Project: Sea Residences - Phase 2 Date: February 13, 2012 Subject: Cost Estimate for deletion of doors at phase 2 Item no. Description Quantity Unit Unit Cost Materials Labor 1 Wood Doors D-19 600 x 2150 mm: to storage room 4.00 set/s PHP 8,700.00 PHP 2,000.00 Ducco paint finish D-19 4.00 set/s PHP 1,500.00 PHP 1,500.00 . 2 Steel Doors D-4 800 x 2100 mm: to garbage room 56.00 set/s PHP 10,220.00 PHP 2,000.00 Ducco paint finish D-19 56.00 set/s PHP 1,000.00 PHP 1,000.00 3 Finishing Hardwares Handles Stainless steel cylindrical lockset Hinges Heavy duty stainless steel (3 1/2 x 3 1/2) 168.00 nos. PHP 500.00 PHP 250.00 3 1/2 x 3 1/2 Loose pin Hinges 12.00 nos. PHP 180.00 PHP 250.00 4 Water meter enclosure 48.00 nos. PHP 3,500.00 PHP 700.00 Total Deductive Amount As per BOQ Prepared By: design coordinates, inc construction project management Rene Bañares CPE-ME Supply and installation of tanguile KD flush door with louver blade single leaf door painted finish, including door jambs and all necessary fixing accessories, as per specification (Hardware measured seperately) Supply and installation of single leaf steel flush door GA#16 Galvanized with honeycomb insulation on GA#14 single rabbet jamb painted w/ automotive pain finish, as per specification (Hardware measured seperately)

Upload: alainmelcrescini

Post on 28-Jan-2016

212 views

Category:

Documents


0 download

DESCRIPTION

s

TRANSCRIPT

Page 1: Door Deductive

Project: Sea Residences - Phase 2Date: February 13, 2012Subject: Cost Estimate for deletion of doors at phase 2

Item no.Description Quantity Unit

Unit CostTotal Unit Cost Total Cost

Materials Labor

1 Wood Doors

D-19 600 x 2150 mm: to storage room 4.00 set/s PHP 8,700.00 PHP 2,000.00 PHP 10,700.00 PHP 42,800.00

Ducco paint finish D-19 4.00 set/s PHP 1,500.00 PHP 1,500.00 PHP 3,000.00 PHP 12,000.00.

2 Steel Doors

D-4 800 x 2100 mm: to garbage room 56.00 set/s PHP 10,220.00 PHP 2,000.00 PHP 12,220.00 PHP 684,320.00

Ducco paint finish D-19 56.00 set/s PHP 1,000.00 PHP 1,000.00 PHP 2,000.00 PHP 112,000.00

3 Finishing HardwaresHandlesStainless steel cylindrical lockset

HingesHeavy duty stainless steel (3 1/2 x 3 1/2) 168.00 nos. PHP 500.00 PHP 250.00 PHP 750.00 PHP 126,000.003 1/2 x 3 1/2 Loose pin Hinges 12.00 nos. PHP 180.00 PHP 250.00 PHP 430.00 PHP 5,160.00

4 Water meter enclosure 48.00 nos. PHP 3,500.00 PHP 700.00 PHP 4,200.00 PHP 201,600.00

Total Deductive Amount As per BOQ PHP 1,183,880.00

Prepared By:design coordinates, incconstruction project management

Rene BañaresCPE-ME

Supply and installation of tanguile KD flush door with louver blade single leaf door painted finish, including door jambs and all necessary fixing accessories, as per specification (Hardware measured seperately)

Supply and installation of single leaf steel flush door GA#16 Galvanized with honeycomb insulation on GA#14 single rabbet jamb painted w/ automotive pain finish, as per specification (Hardware measured seperately)