doe/nsf ilc review april 4-6, 2006 wbs 2.8/3.8 rf systems
DESCRIPTION
DOE/NSF ILC Review April 4-6, 2006 WBS 2.8/3.8 RF Systems. General Goals: Develop more reliable and lower cost L-band RF source components for the ILC linacs. Verify performance goals of the rf system. Chris Adolphsen. ILC Linac RF Unit (1 of ~ 600). Gradient = 31.5 MV/m - PowerPoint PPT PresentationTRANSCRIPT
DOE/NSF ILC Review April 4-6, 2006
WBS 2.8/3.8 RF Systems
General Goals:
Develop more reliable and lower cost L-band RF source components for the ILC linacs.
Verify performance goals of the rf system
Chris Adolphsen
ILC Linac RF Unit (1 of ~ 600)
Gradient = 31.5 MV/mBunch Charge = 2e10 eRep Rate = 5 Hz# of Bunches = 2967Bunch Spacing = 337 ns Beam Current = 9.5 mAInput Power = 311 kWFill Time = 565 sTrain Length = 1000 s
(8 Cavities per Cryomodule)
3.8.1 Marx Modulator• Definition of Work Package
– Marx is ACD Alternate Design to BCD Bouncer Modulator
– Motivation: Reduce cost, size and weight, Improve efficiency, eliminate oil from tunnel
• FY06 Program– Demonstrate basic operation with full power
prototype by end FY06. – Begin design of DFM Unit for service in klystron test
stands at SLAC and where needed. – Down-select to ACD when successful.
ILC BaselinePulse Transformer
Modulator
IGBT’s
Marx Generator Modulator
12 kV Marx Cell (1 of 16)
• IGBT switched• No magnetic core• Air cooled (no oil)
Full Modulator(~ 2 m cubed)
150 kW Air-CoolLoad for Testing
Modulator Structure, Backbone, Backplanes
Marx Features• Direct-coupled voltage stack of ten 12-kV cells
producing 140A pk @ 1.5 msec.• Cell can operate with failed components.
– 4/5 redundant solid state output, re-charging switch banks.
• Modulator functions with up to 2 failed drivers– 10 needed, 12 available
• Vernier cells correct flat top to +/-0.5%.– Second stage correction also being studied to approach
+/-0.1% if possible.
• Buck regulators (2) have 4/5 switch redundancy
Development Team• Engineering
– G. Leyh, Lead; Piotr Blum, C. Burkhart, J. Olsen, SLAC– C. Brooksby, E. Cook, Bechtel/LLNL
• Consultants– S. Cohen, LANL– J. Frisch, K. Jobe, SLAC – G. Majumdar, Mitsubishi– H. Pfeffer, FNAL
• Industrial Participants– Diversified Technologies, Bedford MA– ISA, Dublin CA– Stangenes Industries, Palo Alto CA
Prototype Development Schedule
Marx Modulator Status
• Modulator support structure, backbone, complete
• First prototype Marx Cell ready for testing.
• Equipotential rings, connection planes complete
• PPS system for modulator 30% complete• Air cooled 150 kW test load 25% complete
• 12kV single-cell test stand ready for operation
• As of March 1, 2006,– Labor charges = 187 k$ (576 k$ allocated)
– M&S charges = 280 k$ (370 k$ allocated)
3.8.2 SC Linac Quad and BPM• Goals:
– Characterize field properties of a prototype linac SC quad.
– Verify quad center moves < 5 microns when the field strength is changed by 20% as required for beam based alignment.
– Develop cavity BPMs with micron-scale resolution for multi-bunch (200 ns spacing) operation.
• Project Description:
– Acquired a prototype SC linac quad (80 mm bore, cos[2] type) from CIEMAT/DESY. Building a warm-bore cryostat for it at SLAC.
– Characterize quad magnetic field with a rotating coil, in particular, to measure any motion of the magnetic center when the field strength is varied.
– S-band rf cavity bpms have been designed and a triplet built that will be tested with beam in End Station A (ESA).
– BPMs have half the nominal aperture to simplify testing design concept and because it would be advantageous for the ILC.
– In FY07, propose to test quad and bpms with beam to demonstrate required quad shunting performance.
Cos(2) SC Quad(~ 0.7 m long)
S-Band BPM Design(36 mm ID, 126 mm OD)Field Map
Al Cylinder
Iron YokeBlock
SC Coils
He Vessel
ILC Linac SC Quad/BPM Evaluation
He Vessel Support in the Cryostat
Cryostat and Cryogenic System
Series of measurements (8 minutes each) of a 25 cm long NLC prototype quad - shows that sub-micron resolution is possible and systematics are controllable.
Currently designing longer, wider coil for SC Quad test – will qualify it first with a NC Quad.
X C
en
ter
(mic
rons)
Measurement
For Magnetic Center
Measurements,Adapt Apparatus
Developed for NLCNC Quads
S-Band (2.86 GHz) BPM Mode Spectrum (monopole mode signals suppressed geometrically)
BPM Triplet to be Tested with Beam
SC Quad/BPM Status• Magnet received from DESY in January after initial testing there in a
vertical Dewar. Gas-filled leads received in March.
• With help of Tom Nicol at FNAL, developed a low heat loss, stable support
design for the He vessel. May adopt similar support structure for the ILC
linac.
• Cryostat drawings currently being submitted to the SLAC shops.
• First tests of new magnet measuring coil planned during the next month
using a NC quad. SC quad measurements planned for July.
• BPM triplet built and installed on girder in ESA. Beam test to start April 24.
• As of March 1, 2006
– Labor charges – 112 k$ (144 k$ allocated, 240 k$ requested last October)
– M&S charges – 126 k$ (205 k$ allocated, 250 k$ requested last October)
– Project at ~ 50% point with about half of the requested funding spent.
3.8.3 Coupler Development(LLNL / SLAC)
• Goals:
– Understand rf processing limitations (typically takes > 100 hours per coupler).
– Assess effect of coupler coatings, bellows, and widows on processing time.
– Propose changes to TTF3 design to improve performance and lower cost.
• Project Description:
– Eleven coaxial sections (40 mm ID, 70 Ohm) will be prepared that vary in
terms of material (SS or Cu), bellows (none, 5 or 10 folds) and windows (with
and without).
– A general purpose waveguide (WR650) to coax adaptor has been designed to
power the test sections in vacuum.
– Use the L-band rf source that has been configured at NLCTA (currently
produces 3.3 MW, 1 msec pulses at 5 Hz: need only ~ 2 MW).
To understand processing limitations, plan to process coupler components individually. In particular, determine if bellows or the windows are the source of the long processing time.
Concern that the surface field variations in the bellows and near the windows may lead to excessive mulitpacting.
Coupler Processing Studies
Cou
pler
Su
rfac
e F
ield
Coupler Development Status
• Have decided on basic
layout of system to test
coupler parts – drawings
are being prepared
• Setup uses a detachable
center conductor and 50
cm long test sections
• As of March 1, 2006
– 15 k$ labor charges
(180 k$ allocated)
– Zero M&S (100 k$
allocated)
• Ready for first tests this
Summer.
2.8.1 RF System Design• Doing tracking simulations of multipacting in the TTF3 couplers in
conjunction with coupler R&D program. Will produce 3D map of
multipacting 'activity' -vs- rf power and longitudinal position along the
coupler outer surface.
• Studying ways to reduce rf distribution costs: considering three
changes to the basic design:
1. The circulators in the TDR design are a big cost item (~ 35% of total
distribution system). To eliminate them, power the cavities in pairs using
3 dB hybrids, which would still isolate them.
2. Develop a variable tap-off system to feed the cavity pairs.
3. Replace the three-stub tuner with a mechanical squeeze type phase
shifter that would adjusted after the system is setup.
• As of March 1, 2006
– 83 k$ of labor charges (126 k$ allocated)
Multipacting Simulation of TTF3 Coupler
Bellows
Primaries -Green, Secondaries- RedPrimaries -Green, Secondaries- Red
“Cold Side”
With two-level power division and proper phase lengths, reflections from pairs of cavities are directed to loads. Also, fewer types of hybrid couplers are needed in this scheme. There is a small increased risk to klystrons (total reflection from a pair of cavities sends < 0.7% of klystron power back to the klystron.)
Similar to TDR and XFEL scheme.
Baseline RF Distribution System
Alternate RF Distribution System
FY07-09 RF System Program• Goal: demonstrate viable, cost-optimal rf source for ILC. Operate six
‘production’ sources from industrial vendors by FY10. Supply power
source and couplers for RF unit test at FNAL.
• SLAC has substantial expertise in this area and ILC Americas expects
SLAC to lead this program. Would be responsible for all components
from the AC power to the couplers.
• Program would be comparable in size to that during NLC rf
development.
• Schedule meshes well with FNAL cryomodule program.
• Schedule allows for testing to establish > 2000 hour MTBF’s, which is
minimum allowable in particular availability models.
Yale University Beam Physics LaboratoryPROGRESS REPORT
20-MW MAGNICON FOR ILCsupported under DoE grant DE-FG02-05 ER 41394, 9/1/05 – 8/31/08
Program objectives: (a) To provide laboratory infrastructure at Yale needed to allow tests of a 20-MW, 1.3 GHz magnicon amplifier being designed and built to be an alternative RF source for ILC. (b) To coordinate closely with Omega-P, Inc. in its design and fabrication of the 20-MW magnicon, anticipating future tests at Yale.
Funding profile:FY06grant
FY06, to 3/13/06
FY07 budget
FY08 budget
labor 12,788 14,228 13,427 14,098
materials 6,400 6,400 5,873 10,367
equipment 18,000 6,464 22,000 25,000
other + indirect
22,812 17,201 23,700 15,535
totals 60,000 44,293 65,000 65,000
WBS 3.8.4
Progress to date (9/1/05 - 3/21/06)
A. At Yale Beam Physics Lab, room 112 (M.A.LaPointe, J.L.Hirshfield):
1. added 72 kW ac power, to bring total up to 150 kW;
2. relocated water pipes so that shielding door can close ($11k from Yale towards cost);
3. ordered 150 kW heat exchanger.
B. At Omega-P (V.P.Yakovlev, J.L.Hirshfield):
1. refined conceptual design for magnicon;
2. made preliminary simulations for TE111-mode output cavity (reduced RF
surface field in output cavity, compared with TM110-mode and with MBK);
3. began negotiations with potential industrial partner for fabrication of tube
and contribution of 30 MW / 80 kW modulator, suitable for 1.6 ms pulse width, ~1 Hz rep rate operation of 20-MW, 1.3 GHz magnicon.
20-MW, 1.3-GHz MAGNICON AMPLIFIER FOR ILC
Preliminary design layout and design specifications
peak output power 22.5 MW
average output power 180 kW
pulse duration 1.6 ms
repetition rate 5 Hz
efficiency 75%
gain 44 dB
FWHM bandwidth ~ 2 MHz
beam power 30 MW
beam voltage 300 kV
beam current 100 A
beam perveance 0.61 perv
Ribbon-Beam Klystron Research:
Improving Efficiency in High-Power Klystrons
Chiping Chen
Plasma Science and Fusion Center
Massachusetts Institute of Technology
DOE ILC Review
April 5, 2006
33DOE ILC Review Chiping Chen, Intense Beam Theoretical Research Group
WBS 3.8.5
Ribbon-Beam Klystron
• Klystron is a high capital cost, high operating cost item for ILC.
• Ribbon-beam klystron (RBK) is a leading ACD choice, because it is better than the multi-beam klystron (MBK) BCD choice. – Higher efficiency (75% vs. 65%)– Single beam vs. 6 beams– Energy-free permanent magnet vs. energy-consuming
pulsed magnet
• RBK provides potentially the following savings:– Klystron hardware: 66% (or $60M) saving. – RF system electricity: 20% (or $20M/year) saving.
34DOE ILC Review Chiping Chen, Intense Beam Theoretical Research Group
35DOE ILC Review Chiping Chen, Intense Beam Theoretical Research Group
Ribbon Beam Improves Klystron Efficiency
0 1 2 3
Micro-Perveance
0.0
0.2
0.4
0.6
0.8
1.0
Effi
cien
cy SLAC XP3 Klystron
MBK (Multi-Beam Klystron)
RBK (Ribbon-Beam Klystron)
0.8 - 0.2 P
2/36 /10PerveanceMicro VI
Parameter New Design
Freq (GHz) 1.3
RF Power (MW)
10 (pulsed)
Current (A) 111.1
Voltage (kV) 120
S (cm) 2.2
kox/koy 0.158
B0 (kG) 2.0
a/b 20
a (cm) 1.0
max (deg) 0.75
Current Status and Budget
• 2005 Status– Carried out innovative research to successfully reduce
the twist angle of the elliptic beam (2005).– Applied results of ribbon beam physics studies in our
consideration of design options for the ribbon-beam transport system (2005).
– Determined the feasibility of magnet engineering required for focusing the elliptic electron beam (2005).
– Developed a small-signal theory of RBK (2005).
• 2005-2006 Budget– Total Amount Funded: $30K – $5K left
36DOE ILC Review Chiping Chen, Intense Beam Theoretical Research Group
Summary• Have made good progress toward achieving FY06
goals.
• Gaining expertise in low-frequency, long-pulse rf
sources required for ILC, and beam related issues
with SC quads and ‘cold’ BPMs.
• Starting in FY07, will expand work toward producing a
robust klystron and a lower cost rf distribution system.
• In a good position to ramp up program in the next few
years to produce several prototype ILC rf sources.