document of the world bank€¦ · proxy means test and the bis were approved by cabinet in january...

70
Document of The World Bank Report No: ICR00001886 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-42640 TF-92145) ON A CREDIT IN THE AMOUNT OF SDR 1.00 MILLION (US$ 1.45 MILLION EQUIVALENT) TO THE COMMONWEALTH OF DOMINICA FOR A GROWTH AND SOCIAL PROTECTION TECHNICAL ASSITANCE CREDIT June 28, 2011 Poverty Reduction and Economic Management Department (LCSPR) Caribbean Country Management Unit (LCC3C) Latin America and Caribbean Region (LCR) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 30-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Document of

    The World Bank

    Report No: ICR00001886

    IMPLEMENTATION COMPLETION AND RESULTS REPORT

    (IDA-42640 TF-92145)

    ON A

    CREDIT

    IN THE AMOUNT OF SDR 1.00 MILLION

    (US$ 1.45 MILLION EQUIVALENT)

    TO THE

    COMMONWEALTH OF DOMINICA

    FOR A

    GROWTH AND SOCIAL PROTECTION TECHNICAL ASSITANCE CREDIT

    June 28, 2011

    Poverty Reduction and Economic Management Department (LCSPR)

    Caribbean Country Management Unit (LCC3C)

    Latin America and Caribbean Region (LCR)

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • CURRENCY EQUIVALENTS

    (Exchange Rate Effective March, 2011)

    Currency Unit = Eastern Caribbean Dollar

    ECD 1.00 = US$ 0.37

    US$ 1.00 = ECD 2.70

    FISCAL YEAR

    July 1 - June 30

    ABBREVIATIONS AND ACRONYMS

    ASYCU

    DA

    Automated System for Customs

    Documentation and Administration

    CARTA

    C

    Caribbean Regional Technical

    Assistance Center

    CDB Caribbean Development Bank

    CFAA Country Financial Accountability

    Assessment

    CPA

    CPAR

    Country Poverty Assessment

    Country Procurement Assessment

    Report

    CG Central Government

    DEXIA Dominica Export and Import Agency

    DFID

    DHTA

    Department for International

    Development

    Dominica Hotel and Tourist

    Association

    DSS Dominica Social Security

    EC Eastern Caribbean

    ECCB Eastern Caribbean Central Bank

    ECCU

    ECSE

    Eastern Caribbean Currency Union

    Eastern Caribbean Securities Exchange

    EU European Union

    FAA

    FDI

    Finance (Administration) Act

    Foreign Direct Investment

    GDP Gross domestic product

    GSPS Growth and Social Protection Strategy

    ILO International Labor Organization

    IMF

    IPA

    International Monetary Fund

    Investment Promotion Agency

    MDGs Millennium Development Goals

    MIS Management information system

    MoF Ministry of Finance

    NDC National Development Corporation

    NGO Nongovernmental organization

    OECS Organization of Eastern Caribbean

    States

    PAC Public Accounts Committee

    PRGF

    PRS

    Poverty Reduction and Growth Facility

    Poverty Reduction Strategy

    PRSP Poverty Reduction Strategy Paper

    PSIP

    TM

    USAID

    Public Sector Investment Program

    Task Manager

    United States Agency for International

    Development

    Vice President: Pamela Cox

    Country Director: Francoise Clottes

    Sector Manager: Veronica E. Zavala

    Project Team Leader: Kathy Lalazarian

    ICR Team Leader Kathy Lalazarian

    ICR Main Author David E. Yuravlivker

  • DOMINICA

    GROWTH AND SOCIAL PROTECTION TECHNICAL ASSITANCE CREDIT

    CONTENTS

    DATA SHEET .............................................................................................................................................. I

    B. KEY DATES .................................................................................................................................................. I C. RATINGS SUMMARY...................................................................................................................................... I D. SECTOR AND THEME CODES ........................................................................................................................... II E. BANK STAFF ................................................................................................................................................ II F. RESULTS FRAMEWORK ANALYSIS ..................................................................................................................... II G. RATINGS OF PROJECT PERFORMANCE IN ISRS ................................................................................................... XI H. RESTRUCTURING (IF ANY) ............................................................................................................................. XI I. DISBURSEMENT PROFILE .............................................................................................................................. XII

    1. PROJECT CONTEXT, DEVELOPMENT OBJECTIVES AND DESIGN ............................................................. 1

    2. KEY FACTORS AFFECTING IMPLEMENTATION AND OUTCOMES ............................................................ 8

    3. ASSESSMENT OF OUTCOMES .............................................................................................................. 11

    4. ASSESSMENT OF RISK TO DEVELOPMENT OUTCOME ......................................................................... 18

    5. ASSESSMENT OF BANK AND BORROWER PERFORMANCE .................................................................. 18

    6. LESSONS LEARNED .............................................................................................................................. 20

    7. COMMENTS ON ISSUES RAISED BY BORROWER/IMPLEMENTING AGENCIES/PARTNERS .................... 21

    ANNEX 1. PROJECT COSTS AND FINANCING ........................................................................................... 23

    ANNEX 2. OUTPUTS BY COMPONENT ..................................................................................................... 24

    ANNEX 3. DOMINICA CUSTOMS REPORT PROJECT – HIGH LEVEL ACTION PLAN: PROGRESS AS OF JANUARY 2011 ........................................................................................................................ 28

    ANNEX 4. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION PROCESSES ....................... 39

    ANNEX 5. SUMMARY OF BORROWER'S ICR AND/OR COMMENTS ON DRAFT ICR .................................. 40

    ANNEX 6. COMMENTS OF COFINANCIERS AND OTHER PARTNERS/STAKEHOLDERS ............................... 51

    ANNEX 7. LIST OF SUPPORTING DOCUMENTS ........................................................................................ 53

    ANNEX 8 – MAP (IBRD MAP 33397) ........................................................................................................ 54

  • i

    DATA SHEET

    A. Basic Information

    Country: Dominica Project Name:

    Growth and Social

    Protection Technical

    Assistance Credit

    Project ID: P094869 L/C/TF Number(s): IDA-42640,TF-92145

    ICR Date: 06/28/2011 ICR Type: Core ICR

    Lending Instrument: TAL Borrower:

    THE

    COMMONWEALTH

    OF DOMINICA

    Original Total

    Commitment: XDR 1.0M Disbursed Amount: XDR 1.0M

    Revised Amount: XDR 1.0M

    Environmental Category: C

    Implementing Agencies:

    Commonwealth of Dominica

    Cofinanciers and Other External Partners:

    B. Key Dates

    Process Date Process Original Date Revised / Actual

    Date(s)

    Concept Review: 02/13/2006 Effectiveness: 04/02/2007 04/02/2007

    Appraisal: 10/06/2006 Restructuring(s): 04/30/2009

    Approval: 02/27/2007 Mid-term Review: 06/30/2008 12/01/2008

    Closing: 06/01/2010 12/31/2010

    C. Ratings Summary

    C.1 Performance Rating by ICR

    Outcomes: Moderately Satisfactory

    Risk to Development Outcome: Moderate

    Bank Performance: Moderately Satisfactory

    Borrower Performance: Moderately Satisfactory

    C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

    Bank Ratings Borrower Ratings

    Quality at Entry: Moderately Satisfactory Government: Moderately Satisfactory

    Quality of Supervision: Moderately Satisfactory Implementing

    Agency/Agencies: Moderately Satisfactory

  • ii

    Overall Bank

    Performance: Moderately Satisfactory

    Overall Borrower

    Performance: Moderately Satisfactory

    C.3 Quality at Entry and Implementation Performance Indicators

    Implementation

    Performance Indicators

    QAG Assessments

    (if any) Rating

    Potential Problem Project

    at any time (Yes/No): No

    Quality at Entry

    (QEA): None

    Problem Project at any

    time (Yes/No): No

    Quality of

    Supervision (QSA): None

    DO rating before

    Closing/Inactive status: Satisfactory

    D. Sector and Theme Codes

    Original Actual

    Sector Code (as % of total Bank financing)

    Central government administration 100 100

    Theme Code (as % of total Bank financing)

    Administrative and civil service reform 22 22

    Public expenditure, financial management and

    procurement 11 11

    Regulation and competition policy 22 22

    Social safety nets 22 22

    Trade facilitation and market access 23 23

    E. Bank Staff

    Positions At ICR At Approval

    Vice President: Pamela Cox Pamela Cox

    Country Director: Alan G. Carroll Caroline D. Anstey

    Sector Manager: Veronica E. Zavala Lombardi Jaime Saavedra Chanduvi

    Project Team Leader: Kathy Lalazarian Errol George Graham

    ICR Team Leader: Kathy Lalazarian

    ICR Primary Author: David E. Yuravlivker

    F. Results Framework Analysis

    Project Development Objectives (from Project Appraisal Document) The GSPTAP's development objective is to enhance the Government's effectiveness to

    deliver public goods and services by strengthening the institutional capacity of key

  • iii

    agencies to facilitate Dominica's private sector competitiveness and productivity and to

    provide targeted social assistance to reduce poverty.

    Revised Project Development Objectives (as approved by original approving authority)

    n/a

    (a) PDO Indicator(s)

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 :

    Completed human resource audit of ministries and departments of the public

    service

    Value

    quantitative or

    Qualitative)

    Pace of public sector

    reform slowed by limited

    capacity in the Reform

    Management Unit

    Manpower

    assessment

    completed in the

    public service

    Audit completed

    following wide

    consultation.

    Staffing plans need

    to be approved by

    Cabinet.

    Date achieved 10/31/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 2 : Reduction in time needed to register property from 40 days to 20 days.

    Value

    quantitative or

    Qualitative)

    Property registration time

    is about 40 days.

    Property

    registration time is

    20 days.

    Registration of land

    First title - down to

    60-90 days.

    Direct transfer -

    down to 30 days.

    Part of land - down

    to 35 days.

    Companies have a

    separate registry,

    which takes 1-2

    days.

    Date achieved 10/31/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 3 : One stop shop for tourism investors funded, staffed, developed, fully operational

    website, and used by investors.

    Value

    quantitative or

    Qualitative)

    No one stop shop in

    place.

    One stop shop for

    tourism investors

    fully operational.

    Website developed

    and used by

    investors.

    Achieved. Service

    provided by Invest

    Dominica

    Authority.

  • iv

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Date achieved 10/31/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 4 : Regulatory commission established, funded, staffed and fully functional.

    Value

    quantitative or

    Qualitative)

    No regulatory

    commission for electricity

    in place.

    Regulatory

    commission

    established and

    operational.

    Regulatory

    commission

    established and

    operational.

    Date achieved 10/31/2006 12/31/2010 11/03/2009

    Comments

    (incl. %

    achievement)

    New Electricity Act passed. IRC operational and ED selected.

    Indicator 5 :

    Objective and transparent Beneficiary Identification System (BIS) for selection

    of beneficiaries for Public Assistance (PA) and Education Trust Fund (ETF)

    developed.

    Value

    quantitative or

    Qualitative)

    No systematic criteria for

    beneficiary selection.

    Beneficiary

    Identification

    System for

    selection of

    beneficiaries for

    Public Assistance

    (PA) and

    Education Trust

    Fund (ETF)

    developed and

    fully implemented.

    Partially achieved.

    Proxy means test

    and the BIS were

    approved by

    Cabinet in January

    2011. At this

    writing their use

    has just started, as

    data is being

    inputted into the

    system.

    Date achieved 06/30/2006 12/31/2010 01/01/2011

    Comments

    (incl. %

    achievement)

    Indicator 6 : Central beneficiary registry developed, funded, staffed and fully functional.

    Value

    quantitative or

    Qualitative)

    No consistent record of

    beneficiary.

    100% of public

    assistance and

    Education Trust

    Fund beneficiaries

    registered in

    central registry.

    100% achieved.

    Date achieved 06/30/2006 12/31/2010 11/03/2009

    Comments

    (incl. %

    achievement)

  • v

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 7 :

    Development, dissemination, approval and launch of a time bound, fully-costed

    human resource development and succession plans for ministries and

    departments within the public service.

    Value

    quantitative or

    Qualitative)

    Plans not in existence. Plans developed

    and costed.

    Partially completed.

    Reform

    Management Unit

    has developed a

    methodology for

    preparing a

    succession plan,

    and has identified

    key positions where

    those plans would

    be applied. Cabinet

    has to approve the

    recommendations.

    Date achieved 10/30/2009 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 8 : Improved policy framework and environment for private sector development and

    improved social protection

    Value

    quantitative or

    Qualitative)

    No policy framework

    exists.

    Better targeting,

    planning and

    administration of

    social assistance.

    Achieved. Invest

    Dominica Authority

    established in July

    2007. Strategy

    approved by

    Cabinet in

    December 2010,

    and Action Plan

    being implemented.

    Date achieved 10/31/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    (b) Intermediate Outcome Indicator(s)

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 : Customs IT upgraded from ASYCUDA 2.7 to ASYCUDA World

    Value Customs using ASYCUDA World Achieved. The new

  • vi

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    (quantitative

    or Qualitative)

    ASYCUDA 2.7 implemented system is fully

    operational and is

    seen as a major

    improvement by

    private users.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 2 :

    Technology for paperless transactions installed in first year, 30% reduction in use

    of paper for import declarations by end of second year, and 80% by end of

    project.

    Value

    (quantitative

    or Qualitative)

    Use of paper and forms Paperless

    transactions

    Achieved. Customs

    declarations need

    just one paper copy

    instead of four,

    while cargo

    manifests are now

    an electronic

    document rather

    than a paper one.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 3 : Reduction in the average time for customs clearance, average reduction is 3-4

    days in first year, 2 days in second year, and 1 day in third year.

    Value

    (quantitative

    or Qualitative)

    Customs clearance takes

    seven days.

    Customs clearance

    takes one day.

    Achieved. Since the

    new system was

    implemented in

    July 2010, this time

    has been reduced to

    one day.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 4 : Installed and functioning audit management systems

    Value

    (quantitative

    or Qualitative)

    Need to update audit

    management system

    Audit management

    system

    functioning.

    Partially achieved.

    Auditor general

    office received

    IDEA software in

    early 2010 but staff

    not able to

    complete training.

  • vii

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    SMART stream is

    operational for

    budget process, but

    not for audit.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 5 :

    During first year, Cabinet sets new procurement threshold and 50% of contracts

    awarded through competitive bids, which increases to 7% by the second year,

    and 100% in the third year.

    Value

    (quantitative

    or Qualitative)

    Need to modernize

    procurement regulations

    in the public sector.

    100% of contracts

    awarded through

    competitive bids.

    Partially achieved.

    Currently the

    majority of

    contracts above

    EC$1 million are

    awarded by

    competitive

    bidding. The new

    Procurement Act

    would make that

    compulsory for all

    contracts.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 6 : Analysis and planning for National Investment Strategy, strategy completed,

    adopted and implemented by Invest Dominica Authority for GOCD.

    Value

    (quantitative

    or Qualitative)

    No national investment

    strategy

    Analysis and

    planning for

    national

    investment

    strategy done,

    strategy

    completed,

    adopted and

    implemented by

    Invest Dominica

    Authority by

    GOCD.

    Strategy approved

    by Cabinet in

    December 2010,

    and Action Plan

    being implemented.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

  • viii

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 7 : Number of days to process investment reduced to 30 days in the first year, to 25

    days in the second year, and to 20 days by the end of the project.

    Value

    (quantitative

    or Qualitative)

    Number of days to

    process investment is

    more than 30 days.

    Number of days to

    process investment

    reduced to 20 days

    by the end of the

    project.

    Achieved.

    Proposals of up to

    EC$2 million are

    reviewed by a sub-

    committee of

    cabinet within two

    weeks, and

    proposals above

    that amount are

    reviewed by the full

    cabinet within three

    weeks.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 8 : Draft alternative energy legislation developed, stakeholder discussion conducted,

    and submitted to Parliament for approval.

    Value

    (quantitative

    or Qualitative)

    Lack of alternative energy

    legislation.

    Draft alternative

    energy legislation

    developed,

    stakeholder

    discussion

    conducted, and

    submitted to

    Parliament for

    approval.

    Partially achieved.

    Draft has

    undergone various

    revisions, currently

    draft is being

    reviewed at the

    Attorney General's

    Chambers for

    onward submission

    to Parliament.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 9 : Methods in place for dealing with unexpected tariff and other regulatory issues.

    Value

    (quantitative

    or Qualitative)

    Lack of methodology for

    dealing with unexpected

    tarriff and other

    regulatory issues.

    Methods in place

    for dealing with

    unexpected tariff

    and other

    unexpected

    regulatory issues.

    Achieved. The

    policies

    implemented by the

    IRC include those

    methods and are

    posted in the web.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

  • ix

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 10 : BIS system being used to select beneficiaries for Public Assistance Program

    (PA) and Education Trust Fund (ETF) Program.

    Value

    (quantitative

    or Qualitative)

    No BIS system is being

    used to select

    beneficiaries for PA and

    ETF.

    BIS system being

    used to select

    beneficiaries for

    PA and for ETF

    program

    Partially achieved.

    Proxy means test

    and the BIS were

    approved by

    Cabinet in January

    2011. Their use has

    just started as data

    is being input into

    the system.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 11 : Policies and procedures related to PA and ETF documented and relevant staff

    trained.

    Value

    (quantitative

    or Qualitative)

    Lack of policies and

    procedures related to PA

    and ETF documented and

    relevant staff trained.

    Adapt new

    policies and

    procedures.

    Monitoring plan

    implemented.

    Policies and

    procedures

    established and

    documented in

    operational manuals

    for PA, ETF, and

    SFP and staff was

    trained.

    Date achieved 06/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 12 : Reform management unit planning, designing and implementation plans.

    Value

    (quantitative

    or Qualitative)

    Pace of public reform

    slowed by limited

    capacity in Public Sector

    Reform Unit (PSRU)

    Begin

    implementation of

    modernization

    plans

    RMU has

    developed a

    methodology for

    preparing the

    succession plans,

    and has identified

    key positions where

    those plans will be

    applied. They have

    not been fully

    costed.

    Date achieved 06/30/2010 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

  • x

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 13 : Establishment of a semi-autonomous Registry

    Value

    (quantitative

    or Qualitative)

    40 days for registration of

    property.

    Registration of

    property reduced

    to 20 days.

    Registration of

    land:

    First title - down to

    60-90 days.

    Direct transfer -

    down to 30 days.

    Part of land - down

    to 35 days.

    Companies have a

    separate registry,

    which takes 1-2

    days.

    Date achieved 11/11/2010 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 14 : Public contracts above threshold advertised and awarded through transparent and

    competitive bids

    Value

    (quantitative

    or Qualitative)

    Out-dated regulations

    Procurement

    procedural manual

    developed, and

    100% of contracts

    above threshold

    advertised/awarde

    d through

    competitive bids.

    Partially achieved.

    The majority of

    contracts above

    EC$1 million are

    awarded by

    competitive

    bidding. The new

    Procurement Act

    would make that

    compulsory for all

    contracts.

    Date achieved 11/11/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 15 : Public information campaign to inform the public about new approaches to the

    delivery of social safety net programs implemented.

    Value

    (quantitative

    or Qualitative)

    No systematic public

    information.

    Implementation of

    campaign

    continued.

    Partially achieved.

    The material for the

    information

    campaign has been

    prepared, and some

    aspects successfully

    undertaken. More

    PR to be

    undertaken when

  • xi

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    the system is fully

    utilized.

    Date achieved 10/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 16 : A program database to track beneficiaries and expenditures for the PA, ETF and

    the School Feeding Program in the Ministry of Education is in use.

    Value

    (quantitative

    or Qualitative)

    No database for ETF, SFP

    and PA.

    Program databases

    in place.

    Partially achieved.

    MIS for ETF, PA

    and SFP was

    launched.

    Date achieved 10/30/2006 12/31/2010 12/31/2010

    Comments

    (incl. %

    achievement)

    G. Ratings of Project Performance in ISRs

    No. Date ISR

    Archived DO IP

    Actual

    Disbursements

    (USD millions)

    1 07/04/2007 Satisfactory Satisfactory 0.00

    2 01/19/2008 Satisfactory Satisfactory 0.00

    3 06/27/2008 Satisfactory Satisfactory 0.15

    4 12/18/2008 Satisfactory Satisfactory 0.52

    5 06/28/2009 Satisfactory Satisfactory 0.65

    6 11/06/2009 Satisfactory Satisfactory 1.00

    7 06/24/2010 Satisfactory Satisfactory 1.44

    H. Restructuring (if any)

    Restructuring

    Date(s)

    Board

    Approved

    PDO Change

    ISR Ratings at

    Restructuring

    Amount

    Disbursed at

    Restructuring

    in USD

    millions

    Reason for Restructuring &

    Key Changes Made DO IP

    04/30/2009 N S S 0.65

    A Third Order Restructuring

    was conducted to improve the

    original outcome indicators that

    were somewhat vaguely

    delineated in the Supplemental

  • xii

    Restructuring

    Date(s)

    Board

    Approved

    PDO Change

    ISR Ratings at

    Restructuring

    Amount

    Disbursed at

    Restructuring

    in USD

    millions

    Reason for Restructuring &

    Key Changes Made DO IP

    Letter of the Credit Agreement

    and the PAD.

    I. Disbursement Profile

  • 1

    1. PROJECT CONTEXT, DEVELOPMENT OBJECTIVES AND DESIGN

    1.1 Context at Appraisal

    Dominica went through an economic crisis in 2001-2002, when output contracted by

    about 10 percent and poverty levels rose sharply. The Country Poverty Assessment

    (CPA) conducted in 2002 found that 39 percent of the population was poor, while 15

    percent were indigent, among the highest percentages in the Caribbean.

    In mid-2003, the government adopted a two-stage adjustment strategy to foster

    growth and ensure debt sustainability. The first stage focused on achieving

    macroeconomic stability through fiscal adjustment and collaborative debt restructuring.

    This effort was supported by an IMF Poverty Reduction and Growth Facility (PRGF) and

    the Bank’s Economic Recovery Support Operation (ERSO) in 2004. The program was

    largely successful, as the overall central government balance was reduced from nearly 11

    percent of GDP in 2000/01 to 0.9 percent of GDP in 2004, and public sector debt fell

    from a peak of 130.8 percent of GDP in 2003 to 116.1 percent of GDP in 2004, following

    a restructuring of Dominica’s official debt under the Paris Club framework.

    The second stage of the adjustment strategy focused on key structural reforms to

    establish the basis for private sector-led sustainable growth and poverty reduction.

    This stage was part of the Government’s Medium-term Growth and Social Protection

    Strategy (GSPS) for 2005/06-2009/10. The GSPS had four pillars: (i) Fiscal policy and

    administrative reforms; (ii) Enhancing the investment climate for private enterprise

    development; (iii) Sectoral strategies for growth; and (iv) poverty reduction and social

    protection

    The GSPS focused on invigorating private sector led growth and improving key

    social services, including health and education to build human capital. It gave

    special attention to vulnerable groups such as youth, which had unemployment rates of

    about 40 percent. Thus, employment generation was essential for poverty reduction. That

    called for increasing international competitiveness, improving export performance and

    enhancing the attractiveness of the economy to investors. The latter required reducing

    firms’ costs, improving the reliability of transportation, lowering the cost of energy and

    increasing the productivity of the labor force. The Bank’s analytical work1 and work by

    other donors helped to fine tune the Government’s strategy and action plans.

    The GSPS proposed a number of strategic policy actions to facilitate private sector

    development and improve the environment for private enterprise, including (i)

    accelerating implementation of its comprehensive Public Sector Reform Strategy (PSRS)

    aimed at improving effectiveness of service delivery, enhancing accountability, and

    1 “Towards a New Agenda for Growth”, April 2005; Dominica: OECS Fiscal Issues “Policies to Achieve

    Fiscal Sustainability and Improve Efficiency and Equity of Public Expenditures. June 2005.

  • 2

    streamlining regulations and procedures that may hinder private sector activities; (ii)

    improving the judicial and land administration systems; (iii) implementing

    recommendations emanating from a comprehensive analysis of Dominica’s investment

    climate; and (iv) implementing policy and regulatory measures aimed at lowering costs of

    transport, electricity, water and telecommunication.

    Consequently, the Growth and Social Protection Technical Assistance Project

    (GSPTAP) focused on reforms in four strategic areas: (i) making the public sector

    more efficient and effective; (ii) improving the investment climate; (iii) reforming the

    regulatory framework for the energy sector; and (iv) improving social protection.

    The GSPS had also become the focal point for donors’ support to Dominica. In

    particular, the European Union (EU) allocated approximately US$12 million in grants for

    budgetary support to Dominica, and decided to align and harmonize its tranche

    disbursement conditions for this budgetary support with the Results Framework agreed

    between the Government and the Bank for the GSPTAP. In addition, the EU provided

    another US$580,000 in a grant for parallel co-financing of the technical assistance

    operation (through a Bank administered Trust Fund).

    1.2 Original Project Development Objectives (PDO) and Key Indicators.

    The Project Development Objective (PDO) of the GSPTAP was to enhance the

    Government's effectiveness to deliver public goods and services by strengthening the

    institutional capacity of key agencies to facilitate Dominica's private sector

    competitiveness and productivity and to provide targeted social assistance to reduce

    poverty.

    The Project Outcome Indicators listed in the Project Appraisal Document (PAD) were:

    (i) Increased capacity of the public sector to implement reforms; (ii) Better regulatory framework governing the electricity sector; (iii) Greater transparency and efficiency in public procurement;

    (iv) Reduction in the processing time at customs; and (v) Better targeting, planning and administration of social assistance programs.

    1.3 Revised PDO (as approved by original approving authority) and Key Indicators,

    and reasons/justification

    The PDO and Key Indicators were not formally revised. However, a Third Ordering

    Restructuring designed to clarify the PDO and sharpen the indicators was approved by

    Management and agreed with Government in May 2009. Both original and revised

    indicators are described in Annex 2.

  • 3

    1.4 Main Beneficiaries

    The PAD states that “the project will benefit Dominicans through: (i) enhanced

    private sector competitiveness and productivity and improvement in employment

    prospects resulting from private sector-led growth; (ii) improvement in the quality of

    public goods and services offered by a more efficient public sector; (iii) more competitive

    pricing of electricity as a result of a better regulated electricity sector; and (iv) better

    targeting and efficient delivery of social protection programs. In particular, two groups

    that were expected to benefit from the project were brokers and importers, and then

    existing and potential beneficiaries of social protection programs.

    1.5 Original Components

    The project was comprised of the following components:

    Component 1: Making the public sector more efficient and effective (48% of total

    project costs - US$1,240,000)

    This component provided technical assistance to the Government to implement key

    elements of its public sector modernization strategy focused on streamlining the public

    sector to increase the efficiency of service delivery while lowering costs. It aimed to

    assist in strengthening control over public finances and increasing the transparency and

    efficiency of public procurement. The sub-components included:

    1.1 Strengthening of the Reform Management Unit (RMU). The RMU planned and

    implemented the public sector reform program. The activities that were financed included

    manpower needs assessments in targeted Ministries and Departments and mapping of the

    change management process to guide their re-organization/restructuring. This sub-

    component also supported the improvement of the technological capability of the unit.

    1.2 Strengthening of Customs. Activities supported included: (i) implementation of a

    detailed action plan for the Customs Modernization Program including training of

    Custom’s staff; (ii) implementation of a risk management system for customs

    inspections; and (iii) modernization and automation of ports and customs information and

    payments systems, including the upgrade of ASYCUDA - the customs automated data

    system.

    1.3 Modernization of Registry. This sub-component financed the modernization of the

    Registry through the full-scale computerization of Companies and Trade Marks section

    of the Registry to allow for on-line business registrations and searches. The improvement

    of the computer technology within the land titles section of the Registry was also

    expected to reduce the turn-around time for registering properties.

  • 4

    1.4 Strengthening of Fiduciary Capacity, including: (i) strengthening financial

    management capacity within the Accountant General’s and Auditor General’s

    departments with the introduction of various software programs, Cognos and Smart

    Stream being utilized to account for GoCD expenditures and provide the necessary

    reporting mechanisms in that regard; (ii) implementation of a Procurement Action Plan to

    modernize the public sector procurement system; and (iii) taking measures to integrate,

    where possible, into the pooled procurement initiative being piloted between Grenada and

    St. Vincent and the Grenadines under the ongoing Grenada Public Sector Modernization

    project.

    Component 2: Improving the investment climate (10 percent of total project cost -

    US$252,000)

    This component aimed at strengthening the institutional and regulatory environment for

    attracting investment to Dominica. Specifically, the activities under this component

    sought to address deficiencies in the system of investment promotion as carried out by the

    Dominica National Development Corporation (NDC), and prepare a National Investment

    Strategy and an Action Plan to build a well-functioning investment promotion agency.

    2.1 Development of a National Investment Strategy, to focus the limited public resources

    in areas which support private sector development and where attracting foreign direct

    investment (FDI) could contribute to the national objective of increasing private sector

    led growth for poverty reduction.

    2.2 Development and Implementation of a National Action Plan, including the

    restructuring of the NDC charged with the mandate to implement the National Investment

    Strategy. The restructuring of the NDC involved a split into two separate agencies; (i) an

    investment promotion agency; and (ii) a Tourism Authority. To support implementation

    of the Action Plan, this sub-component financed training of staff in relevant activities

    (market intelligence, direct contacts with investors, services to investors, and after-care of

    investors) as well as upgrading office and technical equipment, publication of

    promotional material, development of an interactive website which will serve to promote

    Dominica’s products and services to the wider regional and international frontiers and a

    special software for access to foreign investors’ databases as well as subscription to

    relevant international business information databases and services.

    Component 3: Reforming the regulatory framework for the energy sector (27 percent to

    total project cost - US$695,000).

    The objective of this component was to regulate the energy sector, including the

    production and distribution of electricity to improve competitiveness. The specific sub-

    components were:

    3.1 Establishment of National Regulatory Commission. This support was to follow

    passage of the Electricity Act, which would provide the legal basis for the establishment

    and operations of an independent regulatory commission for the electricity sector. This

  • 5

    sub-component financed the activities of the regulatory commission for the first 12

    months covering office operational costs, staffing, training and technical assistance. The

    expectation was that after the first year, the operations of the regulatory commission

    would be fully financed from license fees, other fees and levies.

    This component also involved the employment of a number of persons within the IRC

    who provided important support throughout the implementation process.

    An interactive website was also developed and launched for the IRC. This website

    assisted in promoting to the public IRC products and services and also various policies

    and guidelines under which the Institution operates.

    It also envisaged that in the medium-to-longer term Dominica will benefit from the

    regional electricity regulatory initiative, possibly resulting in further reduction of the

    national cost of regulation.

    3.2 Drafting of Alternative Energy Legislation, to provide the legal and regulatory

    framework for the development of alternative energy technologies, including hydropower,

    wind and geothermal energy.

    Component 4: Improving social protection (9 percent of total project costs -

    US$232,000)

    The objective of this component was to strengthen the Government’s capacity to better

    target, plan and administer social assistance programs for poor and vulnerable persons.

    There were three sub-components as follows:

    4.1 Beneficiary Selection System Modernization, including: (i) design and

    implementation of a transparent and objective targeting mechanism for selection of

    beneficiaries; (ii) development of a central beneficiary registry; and (iii) application of

    information from recently developed poverty maps to better target community based,

    school-feeding and short-term employment programs.

    4.2 Institution Strengthening. Improving the administrative capacity to deliver social

    assistance through: (i) development of program databases to track beneficiaries and

    expenditures for the Education Trust Fund (ETF) and the School Feeding Program (SFP)

    in the Ministry of Education and further work on database development for the Public

    Assistance Program (PA) at the Ministry of Community Development; (ii) documentation

    of policies and procedures for the PA and ETF; and (iii) establishing linkages and access

    to the different databases to assist in policy decision making at the sector level.

    4.3 Public Information Campaign. Design and implementation of a public information

    campaign to inform the public about new approaches to the delivery of social safety net

    programs (including the new approaches to targeting and registration of beneficiaries)

    and about other social protection reforms.

  • 6

    Component 5: Project Management (7 percent of total project costs - US$181,000).

    This component financed the operation of the small Project Coordinating Unit (PCU)

    integrated within the Establishment, Personnel and Training Department and employing

    permanent government staff and where necessary contract staff. More specifically, this

    component financed the project coordinator, the cost of the annual project audits,

    computers for the PCU as well as the costs of staff assigned to the project.

    1.6 Revised Components

    Components were not revised during the life of the project.

    1.7 Other significant changes

    The Outcome Indicators of the project were modified following the Mid-term

    Review in December 2008. As described in the Request for Approval of the

    Restructuring, dated May 1, 2009, “the purpose of this modification was to improve the

    original outcome indicators that were somewhat vaguely delineated in the Supplemental

    Letter of the Credit Agreement and the PAD”. This modification, however, was largely

    a reorganization of what was originally in the PAD (see Implementation of M&E below).

    Since neither the development objectives or outcome targets, nor the number and content

    of components/sub-components nor the component costs, financing plan or the allocation

    of credit proceeds were changed, it was deemed to be a Third Order Restructuring 2, not

    requiring approval by the Board of Directors and thereby not a formal restructuring.

    In May 2010, upon request by the Government dated January 29, 2010, the closing

    date of the project was extended from June 1, 2010, to December 31, 2010. Shortly

    thereafter, the closing date of the EU Co-financing Trust Fund and Grant for the

    GSPTAP (TF092145) was extended retroactively and for a second time to August 31,

    20103, and the Administrative Agreement was extended from June 20, 2010 to December

    31, 2010.

    The funding allocations among disbursement categories were modified several times. In September 2008, the percentages of expenditures to be financed in categories 1, 2 and

    3 were increased from 69%, 40% and 59% respectively to 100% to allow full usage of

    the existing IDA allocation for all three categories (the percentages in categories 4 and 5

    were originally 100%, so all categories became 100% financed).

    At the same time, proceeds across categories were reallocated, in response to the

    Government’s request dated August 8, 2008. The reasons for that reallocation were: (i)

    2 As per the guidelines governing the restructuring of investment projects at that time, which were

    approved by the Board of Directors on July 1, 2006.

    3 The first extension from December 31, 2009 to February 28, 2010, was granted in December 2009.

  • 7

    changes in the procurement plan to use one consulting firm, the United Nations

    Conference on Trade and Development (UNCTAD) to implement all activities related to

    customs reform; and (ii) additional resources had been obtained from other sources such

    as the EU budget support contribution. As a result, Categories (1) Goods and (3)

    Training were reduced to allow an increase in Category (2) Consultant Services (Table 1).

    In May 2010, the proceeds across disbursement categories were reallocated again (Table 1), to reflect what was happening on the ground. This reallocation allowed to pay

    for the MIS consultancy which was above the budget allocated for this component, the

    software which was developed for Private lands, the LAN for the Customs department,

    and the drafting of legislation for alternative energy. The de-facto final allocation was

    somewhat different, since the cost of various components exceeded their allocation for

    reasons described below. Those extra costs were financed with savings in other

    components and exchange rate gains.

    Table 1: Amount of IDA Financing Allocated (in SDR)

    Category Original

    Allocation

    September

    2008

    May 2010 Actual

    Expenditures

    (preliminary)

    (1) Goods for the Project

    with the exception of Parts

    2.2.2, 3.1 and 5(c) of the

    Project

    197,000

    78,000

    18,000

    26,580

    (2) Consultant services

    for the Project with the

    exception of Parts 2.2.2,

    3.1 and 5(c) of the Project

    230,000

    414,000

    621,680

    603,545

    (3) Training for the Project

    with the exception of Parts

    2.2.2, 3.1 and 5 of the

    Project

    103,000

    38,000

    20,000

    19,055

    (4) Goods, consultant

    services and training for

    Part 2.2.2 of the Project

    120,000

    120,000

    73,000

    68,879

    (5) Goods, consultant

    services and training for

    Part 3.1 of the Project

    350,000

    350,000

    267,320

    267,154

    TOTAL AMOUNT 1,000,000 1,000,000 1,000,000 985,213

  • 8

    2. KEY FACTORS AFFECTING IMPLEMENTATION AND OUTCOMES

    2.1 Project Preparation, Design and Quality at Entry

    The Project Development Objective (PDO) as well as the 5 original Project Outcome

    Indicators covered most aspects of the operation, but they were general in nature.

    Further, this operation could only partly be held accountable for meeting the PDO, since

    other donors were actively pursuing the same general objective. Nevertheless, the PDO

    and Project components addressed key priorities of the Government’s Growth and Social

    Protection Strategy and the Poverty Reduction Strategy. The Project supported the

    Government’s efforts to carry out reforms prescribed by those Strategies.

    The scope of the GSPTAP, while responsive to the client demands, was overly broad

    thus complicating the management and supervision of the project. That may be

    difficult to avoid when working with a small country and preparing the one and only

    operation in several years. For example, Component 2 – improving the investment

    climate, achieved substantial results, but this area was also being supported by other

    donors. In that respect, however, it should be recognized that at early stages of

    preparation, interventions in labor market reform as well as involvement in the

    agricultural sector were deliberately excluded from the operation, in spite of the fact that

    the latter was an area which the authorities wanted included in the operation, reflecting

    that a degree of selectivity was exercised by the team while attempting to remain

    responsive to client demand. (Minutes of the Concept Note Review Meeting, March 3,

    2006).

    The GSPTAP furthered the two pillars of the FY06-09 Country Assistance Strategy

    (CAS) for the OECS sub-region, approved by the Executive Board in September 2005:

    (i) stimulating growth and improving competitiveness; and (ii) reducing vulnerability by

    promoting greater social inclusion. Elements of the GSPTAP, however, could be

    perceived as contradictory to a guiding principle of the CAS as the Project supported

    establishment of a national regulatory commission (IRC) for electricity in Dominica,

    while the CAS called for regional integration and coordination efforts in that area. It

    should be noted, however, that the Government requested the inclusion of this component

    within the framework of its agreement with the IMF, and that establishment of the IRC

    was seen as a precursor to a regional regulatory authority.

    The PAD points out that design of the GSPTAP drew from lessons learned from

    previous operations in Dominica and elsewhere in the Caribbean. In particular,

    implementation was managed by the Project Coordinating Unit who worked in close

    collaboration with the Reform Management Unit which fell under the auspices of the

    Personnel Services and Training Department, thereby building institutional capacity and

    improving the likelihood of sustainability beyond the life of the Project. Also, the

    management and monitoring of implementation by a high level Steering Committee and

    the appointment of champions to head working groups for each component drew from

    lessons from past experience. In practice, the effectiveness of those arrangements varied

    across components. At the same time, the stated intention of addressing customs reform

  • 9

    and restructuring of the Registry to show early visible results to build ownership of the

    Program was not met because the time needed to implement those reforms was

    underestimated. That suggests that the design of the project did not take fully into

    account the tight capacity constraints in the country.

    Risk assessment in the PAD was appropriate. The overall risk was rated as moderate,

    ranging from high for exogenous shocks and delay in support from donor partners, to low

    for the loss of political support. Most aspects were covered, and the mitigation measures

    were straightforward. In addition, by engaging the EU in parallel financing (which

    increased the size of the project by almost 40%), the Project leveraged available donor

    grant financing, which was one of the mechanisms proposed in the CAS.

    2.2 Implementation

    The Project was off to a slow start. It took some time to identify and recruit the project

    coordinator in Dominica, and there was a change of Task Manager (TM) at Headquarters

    at an early stage of implementation and then again after restructuring. The Trust Fund

    agreement with the EU was signed over one year after the Credit became effective, and it

    required supplemental coordination efforts by both the Government and the Bank. For

    example, the EU monitored progress based on Bank supervision missions, but late in the

    life of the Project, the EU requested a different verification method relating to the private

    land registry indicator.

    The Project spread over a wide set of issues, while implementation capacity within

    government was fairly limited. Thus, several elements of the program which appear

    not to have been a top priority for the government, such as drafting alternative energy

    legislation, were pushed back and were not completed by the closing date. Others, such

    as procurement legislation, underwent various rounds of lengthy consultations, which

    were not completed either. Implementation took longer than planned also because of the

    length of time required for Cabinet and/or Parliamentary approval.

    In addition, there were delays in procurement and contracting of consultants for

    various components of the Project. In some cases, because of the small size of the

    local market, it was not possible to obtain the minimum number of quotes required by

    Bank procedures. Also, apparent misunderstandings among all involved led to protracted

    negotiations with UNCTAD which delayed customs reform. On the other hand, once it

    was launched, the reform of customs expanded and became a comprehensive institutional

    change which could have far reaching benefits for international trade and economic

    activity as a whole (see 3.2 below). Also, government officials pointed out that Bank

    staff were responsive to their concerns and requests, and tried to address them

    expeditiously.

    As mentioned above, at the Mid-term Review in late 2008, the Outcome Indicators

    were reorganized and rephrased in order to facilitate monitoring and supervision.

    Also, as Table 1 shows, the allocation of proceeds among disbursement categories

    changed dramatically over the life of the project. The latter resulted in part from

  • 10

    increases in costs, due to the long time period between their estimation and the actual

    spending, and to the introduction of the new 15% VAT in 2006.

    Disbursement lags led to questions in internal discussions and memoranda on

    whether the Satisfactory rating of the project was justified. Eventually,

    disbursements picked up, but initial delays led to the extension of the closing date of the

    project by 6 months to finalize activities. Nevertheless, several outcome indicators were

    only partially achieved or not achieved by the revised date (Annex 2).

    All in all, the 370 document entries in IRIS testify to the huge costs to the Bank of

    preparing and supervising the GSPTAP. Government officials told the ICR mission

    that it also required a huge effort on their side, and that in the future they would hesitate

    to engage in a new project if it is for less than US$5 million. Since IDA allocations to

    small countries are relatively small, the challenge for the Bank is to prepare fewer, larger

    operations that are relatively simple and straightforward in design, which address a

    reduced number of key priorities and leverage resources from other donors. Hopefully,

    this will reduce the cost of management and supervision.

    2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

    M&E design. The design of the Results Framework was cumbersome. The PDO

    was one long general sentence that covered everything. The Outcome Indicators were

    general and non-measurable (e.g., “increased capacity of the public sector to implement

    reforms” or “greater transparency and efficiency in public procurement”). Several

    Intermediate Outcome indicators were also very general (e.g., “Reform Management Unit

    planning, designing and implementing modernization plans”, or “Reduction in the used

    of paper based customs declarations”). Only at the level of Arrangements for Results

    Monitoring, which specified target values for years 1, 2 and 3 of the Project life, there

    were numerical values that could be monitored. Then, however, the final target values

    for the component of Social Protection asked for 100% compliance in three social

    protection indicators, which was not realistic.

    Implementation. In order to address the problems embedded in the Results

    Framework, the team clarified the PDO and made the Outcome Indicators more

    specific at the Mid-term Review. In fact, however, that was largely done by bringing

    forward what was originally spelled out in the Arrangements for Results Monitoring into

    the Results Framework. For example, “Reduction in the processing time at customs” was

    replaced by “Reduction in the average time for customs clearance from seven days to one

    day”, but the latter was already defined in the table of Intermediate Outcome Indicators

    attached to the original Supplemental Letter and the PAD. As part of the restructuring,

    the Outcome Indicator requiring the establishment of a “self-financed semi-autonomous”

    agency for registry was taken out, after the authorities argued that it was not agreed with

    them nor included in the Credit Agreement.

    Utilization. Restructuring of the Results Framework helped in monitoring progress

    of several outcome indicators. Although it did not eliminate all problems (such as the

  • 11

    requirement for 100% compliance in social protection indicators), it was incorporated

    into the Implementation Status and Results Reports (ISRs). However, since the new

    Results Framework drew from the table of Intermediate Indicators, several duplications

    emerged. Moreover, the original Results Framework still needed to be monitored. As a

    result, supervision missions and the ICR had a hard time identifying which outcome

    indicators needed to be monitored to assess progress in the Program.

    2.4 Safeguard and Fiduciary Compliance

    The Project triggered none of the Bank’s Environmental and Social Safeguard Policies.

    In late 2009, financial management and procurement were downgraded to

    Marginally Satisfactory due to delays in procurement processes and submission of the

    audit report. Those problems were resolved shortly thereafter.

    A procurement supervision mission visited Dominica three months after the closing

    date, and found no major issue regarding procurement. The mission concluded that

    procurement under the project had been carried out, in general, in compliance with

    arrangements agreed in the project financing agreement. This was explained by the fact

    that about 70% of contracts awarded were subject to Bank prior review. In addition to a

    close follow-up, training in the area of Bank procurement procedures was provided to the

    project team and to technical implementing agencies’ staff at a very early stage.

    However, there were a number of delays that were attributed to: (i) the small size of the

    economy limiting the number of bidders; (ii) the fact that coordination and procurement

    functions were the responsibility of one person; and (iii) the departure of the first Project

    Coordinator who attended the Bank procurement training. In addition, the project would

    have benefitted from an early preparation and adoption of the operations manual and

    procurement plan, as well as clear Terms of Reference for implementation.

    2.5 Post-completion Operation/Next Phase

    The integration of the PCU in the Reform Management Unit at the Ministry of

    Finance is expected to help in completing the reforms which had not been finalized by

    the closing date. Longer term sustainability, however, depends on continuous support by

    the political level.

    No follow up operation is considered at the moment.

    3. ASSESSMENT OF OUTCOMES

    3.1 Relevance of Objectives, Design and Implementation

    The objectives of the GSPTAP were and remain relevant for Dominica’s social and

    economic development. If anything, the relevance of these objectives is accentuated by

    the global financial crisis, which makes even more compelling for the country to achieve

    higher levels of efficiency and international competitiveness.

  • 12

    As it closed, the relevance of the Design and Implementation of the GSPTAP is

    mixed. In retrospect, the choice of a Technical Assistance operation over a DPL was

    warranted, both because of the small size of the operation as well as the need for capacity

    building in Government and public agencies. However, trying to be responsive to the

    Government’s priorities, the Project scope was too wide, taxing implementation capacity

    in the country. For example, given support by other donors for improving the investment

    climate for the private sector, it’s hard to assess what was the specific impact of the

    GSPTAP in this area. Also, while the creation of the Independent Regulatory

    Commission (IRC) was envisioned as a precursor to a regional regulatory authority which

    is more cost efficient, its success in improving the regulatory environment in the

    electricity sector reduced interest within Dominica towards the regional approach to

    energy regulation, which was highlighted in the CAS and is now being pursued by a new

    Bank operation.

    3.2 Achievement of Project Development Objectives

    Despite delays and challenges faced during implementation, the operation made a

    substantial contribution to improving the environment for private sector activity in

    Dominica and set the basis for a more efficient system of social protection.

    Commitment by the authorities and a close follow up by the Bank helped overcome the

    slow start, delays in contracting of consultants, limited capacity of implementation, and

    protracted approval processes by Cabinet and Parliament.

    The project had four components: (i) Making the public sector more efficient and

    effective; (ii) Improving the investment climate; (iii) Reforming the regulatory

    framework for the energy sector; and (iv) Improving social protection. An assessment of

    each of the components follows below:

    Component 1- Making the public sector more efficient and effective: Moderately

    Satisfactory. This component provided technical assistance to the Government to

    implement key elements of its public sector modernization strategy focused on

    streamlining the public sector to increase the efficiency of service delivery while

    lowering costs. More specifically, it supported activities to improve human resources

    management, improve and increase the transparency of auditing, modernize procurement,

    restructure the Registry, and reform customs.

    After wide consultation, a Human Resources Audit of Ministries and Departments

    of the Public Service was completed. The audit included a satisfaction survey and a

    review of personnel files of all established positions, followed by consultations with the

    unions. On the succession plans for Ministries and Departments, the Reform

    Management Unit (RMU)/Establishment, Personnel and Training Department took an

    alternative approach in that rather than developing and launching time bound, fully

    costed succession action plans, it developed a methodology (Tool Kit) for preparing

    succession plans when required, and it identified key positions where those plans would

    be applied. Due to the Parliamentary elections at end 2009, this activity was put on hold

  • 13

    until after the new authorities took office. The final report was completed in October

    2010, and Cabinet gave approval of the recommendations and action plan in April, 2011.

    At the Auditor General office, the new auditing management systems were not fully

    operational by the closing date. The office got the IDEA software in early 2010, but

    staff was not able to complete training. The SMART Stream system was used for the

    budget process, but it was not operational yet for auditing. Regarding the new

    procurement legislation, consultations with key stakeholders initially scheduled to be

    completed by March 2010 were still ongoing one year later, and the new legislation

    prepared under the project was not timely finalized as agreed in the TORs discussed with

    the Bank. This was due to the extended consultation process which was required and

    corresponding delays in the drafting process. However, the procurement legislation is on

    the agenda for the next sitting of Parliament scheduled for June 29, 2011. Among other

    things, the new legislation would ensure that all contracts above EC$1 million are

    awarded by competitive bidding. As of March 2011, most but not all contracts were

    subject to competitive bidding, as per the matrix of Outcome Indicators.

    Reform of the Registry is well under way, but not as spelled out in the original

    Results Framework. As mentioned above, when the Framework was restructured after

    the Mid-term Review, the notion of the Registry being “semi-autonomous” was taken

    out. The Registry is part of the Government financial system and as such, it cannot be

    “self financing” either, as all its revenues go to the Treasury and it is financed by the

    budget. As it turns out, however, its revenues are substantial and could finance its

    operations easily. The land registry is fully computerized, and the time it takes to register

    property was reduced: at the time of the ICR mission, First Title registration was taking

    60-90 days, compared to several years before the reform; Part of Land registration was

    taking about 35 days, down from 3-6 months; and Direct Transfer was taking about 30

    days, compared to 3 months before the reform. There is now a separate Registry for

    companies, which also deals with patents and intellectual property. Companies can be

    registered in one day. While newborn children are registered at the hospital, the Registry

    in the Birth and Death section is not fully computerized. A business proposal for a

    Secured Civil Registry and Certificate Issuing System has been approved by Cabinet in

    June, 2011.

    The reform of Customs had a slow start, but it achieved the targets of the Project,

    and is already showing tangible results on the ground.4 Firstly, the upgrade from

    ASYCUDA 2.7 to ASYCUDA World (AW) was completed and is fully operational.

    That reform was fully endorsed by the President of the private brokers association, who

    told the ICR mission that transactions costs of dealing with customs have been reduced

    significantly, and thus doing business in the country became more profitable and

    predictable. Further, the AW is user friendly and web based, and thus available 24/7.

    Secondly, the process of achieving a paperless environment for customs transactions was

    4 The slow start was due to delays on contracting with UNCTAD as well as in the procurement of

    equipment. In addition, the new Customs Act No. 20-2010 became effective only on December 1, 2010.

  • 14

    well under way. Under the new system, the cargo manifest is an electronic document

    fully integrated into the commercial declaration, which Customs receives electronically

    even before cargo arrives to port. Hence, the electronic manifest has replaced completely

    the outdated paper-based manifest (100 percent of reduction). In the case of paper

    declarations, users need only one copy instead of four (75 percent of reduction). Thirdly,

    the last target was virtually achieved, as the time for the clearance of goods was reduced

    from 8.65 days in July 2010 when the new system was launched, to just over one day

    (1.42 days on average in the last quarter of 2010, and 1.29 days on average in the first

    quarter of 2011).5

    Component 2 - Improving the Investment Climate: Satisfactory. This component

    aimed at strengthening the institutional and regulatory environment for attracting

    investment into Dominica. Specifically, the activities under this component sought to

    address deficiencies in the existing system of investment promotion as carried out by the

    Invest Dominica Authority (IDA) and prepare a National Investment Strategy and an

    Action Plan to build a well-functioning investment promotion agency.

    The objectives of this component were achieved, although not necessarily as a direct

    outcome of the GSPTA. Other donors were active in this areas as well. In particular,

    the Invest Dominica Authority was established in July 2007 under another project, and

    analytical work on improving the environment for private investment was financed by

    several donors. Preparation of the National Investment Strategy, however, was supported

    by the GSPTAP, and the Strategy was approved by Cabinet in November 2010. The

    Invest Dominica Authority started to implement the Action Plan shortly thereafter.

    The Invest Dominica Authority has two units: (i) investment promotion; and (ii)

    facilitation of services to investors. The second unit operates the one-stop-shop for

    investors, which is now operational. In addition, the number of days to process

    investment applications has been gradually reduced: proposals of up to EC$2 million are

    reviewed by a sub-committee of Cabinet within 2 weeks, while proposals above that

    amount are reviewed by Cabinet within 3 weeks.

    Component 3 - Reforming the regulatory framework for the energy sector:

    Moderately Satisfactory. The objective of this component was to regulate the energy

    sector including the production and distribution of electricity to improve competitiveness.

    In particular, it supported establishment of a national Regulatory Commission, which

    should be funded, staffed and fully functional; and drafting alternative energy legislation

    and submitting it to Parliament for approval. The rationale behind this component was

    that electricity tariffs in Dominica were among the highest in the Caribbean6 and they

    undermined competitiveness. During preparation, there was discussion on the

    5 The CATT report for Dominica of December 2010, indicator 114, shows that more than 50% of the

    declarations took more than 24 hours to be released because it refers to the whole year 2010.

    6 Electricity tariffs are high largely because a small population is spread over a relatively large and rugged

    terrain, coverage is 97 percent, and due to high fuel costs.

  • 15

    establishment of a regional regulatory commission, which was viewed as more cost

    effective. The Government, however, insisted on a national commission, as per its

    Growth and Social Protection Strategy Paper (April 2006).

    The Independent Regulatory Commission (IRC) was established in late 2007 and

    started to operate in July 2008 when its Executive Director was hired. The GSPTAP

    financed its activities in the first year (several consultants were extended for another 3

    months), but now it is being funded by Government. The guidelines of IRC policies are

    in the web, and those include methods for dealing with unexpected tariff and other

    regulatory issues. Authorities in Dominica are satisfied with the way in which the IRC

    operates, and they intend to maintain it as the national regulatory agency notwithstanding

    the Bank’s current initiative to promote regulation at the regional level, which should be

    more cost effective. Apparently, the success of the IRC as a national regulatory

    commission is also drawing attention in several neighboring islands.

    A draft of alternative energy legislation has been circulated and it underwent several

    revisions, but there was no final version when the ICR mission visited Dominica in

    March 2011.7 The final revision is currently being undertaken at the Chambers of the

    Attorney General for onward transmission to Parliament. Cabinet has to approve the

    final draft before it is submitted to Parliament.

    Component 4 - Improving social protection: Moderately Unsatisfactory. The

    objective of this component was to strengthen the Government’s capacity to better target,

    plan and administer social assistance programs for poor and vulnerable persons. In

    particular, the Project supported: (i) modernization and streamlining the systems for

    beneficiary selection and registration: (ii) activities to strengthen the administrative

    capacity to deliver social assistance; and (iii) design and implementation of a public

    information campaign to inform citizens about new approaches to the delivery of safety

    net programs.

    While the rating of this component reflects the fact that most targets were not

    achieved by the closing date, substantial progress was made in key elements of the

    program (see below). Further, it should be recognized that: (a) this component had a

    late start, as key consultancies started only in 2009; and (b) targets requiring 100%

    identification of beneficiaries, 100% registration, and 100% of ETF, SFP and PA

    beneficiaries and expenditures captured in the data base, were not realistic. In addition,

    there were technical problems in developing the new information system, coordination

    among relevant ministries was initially not smooth, and the process slowed down prior to

    the elections at the end of that year.

    7 Several studies indicate that Dominica has potential for geothermal generation, which could supply all its

    domestic demand and exports of about 15 MW to neighboring islands.

  • 16

    Notwithstanding these difficulties, the welfare system of Dominica is undergoing a

    substantial change, both in terms of policy as well as implementation. At the policy

    level, in January 2011, Cabinet approved means-testing as the target mechanism to be

    used to identify beneficiaries, thereby increasing transparency and removing subjectivity

    from this process, and the National Beneficiaries Information System (NBIS) was

    launched shortly thereafter. Further, the new set-up establishes linkages between the

    core programs in the safety net. In terms of implementation, social workers were trained

    in the new targeting mechanism and potential beneficiaries completed application forms;

    operations manuals for the ETF, PA and SFP were approved; and key monitoring

    indicators were identified and a monitoring plan for the three programs was designed.

    Incidentally, the Ministry of Education will not have a separate data base but it will rather

    have access to the NBIS in areas that are relevant for its work. Finally, the public

    information campaign has been prepared and a number of public relations activities have

    already taken place.

    3.3 Efficiency

    The nature of this Technical Assistance Project did not allow for the calculation of

    net present value or other financial variables. The US$2.6 million project was

    expected to have only a minimal direct economic impact in the short term, and that seems

    indeed to be the case. However, in the medium and longer term, the outcomes of the

    Project are expected to contribute to Dominica’s economic and social development.

    Better control and deployment of human resources within the civil service and lower

    costs of operating the Registry are likely to save fiscal resources. Also, improvement in

    quality and timing of audits as well as more transparent and efficient public procurement

    would result in better value for money. Further, an improved environment for private

    investment and better regulation of electricity are likely to contribute to economic growth.

    In the longer term, development of geothermal generation capacity would lower domestic

    energy costs and improve the balance of payments by reducing fuel imports and

    exporting electricity to neighboring islands. In addition, the comprehensive reform in

    customs could be a point of before and after in international trade and have a direct

    impact on competitiveness and economic activity. In the social protection area, the new

    beneficiary information system was still being put in place, but once it becomes

    operational it would save administrative costs and enhance both the coverage and

    efficiency of the social safety net.

    3.4 Justification of Overall Outcome Rating Rating: Moderately Satisfactory

    The PDO and key associated outcome targets of the GSPTAP were largely achieved,

    or are likely to be achieved relatively soon, notwithstanding a slow start and delays

    during implementation. The reform process of the civil service was advanced by the

    Program. The Registry of land and companies is working much better, and the upgrade

    to ASYCUDA World has already had a major impact on efficiency at customs. The

    Invest Dominica Authority is providing information and services to investors, and the

    recently established IRC is perceived by both the authorities and the public as fulfilling a

  • 17

    positive function in the electricity area. Delays were longer in the social protection

    component, and targets were not achieved by the closing date. However, the technical

    work on the new National Beneficiaries Information System (NBIS) has been completed,

    Cabinet has approved means-testing as the targeting mechanism, and the system will

    become operational shortly. The NBIS would help improving both targeting and coverage

    of social protection programs, even if their coverage does not reach 100% as specified in

    the Outcome Indicators.

    3.5 Overarching Themes, Other Outcomes and Impacts

    (a) Poverty Impacts, Gender Aspects, and Social Development

    Insofar as the improved environment for private sector development succeeds in

    attracting more investment, the resulting generation of new jobs would contribute to

    reducing poverty. In addition, the new National Beneficiaries Information System

    would improve coverage and efficiency of social protection programs. As of March 2011,

    information of about 75% of current beneficiaries was entered into the new system, and

    95% of those were confirmed. Better targeting of beneficiaries is expected to result in a

    more efficient allocation of social expenditures. Improved coordination of the delivery of

    social assistance would save administrative costs. Authorities, however, are concerned

    that some people who were rejected by the new system because of size of household or

    age may still need help, and they are looking for mechanisms to address that problem.

    (b) Institutional Change/Strengthening

    The human resources audit of established position in Ministries and Departments,

    which was completed under the Project, would improve management in the public

    sector. The Auditor General office was strengthened with new hardware and software,

    the Registry was restructured and is now performing its duties within shorter periods of

    time, and customs administration was taken to a higher level by the upgrade to

    ASYCUDA World. The establishment of the IRC, with transparent methods of operation,

    was a major institutional change in the energy area. When the new procurement law is

    approved by Parliament, it would also be an institutional improvement. Finally, when

    fully operational, the new NBIS will improve the effectiveness and efficiency of

    institutions managing key social protection programs.

    (c) Other Unintended Outcomes and Impacts (positive or negative)

    The reform at customs, which was one of four sub-components within the first

    component of the Program, acquired increased importance over time and became a

    major outcome of the GSPTAP. A comprehensive and detailed M&E matrix was

    developed during implementation, containing specific steps in eight focus areas: (i) legal

    framework; (ii) organization and management; (iii) human resources management and

    training; (iv) information and communication technology; (v) control systems and

    processes; (vi) external cooperation; (vii) enforcement and compliance; and (viii)

    integrity (Annex 3). This matrix spells out the tasks in each area as well as who was

    responsible for execution and the expected time frame of completion. This sub-

  • 18

    component took a long time to take off, but import brokers see those reforms as a major

    improvement in the system, which greatly facilitates international trade.

    3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

    N/A

    4. ASSESSMENT OF RISK TO DEVELOPMENT OUTCOME Rating: Moderate

    The risk that development outcomes would not be maintained varies somewhat

    across the components of the Project. The risk to outcomes of component 1 is low to

    moderate, as it strengthens institutions in the public sector and improves its operational

    efficiency, thereby creating stakeholder groups who benefit from those reforms and

    would oppose back tracking. An example of that is the reform at customs, which

    facilitates and reduces costs of international trade. Likewise, for the improved operations

    of the Registry, and for the services provided by the Invest Dominica Authority

    (component 2). The risk could be significant, however, with regard to the new

    procurement legislation, which has been bouncing back and forth for a long time.

    Approval of this law is required to ensure that all public contracts above threshold are

    advertised and awarded through transparent and competitive bidding.

    The risk to the liberalization and current regulation of production and distribution

    of electricity is moderate. While the new IRC is perceived as doing a good job and

    protecting consumers, the cost of maintaining a national regulator is high. If this cost

    becomes unbearable, the government may decide that it is advantageous to participate in

    the regional regulatory authority, the development of which is being supported by the

    Bank.

    The risk to the sustainability of the new National Beneficiaries Information System,

    once it’s operational, is low. Again, its higher efficiency is likely to save administrative

    costs and draw support from beneficiaries.

    5. ASSESSMENT OF BANK AND BORROWER PERFORMANCE

    5.1 Bank Performance

    (a) Bank Performance in Ensuring Quality at Entry

    Rating: Moderately Satisfactory

    The areas included in the GSPTAP were all of strategic relevance for Dominica. In

    fact, they were also part of the Growth and Social Protection Medium Term strategy of

    the government. However, the value added of the second component – Improving the

    Investment Climate, is not so clear since there were other donors providing support in

    this area. The Results Framework was general and with Outcome Indicators difficult to

    measure. A subsequent Table of Arrangements for Results Monitoring in the PAD

  • 19

    presented interim and final target values for several OIs, but some called for 100%

    compliance, which was not very realistic. The implementation arrangements were good,

    with the PCU collaborating with the Ministry of Finance and the creation of a Steering

    Committee and working groups for each component. However, the slow start of the

    Project suggests that assessment of readiness for implementation was lacking. Finally, the

    Risk Assessment included in the PAD was appropriate, covering most aspects of risk and

    describing mitigating measures for each one of them.

    (b) Quality of Supervision

    Rating: Moderately Satisfactory

    The project lost its Task Manager (TM) almost right after Board approval, and

    there was another TM change in the last year of implementation. While that is not

    uncommon in the Bank, the two transition periods between TMs appear to have resulted

    in delays in receiving responses to no-objection requests. Also, it took some time for

    n