October 28, 2014 sPHENIX Assembly Shown in Shield Wall Opening

TRANSCRIPT

Page 1: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

DON LYNCHOCTOBER 28, 2014

Infrastructure, Integration and Installation

Page 2: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Detector Integration & Assembly Concept

Page 3: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Shown in Shield Wall Opening

Page 4: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

1. BABAR magnet transported to PHENIX possession in bldg 912 test area. BABAR Magnet becomes sPHENIX magnet

2. sPHENIX magnet tested at 9123. Complete Stack modifications design and fabricate4. HCal outer, HCal Inner, EMCal, Tracking detector, global support structure, global infrastructure and

assembly/installation fixtures design and procurement5. HCal outer, HCal Inner, EMCal and Tracking detector assembled into modules and tested at

assembly areas (TBD)

sPHENIX Assembly Plan Chronology

4

Page 5: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

(End of run 16)

6. PHENIX Decommissioning

sPHENIX Assembly Plan (cont’d)

5

Page 6: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

7. Global support structure and global infrastructure components assembled and installed at 1008 AH and IR as appropriate. Old beampipe sections installed in IR with temporary supports and baked out for run)(BES II, run 1. After run shield wall disassembled but base remains in AH)

sPHENIX Assembly Plan (cont’d)

6

Page 7: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

8. Central Pedestal (CP) base and HCal support assembled at 1008 AH.

Page 8: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

9. 1/2 of HCal outer transported to 1008 AH Lower ½ HCal cables routed to north and south ends of detector and tied off.

Page 9: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

HCal Assembly Concept:

64 modules connected at ends, 4 sets of intermediate spacers

5200 mm

Page 10: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

10. sPHENIX Magnet Transported to 1008 and mounted on CP

Page 11: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

Inner HCal Design with EMCal Interface

4275 mm

Page 12: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

Inner HCal Support Structure Concept

Page 13: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Detectors Internal support10/9/2014 13

Outer Hcal

Magnet

Inner-Outer Hcal Mounting

Inner Hcal

Inner Hcal to EMCal Mounting

EM Cal

Flux Return End Cap

sPHENIX Assembly Plan (cont’d)

Page 14: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

5200 mm

Page 15: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

Page 16: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

Page 17: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

Page 18: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

Page 19: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

12. All Inner HCal modules transported to 1008 AH

13. Inner support structure assembled with installation fixture, all Inner HCal mounted on Inner support structure then this assembly inserted into Magnet and Inner support structure mounting hardware (connecting Inner support structure to lower Outer HCal and/or CP)

14. Inner HCal cables routed out of magnet & tied off

15. Remainder of Outer HCal installed and connected to inner support and lower HCal support/CP, cables routed from Outer HCal and tied off

16. Install new/modified Beam pipe sections in IR on temporary supports and bakeout.

Page 20: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

(BES II, run 2 the following steps can be performed will BES II run 2 is underway)

17. CP upper rack platform installed on CP above Outer HCal

18. Racks and Cables installed/routed for Inner and Outer HCal modules on CP

19. All EMCal modules installed inside Magnet

(the following steps can be performed while BES II run 2 is underway)

20. CP upper rack platform installed on CP above Outer HCal

21. Racks and Cables installed/routed for Inner and Outer HCal modules on CP

22. All EMCal modules installed inside Magnet

Page 21: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

23. EMCal racks, cables and infrastructure services installed on CP

24. Tracking modules installed inside Magnet

25. Tracking module racks, cables and infrastructure services installed on CP

26. End Cap flux returns installed.

Page 22: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

27. Move shield wall base to side of AH

Page 23: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

NOTE: Full assembly fits through shield wall opening

Page 24: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

28. Entire detector moved to IR

Page 25: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

29. Move entire assembly north to center on IP

Page 26: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

October 28, 2014

sPHENIX Assembly Plan (cont’d)

30. Shield wall, rebuilt, commissioning and full field magnet test (magnet test requirements currently under evaluation may test sooner)

Page 27: DON LYNCH OCTOBER 28, 2014. October 28, 2014 sPHENIX Detector Integration & Assembly Concept

sPHENIX in the IR