doug thiessen outlook 2012
DESCRIPTION
Doug Thiessens Presentation at Outlook 2012TRANSCRIPT
![Page 1: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/1.jpg)
Port of Long Beach Development Projects
AGC of California’s Construction Outlook 2012
D.A. Thiessen, P.E.Managing Director, Engineer
February 8, 2012
![Page 2: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/2.jpg)
Economic Engine
• 2nd busiest U.S. container cargo seaport; part of the world’s 6th busiest port complex
2
![Page 3: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/3.jpg)
Jobs engine
• 30,000 jobs locally, 300,000 regional jobs and • 1.5 million national jobs
![Page 4: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/4.jpg)
U.S.-Asia Trade Routes
Pacific Northwest (Prince Rupert, Vancouver, Seattle, Tacoma)
Port of LONG BEACH (San Pedro Bay)
Mexico (Lazaro Cardenas)
All Water (Gulf and East Coast)
3
3
1
4
2
1
4
![Page 5: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/5.jpg)
Future
•Port is fiscally strong, investing $4 billion over next decade in terminal, infrastructure improvements
![Page 6: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/6.jpg)
Capital Expenditures
2011 2012 2013 2014 2015 20160
100
200
300
400
500
600
700
800
900
Misc ProjectsMiddle HarborPier GGD BridgePier SRail
$M
![Page 7: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/7.jpg)
Navigational Projects
![Page 8: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/8.jpg)
![Page 9: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/9.jpg)
Gerald Desmond Bridge
• Replacing obsolete bridge with a $950 million replacement to improve traffic flow and safety
![Page 10: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/10.jpg)
Existing GD Bridge
10
![Page 11: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/11.jpg)
New Cable-Stayed Bridge
•Improve traffic flow and safety•Bids due March 2012
![Page 12: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/12.jpg)
Design build
•RFP for estimated $675 million design-build contract issued September 2, 2011.
![Page 13: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/13.jpg)
Rail Enhancements
• $1.1 billion in projects to expand rail yard, realign tracks to support increased on-dock rail operations
![Page 14: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/14.jpg)
Off Terminal Rail ProjectsThenard Jct. Realignment
Cerritos Channel Rail Bridge
Expanded Control Points
Closure of Reeves Crossing
Navy Mole Storage
Yard
Reeves Grade Separation
Wye Track Realignment
Pier B Rail Yard
Ocean Blvd. Track
Realignment
Harbor Scenic Track
Realignment
Pier F Support Yard
Pier B Realignment
$1.1 billion in projects
![Page 15: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/15.jpg)
Shore-to-Ship Power
• Ships switch off engines and shift to shore power • to improve air quality
![Page 16: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/16.jpg)
Port-wide plug-in
• $200 million investment
• By 2014, 50% of container ships will plug in to shore power
• By 2020, 80% of container ships will plug in to shore power
![Page 17: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/17.jpg)
Terminal Projects
Pier GRedevelopment
![Page 18: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/18.jpg)
Pier G Redevelopment
• $470 million terminal redevelopment, adding• deep-water berths & expanding on-dock rail
![Page 19: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/19.jpg)
Pier G Redevelopment Program
![Page 20: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/20.jpg)
Terminal Projects
Middle Harbor Terminal
Development
![Page 21: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/21.jpg)
Middle Harbor
$1.2 billion Middle Harbor Project will improve terminal efficiency, cut pollution 50%, create 14,000 new jobs
21
![Page 22: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/22.jpg)
Terminal Projects
Pier S Terminal
Development
![Page 23: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/23.jpg)
Proposed Pier S Project
• Port proposes development of Pier S marine container terminal and Back Channel safety
improvements
![Page 24: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/24.jpg)
Pier S Terminal Project
•Draft EIR released Sept 16th. $650 million green shipping terminal to support 35,000 new jobs
![Page 25: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/25.jpg)
Proposed Pier S Project
![Page 26: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/26.jpg)
Project Background
• Badly contaminated oil field
Original Pier S Project approved decade ago
• Need for navigational improvements
• Only cleanup completed
• New, updated EIS/EIR
![Page 27: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/27.jpg)
Three-Berth Alternative
• 160-acre container terminal
• Wharves, buildings, truck gates
• On-dock rail yard• Dredging• Back Channel
navigational improvements
![Page 28: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/28.jpg)
Three-Berth PlanHeim
Bridge
Ocean Boulevard
![Page 29: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/29.jpg)
Environmental Measures
• CAAP Measureso Shore Powero Low-sulfur fuels o Emissions controlso Vessel speed
reduction• On-dock rail yard• LEED buildings
![Page 30: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/30.jpg)
What can AGC do for POLB?
• Members continue to bid our work• Advocate for approval of EIRs for upcoming
projects. Don’t sit on the sidelines• State and Federal transportation funding• Get familiar with our requirements:
like our sbe/vsbe programVisit our website www.polb.com
![Page 31: Doug Thiessen Outlook 2012](https://reader033.vdocuments.net/reader033/viewer/2022061221/54be572b4a795981308b458f/html5/thumbnails/31.jpg)
Questions?
For more information, go towww.polb.com