The consequent changes in the legal and

institutional environment required changes to some key outcome indicators which were

amended accordingly (as expressed in the restated Development Credit Agreement (DCA) of

2009, and shown in the ICR Data Sheet). The PDO for NTB-WRMP was unchanged during

implementation. The key outcome indicators were amended through the Grant Agreement, as

shown in the ICR Data Sheet.

1.4 Main Beneficiaries

1.4.1 The primary target population of WISMP comprised:

(a) The water users in the Project‟s river basins in the 14 Project provinces, notably

men and women farmers, urban and rural settlements, industries, and communities

that depend for their livelihood on water from the rivers;

(b) Men and women farmers, as well as landless laborers and by extension the rural

population, in the Project areas, as they will benefit from better water availability and

from programs to assist in strengthening the rural economy. As the Project intended

to cover approximately 2.35 million ha of irrigated area, it would affect around 6.7

million farmer households or 40 million rural dwellers that directly depended on

irrigation, whilst an additional group‟s income in the rural space depended indirectly

on the performance of irrigated agriculture;

(c)The population on Java as food security and environmental quality will be

improved; and

(d) The communities living in the upper catchment areas in the Project areas and that

would be assisted with programs to improve the management of the soils and land

cover to reduce soil erosion.

1.4.2 For WISMP 1 at least 1.3 million poor farm families, especially share-croppers, as

well as possibly 1 million daily laborers were likely to benefit directly from the more reliable

irrigation service and increased income, and indirectly from improved access to agricultural

information and extension services, and new business opportunities. For NTB-WRMP the

beneficiaries were estimated at around 200,000 households.

1.5 Original Components

1.5.1 The WISMP1 project has the following three components:

Component A. Basin Water Resources Management (Base Cost – US$56.7M)

A1. Sector Governance and Basin Planning (Base cost – US$14.1M): to assist in

establishing and/or strengthening of the following institutions: (a) National Water Council

(NWC) and its precursor the Coordination Team (of Ministers) for Water Resources

Management, with their Secretariats; (b) National Steering Committee for Water Resources

(NSCWR) plus Secretariat; (c) Provincial Water Resources Council (PWRC) plus Secretariat,

in 12 provinces; (d) Basin Water Resources Committees (BWRC) in project river basins; and

(e) Dam Safety Commission (DSC) and Dam Safety Unit. In addition, Provincial Planning

Units were to be established as well as the Central Basin Planning Unit.

5

A2. Management Capacity of Basin Agencies (Base Cost - US$10.4 M): to establish

and/or strengthen the River Basin Management Units (Balai PSDA), under provincial budget

and Basin Corporations (PJTs), including all studies, training and technical assistance.

A3. Fiscal and Cost Recovery Policy (Base Cost - US$2.00 M): to establish and/or

strengthen the fiscal position and cost recovery of water management in river basins through

funding to the Balai PSDA, PJT (Basin Corporations), provincial and kabupaten Bapedaldas

(Environmental Management Offices) and provincial Dinas PUP, contingent upon the Annual

Work Plan/Program (AWP) review.

A4. Basin Management and River Infrastructure Improvement (Base Cost - US$28.7

M): including: (a) support for operation and monitoring; (b) river infrastructure maintenance

(RIM) - operationalization of asset management and routine maintenance; (c) prioritized

urgent repairs of key river and flood control infrastructure; and (d) establishment of a

National Water Quality Monitoring Network.

A5. National Capacity Building Network (Base Cost - US$1.6 M): To develop a

sustainable human resources (HR) capacity building process for water resources and irrigation

management, it was necessary to reorient higher education programs towards multi-

disciplinary and integrated approaches.

Component B. Participatory Irrigation Management (Base Cost - US43.0 M)

B1. Water User Associations Capacity Building (Base Cost - US$8.3 M): to establish and

operationalize: (a) Kabupaten Irrigation Commissions (Komisi Irigasi), with Kabupaten

Dinas, WUAFs (GP3A) and other stakeholders and gender sensitive; and (b) scheme-level or

apex WUAFs (IP3A), and individual WUAs, with voluntary active women‟s participation

(GP3A,IP3A2) in all schemes.

B2. Irrigation Department Capacity Building (Base Cost - US$5.1 M) at Kabupaten level

since the role of Kabupaten Dinas PUP would orient more to facilitation and be reorganized

so technical staff, extension workers (KF'L) and Community Organizers would work with

WUAFs to provide technical/management guidance for O&M and construction, including:

B3. Irrigation Infrastructure Improvement (Base Cost - US$26.8 M) funded Kabupaten

and provinces that adopted the institutional model of the irrigation reform PKPI. Once the

Kabupaten Irrigation Improvement Facility (KIIF) had been established WUAF could also be

funded.

B4. Irrigated Agriculture Improvement Program (IAIP) (Base Cost - US$2.7 M) aimed

to: (a) strengthen farmer organizations‟ (WUAFs) technical, organizational, and managerial

capacity to formulate demands and to interact efficiently and with bargaining power with

service providers (research, extension, agricultural inputs, processing, credit, etc.); and (b)

make service providers (public and private) more responsive (demand driven), farmer

oriented and accountable.

Component C. Project Management (Base Cost US$8.1M)

This Component would support the National Project Management Unit and the National

Project Implementation Units, as well as the Provincial and Kabupaten Project Management

2 IP3A is Induk P3A or apex WUAF and is the voluntary working entity of all GP3As in one irrigation

system

6

and Project Implementation Units. The following were the main Technical Assistance

packages to support Project Management: (a) Financial Management Service (FMS); (b)

Impact Monitoring and Evaluation Unit (IMEU); and (c) Preparation of WISMP 2.

1.5.2 The NTB-WRMP intentionally had an identical project structure, components and

sub-components. More specifically it has three components: (a) Basin Water Resources

Management (Euro 5.17 million); (b) Strengthening Participatory Irrigation Management

(Euro 4.60 million) and (c) Project Management and Technical Assistance (Euro 0.93

million). Despite this overall similarity, there was a significant difference in the proportion of

costs of the various expenditure categories between the two projects. For NTB-WRMP the

Services category (TA, Training, Studies and M&E) amounted to 56% of total costs and

Works to 36% compared with 46% and 37%3 respectively for WISMP.

1.6 Revised Components

1.6.1 There was no significant modification of the components in the program project,

except that under WISMP1 the activities related to dam safety management and some

activities related to water environment management were taken out. This is because: (a) the

dam safety management related activities were taken up by a parallel Dam Operational

Improvement and Safety Project financed by the Bank; and (b) the Ministry of Environment

had already got its own similar program funded by the Government.

1.7 Other Significant Changes

1.7.1 Changes in design. Some aspects of the Program changed after WISMP 1 was

approved in 2003 prior to the issue of UU 7/2004, such as the re-arrangement of irrigation

system and basin water resources management authority and mandates. These adjustments

mainly affected the irrigation component and were accommodated in the restated DCA and

approved by management:

Transfer of irrigation management authority to the WUAFs was replaced by

participatory irrigation management (PIM) as public irrigation asset ownership and

control was vested in the State. PIM Principles were agreed upon and confirmed in

the restated DCA;

Cost recovery through service fees by government agencies was precluded

through the Law on Water Resources and the regulations on public administration. As

a consequence, alternative mechanisms were developed through (i) enhanced

contributions from water users by sharing management tasks and responsibilities and

(ii) enhanced government budget allocations. Another consequence was that the

support for corporatization of basin agencies that recover costs from irrigation water

users could not be materialized.

1.7.2 Changes in regulations. The issuance of revised government and ministerial

regulations necessitated a further adjustment at the Mid-Term Review (MTR) through a DCA

Amendment. This involved some changes in the key indicators.

1.7.3 Changes in financing mechanism of GoI contribution. The co-financing method for

the GoI contribution was changed into parallel financing for participating provinces

and kabupaten to harmonize central and local government project budgeting

processes. Under the initial co-financing arrangement both central government

budget (APBN) and local government funds (APBD) were applied together which

3 Including all River Infrastructure Maintenance (RIM) expenditures.

7

caused administrative difficulties during implementation. Parallel financing separated

the central and local budget processes. After the change, disbursement increased

significantly. The change was approved by the management and incorporated in the

DCA amendment of 2009.

1.7.4 Changes in implementation arrangements. Following the issue of Government

Regulation 38/2007, the responsibility for guidance to WUAF was changed from MoPW to

MoA. This had only budgeting consequences as MoA was already fully engaged in the

implementation process. This minor change was approved by management through the

supervision aide memoire.

1.7.5 Changes in scope and scale. The scope of activities remained the provincial and

district water resources and irrigation agencies and their river basins and irrigation systems.

National basins and systems were excluded from the project after the new water resources law

UU 7/2004 because of the lack of downstream regulations on management arrangements for

national basins. The geographic scope of activities increased during the implementation of the

program and was approved by management through the supervision aide memoires:

The number of provinces included increased by 2 to 14 with the inclusion of Aceh

and the splitting of South Sulawesi into South and West Sulawesi;

For the Basin Water Resources Management component, the initial number of 42

basins grew to 54 basins due to re-delineation of the river basin boundaries in 2006;

For PIM the number of participating districts (kabupaten) grew from 70 initially to

ultimately 99 due to splitting of 6 participating districts and the introduction of 23

new districts in 2009 for initial introduction of the reform only.

1.7.6 The above changes also affected NTB-WRMP. In addition, during implementation

increased attention was given to watershed conservation, which was an issue of particular

relevance to NTB, but of less crucial interest to most of the 12 provinces covered by WISMP.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

2.1.1 Soundness of Background Analysis: WISMP was an extension and consolidation of

the broad and coherent support the Bank provided from 1997 onwards. This support

emphasized institutional development. It took both the form of gradual introduction of new

administrative and regulatory mechanisms at local and national government levels, and the

extensive piloting thereof in the field. Even after the issuance of proper “facilitating”

national-government regulations, few local governments were able to act upon them. Water

users, and especially farmer irrigators, were ill prepared to assume their new responsibilities.

Progress was slow since the local governments, newly empowered by the 1999 Regional

Autonomy Laws, and civil society-based organizations had to adjust and develop the requisite

local consensus and absorb the new opportunities.

2.1.2. JIWMP first introduced and piloted novel irrigation management arrangements on

Java and notably set up, and “coached” a large number of autonomous, self-governing

Federations of Water User Associations (WUAFs) of irrigators. JIWMP also introduced and

supported River Basin Management Units under provincial governments (Balai PSDA) and

Water Resources Management Committees to foster integrated resource management and

enhance accountability. In parallel, WATSAL built on this new body of field experience, and

supported the development of a broad-based framework of policy, legal, regulatory and

administrative reforms at national and local levels. Thereafter, IWIRIP replicated these

reforms in seven provinces outside Java, whilst continuing support in the Java provinces. The

pilot reforms under JIWMP and IWIRIP had been successful as demonstrated in a

8

representative household survey completed in April 2003. They appeared robust after four

solid years of field implementation, and the gradual consolidation of the new legal and

regulatory frameworks at the national level. These pilot areas covered approximately 235,000

ha in 63 kabupatens in 12 provinces.

2.1.3. WISMP Phase I was the response to the challenges of the reform implementation and

a consistent and systematic extension of this prior support, whilst offering the opportunity to

further improve and adapt the institutional designs to Indonesia‟s diversity. Project

preparation and design was therefore firmly grounded in a wealth and depth of prior

experience and piloting. The whole WISMP program was sensibly structured as a three-

tranche, 12-year APL, which ensured the longer period of continued financing required with

benefits not only in continuity but also greater flexibility.

2.1.4 Assessment of Project Design. The project development objectives (PDO) were well

chosen and appropriate, stressing better water allocation and water conservation, better sector

governance, and increased agricultural productivity and improved irrigation performance. The

division of the project into two main components, one mainly supporting change in overall

management and planning institutions and the other looking at participative irrigation

management and strengthening of Water User Associations and Federations (WUAs/WUAFs)

struck a good and sensible balance. However, project design was too complex and ambitious

in a number of respects, although such design may well be justified for an institutional reform

oriented operation of this nature: (a) the project‟s geographic coverage extended to 12

provinces and included 70 kabupatens4; (b) the project supported a wide range of reforms and

initiatives through some 9 sub-components; (c) project organization was also complex,

involving four ministries, namely the Ministry of Public Works, formerly the Ministry of

Settlement and Regional Infrastructure (Kimprawil), the Ministry of Home Affairs (MoHA),

the Ministry of Agriculture (MoA) and the Ministry of Environment (KLH). Implementation

arrangements involved setting up Project Management Units (PMU) and Project

Implementation Units (PIU) for each of the participating Ministries at each of the three levels

– national, provincial and kabupaten; (d) the project was co-financed by the Government of

Netherlands and the associated NTB-WRMP project parallel financed by the European

Union.

2.1.5 The project scope, both geographically and in the range of activities, supported

imposed a heavy burden on both project management and Bank supervision. Setting up the

many PMUs and PIUs required significant new recruitment and created difficulties in getting

staff of adequate qualification and experience. Overall guidance was provided by a National

Steering Committee (on Water Resources) chaired by the National Development Planning

Agency (Bappenas) with the main responsibility for implementation resting with the

Directorate General of Water Resources (DGWR) of Kimprawil and the participating

provincial and kabupaten governments. The decentralized approach adopted by the project

and Government‟s fiscal decentralization helped implementation. Adequate regard was paid

to Bank safeguard policies for environmental and social concerns.

2.1.6 Government commitment: The overall WISMP program and the WISMP Phase I

project constituted a major plank in the Government (GoI) policy of decentralization. GoI had

issued the new decentralization legislation covering administrative regional autonomy (Law

22) and fiscal balance (Law 25) in 1999. These major sector reforms were to be implemented

through the Five-Year Development Strategy (Propenas) which became law in 2000. At

project appraisal, GoI had completed the most significant parts of the Water Resources

Reform Program on which WISMP was based. All the 12 provinces and their constituent

4 From 2009 onwards, 14 provinces and 99 kabupaten

9

kabupaten had 2 to 4 years of piloting river basin management and participatory irrigation

management, and had started reforms at the local government level. 63 out of the 70

kabupatens had already adopted the irrigation reform principles and were participating in the

JIWMP and IWIRIP programs. In terms of river basin management, some 23 River Basin

Management Units (Balai PSDA) had been established in all the river basin territories (SWS)

of Java and a further 10 had been formed in the Outer Islands. The WISMP program and the

Phase I project were therefore at the heart of a major GoI policy initiative. Weak aspects of

government commitment were the more than two years delay in WISMP loan effectiveness,

the inability to introduce legislation to enable cost recovery and frequent late budget releases.

The two-year delay in loan effectiveness was due to the government‟s decision to await the

issuance of the new water law in 2004, which led to no disbursement before 2006.

2.1.7 Stakeholder commitment: Interest in improving irrigation system infrastructure and

management grew with the advances made by earlier projects. Local government, civil

society, farmer groups including WUAs and farm families were all enthusiastic about the

project. However, the speed with which this underlying commitment could be put into

practice depended on the time taken for issuing of the necessary laws and regulations at

national, provincial and district (kabupaten) levels.

2.1.8 Risks: The PAD identified a large number of risks. These included (a) the possibility

that the sector agencies would dominate the public consultation process; (b) that inadequate

priority and resources would be given to collect information for management information

system (MIS) establishment and M&E activities; and (c) that insufficient priority and support

would be given to the fiscal sustainability and cost recovery aspects.

2.1.9 The first of these risks has been successfully mitigated during project implementation

by encouraging the participation of water users and civil society. The other risks duly became

apparent during implementation. With such a large, complex and innovative project coming at

a time when political changes and strategy still remained to be consolidated there were clearly

many uncertainties and numerous risks to be faced. Three important risks were not listed: (a)

risk of implementation delays due to lack of the necessary laws, decrees or other legal

instruments to allow implementation to proceed systematically, particularly since in most

cases enabling legislation was required at the highest level in order to get – “by cascade” - the

necessary instruments at Ministerial, Provincial and Local Government levels; (b) delays in

release of government annual budget at the central and local levels, which has been a chronic

problem for many years; and (c) the over-frequent transfer of staff, which is also a

longstanding problem and one which has a very negative impact on building institutional

capacity, dissipates training impact and slows implementation. Considering the number of

uncertainties and challenges the project faced in implementation, a substantial overall risk

rating would have been more appropriate.

2.1.10 QAG “Quality at Entry”. The project was reviewed by the QAG and received an

overall rating of satisfactory.

2.1.11 NTB-WRMP did not share the experience of long involvement in water resources and

Bank projects and the same depth of background analysis. The fact that the province had

missed out on earlier assistance was one of the reasons for EU interest in funding. To enable

the project to run concurrently with WISMP it had to be prepared quickly and with a more or

less identical design as WISMP. There do not appear to have been very substantial inputs of

government officers in project identification and appraisal. The project assessment was

carried out on the basis of a consultant assessment report, and there was not a formal appraisal

mission nor a project appraisal document. As a result, the design in terms of activities to be

undertaken was identical to those included in WISMP and were not tailored to the particular

needs of NTB, especially in regard to the need for catchment rehabilitation and management.

Also some aspects of the design were inadequate, most noticeably in relation to M&E. There

10

was a serious lack of definition of appropriate key performance indicators, and there was no

baseline survey. Consequently whatever M&E data was eventually collected provided little

help to project management since the results could not be interpreted5.

2.1.12 The project design was almost identical for WISMP 1 and NTB-WRMP. Under the

WISMP Program, the first phase project focused largely on institutional change and capacity

building. In contrast, NTB-WRMP‟s targeting of agricultural productivity and income

improvement, although not officially part of the project objectives, appears overly optimistic.

The degree of commitment of both the provincial and local governments and other

stakeholders on the other hand appears to have been equal to or greater than that for WISMP,

perhaps as a result of the grant financing.

2.1.13 Recognizing the relative lack of experience in project implementation, the NTB-

WRMP had significantly heavier technical assistance (TA) and training inputs than WISMP.

This emphasis in support for institutional change and capacity building was a strong feature

of the project design.

2.2 Implementation

2.2.1 During WISMP I and NTB-WRMP implementation there were a number of factors

which affected the projects. These include:

(a) The issuance of Law 7/2004 meant that the strategy of handing over irrigation

authority to the WUAFs had to be modified to that of participatory irrigation

management (PIM). It also meant that water users could only share in operating costs

by taking up specified tasks and responsibilities and providing their labor. Cost

recovery through service fees was precluded.

(b) Initially, WISMP1 included 12 provinces and 70 kabupatens6, of which 63 had

participated in the precursor JIWMP and IWIRIP programs. As implementation

progressed, the project scope expanded to include 99 kabupatens and 54 river basins.

(c) Problems in timely release of budget were partially solved at MTR by modifying

financing arrangements from joint to parallel financing for both central government

funds (APBN) and local government funds (APBD). Nevertheless, the problem of

late release of APBN continued to affect the pace of implementation.

(d) Staff continuity and capability, particularly at the kabupaten and field levels often

proved difficult. Although the project had a large training program, the rapid transfer

of staff meant that the staff training benefits were often either very much diluted or

lost entirely.

(e) Recruitment and fielding of TA teams was delayed until late 2007. Some TA

support during the initial period was provided by bridging TA from IWIRIP and later

5 The project design was much criticized in the EU Final Report (page 19) (Final Evaluation of the Nusa Tenggara

Barat Water Resource Management (NTB-WRM) Project Submitted November 2010 and revised January 2011. 6 North Sumatra (2) West Sumatra (2) South Sumatra (2) Lampung (2) East Nusa Tenggara (2) Central Sulawesi

(3) South Sulawesi (12) West Java (8) Central Java (17) DI Yogyakarta (5) East Java (15) Banten (only river basin

management).Numbers in brackets refer to number of kabupatens. During implementation on their request

additional provinces and kabupaten joined the project: Aceh Province (2) in 2006, West Sulawesi after the split

from South Sulawesi in 2007, a number of new kabupatens (17) were added (also due split) so that total numbers

in the project at the end of implementation is 14 provinces and 99 kabupatens.

11

through individual consultants. The support provided by local consultants was

variable in its impact. Much of the consultancy input for MPW was delivered at the

central or provincial headquarters level with little support provided at the kabupaten

or field level, where it was most required. In contrast, most of the TA for MOHA was

delivered at the kabupaten level.

2.2.2 The new Water Law also had a major impact on the Basin Management Component

in that it led to reorganization of river basins (SWS), shifting most of the important basins to

central management and thus excluding them from the WISMP program in line with the

project design. Much of the staff from the provincial agencies that were involved in basin

management functions were moved to the central agencies for managing the central basins.

This also disrupted the flow of funds to the provincial basins.

2.2.3 NTB-WRMP initially got off to a slow start due to the changing political situation,

elections and delays in processing and approving provincial legislation required the

establishment of the Provincial Water Council (Dewan SDA) and Basin Water Councils

(TKPSDA). Originally it was expected that these would be established by the end of

December 2006. However, the final version of the Governor‟s Decree establishing the Dewan

SDA and specifying its membership was issued only in July 2009, followed by a decree from

Dinas PU to establish the council‟s secretariat in August 2009. Establishment of three

TKPSDAs, respectively in Lombok, Sumbawa and Bima Dompu was similarly delayed. The

decree to establish the Lombok TKPSDA (Lombok being a national basin) was issued in

February 2009, the one for Bima Dompu was established in 2010 and that for Sumbawa was

on-going at the time of the ICR.

2.2.4 Similarly, establishment of the three River Basin Management Units (Balai PSDA)

and the Water Resources Information Unit were delayed by the changes in the national legal

setting and the need to develop and approve local regulations. The required Governor‟s

Decree was issued in August 2008. However, due to budget and staff shortages the Balai only

became functional in April 2009.

2.2.5 In a manner analogous to delay in release of the Bank loan proceeds for WISMP, a

major cause of slow implementation of NTB-WRMP was the frequent delay in release of the

EU grant through the central government budget (DIPA), either due to delays in DIPA per se;

or as a result of late release of provincial counterpart funds (APBD) – which are expected to

be made available before DIPA can be released; or as a result of blocking of the DIPA due to

submission of unacceptable budget requests or submission of modifications to budget

requests. Both of these latter problems reflected a generic and pervasive lack of planning. The

problem of late release was also further aggravated by the accepted convention that for each

item of expenditure, funding had to be provided 80% from the EU grant (through DIPA) and

20% through the APBD counterpart budget. Following the MTR, the project and grant

agreements were modified to allow a more flexible approach while maintaining the overall

principle of the 80:20 share in funding. As a result of these difficulties expenditure on

Component A at end 2007 was less than 8% of total allocations.

2.2.6 As a result of tendering delays, the TA Team was mobilized only in January 2008.

Subsequently, activities lagged because the consulting firm was unable to mobilize an

adequate number of specialists. Of the six specialists who were to support specific activities

in Part A only the Hydrology Specialist was fielded in April 2008 and the MIS/Database and

Water Allocation Specialist in April 2009. Difficulty in maintaining a fully staffed TA Team

continued during the remainder of implementation.

12

2.2.7 Adequacy of staff, in numbers, qualification and continuity also proved a major

difficulty, as was the case in WISMP. Excessive staff relocation negatively impacted on the

whole project, in particular reducing the beneficial impact of training and capacity building7.

2.2.8 The MTR of WISMP and NTB-WRMP in February/March 2008 had a positive

impact on project performance. Although there were no significant changes in project design

or restructuring, a number of changes were made regarding procurement and funding

arrangements. Most importantly these allowed a change from joint to parallel financing and

greater flexibility in the procurement arrangements and increasing financing limits, including

amendments to the Development Credit Agreement (DCA) and the Grant Agreement (GA).

2.3 Monitoring and Evaluation Design, Implementation and Utilization

2.3.1. WISMP M&E design: The PAD (Annex 1) listed a large number of key performance

indicators. There were 14 End-of-Program Indicators, which were also in the nature of

outcome indicators, relating to the WISMP program. These were followed by 18 outcome

indicators (10 for the Component A and 8 for the Component B) and 39 output indicators.

However, only 10 outcome indicators were included in the DCA (7 for Component A and 3

for Component B). In hindsight the number of indicators was clearly too large and not all

indicators were readily measurable.

2.3.2. At the design stage, an Impact Monitoring and Evaluation Unit (IMEU) was engaged

to ensure that WISMP would have an effective and adaptive learning process. IMEU had

responsibility for monitoring and evaluating key outcomes and impacts of the water and

irrigation sector reforms and documenting perceptions and recommendations of stakeholders

about WISMP activities. As an independent M&E body, IMEU monitored WISMP outputs

and evaluated its outcomes and impacts, at the national, provincial, kabupaten, river basin and

irrigation system levels, and reported directly to the National Steering Committee For Water

Resources (NSCWR). However, IMEU only issued its first report in April 2009, barely 20

months before implementation completion. Technical support on M&E was provided

nationally to four NPIUs, and provincially to four PPIUs to monitor the output level

indicators of Dinas PSDA/Pengairan, Bappeda, and Dinas Pertanian. The NPMU took charge

of consolidating all the information from the NPIUs and PPIUs.

2.3.3. M&E implementation: In order to enhance the project monitoring and supervision

process, during the MTR, the Bank teams suggested revising the original set of indicators to

accommodate the changes in legal and institutional settings and sector environment. Some of

the changes were triggered by the new laws and regulations, in particular Water Law 2004

and Ministerial Decrees 11a, 12 and 138. Subsequently, three outcome indicators (for

Component A) and the target dates for all ten indicators (in the 2005 DCA) were revised

through the 2009 DCA amendment. Despite the wide range of indicators listed in the PAD,

there was no systematic tracking of the indicators to demonstrate the achievement until the

time of the Mid-Term Review (MTR), following which a revision of the key indicators took

place through a DCA amendment in 2009. Moreover, only four PDO level outcome indicators

7 The February/March Supervision Mission Aide Memoire cites that the staff of the Sumbawa Barat

KPIU had been replaced three times in the previous year. 8 Decree 11, 12 and 13 created the concept of geographical boundaries between national and provincial

river basins. The national river basin authority replaced and made obsolete some of the provincial

River-basin authorities. The objective of the project is to strengthen the local institutions; therefore, the

project has limited the scope of work at only the provincial level river-basin. The indicators have been

modified accordingly.

13

and one intermediate outcome indicator were used to report the findings and outcomes of

supervision missions in the Implementation Status Reports (ISRs).

2.3.4 M&E utilization: After the MTR, rigorous efforts were made to keep better track of

project achievement by introducing a list of measurable output indicators which were

included in each mission aide memoire besides the above mentioned key performance

indicators used in the ISRs. In parallel, the Borrower, through the technical assistance

provided under Component C involving both IMEU and PMU/PIUs, produced consolidated

evaluation reports with appropriate data for the final assessment of the project as detailed in

the Borrower‟s ICR. While all the output and outcome indicators in Annex 14 of the PAD are

included in the IMEU‟s final report, it is difficult to extract the overall assessment of the

sector wide achievement. Because of the delay in start-up of M&E and limited information

produced, the output was not used to inform decision making and resource allocation in

WISMP Phase I. The lessons learned from implementation of M&E under the WISMP Phase

I have been incorporated into the M&E design of the Phase II project.

2.3.5 Methodological “soundness”, data quality, and M&E sustainability. M&E was

handicapped by the large number of indicators that were expected to be monitored and the

system does not appear to have proved a worthwhile tool to project management in

implementation. The likelihood of insufficient priority and resources being given to collection

of MIS data had been correctly identified as a risk at appraisal, based on experience with

other projects in Indonesia and in the region. Even the provision of technical assistance

proved inadequate. Like other institutional strengthening projects much of the investment

under WISMP was in “soft” items such as training and TA. For these aspects M&E was

unable to measure the quality of such investments nor the benefits accruing from them. Future

sustainability of M&E will be ensured by the Phase II project.

2.3.6 NTB-WRMP M&E design was inadequate, as mentioned in paragraph 2.1.11. The

design assigned no clear responsibilities for M&E, nor suggested any M&E plan. Key

performance indicators were not well defined and there was no baseline survey, nor did the

design include any M&E inputs by the TA Team. As a result, M&E undertaken was confined

to monitoring of the project‟s financial and physical progress. Repeated requests by

supervision missions for more quantitative information on the project‟s progress remained

unsatisfied. Therefore, the information collected was of little use to project management in

informing decisions and learning lessons from the implementation experience.

2.3.7 The EU fielded M&E missions during the project period, including a mid-term

review mission and a completion evaluation mission. The findings and recommendations of

the EU missions on inadequate high-level guidance on the sector reform process, rigidity of

the financing/budget system and inactivity of some water resource councils and irrigation

commissions, as well as recommendations for improving project management were largely

incorporated in the remaining project implementation period. Recommendations such as the

need for strengthening the M&E system and more attention to the sustainability of new

participatory management institutions have also been considered in the design for the follow-

up program, the second phase of the Water Resources and Irrigation Sector Management

Program (WISMP2) under which NTB province and all districts have been included.`

2.4 Safeguard and Fiduciary Compliance

2.4.1 Generally speaking, project implementation in both WISMP and NTB-WRMP was in

compliance with the applicable Bank and government policies and requirements. The detailed

assessment is as follows:

2.4.2 Environmental and Social Safeguards: The Bank policy on environmental assessment

was triggered for this project. Environmental guidelines were developed as part of the Project

14

Management Manual to guide project staff on environmental safeguards management during

implementation. No significant environmental impacts were observed during site visits and

interactions with PIUs and local communities. However, the monitoring and reporting of the

process and results of environmental screening and management under the project leave much

room for improvement. The Bank‟s policy on Involuntary Resettlement was also triggered,

given that the physical works were minor and limited to the rehabilitation of the existing

system, simple frameworks for land acquisition and resettlement were prepared for the project.

No land acquisition with compensation was reported during project implementation. Very

limited land acquisition took place for the community-based irrigation canal rehabilitation. The

land was voluntarily donated by the land (paddy field) owners, which is a very common

practice for interventions aiming at improved irrigation water supply and drainage.

Furthermore, the Bank policy on Indigenous Peoples was triggered. Considering that the

project covers a number of provinces having indigenous groups, and the exact project sites

could not be identified during the project preparation stage, a simple indigenous peoples

framework was developed to guide the project implementation units in dealing with indigenous

groups if present in subproject areas. During project implementation, no issues on indigenous

peoples were reported partly because the program was implemented in a highly participatory

way.

2.4.3 Financial Management: Some financial management (FM) weaknesses affected project

implementation, including frequent delay in issuance or required revision of budget documents

(DIPA and DPA), and lack of random verification of 3rd

party invoices at the PMU level.

Delay in the budget document (DIPA) release proved to be a chronic problem during project

implementation mainly because different sources of funds have separate mechanisms and

process timing. IFR submission was delayed often because of the many layers of reporting and

data consolidation, and lack of effective information management system. The internal control

system appears to have worked adequately during project implementation, except in one

particular case which called for more careful verification and confirmation of third party

invoices in future.

2.4.4 Implementation of Anti Corruption Action Plan (ACAP): In general, the ACAP was

implemented diligently during the project period as illustrated by the following: (i) Information

disclosure: at the central level, information was displayed through the Ministry of Public

Works‟ website, and the website was complemented with the website of the Impact Monitoring

and Evaluation Unit (IMEU), which published reports and activities online. Participating local

governments with their own websites also featured activities and sub-projects funded by

WISMP; (ii) Participation: farmer groups, associations, and other groups such as academia

participate in the project in various forms. In some kabupatens, however, more support to

farmers groups in capacity building and improving collective decision making would have

been desirable; and (iii) Complaints Handling: various channels were available, at least at the

central level. The low level of complaints indicates that the channels may not have been widely

communicated. An INT case related to one of the TA consultancy contract under Component 1

of WISMP1 affected the full completion of some activities of basin water resources

management. The resolution of this case led to strengthened financial control through invoice

and payment verifications.

2.4.5 Procurement: Overall procurement implementation was in compliance with Bank

procurement policies and agreed procedures. The main issues related to procurement involved

generally inadequate procurement capacity at different government levels which were

enhanced largely by procurement specialists from the TA consultants. Delays in tendering,

particularly the key implementation support TAs substantially affected project progress in the

initial years. Some recurring weaknesses in procurement both at the central and regional

levels, notably in contract management, use of shopping method by the district implementing

units, were addressed through hands-on training.

15

2.5 Post-completion Operation and Next Phase

2.5.1 As set out in Section 2, the WISMP Phase I project was part of the larger WISMP

program, financed by an Adaptable Program loan (APL). As such the longer-term program

objectives of increased production and improved incomes and living standards will only be

achieved if the progress made under the first phase project is supported by continued

financing under subsequent phases. Four triggers were identified at appraisal for initiating

WISMP Phase II. These were. (a) four fully functional provincial river basin management

units (Balai PSDA); (b) fifty WUAFs legally established and functional with respect to

governance, maintenance and rehabilitation of schemes, financial sustainability, and using

extension services and credit; (c) operational guidelines agreed on river basin management

including environmental and social safeguards; and (d) fifty per cent of external funding

disbursed. All four triggers have been met or exceeded, confirming that the WISMP APL

program is ready for the next phase, which would include NTB.

2.5.2 Investments made and initiatives taken under the WISMP Phase I and the NTB-

WRMP projects will be further supported and maintained under the succeeding Phase II

project that was approved in March 2011. A major objective of the whole program is

participative irrigation management and an increased role of WUAs/WUAFs in operation and

maintenance of irrigation systems. This change will increase the overall sustainability of the

whole irrigation sector by reducing the burden on Government and allowing the sector

agencies to focus more closely on O&M of those major works that are beyond the O&M

abilities of WUAs and WUAFs.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

3.1.1 WISMP Relevance of Objectives: The project development objectives (PDOs)

(paragraph1.2.2) are as relevant at loan closing as they were at appraisal. Population growth,

urbanization, economic development and the impacts of climate change place increasingly

high pressure on land and water resources and increase the vulnerability of the nation to water

related risks such as floods. Under such circumstances, improved water allocation and

management, better sector governance and sector fiscal sustainability are critically important

for Indonesia. Greater involvement of stakeholders and the private sector , better coordination

of government agencies, rehabilitation of schemes where required with sustainable O&M

arrangements, leading to better services and increased water productivity and higher farm

income remain central to Government policies.

3.1.2 Relevance of Design and Implementation: The WISMP Program remains fully in line

with the national decentralization and democratization policies. The key elements of

interventions for improving planning and management capacity, governance and fiscal

sustainability and an integrated and participatory management approach at the river basin and

system levels remain highly relevant. A vital feature of the design was to make the program

an Adaptable Program Loan (APL) which provided the necessary time, flexibility and

security of financing essential for significant restructuring of a major government institution,

or group of sector institutions. The ability to spread the institutional changes over the duration

of the whole program has undoubtedly given a degree of flexibility that has had a strongly

positive effect on implementation, particularly in helping to address such long-standing,

delicate issues as division of responsibilities and collaboration between central, provincial and

district governments. Change in long established government institutions often tends to be a

long and slow process. What happens during implementation is therefore arguably more

important than the plans laid out in the project design.

16

3.1.3 NTB-WRMP Relevance in Objectives, Design and Implementation reflects the

project‟s close relationship with WISMP. As such, most of the assessments mentioned above

also apply to NTB-WRMP. The only significant point of difference is in the project‟s poverty

alleviation objective. No claim for immediate poverty alleviation benefits was included in the

development objective of WISMP. The fact that such benefits were claimed for NTB implied

that the province – one of the poorest in Indonesia and without the advantage of involvement

in earlier Bank projects – was capable of achieving in five years what for WISMP could only

be achieved in the second phase. The objective of poverty alleviation was therefore overly

ambitious and not strictly relevant to project implementation as a one province expansion of

the WISMP program.

3.2 Achievement of PDO

WISMP 1

3.2.1 PDO (a). Water allocation, water quality and water conservation improved in Project

basins, and river infrastructure better maintained, through strengthened capacity for planning

and management and investments. This PDO is considered partially achieved although the

M&E system wasn't really able to well capture progress towards achievement of the PDO.

Water allocation plans were prepared for 9 basins through a participatory approach to enable

more equitable allocation and reduce water use conflicts. Progress was slower than expected

in developing a Water Use Rights Framework. The upcoming Government Regulation on

Water Use Rights will be piloted in two basins under WISMP 2. Similarly, developing a

strategic framework for environmentally sustainable river basin planning has also moved

slowly. Training was undertaken for 53 Balai PSDA and 11 Balai (B)WS. Although some

progress has been made in water quality classification, the assessment of the more profound

impact on the aquatic environment could not be undertaken in the absence of MoEnv

regulations and their participation, and it is not very clear how effective the water pollution

control is for lack of related data. Much of the activity in water quality pertained to setting up

ambient water quality network stations on selected rivers, collecting and analyzing data and

publishing in-stream water quality. In each of the 14 Dinas PUP, Surat Keputusan9 has been

issued for role sharing in hydrometeorology between the relevant Dinas PUP and UPTD or

Balai PSDA in each participating province. The hydrometeorology asset management

function was fully transferred from the Dinas PUP to their Balai PSDA. Hydrometeorology

network rationalization has been completed in 48 Balai PSDA, and implemented and fully

operational with adequate operational budget in 24 Balai PSDA. Four Balais PSDA have been

improved in terms of hydrological information and database, water quality monitoring and

pilot water allocation & management, as a result of on-the-job training, improvement of

facilities and other capacity-building activities. MoPW has staffed and funded a national basin

planning unit. Two provinces have established Basin Planning Units (BPUs), one of which

has prepared basin strategic and master plans. Planning units have been established in most of

the Dinas PUP, but lack adequate staff and are therefore at present non-functional. Only some

Basin Water Resources Committees (BWRCs) (mainly in Java) have reviewed basin strategic

and master plans (including investment prioritization and review) and 13 PWRCs have

prepared a draft provincial policy on water resources. With the establishment of the necessary

legal and administrative decrees in all project provinces completed in 2010/2011, PWRCs and

BWRCs are expected to become more active in decision making in water resources planning

and management related decisions and activities. The project has also seen different levels of

improvement in the management performance of provincial basin management units (Balai

PSDA).

9 Local Government Decree.

17

3.2.2 Satisfactory results were achieved from the Basin River Infrastructure Maintenance and

Management (RIM) sub-component, as observed in the supervision mission and interviews

with the beneficiaries, in spite of limited investment. The small scale rehabilitation and

upgrading works for improving bulk water supply and flood risk management in some 50 Balai

PSDA, have yielded expected outcomes. Furthermore, through public consultation and

beneficiary participation not only the river infrastructure investments and O&M were better

aligned with regional priorities, but the quality and cost-effectiveness of the project works

were improved as well. River infrastructure works, especially in the Citarum basin financed

under the project, are providing intended benefits to the beneficiary communities (protecting

houses, schools and home industries from seasonal flooding, which has both an economic and

social benefit), despite the fact that they could have been more closely linked to water

resources management planning in the respective basins. The RIM program involved

rehabilitation and/or upgrading of river infrastructure. The river infrastructure is expected to be

better maintained as asset management is practiced and quality assurance practice enforced10

.

3.2.3 Good progress has been made in establishing Management Information Systems

(MIS). Six provincial Dinas PUPs (and Balai PSDA) have developed MISs linked to the

respective Bappeda. The system is intended to be linked to DGWR, but this has not yet been

achieved. Monitoring and Evaluation (M&E) has been developed covering 13 provinces and

84 kabupaten. With TA inputs and support from Bangda, M&E performance improved, but

remains less than required, and was largely confined to monitoring of the project‟s physical

and financial progress, and project outputs.

3.2.4 In support of capacity building, 10 universities and polytechnics have set up five new

modules for integrated water resource management as well as collaboration with the Indonesia-

Netherlands knowledge sharing program for the water resources sector.

3.2.5 PDO (b). Sector governance enhanced, and sector fiscal sustainability

strengthened, nationally and in Project basins through setting up Water Resources

Councils; ensuring broad stakeholder involvement; unbundling of operational tasks;

and Private Sector Participation; and improved cost recovery. This is virtually

achieved.

Sector governance has improved at the national, provincial and provincial basin levels as a

result of the institutional changes, multi-stakeholder forum establishment and capacity-

building of management agencies supported by the project. Most importantly, the

achievements include establishment of the National Water Resources Council (NWC) in

200911

(NWC). Thirteen out of the fourteen project provinces established Provincial Water

Resources Councils (PWRCs) by 2010, of which nine are functional. PWRCs are required to

have 50% beneficiary representation including women and vulnerable groups. Nine provinces

have established a total of sixteen Basin Water Resources Committees (BWRCs) in 2009/2010

covering national and provincial river basins with balanced government - stakeholder

representation including women and vulnerable groups. Nine BWRCs have started operating

but they still need further support for their development and firm grounding in the management

and administration systems.

3.2.6 The project has successfully supported role-sharing between the central, provincial and

district water agencies. In each of the 14 participating provinces a Balai PSDA has been

established, each of which is fully funded by the provincial government budget (APBD). All

10 This is expected to be a focus of WISMP-2 11

NWC was established and staffed in July 2008 but was formally established by PerPres 6/2009

18

71 participating kabupatens covering an area of 1.4 million hectares provide an average of

Rp130,000 (US$14) per ha, more than double the target figure. The revised DG Water

Resources Decree now provides the basis for Provincial Balai PSDA to prepare memoranda of

understanding (MOU) with national B(B)WS, so far mainly on hydrology management,

supported by training in 10 provinces. There has been improvement and rationalization of

hydrology networks in 15 basins involving the Balai PSDA as well as Balai (B)WS. To date

some 69 MOUs have been agreed, compared to the 11 originally expected. In going forward,

the role-sharing and financing arrangements between provincial and national basin

management units must be expanded beyond hydrology and water infrastructure O&M and

into core areas of water resources management. This is also anticipated in the second phase of

WISMP, and calls for more detailed and strong backing by government regulations.

3.2.7 The idea at appraisal that part of the costs of water management by the basin agencies

could be recovered has not been realized since Balai and Dinas as part of government lack any

legal basis for levying water management fees.

3.2.8 In conformity with the new Permen PU31/2007, 13 provincial irrigation commissions

(Komisi Irrigasi) have been established and 98 irrigation commissions at the kabupaten level

since 2007/2008. Most of these commissions started operating in 2007/2008 although further

strengthening is still necessary for them to meet the requirements and implement the tasks as

per PerMen. Women are also represented in the commission, but no data is available on the

extent.

3.2.9 PDO (c). Increased agricultural productivity and improved performance of irrigation,

based on participatory irrigation management, through setting up and strengthening WUAFs;

strengthening restructured Dinas PUP of local government; financing rehabilitation and

improvement of existing irrigation schemes; and facilitating access to agricultural support

services and micro-credit. This is fully achieved. The achievement of the project objective is

assessed mostly on qualitative information due to lack of systematic M&E data. However,

irrigation performance improvement and agricultural productivity increase are quite evident

from the field visit observations during supervision missions and from a number of surveys12

.

In all, 11 provinces and 70 kabupaten have adopted the irrigation reform principles through

issuing local government regulations on participatory irrigation management.

3.2.10 A total of 1,651 WUAFs have been established, of which 1,296 have been legalized to

undertake the lower canal (tertiary) system O&M and contribute to the management of

secondary systems. M&E surveys showed that out of 334 GP3A surveyed participation was

rated high in 74% of cases and moderate in 24%. The associated training activities includes

public awareness (208 sessions for 660 GP3A), development of socio-economic-technical and

cultural profiles or PSETK (172 sessions, 580 GP3A), organization (107 sessions, 209 GP3A),

and financial management (108 sessions, 209 GP3A).

3.2.11 A major sub-component was for the reformulation of tasks and responsibilities of the

Dinas PUP at the kabupaten level to enable implementation of its new mandates in providing

technical and financial support to WUAFs for system O&M. This has also involved a large

training and TA program covering 13 provinces and 56 kabupaten, as detailed in Annex 2.

12

Surveys were undertaken by the NPMU and the NPIUs with the assistance of different TAs. In

addition, the Padjadjaran University made a comparative analysis based on surveys in participating

kabupatens in 2009. These data are incorporated in the various reports (including the Government

ICR). The evaluation from the Impact Monitoring and Evaluation Unit (IMEU) under Bappenas also

reported on the production and productivity changes in the project areas.

19

3.2.12 Some 1,265 proposals for IMF funding by WUAFs in 64 kabupaten have been

presented to the Dinas PUP for review, of which some 470 have been endorsed to date and

included in annual work plans, compared to a target of 200.

3.2.13 In 18 kabupaten pilots were carried out to help strengthen the linkage of WUAFs to

market partners by providing special training programs on marketing, engagement with private

sector, post-harvest management, and provision of credit for investments in value adding

activities.

3.2.14 In summary, the Komir Irrigasi-WUAF-Dinas partnership structure established has

substantially improved irrigation services and management of primary and secondary canal

systems. The project has also strengthened the support of irrigation and agricultural services to

the WUAFs and participatory decision-making for irrigation management at the kabupaten

level. Consequently, System performance and sustainability have improved as evidenced by

more reliable and equal water distribution in the project schemes. Conflicts over irrigation

water use have been much reduced, for example in Central Java, as a result of the project.

Farmer user communities are now responsible for O&M of the lower canal systems and in

many cases contributing in cash or kind to main system O&M. This is in addition to a general

increase in local government budget for irrigation scheme O&M. Finally, in terms of

agricultural productivity improvement, the government‟s official statistics showed that in the

project areas the productivity rose by 15-20% on average through increasing cropping intensity

and yields, which was made possible in project areas by improved irrigation system

performance and agricultural support services. The impact observed is more profound

considering the radiation effect this project has had on government programs. Looking

forward, fully functioning of Komirs Irrigasi and WUAFs in the participating kabupaten still

requires continued support and nurturing. Further, dedicated efforts by the different levels of

governments are needed to allocate adequate O&M funding for the main systems of the

irrigation schemes under their respective jurisdictions. The experiences and lessons learned

from kabupaten schemes need to be expanded into provincial and national scheme

management with strong policy support. Finally, there is a need to continue the integration of

irrigation and agricultural development interventions within the program and between this and

other programs.

NTB-WRMP

3.2.15 PDO (a). Institutional strengthening of and performance improvement in basin water

resources management, and river infrastructure upgrading: This is largely achieved. Despite a

slow start, by the end of implementation the objective related to basin water resources

management has been largely achieved. The Provincial Water Council (Dewan SDA) and its

secretariat have been established and are functional. Two of the three River Basin Councils

(TKPSDA) were set up and the third one was being established at the end of the project. Dinas

PU has completed its institutional reform activities. Three Balai PSDA and the Balai ISDA

have been established and are functional. Initiatives have been taken through signing of MOUs

to facilitate role sharing in water resources management between national agencies and those

within the province. These MOUs enabled the Balai PSDA to be involved in management of

the national basin in Lombok and the provincial Balai to engage in management of other

assets, such as dams, which are under central government authority.

3.2.16 A Dinas PUP Surat Keputusan (Decree) has been issued for role sharing in

hydrometeorology between the relevant Dinas PUP and UPTD or Balai PSDA in the

Province, and hydromet asset management has been fully transferred from the Dinas PUP to

the relevant UPTD or Balai PSDA. Four Joint Operation Agreements between Dinas PUP and

Balai PSDA Lombok, Balai PSDA Sumbawa, Balai PSDA Bima-Dompu and Balai ISDA

20

were signed in 2007. All Balai PSDA including Balai ISDA have participated in basin water

resources management activities; the project has rationalized the hydromet network and put in

place the necessary staff and training, both in the Balai PSDA and in the Balai ISDA.

However, the impact and benefits from the training and capacity building in network

management, data collection and the associated training in GIS remain unquantifiable. No

M&E system recorded the results of the training and capacity building delivered by the

project. In many cases the selection of the staff to be trained was inappropriate. The over-

frequent staff transfer meant that staff either failed to complete the courses or were transferred

to other duties soon after training. Capacity building was also undermined by budget

shortages, particularly for transport which meant that even those who had completed part of

the course were deprived of the necessary opportunities for fieldwork. As a result of the

above, the effects of such technical training are uncertain.

3.2.17 Other training and capacity building activities, such as financial management,

procurement and water allocation are reported to have been successful in improving staff

competence. Capacity building and training to improve planning capability has only made

limited progress. This included the production of strategic plans for Lombok and Bima

Dompu basins.

3.2.18 The provincial planning team in Dinas PUP has been established with appropriate

staffing and funding, supervising the outsourced planning services. Strategic plans for

Lombok and Bima Dompu basins have been completed and legalized; and a strategic plan for

Sumbawa is under preparation.

3.2.19 The Basin River Infrastructure Maintenance and Management (RIM) sub-component

and the Water Resources sub-component have both made satisfactory progress. Following a

very slow start the RIM sub-component became active, at five sites in Lombok involving

mainly flood and river bank erosion prevention through construction or repair of bank cladding

and concrete structures. In a similar way the project financed re-greening of critical areas

including establishing trial plots in Sumbawa and Lombok. These pilot or study activities are

expected to provide the basis for larger scale investments in the future.

3.2.20 PDO (b). Institutional strengthening of and performance improvement in

participatory irrigation management, and irrigation scheme rehabilitation: This is

fully achieved. The Province and all the kabupaten have issued the necessary regulations

(PerDas) and established Irrigation Commissions (Komir). They have also established 214

WUAFs, of which 184 have already signed MOUs with the Governor or the Bupati. All the

Komirs have started functioning, with established secretariats and funding from the local

budget. The Komirs meet regularly to discuss irrigation-related issues, review WUAF

proposals and endorse the kabupaten annual irrigation plan. So far the Komirs have evaluated

91 proposals for financing by IMF which have been endorsed by the Dinas PUP. Half of the

Komir members are representatives from WUAFs and other independent, non-governmental

organizations. As a result of the improved coordination and collaborations between Dinas,

Komirs, WUAFs and WUAs, there has been very significant reduction in water conflicts as

evidenced in different irrigation systems in the projt districts. The area co-managed with the

WUAFs has reached 145,000ha, more than double the target of 60,000ha, and constitutes about

half the total irrigated area of the Province. The project has partly financed the rehabilitation of

287 irrigation schemes covering 188,250ha. Parts or all of the rehabilitation work was carried

out by the WUAFs, through co-management with the Dinas. The quality of the works

completed by the WUAFs is generally superior to that by contractors. Furthermore, the

Province and most of the kabupaten have allocated the target O&M budget of Rp60,000 (US$

6.7) per ha from the APBD. WUAFs are expected to be engaged in O&M, although some has

been given to contractors, which is not the aim of the project.

21

3.2.21 Agricultural development supported by the project appears to have had a significant

impact on crop production. The NTB Provincial statistics indicate a higher crop intensity with

harvest area increased by almost 10% between 2005/6/7 and 2007/8/9, while average yield of

paddy over the same period increased by over 4%. However, in the absence of any adequate

M&E system or any control group of farmers it cannot be decisively stated that all of these

increases are due to the project. Technical assistance and training have been provided for a

package including (i) System of Rice Intensification (SRI)13

; (ii) integrated pest management,

(iii) agribusiness development; and (iv) adaptation to climate change. Such supports have been

very well received by farmers. Demonstration plots of SRI over a land area of 200 ha resulted

in adoption of this technology over an area of 2,000 ha by the farmers, with a yield increase of

20%-40% compared with conventional rice production systems.

3.3 Efficiency

3.3.1 Through the establishment of new democratic and participatory management

institutions, both WISMPI and NTB-WRMP have provided more reliable and efficient water

delivery to irrigated agriculture, and generated confidence among farmers/irrigators in

planning and implementing improved agricultural practices. As a result, agricultural

productivity has increased. Specifically the increase of crop production is due to: (i) enhanced

cropping intensity; (ii) crop yield increases; and (iii) changes in crop patterns shifting to

higher value produce. Also the change of the government agencies towards service

orientation and facilitation has been an important contribution. In calculating the above the

types of the project benefit from the incremental crop production, crop budgets have been

prepared for the “with project” and “without project” situations. Benefit aggregation is based

on physical achievement by year and incorporates the cropping pattern changes. Other

benefits not accounted for in the analysis include (i) cost savings from appropriate and timely

river infrastructure maintenance; (ii) cost savings relating to improved management of

flooding and mitigation of associated loss; (iii) efficiency gains from institutional

strengthening and development associated with the program; and (iv) conflict reduction

between upstream and downstream water users. The overall project ERR is for WISMP

estimated at 23%, which indicates the project is economically viable and robust.

3.3.2 Financial analysis has been conducted, using crop budgets and farm models under with

and without project situations to gauge the financial attractiveness to the farmers. The results

of the farm household income analysis show a substantial increase in farmers‟ income from

improved crop production with the implementation of the project, with the change in farm

household income increases in Java and outside Java at 32% and 27% respectively.

3.3.3 For NTB-WRMP, though no systematic and verifiable data available from M&E, it is

generally believed that the crop yield and cropping pattern increases achieved under the

project were higher than in non-Java areas under WISMPI. As such, adopting same approach

for economic analysis and using non-Java data for crop production, it was conservatively

estimated that the ERR for NTB-WRMP was at 21%.

3.3.4 In comparison with the without project situation, the fiscal impact of both projects are

largely positive as the Project introduced participatory operation and maintenance (O&M)

practices for target irrigation schemes. The funding for O&M for tertiary canal systems after

rehabilitation has been covered by the WUAs and WUAFs, while the O&M costs for the

improved secondary and main canals, which are noticeably lower after rehabilitation, are

covered by the government as per current water sector policies.

13

SRI has been developed over the last 30 years and includes planting seedlings at less than 15 days

old, optimal spacing to allow weed control, careful irrigation to create aerobic conditions, and use of

compost.

22

3.4 Justification of the Overall Outcome Rating

Rating: Moderately satisfactory

3.4.1 Based on the above considerations and as also reflected in the Data Sheet and Annex

2, the overall outcomes of both WISMP 1 and NTB-WRMP projects are rated as moderately

satisfactory

3.5 Over-arching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects and Social Development

3.5.1 WISMP 1 did not have a specific poverty focus. However, most of the farmer

families benefitting from the project are poor. Direct beneficiaries are estimated at some 1.3

million families, or around 7.8 million people. Overall in all the provinces covered by the

project there are some 6.7 million farmer households or about 40 million people who depend

on irrigation. The data available from surveys indicates that these groups have already started

to benefit under this first phase of WISMP and these direct benefits are expected to continue

to grow under the proposed second phase.

3.5.2 NTB-WRMP had a specific poverty alleviation focus. The total population of NTB

Province at appraisal was reported to be around 4.1 million, almost 60% falling into the two

lowest economic status categories. Within the province, densely populated East Lombok was

particularly poverty affected. Because of the lack of an adequate M&E system and baseline

data it is difficult to assess the project‟s impact on production, farm incomes and poverty

alleviation. Some indications can be drawn from the provincial statistics. The official

statistics show that over the period from 2005 to 2009 the incidence of poverty declined by

3% in Lombok Timur kabupaten and 7.6% in Lombok Barat. In the two areas not covered by

the project, poverty incidence in Kota Mataram and Kota Bima increased by 5.4% and 0.3%

respectively. Absolute numbers of poverty effected persons declined by over 13% in the

seven project kabupaten and increased by 45% in Mataram and Bima. Some 200,000 farmers

(representing around one million people) in the seven kabupaten were reported to be WUA

members. It can be expected that the project‟s support to decentralization of water sector

management and greater participation by farmers and WUAFs in irrigation will have a

beneficial effect in reducing poverty in the medium and longer term.

3.5.3 The project promoted women‟s participation in project implementation as

stakeholders, decision-makers and beneficiaries. This is particularly true with the

participatory irrigation management component. Despite the lack of adequate monitoring and

gender disaggregated data, generally very positive changes in terms of increasing women‟s

participation in the project activities such as WUA/WUAF establishment and management,

irrigation and agriculture improvement activities and practical training14

, were reported by

different PMUs and WUAFs through their progress reports and WUAF profiles during project

implementation. The project benefited women„s groups and women-farmers (widows,

divorcees, households in which the husband was away from home for prolonged periods

earning a salary in the non-agricultural sector) since they would have better access to water

for household use, for agricultural production and for rearing of poultry and small livestock.

3.5.4 Social development has been encouraged by the project through the establishment

and support to WUAs, WUAFs; water resources councils and irrigation commissions. All

14 In conformity with Muslim religious custom, men and women do not participate in the same public

events unless they are family members.

23

these increase rural communities‟ participation in planning, construction and O&M of water

resources and irrigation infrastructure and have resulted in strengthening of civil society in the

project areas. The creation of WUAs and WUAFs has had benefits beyond purely improved

water management and irrigation. The groups have helped to develop a range of income

generating activities and have enabled linkages with the private sector, particularly in

improving farmer‟s access to market and in introducing contract farming practices.

Involvement of WUAFs in rehabilitation or improvement of works has been particularly

successful, either through joint operation with a contractor, labor contribution, or through a

service agreement where the WUAF takes the place of the contractor. Such engagements have

resulted in greater transparency, fewer opportunities for leakage of funds and better

ownership by the farmer users. The fact that all three systems provide direct benefit to the

local village economy and strengthen the relationship between the users and the service

provider is an additional bonus.

(b) Institutional Change and Strengthening

3.5.5 Sector Governance. With the establishment of National, Provincial and Basin Water

Resources Councils and the Irrigation Commissions under both projects, platforms have been

created for the stakeholders to participate in the decision making processes regarding the

management of their water resources and irrigation systems. Following activation of these

platforms, accountability and transparency in the sector have been enhanced, effectiveness

and efficiency of budget use improved in the project areas. These platforms also create better

coordination and cooperation among the government agencies in development and

implementation of their programs, priority setting and creation of synergies and mutual

program support. This is most evident in the irrigation component as the development of these

councils for river basin management is quite recent. The role of these councils and

commissions in the future is essential not only for the management of the sector itself, but

also for creating the necessary linkages with the local planning processes.

3.5.6 Service Orientation. Traditionally the government agencies were supply and project

oriented. A change towards a demand and service orientation is ongoing and is more evident

for the irrigation sector. In particular, at the kabupaten level, the water user communities and

government agencies are beginning to manage the irrigation systems in partnership using the

irrigation commission as the decision making platform. For basin water resources

management, such mechanisms still have to evolve as the stakeholder platforms are only

recently established. Moreover, the development of an effective system of accountability in

basin management requires more time as the uses and users of bulk water services are more

diverse, less aware of the water issues and historically less involved in water management

decision processes. The service orientation is least developed in the national systems as

operation and maintenance is usually delegated to provincial and district levels by the national

agencies that tend to be more project and construction oriented.

3.5.7 Capacity Building. The project made significant investments in technical and

management training and TA support for both government agency staff and for members of

WUAs and WUAFs. As a result, the professional competence of the government agencies

involved in WISMP is reported in the IMEU report to have improved, even if the impact has

been reduced by the frequent re-posting of staff. For the water users the training and TA

support have proved effective in introducing improved water management and helping

establish and operationalize the WUAs and WUAFs.

3.5.8 Cost Recovery. A fiscal policy study was completed under WISMP to recommend

policy actions to address the cost recovery issues of the sector. This included formulation of a

direct/indirect cost recovery system. At present any application of such a system is impossible

in the absence of a national policy. Law No.7/2004 excludes direct cost recovery for most

water uses including irrigation and confines direct cost recovery to abstractions for

24

commercial or industrial use. The participatory management supported by the projects

involving the users/stakeholders, introduction of asset management concepts and practices

and increased financial responsibility of local governments for system rehabilitation and

O&M all serve to reduce the overall fiscal burden on the national government and improve

cost-effectiveness.

(c) Unintended Outcomes and Impacts

3.5.9 Design and implementation of the two projects has proved to be a valuable vehicle in

bringing about closer collaboration between the main donors active in the water sector.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

3.6.1 As this is a Core ICR, neither a formal beneficiary survey nor a stakeholder workshop

was organized during the ICR preparation.

4. Assessment of Risk to Development Outcome

4.1 The fact that the institutional development and capacity building is a key objective of

both projects, lays a good foundation for post-completion operation of project facilities and

institutions. Another very favorable factor is that the operating/management agencies such as

Dinas, Balais PSDA and Irrigation/Agricultural Services, as well as such user community

organizations as WUAs/WUAFs, have been directly involved in project design,

implementation and on-the-job training from the start. As a result, transition from

implementation to operation becomes a straightforward process. In addition, the second phase

of WISMP APL (WISMP2), which started soon after WISMP1 and NTB-WRMP were

completed, covers virtually all participating provinces and Kabupatens including NTB. This

provides further assurance for sustaining the project interventions and results.

4.2 In terms of risks to sustaining project results and outcomes for both WISMP1 and NTB-

WSMP the following aspects deserve close attention and will need to be carefully managed in

the follow-up program (WISMP2). They are generic in character and therefore combined

below.

(a) Role sharing between national and provincial river basin management agencies. WISMP

focused on the improvement of management capacity at the national and provincial levels. In

the context of decentralization the project only involved provincial basins and agencies

because at the time of project appraisal all basin management was a provincial responsibility

(except for typical development and construction activities and 2 public basin corporations PJT

I and PJT II). Two administrative interventions have had a major impact on the provincial

Balai PSDA: (i) The introduction and delineation of national, provincial and district basins in

2006 creating lack of clarity on the role sharing of water resource management tasks between

national and provincial agencies; and (ii) the restructuring of the Provincial Dinas PUP which

includes the UPTDs/Balai PSDAs in 2007, leading to changes in their administrative structure

and range of activities. Further, the current role sharing is based on availability of annual

budget, without multi-year role sharing arrangements established by decree it would be

difficult to plan activities, develop human resources and address management issues. The new

management environment requires further clarity and agreement on role sharing and financing

which will be part of the WISMP-2 process;

(b) Role sharing and financing arrangements between national, provincial and kabupaten

irrigation management agencies. As central and provincial agencies generally lack field staff,

the Kabupaten irrigation services (Dinas PUP) are expected to provide the O&M services in

provincial and national systems which are areas outside their jurisdiction. Consequently,

Kabupatens with a large irrigation area under national or provincial responsibility are

increasingly overburdened and under-resourced. For national systems, the provinces receive

25

O&M budget from the central government (through delegated task or TP15

) but implementation

still relies heavily on the Kabupaten agencies. There is no TP system from provinces for

Kabupaten operational services. This has created problems in several Kabupatens as it involves

direct allocation of funds or allocation of human resources paid from Kabupaten budget for

national or provincial systems. To overcome these problems, a system of ad-hoc agreements

between the Kabupaten and Province on implementation of O&M works in provincial and

national systems is used. The budgets associated with these annual agreements do not provide

for Kabupaten service costs and overheads, and they do not provide the Kabupaten with

incentives to invest in their organization. A government or ministerial regulation is required to

guide the conclusion of multi-year agreements with financial commitments, between

Kabupaten and provincial and/or national governments, on their respective roles in

management and financing of provincial and national irrigation systems.

(c) From project to service orientation. Service oriented government agencies are essential to

achieve and sustain the development objectives. In many Kabupatens much progress has been

made in the development of management partnerships between government services and the

WUAs/WUAFs. However, in many water resources agencies, especially at provincial and

national levels, project-orientation still prevails. An important step towards service-orientation

is the definition of services and service standards (already a legal requirement) in qualitative

and quantitative terms, accompanied with measurable performance indicators and reporting

systems for accountability and transparency, including the stakeholder platforms. Service

standards combined with asset management plans provide the necessary legal basis for budget

allocation. In WISMP-2, the formulation of service standards for irrigation and water resource

management agencies, and preparation of asset management plans are expected to be standard

activities for participating Kabupatens, Provinces and Balai WS.

(d) Asset management planning for transparent multi-year financial planning. Budgets for

water resources and irrigation management agencies at kabupaten, province and national levels

are traditionally supply oriented and often based on historical allocations. The challenge is to

convince local parliaments (DPRDs) of the real needs. Kabupatens and provinces need to

move from a supply based to a need-based budgeting system which requires the development

of asset management plans that include short, medium and long term investments and O&M

financial needs. This also provides more transparency in budget allocation and use

effectiveness. This is one of the key actions for WISMP-2;

(e) Human Resource Management, Targeted Training and Staff Rotation. Many National,

Provincial and Kabupaten agencies face staff shortage as a result of a long period of no-hire

policy which only ended a few years ago. Consequently retired personnel were not replaced,

and gaps developed in staffing, knowledge and experience. A new generation of young staff

combined with the high level of staff rotation at all levels necessitates continuation of targeted

training and coaching to sustain project outcomes. However, HR management plans aiming at

knowledge development are not yet fully developed and the present knowledge management

infrastructure still requires considerable strengthening.

4.3 Based on the above considerations the overall risk to development outcome is rated

moderate.

15

Tugas Pembantuan (TP) is a means of transferring budget funds from Central to Local Government

under a co-management arrangement.

26

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Ensuring Quality at Entry

Rating: Moderately satisfactory

5.1.1 The WISMP Program was designed to address the critical sector issues of

governance and institutional capacity, and still remains in line with the national

decentralization policy, although some aspects of the Program have been readjusted following

the issue of Government Decree UU 7/2004 (such as rearrangement of basin water resources

management authority and mandates). The Bank‟s unique sector experience, particularly

since 1999 including Bank-financed operations such as WATSAL, had been reflected in the

project design. The key elements of an integrated and participatory management approach and

interventions for improving planning and management capacity and fiscal sustainability at the

river basin level and below, are still highly relevant and in line with the WATSAL Letter of

Sector Policy upon which WISMP is based.

5.1.2 The two substantial components (Basin Water Resources Management and

Participatory Irrigation Management) were designed to complement one another in

contributing to the achievement of the PDO. The implementation arrangement, involving

three line ministries and coordinated by the National Steering Committee (Secretariat in

Bappenas) has proven effective, and an independent monitoring and evaluation unit was

established and functioned throughout project implementation. The project design also

incorporated social and environmental factors and was fully in compliance with safeguards

policies. The assessment of risks and mitigation measures proposed at appraisal were

generally realistic and adequate although the major chronic problem of late release of

government budget was not identified as a risk. The project design was over ambitious in

geographical coverage and complexity of sub-components and activities. This presented a

heavy burden on management and supervision. As a result, achievement of objectives has

been mixed. Design of the M&E system in both projects was inadequate. In both there was

insufficient attention given to identifying suitable indicators and for the NTB-WRMP a

complete lack of any baseline survey as discussed in Section 2.3 (in particular paragraph 2.3.5

and 2.3.6).

5.1.3 The QAG panel rated the project‟s strategic relevance and approach as highly

satisfactory, environment aspects as marginally satisfactory and all other aspects and the

overall rating as satisfactory. The panel was critical regarding environmental aspects because

they were inadequately covered in the PAD, due to time constraints. The panel also criticized

the long list of conditions for loan effectiveness which had been deferred from negotiations

and Board presentation.

5.1.4 The decision to expand the project to include NTB with financing from the EU was

excellent. Generally the preparation under EU responsibility was adequate although there

were some inevitable conflicts of approach over project development objectives. Moreover

the project did not have the advantage of a wealth of previous experience, as was the case

with WISMP. Preparation and appraisal were undertaken expeditiously in order to allow

concurrent implementation with WISMP. Little attempt was made to tailor the project to the

local situation of NTB. In order to satisfy the EU‟s overall development agenda and strategy

the project development objective had to include poverty alleviation. There were also

differences in project presentation and reporting format. The Bank‟s main concern appears to

have been that the two Components A and B provided a basis for project implementation.

Inadequate attention was paid to other aspects, in particular the totally inadequate

arrangements for M&E, failure to identify appropriate key performance indicators and the

27

lack of any baseline survey. These short-comings constituted significant flaws in the project

design.

(b) Quality of Supervision

Rating: Satisfactory

5.1.5 Bank supervision involved an integrated team of senior headquarters based and senior

country based technical staff. There were a total of some 20 supervision missions including

smaller follow-up visits over the life of the project16

. Since both WISMP and NTB-WRM

were by nature a process as much as a project, supervision had a heavier than usual task in

adjusting implementation to changes in legislation, institutions and funding arrangements.

The supervision missions focused on the project development impact in addition to

monitoring the physical targets. Because there were two projects (WISMP1 and NTB-

WRMP), a single task team could draw on two sets of SPN resources which allowed the team

to supervise far more closely than would otherwise have been the case.

5.1.6 Supervision was diligent in undertaking joint supervision of WISMP and NTB-WRMP

and maintaining close contact not only with EU, but the other donor agencies involved in

water sector development, including the Asian Development Bank and bi-laterals including

the Netherlands and Japan. The supervision missions were responsive to the emerging issues

in the implementation. The WISMP Development Credit Agreement (DCA) amendments and

MTR revised the project targets, and addressed the issues in procurement and financing

arrangements. A shortage of staff in the Resident Mission Jakarta initially resulted in delays

in providing No objection letters (NOL) which slowed completion of TA contracts. Fiduciary

and Safeguard aspects were generally covered by the supervision missions and the problems

in procurement were addressed properly. The core members of the supervision missions were

maintained throughout project implementation and enjoyed excellent working relationships

with their counterparts. The key implementation issues (such as counterpart funding and

implementation delays of works) and proposed actions by the previous supervision missions

were generally followed up by subsequent missions.

5.1.7 The main omission in supervision was in regard to M&E. For WISMP supervision

should have paid more attention to the key performance indicator monitoring and included

KPIs earlier in the series of Implementation Status Reports (ISRs). For NTB-WRMP the

absence of any worthwhile design or arrangements for M&E was continuously ignored. At

the MTR the main recommendations were that an M&E system should be established, that

there should be mainstreaming of poor and gender issues and that the project should have an

overall work plan. None of these recommendations were implemented.

(c) Justification of Rating for Overall Bank Performance

5.1.8. Based on the ratings of (a) and (b) above, overall Bank Performance for WISMP 1

was moderately satisfactory, and that for NTB-WRMP is moderately satisfactory as well.

5.2 Borrower Performance

(a) Government Performance

Rating: Moderately Satisfactory

16 There were some 20supervision missions, accounting for around 225 staff -weeks for WISMP and a further 54 staff-weeks for NTB-WRMP

.

28

5.2.1. The Government of Indonesia, through the responsible ministries and local

governments, demonstrated throughout the project a strong commitment to the water

resources and irrigation sector reforms supported by WISMP and NTB-WRMP. The National

Steering Committee for Water Resources (NSCWR) through its secretariat in Bappenas

provided strong leadership during project preparation and implementation. MoF and local

governments concerned provided sufficient counterpart funding with an innovative parallel

financing mechanism in the later stage of the project. MoPW, MoHA and MoA coordinated

effectively in project design, overseeing and supporting critical aspects of implementation,

and provided staff and resources for the projects. Local governments at provincial and

Kabupaten levels created favorable enabling environment for the projects, by issuing required

guiding regulations, establishing multi-stakeholder organizations and providing necessary

budgets for project implementation and O&M. Delays in providing the essential enabling

legislation postponed the start of both projects by almost two years. During implementation,

progress was repeatedly slowed by the late release of government budget (DIPA), which is a

chronic problem. In many cases there was a lack of staff continuity which was particularly

unfortunate since the heavy training input provided was thereby often largely wasted. For

WISMP, TA support was also less than fully satisfactory with a heavier concentration on

central agencies and inadequate TA support provided in the field to kabupaten staff and

WUAs/WUAFs. For NTB-WRMP, which had a proportionately heavier TA support, the

situation was more satisfactory. Government performance is therefore rated as moderately

satisfactory.

(b) Implementing Agency (or Agencies) Performance

Rating: Satisfactory

5.2.2 There were many implementing agencies involved in the WISMP1 and the NTB-

WRMP projects and performance varied a lot across the board. Generally speaking, Part A

implementing agencies performed relatively poorly partly because of the lack of clarity and

delay in issuance of basin management regulations. The majority of the implementing

agencies (including PMUs and PIUs) made dedicated efforts to overcome the many

challenges and address the practical issues emerging in order to minimize project delays. The

three sectoral PIUs at different levels worked effectively together for institutionalizing PIM

(Part B of the project), under coordination of NPMU, PPMUs and KPMUs, while for Part A

good progress was also made in capacity & institutional building with some linkage to tackle

practical issues such as water allocation and flood protection in selected basins. The

development of rice intensification, improved marketing and agri-business capability in NTB-

WRMP has proved successful and provides a model for replication under WISMP2. A

number of aspects need to be improved in the follow-up program (WISMP2). These include:

avoiding the over-rapid transfer of staff which disrupts implementation and severely reduces

the impact of training and capacity building; strengthening work programming and budget

preparation/release; establishing an adequate and practical M&E system and ensuring its

effective use in tracking project progress and outcomes; and arranging for timely recruitment

and fuller utilization of TA consultants. Despite these criticisms in view of both projects‟

complexity and reform orientation guided by evolving regulations, the implementing

agencies‟ overall performance is rated satisfactory.

(c) Justification of Rating for Overall Borrower Performance

5.2.3 Based on the above considerations, the overall Borrower performance is rated

moderately satisfactory.

29

6. Lessons Learned

6.1. The WISMP Program was envisaged as a challenging and adaptable program to support

the long-term institutional development and capacity building in Indonesia‟s water resources

and irrigation sector. The Phase I project, with a quite complex design and changing policy

environment in the course of implementation, achieved plausible results and yielded

important lessons which could benefit the design and implementation of the second phase

project and follow-up investments in the country and similar operations elsewhere. These

lessons are summarized briefly below:

6.2. Institutional development/reform-oriented investments in the water sector should take a

long-term program approach synchronized with government policy reform implementation,

and with flexible design which can adapt to evolution of the policy environment. Accordingly

the project design should be kept simple and realistic in terms of project targets;

6.3. A participatory approach in basin water resources and irrigation management improves

decision-making effectiveness, and enhances ownership of the solutions by different

stakeholders. The alignment between irrigation sector reform interventions and agricultural

production activities of interest to communities creates incentives for active involvement of

beneficiaries and enhances program sustainability;

6.4. Inter-agency collaboration and coordination proved essential not only for project

implementation but also for ensuring project impact and sustainability, as demonstrated in the

integration of irrigation sector reform interventions and agricultural productivity improvement,

which has created incentives for farmer participation and has enhanced project sustainability;

6.5. Role-sharing, in a decentralization policy environment, between national, provincial and

district agencies for basin water resources and irrigation management for national

basins/schemes should be structured through legal arrangements, instead of being addressed

through ad hoc agreements.

6.6. It‟s critical to retain a stable team of government staff during the implementation period as

a high rate of staff rotation in government services resulted in a continuous need to train new

people and transfer knowledge, thereby limiting the effectiveness of the capacity-building

program under the projects;

6.7. Adopting advance procurement, flexible contracting and parallel financing arrangements

for counterpart funds was proven to be effective in enhancing implementation readiness,

achieving the annual program targets. And the results would have been better if the budget

approval and release were more timely; and

6.8. M&E indicator design should be specific and easy to measure, and be able to reflect PDO

achievement. M&E implementation arrangements should be included as an integral part of

project management with designated staff, and M&E results should be utilized in supporting

decision-making (incl. making timely adjustments in project implementation and resource

allocations).

7. Comments on Issues Raised by Borrower, Implementing Agencies and Partners

(a) Borrower/Implementing Agencies

Comments received and incorporated

30

(b) Co-financiers

Comments received (See Annex 8) from the EU and Dutch Embassy (Jakarta) and

incorporated in the text.

(c) Other Partners and Stakeholders

No issues raised.

31

Annex 1. Project Costs and Financing

WISMP

(a) Project Cost by Component (in US$ million equivalent)

Components

Appraisal

Estimate(PAD)

Actual /Latest

Estimate(ICR) Percentage of

Appraisal (US$ million) (US$ million)

A. Basin Water Resources Management 56.70 31.48 55

B. Participatory Irrigation Management 42.96 72.43 168

C. Project Management 8.13 10.27 126

Total Baseline Cost 107.79 114.18 106

Physical Contingencies 0 0

Price Contingencies 7.32 0

Front-end Fee 0.45 0.45 100

Total Project Costs 115.60 114.63 99

(b) Financing Arrangements

Source of Funds

Appraisal (PAD) Actual (ICR) Percentage of

Appraisal Estimate

(US$ million) (US$ million)

IBRD Loan 45.00 44.60 99

IDA Credit 25.00 27.48 110

Trust Fund ( from Netherlands) 14.00 13.90 99

Government( Central and Local) 30.48 26.89 88

Local Communities 1.12 1.76 157

Total Funds 115.60 114.63 99

32

NTB-WRMP

(a) Project Cost by Component (in Euro million)

Components Initial Estimate

Actual

(ICR) Percentage of

Initial

Estimate (Euro million) (Euro million)

A. Basin Water Resources Management 5.17 3.47 67.1

B. Participatory Irrigation Management 4.70 7.58 161.3

C. Project Management 0.93 0.63 67.7

Total Baseline Cost 10.80 11.68 108.1

Contingencies 0.46 0.00 **

Bank’s Administration Fee 0.47 0.45 95.7

Total Project Costs 11.73 12.13 103.4

(b) Financing Arrangement(in Euro million)

Source of Funds

Initial Estimate Actual

(ICR) Percentage of

Initial Estimate

(Euro million) (Euro million)

European Union 9.50* 9.45 99.5

Government( Central and Local) 2.23 2.27 101.8

Local Communities 0.00 0.41 (***)

Total Project Cost 11.73 12.13 103.4

* Excludes Euro 500,000 kept in EU for M&E and Audit **All contingency were used up

***Local Community contribution was not assumed during preparation

33

(c) Grant Financing by Component and Categories (Euro)

Categories

Allocation of Grant in (Amended) Admin. Agreement Actual Spent

Component A (BWRM)

Component B (IMT)

Component C (Project Mgt')

Total Component A

(BWRM) Component B

(IMT)

Component C (Project

Mgt') Total

1. WorKS except under Parts A3 & B3 40,000 35,000

75,000 71,120 5,766 0 76,886

2. GOODS except under Parts A3 & B3 200,000 225,000 125,000 550,000 393,874 70,371 145,055 609,300

3. Consultant Service except under Parts A3 & B3 200,000 200,000 1,600,000 2,000,000 566,402 1,132,805 0 1,699,207

4. Training and workshop except under Parts A3&B3 and incr. ops cost 995,000 1,505,000 750,000 3,250,000 839,289 2,182,151 335,716 3,357,156

5. RIM A Sub-Project funding allocation 454,500 0 0 454,500 385,450 0 0 385,450

6. RIM B Sub-project funding allocation. 400,000 0 0 400,000 445,014 0 0 445,014

7. A1 Sub-project funding allocation. 0 250,000 0 250,000 0 263,556 0 263,556

8 A2 Sub-project funding allocation. 0 1,495,500 0 1,495,500 0 1,491,233 0 1,491,233

9. B1&B2 Sub-project funding allocation. 0 550,000 0 550,000 0 620,388 0 620,387

10. Unallocated 0 0 0 0 0 0 0 0

D/A

57,027

Total Implementation Cost 2,289,500 4,260,500 2,475,000 9,025,000

9,005,216

Bank's Administration Fee

475,000

450,261

Total Project Cost 9,500,000 9,455,477

Note: some figures were rounded

34

Annex 2. Outputs by Component

WISMP1 Outputs by Component

Outputs Target

in PAD

December

2010

achieved

%

Remarks

WISMP1 Component A

National Water

Council (NWC)

National Steering

Committee for Water

Resources (NSCWR)

NWC and NSCWR

secretariats fully

staffed, funded and

monitor

implementation of

NWC decisions.

NWC established by

Presidential Regulation no

6/2009 with multi-

stakeholder representation.

Secretariat of NWC started

functioning in July 2009.

Presidential Regulation on

National Water Resources

Policy and Presidential

Decree on Ground Water

were prepared by NWC and

enacted in 2011.

Secretariat NSCWR remains

fully active throughout.

100

Provincial Water

Resource Council

(PWRC)

12 PWRC established

and functional

13 out of 14 provinces have

established multi-stakeholder

PWRCs. 9 PWRCs have

secretariats established, and

are fully functional.

70 Formerly in all the

provinces under WISMP-1

there were Provincial

Water Resources

Coordination Committees

(PTPA) that do not have

representation of

stakeholders nor have

function description that

aligned with the new

policies.

Decree on the

establishment of multi-

stakeholders PWRC was

issued in 2009.

River Basin Water

Council (BWRC)

12 BWRCs meet

regularly on policy,

water allocation,

regulation and

agencies activities.

16 multi-stakeholder BWRCs

established and operational

(15 National and 1 Provincial

Basin WRC). According to

the Water Law no 7/2004 the

establishment was based on

needs. 9 BWRC and its

secretariat are functional.

These BWRC have been

engaged in review of river

basin strategic plan and user

conflict resolution.

125 Formerly most of the river

territories have a River

Basin Water Resources

Coordination Committee

(PPTPA) without

representation of

stakeholders nor have

function description that

aligned with the new

policies. River Basin

Councils are not a legal

obligation but can be

established if stakeholders

feel the need.

River Basin

Management Unit

(Balai PSDA)

5 Balai PSDA and 1

River Basin

Corporations operate

based on: a) annual

work programs, b)

introduction of cost-

effectiveness and

criteria for works

selection, 3)

implementations of

cost recovery,

operations cost

accounting and

infrastructure asset

54 Balai PSDA, prepare

annual work programs and

operate based on more cost-

effectiveness considerations

including public consultation

for prioritizing maintenance

of river and flood control

structures Accounting system

improved. Sector MIS

improved. Quality Assurance

program was practiced in all

Balai PSDA and piloted in 2

Balai PSDA. Asset

Management piloted in 3

Largely

achieved

No river basin

corporation could be

established during

WISMP-1

implementation due to

changed financial

administrative

regulation.

35

management, and 4)

operational QA and

sector MIS.

Balai PSDA. Cost recovery

through service fees by

government agencies was

precluded by Water Law no

7/2004.

Role sharing MOU

between national and

Provincial Water

Resource Agencies.

Role-sharing in

hydrology operational

between all agencies.

A revised DG of Water

Resources Decree on BWRM

MOU has been issued in

November 2010. Role-

sharing MOU between the

Provincial Balai PSDA and

the National B(B)WS in the

overlapping river basin is

progressing, most on

hydrology and water quality

management. Role sharing

on hydrology management

arranged in 10 provinces.

Largely

achieved

No role sharing on O&M

of river basins is in place

as there is no financial

mechanism yet that

facilitates O&M fund

transfer from national to

provincial agencies (TP) to

implement O&M in

National Basins delegated

to the Provincial Basins

organizations.

River Improvement

and Management

(RIM A - RIM B)

Design and implementation

of River Improvement

Management A/RIM A was

participated by stakeholders.

RIM-B is carried out through

force account by Balai PSDA

with participation of affected

communities. The RIM

component has lagged in

most of the provinces

because of the late arrival of

national/local counterpart

budget and consequent late

tendering process.

Fully

achieved

No targets on RIM were

set as the works are very

localized and focused

mostly on protection of

settlements throughout the

participating basins.

Training

Technical and

financial management

and communication

skills training

completed for 26

Balai PSDA.

Training in technical and

financial management is

undertaken in 54 Balai

PSDA. 11Balai (B)WS also

received training under

WISMP program since 2009.

Fully

achieved

The original training

program is for Balai PSDA

staffs only. DGWR request

to include B(B)WS in the

training class was granted

after the MTR.

WISMP1 Component B

Local Government

Irrigation

Regulations (Perda)

revised to reflect

PP20-2006

Most of the remaining

Kabupaten had already a

Perda reflecting the

participatory Irrigation

Management principles but

these were based on Law

7/2004 and issued prior to

PP20/2006

-Province 11 9 81

-Kabupaten 70 52 74

WUAF/GP3A

Area figure represents the

total area of the complete

irrigation system that is

improved, not the GP3A

coverage area.

- Established 1150 1,651 144

- Legalized 1150 1,296 113

- Area covered (ha) 1,500,000 953,574 63

Irrigation

Commission / Komisi

Irigasi

- Established

- Province 11 12 109

- Kabupaten 70 95 136

36

MoU Province

Kabupaten on

management role

sharing

11 67 609

MoU GP3A –

Kabupaten /Province on system management

150 721 480

WUAF/GP3A

Proposals for works

- Received

- Evaluated by

Komir

200

200

1,265

470

235

Though work agreements

are reported, no reports

received on the amount of

works processed through

the Komir.

Participatory Design (ha)

-Kabupaten

- Province

343,000

478,193

339,247

138,946

139

Participatory

Construction(ha)

Kabupaten

Province

Type of GP3A

contracts (no)

- Subcontract

- Force Account

- Full Contract

268,000

348,398

202,920

145,478

435

387

316

130

Participatory O&M (ha)

690,000

1,027,194

626,710

400,484

152

Training

5,000 WUAF officers

and staff, including

women, trained and 100

workshops held.

Training Completed

10,000 of WUAF members

were trained on PPSIP

- Public awareness – 208

sessions, 660 GP3A

- PSETK – 172 sessions,

580 GP3A

- Organizations – 107

session, 209 GP3A

- Financial Mgt/Admin –

108 sessions, 209 GP3A

200

37

NTB-WRMP Outputs by Component

Outputs

Target

in PAD June 2011 %

Remarks

Achieved

NTB-WRMP Component A

National Water Council (NWC)

National Steering Committee for Water

Resources (NSCWR)

NWC and NSCWR secretariats fully

staffed, funded and

monitor implementation of

NWC decisions.

NWC established by Presidential

Regulation no 6/2009. Secretariat

NWC started function after established and staffed in July

2009.

Secretariat NSCWR fully active and has major influence.

100 As in WISMP-1

It is a national program

Provincial Water Resource

Council (PWRC)

PWRC established

and functional

The PWRC established in 2009

has 30 members representing various government agencies and

stakeholders. The PWRC has coordinated water resources

strategy and policy and reviewed

the strategic plan of WS Lombok.

100

Continues strengthening

program is needed

River Basin Water

Resources Council (River

BWRC)

BWRCs are

established covering

the whole territory of the province. Each

BWRC has

stakeholders representation,

reflecting gender

sensitivity and fully functional, evidenced

by the number of

meetings held, basin programs reviewed

and conflict issues

addressed.

2 BWRC (BWRC Lombok and BWRC Bima Dompu) established

with stakeholders including

representation of women groups. BWRC Sumbawa will be

established in 2011, due to delay

in establishment of Balai PSDA in charge.

BWRC Lombok established in 2009, discussed provincial

climate change policy, WS

Lombok strategic plan and resolved basin management

conflict. BWRC Bima-Dompu

established in September 2010

and started to function.

Fully achieved

River Basin Councils are not a legal obligation, according to

the Law, but can be established

if considered necessary by the stakeholders.

River Basin Management

Unit (Balai PSDA)

All UPTD or Balai

PSDA established, covering the whole

territory of the

Province, and appropriately staffed

and fully operational

as determined by the UPTD or Balai

PSDA annual

institutional reviews, with approximately

100 staff fully

trained, and at least half of all such

entities are receiving

50% of their budget from the relevant

Province Govt.

budget for operational costs.

3 Balai PSDA (Lombok, Sumbawa, and Bima-Dompu) and

1 Balai for hydrology and water

resources information (Balai ISDA) established, in mid of

2008.

Restructuring of Dinas PU to

comply with Govt. Regulation no

41/2007 on Streaming of Provincial Administration has to

be implemented and completed in

2009. Classical training is carried out for more than 100 staffs,

including on the job training. .

These Balais receiving 50 % of

their budget operations from the

provincial government.

Fully

achieved

Those Balais are budgeted and

functional. Various training

sessions were carried out 2006-2010. More than 100 personnel

were trained.

Role sharing MOU

Province – Balai WS

Role-sharing in

hydrology

operational between all agencies.

A role-sharing between Province

(Balai PSDA Lombok, Balai PSDA Bima-Dompu, Balai PSDA

Sumbawa and Balai ISDA and

Balai WS Nusa Tenggara I established in the form of MOU

in 2009. It consists of Water

Resources Data and Information, hydrology operation and O&M of

river, embung and dam role

sharing.

Fully

achieved

MOU is based on DG of Water Resources Decree, issued in

November 2010

38

River Improvement and

Management.

(RIM A and RIM B)

No specific target

Number of RIM sub-projects and

their benefits available in

individual sub-projects reports

and partly in TA/s progress

reports.

Fully

achieved

Note:

RIM A: 13 packages

RIM B: 34 packages

Provincial Planning Unit

A Provincial

Planning Unit in Dinas PUP

appropriately staffed

and funded, and producing basin

water resources

management plans (BWRMP or

Rencana)

A Planning Unit was established and staffed within Dinas PU in

May 2008.

By the restructuring organization of Dinas PU, the functionality of

Planning Unit was transformed as

to manage and supervise the preparation of strategic and

master plan of its basin prepare by

the consultant.

Largely achieved

The River Basin Management Units or Balai PSDAs are

preparing Strategic Plan/Pola

(policy and strategy of the basin) or Master Plan/Rencana.

As the basis for BWRMP As

Lombok is a national WS, its Strategic Plan/Pola is being

prepared by Balai WS in

coordination with Province (Dinas PUP and Balai PSDA).

Strategic Plan of Bima-Dompu

is prepared by Balai PSDA Bima-Dompu.

Training

Technical and

financial

management training provided to Dinas

and Balais PSDA.

Different types of training were

provided in class as well as on the job. More than 100 persons were

trained.

On the job training in MIS/Data Base, GIS, Hydrology, Water

Allocation and RIM provided for

Balai PSDA, Balai ISDA and Dinas PU staffs.

Fully

achieved

Types of training:

Database/MIS, Quality

Assurance, Procurement and Financial mgt‟, RIM A and RIM

B, etc. and Public Consultation

to the Local Parliament members.

39

NTB-WRMP Component B

Perda reflecting PP20-

2006

PP nr. 20/2006 reflects

Participatory Irrigation

Management -Province 1 1 100

-Kabupaten 7 7 100

GP3A/WUAF

Area figure represents

the total areas covered by

GP3A/ WUAF. - Established 160 214

- Legalized 160 213

- Area (ha) 60,000 144,954

Irrigation Commission

(Komir)

The commission is

considered established

when with a secretariat

and budgeted from

APBD

- Established

- Province 1 1 100

- Kabupaten 7 7 100

MoU between

Province - Kabupaten on

management role sharing

Document for annual

work program. 7 7 100

MoU between

GP3A – Kabupaten

/Province on system

management

NA 184 Fully

achieved

MOU reflects the general

agreement for a longer

period of time.

In annual basis it is

reflected by MOA

(Memorandum of

Agreement)

WUAF Proposals for

works

- Received

- Evaluated and

endorsed by

Komir

-

-

100

100

100

91

100

91

The figure is

the number of proposals

sent to Komir in last 2

years of the project.

Participatory Design (ha)

-Kabupaten

- Province

60,000

168,107

84,308

83,799

280

Some designs were done

in-house by Dinas PUP

staff

Participatory

Construction(ha)

Kabupaten

Province

Type of GP3A contracts

(no)

- Subcontract

- Force Account

- Full Contract

60,000

188,252

90,028

98,224

29

152

105

314

There were cases where

participatory

constructions were done

without existence of the

WUAF. (especially an

emergency works)

Training WUAF board and

members, and

government staff,

including women,

Training and Workshop

Completed:

- Public awareness of

Fully

achieved

Training provision also

involved NGOs and

Universities that have

experience in the reform

40

trained and related

workshops held.

PIM

- Technical (Design,

construction, PSETK,

O&M)

- Agriculture (SRI, On-

farm Water.

Management, Organic

farming etc.)

- Organization (Financial

management, admin,

communication)

- AWP preparation

Over 2,000 WUAF

members, and government

staff were trained during

project period

process of the

participatory Irrigation

management in Indonesia

41

Annex 3. Economic and Financial Analysis

Project Benefits

1. Quantifiable benefits: The WISMP I and NTB-WRMP NTB has provided more

reliable and efficient water delivery to irrigated agriculture, and generated confidence among

farmers/irrigators to adopt and implement improved agricultural practices. As a result, the

agricultural productivity has been increased. Specifically the increase of crop production

would be achieved through (i) enhanced cropping intensity; (ii) crop yield increases; and (iii)

changes in crop patterns shifting to high value produce. To calculate the above types of the

project benefit from the incremental crop production, crop budgets have been prepared for the

“with project” and “without project” situations. Benefit aggregation is based on physical

achievement by year and incorporate the cropping pattern changes.

2. Non-quantifiable benefits: Other benefits not accounted for in the analysis include

(i) cost savings from appropriate and timely river infrastructure maintenance; (ii) cost savings

relating to improved management of flooding and mitigation of associated loss; (3) efficiency

gains from institutional strengthening and development associated with the programme; and

(4) conflict reduction between upstream and downstream water users. Under the project, there

are interventions to improve management of the river basins in Component 1, it is not

possible to measure the individual effects of these capital improvement costs, but the benefits

accrued are assumed to be captured in the increased agricultural productivity under

Component 2.

3. The data sources from for quantifying Project benefits. The crop yield increase, crop

intensity increase, and/or changes in cropping patterns from paddy to higher valued crops

were derived from data collected of various sources17

. In addition to the data collected from

WISMP-1 implementation, various other sources of information on incremental agricultural

production were taken into account from data gathered from several agencies and reports. In

each case, the impact of the project is compared to a without-project situation, with

incremental benefits generated from (i) crop yield increase; (ii) Cropping intensity increase;

and/or (iii) changes in cropping patterns (from paddy to high value crops). In addition,

separate estimates were made for Java and off–Java to reflect the general differences in

productivity in the two areas. The production parameters used a weighted average for the

Java and non-Java to get an overall set of parameters to apply to all project areas. The

without project assumes all conditions will remain the same. A sizeable effect of the project

on cropping intensities is shown in Table 2. The increases on Java at 3.4% were lower than

off-Java at 5.2%.18

17

Based on the surveys carried out by the NPMU and the NPIU. In addition, in 2009 the Padjadjaran

University made a comparative analysis based on surveys in participating kabupatens. These data

were incorporated in the various reports (including Government ICR). 18

NTB was not included in the analysis as no systematic and verifiable data available for NTB (see

Main Report Section 3.2.20).

42

Table 1. Measures of change in cropping intensities for Java and off-Java

Java / off-Java WOP WP Net Change

Java Islands 259% 268% 9%

Off Java Islands 218% 229% 11%

4. The yield changes also show a somewhat higher gain on off-Java compared to Java as

shown in Table 3. Off-Java has a lower base making the likelihood of a larger relative

increase. In absolute measures, the increase in yields on Java and off-Java were estimated to

be the same at an increase of 0.50 MT increase for both regions. While there is an apparent

productive advantage in growing SRI, compared to a regular rice crop, it is believed to have a

rather limited potential area because of the high levels of organic inputs that are limited in

quantities necessary for more extensive use. Maize yields increase 50% more off-Java than on

Java, perhaps reflecting a comparative advantage in Maize production off-Java.

Table 2. Changes in Yields of crops grown in irrigated areas Of Java and Off-Java

Java - Off Java WOP WP Net Change

Yield change (Rice MT/ha) Java 5.26 5.76 9.5%

Off Java 4.04 4.54 12.4%

Maize, MT/ha Java 3.17 4.08 28.7%

Off Java 2.80 4.00 42.9%

5. The projected cropping patterns as a result of project interventions show some

variation. As one might expect, increases in rice area is limited on both Java and off-Java

because they are already at a very high rate in irrigated areas. The SRI shows a four-fold

increase in cropped areas on both Java and off-Java because of the low baseline planted areas.

Soybeans show a 50 percent estimated increase in cropped area off-Java compared to less

than 10 percent for Java. This difference may reflect the acceptance of soybeans as a high-

valued crop off-Java. Maize showed no change on Java and a minor increase, 2.7 %, off-

Java.

Economic Analysis

6. World Bank commodity price projections (2015-2020) were used to estimate farm

gate prices in constant 2010 terms, along with incorporating the World Bank current price

information. Based on the above methodologies for quantifying project benefit, incremental

benefits generated directly from total project costs (including Component 1 and Component

2) of project intervention are identified and quantified. Cash flows of benefits and costs are

projected over the project economic life to estimate the base case Net Present Value (NPV) at

a discount rate of 12%. Based on the aggregated cash flows and the total project costs

(including costs under component 1 and component 3), the whole project ERR is estimated at

23 % with NPV at US$ 74.58 million.

43

Sensitivity Analysis

7. Key factors influencing project results are (1) project cost increases and (2) decrease

in the price of rice – the major farm commodity in the project area. Sensitivity test has been

conducted on these factors with the results below. This sensitivity analysis shows that the

factor having the significant effect on the EIRR is the decrease in rice price. However,

economic price of rice used in the analysis is based on the Bank projection, which has

reflected the declining trend of rice price. The EIRR in general is therefore resilient to

negative changes in major output price decline and project cost increase.

Table 3. Results of Sensitivity Test

Results of Sensitivity Test – ERR (%)

Base Scenario 23%

Project Cost increase +40% 12%

Crop price reduced by 28% 16%

Cost+18% & Price -15% 12%

Financial Analysis

8. Financial analysis can only be applied to the income generating entities. For farmers‟

households, an income analysis has been prepared, using crop budgets and farm models under

with and without project situations to gauge the financial attractiveness to the farmers. The

results of this analysis are very much affected by farm size. The average farm sizes

throughout Indonesia have become smaller. Between 1995 and 2007, the average farm size on

Java changed from 0.493 to 0.36 hectares. Over the same period of time, the average farm

size off-Java changed from 1.491 to 1.347 hectares. For the purposes of these household

income estimates, we are using the farm area of 0.360 hectare per farm on Java and 1.347

hectares per farm household off-Java.

Table 4. Farm Income Analysis

Region Average Farm

Area, Ha Farm income WOP

Rp/farm Farm income WP

Rp. Per farm Change

Java 0.36 5,752,446 7,580810 32%

Off Java 1.347 10,606,935 13,346,628 27%

9. The results of the farm household income analysis show a substantial increase in

farmers‟ income from improved crop production with the implementation of the project.

Within the Component 2 (PIM) the relative change in farm household income on Java was

32%, and the increase in farm household income off-Java was estimated to increase by 27%.

10. The project is therefore financially attractive to farmers participating in the project,

and the substantial increases in beneficiary farmers‟ incomes has provided adequate

incentives and ability for farmers to take over responsibility for O&M of on-farm irrigation

system through the WUAs/WUAFs.

44

11. For NTB-WRMP, though no systematic and verifiable data available from M&E, based

on the various reports and field visits it is generally believed that the crop yield and cropping

pattern increases achieved under the project were higher than in off-Java areas under

WISMPI. As such, adopting the same approach for economic analysis and using non-Java

data for crop production, it was conservatively estimated that the ERR for NTB-WRMP was

at 21%, with similar sensitivity results.

Fiscal Analysis

12. In comparison with without project situation, the fiscal impact of both WISMP 1 and

NTB-WRMP NTB is largely positive as the Project introduced participatory operation and

maintenance (O&M) practices for target irrigation schemes. The funding for O&M for tertiary

canal systems after rehabilitation has been covered by the WUAs and WUAFs, while the

O&M costs for the improved secondary and main canals, which are noticeable lower after

rehabilitation, are covered by the government as per current water sector policies.

45

Annex 4. Bank Lending and Implementation Support/Supervision Processes

WISMP1

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Guy J. Alaerts Lead Water Resources

Specialist ECSS1

Task Team

Leader

Ilham Abla Senior Operations Officer EASIS Operations and

Irrigation

Theodore Herman Consultant EASIS Water Resources

Kikkeri Ramu Consultant EASIN Water Resources

Management

Paulus Van Hofwegen Sr. Water Resources Spec. EASIS Irrigation

Institutions

Douglas Vermillion Consultant EASRD IM Institution

Brian Bruns Consultant EASRD WRM Institution

Yogana Prasta Operations Advisor EACIF Operations

Supervision/ICR

Xiaokai Li Sr. Water Resources Mgt.

Specialist EASIN

Task Team Leader

(2009.10-2010)

Guy J. Alaerts Lead Water Resources Specialist ECSS1 Task Team Leader (Until 2009.10).

Paulus Van Hofwegen Sr. Water Resources Spec. EASIS Co-TTL, Irrigation

Institutions

Ilham Abla Senior Operations Officer EASIS Operations and

Irrigation

Irama Aboesoemono Consultant EASIS Water Resource

Mgt.

Dayu Nirma Amurwanti Operations Analyst EACIF Anti

Corruption/Good

governance

Theodore Herman Consultant EASIS Water Resources

Bisma Husen Senior Procurement Specialist EAPPR Procurement

Sulistiowati Ms. Consultant EASIS Social Safeguards

Vivianti Rambe Consultant EASIS Social Safeguards

Kikkeri Ramu Consultant EASIN Water Resource

Mgt.

Andrew Daniel Sembel Environmental Spec. EASIS Environment

Renganaden Soopramanien Lead Counsel LEGAF Legal

Unggul Suprayitno Sr Financial Management

Specialist EAPFM Financial Mgt.

Anita Kentjanawati Tuwo Procurement Spec. EAPCO Procurement

Tomoko Kato Operations Officer EASIN Operations/Gender

/Result indicators

46

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY99 13.5

FY00 1.05 9.1

FY01 24.21 328.0

FY02 12.86 83.00

FY03 41.18 251.95

FY04 3.28 10.14

Total: 695.69

Supervision/ICR

FY99 0.00 0.00

FY00 0.00 0.00

FY01 0.00 0.79

FY02 0.00 0.12

FY03 0.00 2.06

FY04 13.23 127.14

FY05 28.69 142.11

FY06 36.22 164.09

FY07 41.88 142.67

FY08 33.43 139.48

FY09 23.50 95.97

FY10 26.34 123.32

FY11 18.62 90.02

FY12 3.26 7.44

Total: 225.17 1305.21

47

NTB-WRMP

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending/Grant Preparation Guy J. Alaerts Lead Water Resources Specialist ECSS1 Task Team Leader

Ilham Abla Senior Operations Officer EASIS Co-TTL Irrigation

Theodore Herman Consultant EASIS Water Resources

Kikkeri Ramu Consultant EASIN Water Resources

Management

Anthony Toft Sr Counsel LEGES Legal

Supervision/ICR

Guy J. Alaerts Lead Water Resources Specialist ECSS1 Task Team Leader

2006-2009

Xiaokai Li Sr Water Resources Mgt.

Specialist EASIN Task Team Leader

2009-2011

Ilham Abla Senior Operations Officer EASIS Co-TTL Irrigation

Paulus Van Hofwegen Sr Water Resources Specialist EASIS Irrigation Mgt

Irama Aboesoemono Consultant EASIS Basin Mgt

Dayu Nirma Amurwanti Operations Analyst EACIF Good Governance

Christina I. Donna Financial Management Specialist EAPFM Financial Mgt

Melinda Good Sr Counsel LEGES Legal

Bisma Husen Senior Procurement Specialist EAPPR Procurement

Vivianti Rambe Consultant EASIS Social safeguards

Kikkeri Ramu Consultant EASIN Water Resources

Andrew Daniel Sembel Environmental Specialist EASIS Environment

Unggul Suprayitno Sr Financial Management

Specialist EAPFM Financial Mgt

Tomoko Kato Operations Officer EASIN Gender/M&E

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY05 6.18 35.13

FY06 17.17 98.03

FY07 2.00 19.15

Total: 24.35 152.31

Supervision/ICR

FY07 0.00

FY08 7.69 19.18

FY09 16.44 31.63

FY10 12.56 34.37

FY11 14.88 47.76

FY12 2.21 5.37

Total: 53.78 138.31

48

Annex 5. Beneficiary Survey Results

N.A

49

Annex 6. Stakeholder Workshop Report and Results

N.A

50

Annex 7. Summary of Borrower’s ICR

The Directorate General of Water Resources, Ministry of Public Works contracted the

consulting firm to assist in preparing a Final Report (Implementation Completion Result

Report (ICR) dated December 2010) 19

on the project. This presents a great deal of data on

project implementation and shows a high degree of consistency with the Bank‟s ICR findings.

The Final Report/ICR main text extends to some 150 pages and is on-file. The following

summarizes the Final Report/ICR‟s highlights, main findings and lessons learned.

Financial and Economic Analysis. A detailed financial and economic analysis concluded

that the project was relatively successful with attractive returns to farmers and an adequate

economic return to Indonesia. Sensitivity analysis showed that the project was relatively

insensitive to the sensitivity tests made.

Rating of Bank Supervision – Satisfactory. World Bank carried out its role very well, in

giving supervision work on the subject of periodic technical and non technical. The World

Bank is also responsible for providing recommendations to the provincial and district

governments in improving the role of women and poverty reduction.

Lesson Learned:

(a). Implementation of a good irrigation perspective for GP3A and armed with training in

design and operation and maintenance will help implementation of the irrigation network to

be more effective and more sustainable, have a positive impact and improve transparency in

the use of surface water or ground water. The status of GP3A helps to increase and prioritize

maintenance and repair of irrigation system design with good quality. Farmer irrigation fees

and their labor contributions, will alleviate the cost of operation and maintenance and minor

rehabilitation. Use of IPAIR implemented by aid of GP3A encourages transparency.

Decentralization will help the progress of implementation of more transparency in

participatory irrigation management of IPAIR funds;

(b). For rehabilitation/repair of irrigation, both the obligation of central government,

provinces, districts must be implemented with transparency, including GP3A. The latter have

a role/participate in all aspects of development, finance, from the tendering process until the

execution and the work is completed. Regulation of the governors and ministers circular is

required for participatory irrigation repair.

(c). Management of water allocation both for business and for agriculture carried out with

regulations and legislation in force today, and must be fair and transparent, both surface water

and ground water. Water allocation should be effective and efficient for the necessary

understanding and cooperative operation and agreement that the water source should be

adequate and environmentally sustainable. Relevant agencies should carry out analysis of the

water quality of the potential sources of water. The above tasks need to be undertaken in

accordance with job description O&M duties at central, provincial and district levels,

according to the authority of each.

(d). The main activities in the implementation of participatory irrigation covers O&M and

repair/rehabilitation using net base budget (NBB). This needs the necessary amount of budget

19

Penyusunan Implementation Completion Results Report (ICR). PT. GEO ISSEC, Engineering

Consultant, Jakarta, December 2010

51

including annual periodic financing from IPAIR through GP3A, especially for O&M and

expected according to the NBB. As for rehabilitation activities funds can be obtained through

the state budget but needs to consider cost recovery.

(e). Implementation of WISMP I still has a concentration on capacity building activities of

water resources and participatory irrigation. Land acquisition is not yet happening. Later land

will be required, especially for water resources and participatory irrigation. From the

observations obtained in the field, a considerable expanse of padi drying area (3000-5000

M2) for advanced GP3A who already have heuler (rice huller) with an area of about 2000 M2

while driel (grain dryers) are damaged. For the future there is a need to anticipate land

acquisition, and include GP3A to get involved and NPIU NPMU included and a land

acquisition committee formed by members 50% government and 50% of non-governmental.

(f). M&E activities should be conducted by an independent team after WISMP I finished. The

task that needs to be done by the team carrying out existing M and E contained in the lessons

learned include the institutional, participatory irrigation benefits measurable / not measurable,

cost effectiveness and marketing policies and supporting regulations in the implementation of

the M and E should be done sequentially, among others, the baseline survey.

(g). Training activities are still needed. Training needs surveys, competency studies, task

analysis and performance analysis, the success of training, if conducted in accordance with

the needs using Bottom-up TAN approach.

(h). Priority in provision of resources assigned to each river area is determined by

Government and local governments in accordance with their authority. Consideration should

also be given to make sure that assistance is provided fairly without penalizing any group of

farmers.

(i). Both the SDA and TKPSDA boards, are large institutions with a very large number of

members, making it difficult to reach a unanimous decision. The secretariat of the

Board/TKPSDA must be strong and able to prepare materials for key sessions of the

Board/TKPSDA.

(j). Land conversion from irrigated rice into other uses needs carefully technical scrutiny, as

this affects their food availability. Regarding food security policy, this should be considered a

policy of food sovereignty, with reliance on imports and other rice producing countries

reduced.

(k). The State's Asset Management is important. Issues that need to be considered include

whether the management should be part of BMN, not only focused on inventory and

registration of state assets, but more broad, encompassing both use and security.

(l). With the loss of the Partnership Sub Dit NSPM preparation tasks (Norma Standard

Guidelines Manual) partnerships and the role of the community in natural resources

management must be accommodated in other Sub-DIT, for example in the Sub Directorate of

Settings.

(m). Incidence Sub Dit Dit Bina Settings in PSDA, suggesting the need for close cooperation

with the law and as amended by invitation or not to overlap each other waiting for the

completion of tasks.

(n). PPIU in 2007 had no echelon V (subjective) staff. This should be considered for cadre -

forming, and to allow career advancement.

52

(o). Implementation of WISMP by the Indonesian Government was mainly assisted by

funding from World Bank. Need to establish a coordination body to further perfect WISMP

implementation from planning to development.

Conclusions and Suggestions:

(a) Coordination: Coordination is the core problem in both SDA Board of National,

Provincial and Regency/Municipality and in Natural Resource Management Coordination

Team based on river basin (TKPSDA). A region may have has only a Provincial Water

Resources Council and do not consider it necessary to have TKPSDA.

Suggestions: Because of the nature of their duties Dewan SDA shall establish and formulate

natural resource management policy (tasks, staffing) and TKPSDA more on the

implementation of plans and programs. Coordination at the central conducted by the NSC and

NPMU can work well with coordination meetings (workshops), guidelines, but the

coordination of the provincial/district undertaken by PPMU / KPKU still needs improvement.

Coordination meetings are often not fully attended by PPIU / KPIU related offices;

preparation of the AWP is supposed to be consolidated at the PPMU, more often PPIU /

KPIU delivered directly to NPMU. Necessary monitoring and follow-up by NPMU assisted

by consultants, for coordination at the provincial / district got a favorable response from PPIU

/ KPIU. In order to facilitate the coordination can be done through their respective provincial

website.

(b) Institutions: Based on the PP. 41 of 2007, about the structure of the Organization as a

UPTD Balai PSDA may only have one Head of Administration and Functional.

Suggestions: Need a review of clausule PP. 41/2007 because based on the fact the extent of

the working area of a Hall of PSDA and magnitude of the task that must be carried at least the

required 2 (two) head section and Kasub Bag TU as long as it lasts.

(c) Administrative Barriers: Almost everywhere in both the provincial and district there are

bureaucratic obstacles, especially regarding the budget. DIPA disbursements are realized

slowly and often towards the end of the fiscal year, so this is clearly affecting the smooth

implementation of the work.

Suggestions: DIPA delay (Bappeda) makes it impossible to carry out the program perfectly,

or sometimes cannot even be implemented at all, because of lack of time. This leads to a lack

of synchronization between programs. The mechanism is the DIPA Bappeda 'Program Budget

69' (Bangda). In this case the Directorate of Budget (Kemt. Finance) and DG.Banda (Kemt.

DN) need to consider changing the mechanism.

(d) Land Conversion: With increasing population and the inevitable development of

technical irrigated rice, land conversion into residential land and plantations and other

interests is happening rapidly.

Suggestions: The problem of food security should be a focus of concern, setting a land use

change ban.

(e) Shortage of Human Resources. Frequent rotation and moving staff caused a chain effect,

also involving decision-making officials. For example in the Office of Food Crops in Lahat

regency over a short time the head was replaced three times, resulting in a three times

replacement of the KDP.

Suggestions: Man Power Planning should be a reference so that each movement in human

resources is part of a planned rotation from the beginning, not less important is the formation

of cadres.

(f) Public awareness campaign. Increased public awareness of water resource management

is objective of the WISMP program, which is not always easy to achieve, especially the

Parliament target group

53

Suggestions: Intensification of socialization and lobbying, especially with the Parliament,

because they have a very strategic role in the issuance of regulations concerning the provision

of funds in natural resources management.

(g) Division of Responsibilities: For resource management issues in the province, some

agencies are directly related to natural resources, both the central and the local agencies. The

division of roles between the two should be clear.

Suggestions: KSO, SKKS and SPKS Cooperation outlined in the MoU which was followed

by OCA as the details of its follow-up. The type and amount of the value of work performed

GP3A (KSO, SKKS, SPKS) in construction as well as the OP is still relatively small,

although previously set forth in the MOU / KSO. This is because the 'bargaining position'

GP3A is very weak, because the initiative came from the office.

There should be a minimum limit (e.g. 20%) of the value of the work carried out by GP3A

(KSO, SKKS, SPKS).

(h) Community Assistance Team (TPM): There is a need for members of the TPM, since

the TPM is vital for all field activities, problems, organization, agriculture and training to help

them build GP3A.

Suggestions: Ideally, each village is available a power TPM that it knows about the technical

organization of agriculture and good communication techniques with farmers. Use of existing

PPL power can take precedence.

(i) Training: There should be training for the implementation of the task of managing

GP3A, so that they can be independent in matters of organization and financial administration

of design, construction and O&M. Smooth transition from participatory for GP3A to

independent.

Suggestions: Training Need Assessment (TNA). Some GP3A complained that the training

provided is often tedious. Before creating or implementing training programs first conduct a

TNA, so that appropriate training is carried out as needed.

(j) Water User Association Federation (WUAF or GP3A): GP3A as a mix of WUA (P3A) is

an asset and economic potential to be developed. Distribution like stimulant to them as to

Gapoktan, should be the concern of all parties.

Suggestions: It should be equal treatment of local government for the establishment of funds

to GP3A as those committed against Gapoktan.

(k) Irrigation Commission (KOMIR): Irrigation Commission must work optimally, because

the members of the KOMIR still concurrent with other positions or try to own, but its

existence is very strategic in GP3A independence.

Suggestions: It should be the policy of NPMU to PPIU and KPIU to rearrange the setting,

duties and functions of members KOMIR.

(l) System of Rice Intensification (SRI): SRI has proved to be one type of farming that is

environmentally friendly and water saving, as well as short-duration and able to provide good

quality food in the future. From the test results in 18 district data showed that the results

achieved on average 6.4 to 9.72 tons/ha.

Suggestions: It should be an obligation of all parties, both Government and farmers to

maintain conditions conducive for production and marketing.

(m) Funds Absorption: Absorption rate of funds as much as 17 PIU Province / Regency /

City is relatively low, especially PIU, Bappeda and the Department of Agriculture due to the

late receipt of DIPA, because the use of Budget 69 and finance ministries that have special

rules for disbursements.

Suggestions: Need to improve budget management, particularly in the use of budget Bangda

DG 69 by the Ministry of the Interior. Government budgeting should be related to the

54

Ministry of budget. Other than that there should be an evaluation of the parties that

participated in the program WISMP mainly on activities that fund absorption is very low.

(o) Budget for DG Bangda: Using the number of budget 69 (Kemen Budget Finance) that

the process is not simple and the National politic conditions that interfere with the system

policy of the government budget.

Suggestions: Budgeting through a mechanism that further facilitates the process of receiving

good DIPA to Central, Provincial and District levels.

(p) Agribusiness: Agribusiness activity has not been implemented seriously, because GP3A

did not understand yet the market potential it contains.

Suggestions: Need intensification of agriculture-related training, business methods, the rules

of doing business, organization, preparation of reporting systems, etc.

(q) Report Consolidation: Not yet optimal coordination and reporting system between the

PPMU and KPMU resulting lack of information obtained dikabupaten activities.

Suggestions: Progress Report. The report not only presents the physical progress and

budgeting alone, but also the course of program implementation, the obstacles that occur in

the field which are resolved or not, and issues arising. PPMU given a role to arrange periodic

'Consolidated Report' and implement monitoring and evaluation (ME) and make annual

reports. The format of the 'Reports' needs to be prepared by NPIU.

(r). Improved Budget System: Need to improve budgeting systems, financial reporting

mechanisms and financial monitoring. It is expected that the financial M&E should produce

solutions to improve financial management systems.

(s) Coordination: Implementation of WISMP by the Indonesian government was mainly

assisted by funding from World Bank. Need to establish a body of coordination to perfect

implementation of WISMP from planning to development.

55

Annex 8. Comments of Co-financiers on the ICR

European Union (EU)

(a) Sustainability is not sufficiently discussed in our opinion. Many of the result level

indicators are based on government decisions and institutional arrangements - such as

establishment of Provincial Water Resources Council, Water User Association Federations,

etc.. These are important indicators, but we would find it useful to have more information on

the capacities of the institution and bodies supported by the project to manage water

resources as envisioned by the project beyond the implementation phase. If there is interest

from the parties concerned, the EU Delegation could field monitors to look at the

sustainability of the project results in the near future.

(b) Monitoring and Evaluation (section 2.3): We would appreciate if reference could be made

to the EU contribution to the monitoring and evaluation of the project. The EU fielded a

monitoring for short term mission in 2007 and hired a team of experts to contribute to the

evaluation of the project in late 2010

(c) Poverty aspects (sections 3.1.3 and 5.1.4): We think that attention to the poverty issues

during the project design was relevant considering poverty issues in NTB province and the

importance of access to water for farming communities who are in a situation of poverty.

Poverty alleviation was not referred to as a specific objective or result of the project, however

a “particular emphasis on the poor” was foreseen. We do not think this made the project

objective over ambitious.

Netherlands Embassy, Jakarta

(a) WISMP 1 has been designed as a state of the art program for Integrated Water Resources

management of River Basins and for Participatory Irrigation Management. The project was

part of the overall reform process of the water sector in Indonesia. Success of such a program

relies heavily on institutional change and capacity building processes at decentralized levels

of government and of local communities and organizations (notably Water Users

Associations). The project was implemented by the Government and project implementation

has been rated by the ICR as moderately satisfactory. The report mentions as one of the

factors that the TA support concentrated on the central agencies and was inadequate toward

the district level staff and the Water Users Associations.

(b) In combination with the „over-rapid‟ transfer of staff, the insufficient funding of district

agencies and the changes in administrative structure and mandates, the results of the project at

provincial, district and local level have been only partial and are still very fragile. There exists

a need for „continued support and nurturing‟, „further clarity and agreement on role sharing

and financing‟, additional „government regulation‟ etc. The report expects that during

WISMP2 these aspects can be dealt with. In combination with the extension of the project

period and the downward revision of some key project targets (notably financial sustainability

of irrigation) it would appear that the results of WISMP I are as yet far less sustainable than

envisaged.

(c) Although the WISMP I is part of the overall reform process of the water sector, the ICR

does not address the relevance and effectiveness of the project in this context. The articulation

of the project with other donor efforts (notably the ADB co-funded PISP) is not analyzed. An

assessment of such an aspect should have been included in the ICR.

56

Annex 9. List of Supporting Documents

1. QAG evaluation of Quality at Entry.

2. Project Appraisal Document ( PAD)

3. Project Environmental Guidelines and Resettlement Framework

4. Letter of Development Policy

5. Aide Memoires and related Annexes prepared by the supervision missions

6. Aide Memoire and related Annexes of the ICR mission

7. Government ICR and its Annexes

8. Financial and Economic analysis (spreadsheets)

CelebesSea

Java Sea BandaSea

Sulu SeaAndamanSea

PACIFICOCEAN

INDIAN

OCEAN

Halmahera

Morotai

Peleng Obi

Muna

Ceram

Buru

Sula Is.

Timor

Flores

Alor

WetarMoa

Babar

Sumba

Sumbawa

Lombok

NatunaBesar

Belitung

Madura

Bangka

Lingga

Nias

Enggano

Simeulue

Bali

BANTENTotal Basin Management Units: 3Project Core Basin Management Units: 1Total Kabupatens: 5Project Kabupatens: 0

JAWA BARATTotal Basin Management Units: 5Project Core Basin Management Units: 2Total Kabupatens: 22Project Kabupatens: 8

SUMATERA UTARATotal Basin Management Units: 7Project Core Basin Management Units: 1Total Kabupatens: 21Project Kabupatens: 2

NANGROE ACEH DARUSSALAMTotal Basin Management Units: 2Project Core Basin Management Units: 0Total Kabupatens: 23Project Kabupatens: 4

SUMATERA BARATTotal Basin Management Units: 2Project Core Basin Management Units: 1Total Kabupatens: 13Project Kabupatens: 2

SUMATERA SELATANTotal Basin Management Units: 2Project Core Basin Management Units: 1Total Kabupatens: 10Project Kabupatens: 2

LAMPUNGTotal Basin Management Units: 3Project Core Basin Management Units: 1Total Kabupatens: 8Project Kabupatens: 2

JAWA TENGAHTotal Basin Management Units: 6Project Core Basin Management Units: 3Total Kabupatens: 35Project Kabupatens: 17

D.I. YOGYAKARTATotal Basin Management Units: 2Project Core Basin Management Units: 1Total Kabupatens: 5Project Kabupatens: 5

NUSA TENGGARA BARATNUSA TENGGARA BARATNUSA TENGGARA BARATTotal Basin Management Units: 3Total Basin Management Units: 3Project Core Basin Management Units: 0Project Core Basin Management Units: 0Total Kabupatens: 7Total Kabupatens: 7Project Kabupatens: 7 Project Kabupatens: 7

Total Basin Management Units: 3Project Core Basin Management Units: 0Total Kabupatens: 7Project Kabupatens: 7

JAWA TIMURTotal Basin Management Units: 9Project Core Basin Management Units: 3Total Kabupatens: 38Project Kabupatens: 15

SULAWESI TENGAHTotal Basin Management Units: 6Project Core Basin Management Units: 0Total Kabupatens: 7Project Kabupatens: 3

SULAWESI SELATANTotal Basin Management Units: 5Project Core Basin Management Units: 1Total Kabupatens: 26Project Kabupatens: 12

NUSA TENGGARA TIMURTotal Basin Management Units: 2Project Core Basin Management Units: 1Total Kabupatens: 12Project Kabupatens: 2

Me

nt a

wa

iI s .

SULAWESI

JAWA

SUMATERAKALIMANTANRIAU

BENGKULU

BANGKA-BELITUNG

JAMBI

D.K.I. JAKARTA

BALI

KALIMANTANBARAT

KALIMANTANTENGAH

KALIMANTANTIMUR

KALIMANTANSELATAN

SULAWESIUTARA

GORONTALO

MALUKUUTARA

SULAWESITENGGARA

MALUKU

IRIAN JAYA(PAPUA)

AUSTRALIA

SINGAPORE

VIETNAM

TIMOR-LESTE

BRUNEI

PHILIPPINES

MALAYSIA

MALAYSIA

JAKARTA

Medan

SurabayaBandung

Semarang

Palembang

UjungPandang

PontianakSamarinda

Banjarmasin

Bandar Lampung

Padang

Pekanbaru

Yogyakarta

Kupang

AmbonKendari

Palu

Manado

Denpasar Mataram

Jambi

Bengkulu

Banda Aceh

PalangkarayaPangkal Pinang

Gorontalo

Ternate

105

105

0 0

120

120

INDONESIA

0 100 200 300

0 100 200 300 400 Miles

400 Kilometers

This map was produced by theMap Design Unit of The World Bank.The boundaries, colors, denominationsand any other information shown on thismap do not imply, on the part of The WorldBank Group, any judgment on the legal statusof any territory, or any endorsement oracceptance of such boundaries.

INDONESIA

WATER RESOURCES AND IRRIGATION SECTOR MANAGEMENT PROGRAM PHASE 1 PROJECTAND

NUSA TENGGARA BARAT WATER RESOURCE MANAGEMENT PROJECT

PROJECT PROVINCES, WRISMPP1P

PROJECT PROVINCE, NTBWRMP

MAIN ROADS

PROVINCE HEADQUARTERS

NATIONAL CAPITAL

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARIES

At the later stage of the project: a. Number of WISMP provinces become 14 due to West Sulawesiprovince split from South Sulawesi b. Number of WISMP kabupatens increased from 70 to 99 due to new kabupatens split from existing kabupatens and several new kabupatens joined the project

APRIL 2012

IBRD 39248