dover harbour useful info

Upload: paul-karadi-kirupaharan

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Dover Harbour Useful Info

    1/48

    Halcrow Group LimitedBurderop Park Swindon Wiltshire SN4 0QD

    Tel +44 (0)1793 812479 Fax +44 (0)1793 812089

    www.halcrow.com

    Halcrow Group Limited has prepared this report in accordance with

    the instructions of their client, Dover Harbour Board, for their soleand specific use. Any other persons who use any information

    contained herein do so at their own risk.

    Halcrow Group Limited 2009

    Dover Harbour Board

    Port of Dover 30 Year Master Plan

    Zoning Report

    July 2005

    Halcrow

  • 7/28/2019 Dover Harbour Useful Info

    2/48

    Dover Harbour Board

    Port of Dover 30 Year Master Plan

    Zoning Report

    July 2005

    Contents Amendment RecordThis report has been issued and amended as follows:

    Issue Revision Description Date Signed

    1 0 Draft 11.05.05 MBM

    1 1 DHB comments - Revised 17.06.05 MBM

    2 0 Redraft 29.06.05 RJC

    2 1 DHB comments 04.07.05 RJC

    2

    2

    DHB comments 2

    08.07.05

    RJC

    2 3 DHB comments 3 29.07.05 RJC

    2 4 DHB comments 4 18.11.05 RJC

  • 7/28/2019 Dover Harbour Useful Info

    3/48

    Issue 2 Rev 4 18 November 2005

    Contents

    1 Introduction 1

    1.1 General 1

    1.2 The Issues 2

    1.3 Objectives 2

    2 Trade Forecasts 4

    2.1 General 42.2 Freight Traffic 4

    2.3 Car Traffic 5

    2.4 Coaches 5

    2.5 Fresh Produce (Fruit) 5

    2.6 Aggregates 5

    2.7 Cruise Liners 5

    2.8 Trade Summary 6

    2.9 Traffic Growth Beyond 2034 6

    3 Eastern Docks Capacity Studies 73.1 General 7

    3.2 The Need for a Robust System 8

    3.3 Harbour and Marine Capacity 8

    3.4 Berth Capacity 9

    3.5 Internal and External Access Capacity of Eastern Docks 10

    3.6 Overall Capacity Conclusions 11

    4 The Environment of Dover Harbour 13

    4.1 Introduction 13

    4.2 Constraints 134.3 Opportunities 16

    5 Development Options 18

    5.1 Approach 18

    5.2 Exclusion of Stage 1 and Stage 2 Development Options 18

    5.3 Choice of Zoning Report Development Options 19

    5.4 Zoning Report Development Options 20

    5.5 Phasing of Zoning Report Development Options 28

  • 7/28/2019 Dover Harbour Useful Info

    4/48

    Issue 2 Rev 4 18 November 2005

    6 Planning Structure 306.1 Introduction 30

    6.2 Assessment Criteria 32

    6.3 Outline Economic Impact 36

    6.4 Planning Findings 38

    7 Conclusions 39

    8 Zoning Plan 41

    8.1 General 41

    8.2 Ferry Trade 418.3 Other Trades 43

    8.4 Summary 44

    Figures

    Appendix A Preferred Option Sketches

    Appendix B Preferred Option Descriptions Table

    Appendix C Phasing of Preferred Options

  • 7/28/2019 Dover Harbour Useful Info

    5/48

    Issue 2 Rev 4 18 November 2005 1

    1 Introduction

    1.1 GeneralDover is the busiest ferry port in the world and provides a vital link

    between the UK road network and the rest of continental Europe. The

    port is administered by Dover Harbour Board (DHB) as a Trust Port.

    The remit of the port is therefore to operate on a commercial basis to

    best serve the interests of the United Kingdom, the surrounding

    communities and the users of the port.

    In 2003, the DHB decided to draw up a 30 Year Master Plan for the Port.

    This master plan was required to set out the pattern of development for

    the port so that it could address changes in traffic, continue to contributeto the local economy and minimise the negative impacts on the town of

    Dover.

    The master plan is being developed using a staged approach. Phase 1 in

    2003 included traffic forecasts and assessments of the existing and

    potential port capacities. It indicated how each trade sector could develop.

    Phase 2 began in 2004 and involved preparing an incremental

    development plan, focused on maximising use of the existing harbour

    (both Eastern and Western Docks). It analysed investment return and

    prioritised conflicting options.

    Halcrow is the Engineering Consultant for Phase 2 of the Master Plan,

    whilst High Point Rendel (HPR) is the Financial Consultant. Phase 2

    includes the following stages, of which we are currently at Stage 3 :

    Phase 2 Stage 1 : review port traffic forecasts, outline

    development options based on prioritisation of trade;

    Phase 2 Stage 2 : undertake capacity study of Eastern Docks,

    refine development options based on port trade growthrequirements.

    Phase 2 Stage 3 : consultation and further development of

    feasible options to create a zoning plan covering both the Eastern

    and the Western Docks

    Phase 2 Final Report Stage : following further public

    consultation.

    This report sets out the likely development of the port as the basis forpublic consultation.

  • 7/28/2019 Dover Harbour Useful Info

    6/48

    Issue 2 Rev 4 18 November 2005 2

    1.2 The IssuesDover Harbour has always been the historic gateway between the UK and

    the Continent and also close to the major shipping lanes into the North

    Sea. 80% of trade is ferry related. Operators include P&O, SeaFrance,

    Norfolk Line, SpeedFerries and Hoverspeed.

    The port has also diversified to include cruise facilities (two berths), a

    cargo terminal with temperature controlled storage, an aggregate facility

    and the yacht marina. On land are a shopping complex, hotel

    development, property and a business park.

    The area of land and water in which the port operates is restricted. Ferry

    operations are concentrated in the Eastern Docks (shown in Figure 1.1).

    While all is running smoothly, the existing port is able to handle the

    present levels of traffic without difficulty. The system is complex and any

    disruption due to bad weather, breakdowns, labour disputes, political

    demonstrations or security issues very quickly clogs the local roads with

    traffic. This causes frustration for the port users and disrupts the lives of

    the towns residents.

    The challenge is to see how the port can handle increasing traffic while

    reducing the incidence of these traffic problems. This has to be done

    while dealing with ever increasing security and without compromising the

    very high safety standards that the port applies.

    1.3 ObjectivesThe overall objective is to provide DHB with the foundation for a

    workable business plan for the port for the next 30 years, including

    recommendations to maximise the commercial and economic potential of

    the port and its assets.

    The Master Plan will pay particular attention to the following aspects :

    Reliable traffic/trade forecasts for ferry, cargo, cruise and marina;

    The optimum use of the berthing facilities available;

    Take account of cargo terminal capacity, manoeuvring capacity,

    internal and external access capacity;

    Identify impacts of government policy and environmental

    constraints;

    Define capacity in each area of port operation;

  • 7/28/2019 Dover Harbour Useful Info

    7/48

    Issue 2 Rev 4 18 November 2005 3

    Maximise the commercial and economic potential of the port,

    including redevelopment and alternative uses for some or all

    areas;

    Look carefully at the relationship between the port estate and the

    rest of Dover;

    Identify the preferred way forward for the Port of Dover.

    The master plan will include actions to be taken to improve the

    infrastructure and modes of operation, to achieve the vision. The master

    plan will not be a static document since it will be subject to regular review

    and updating.

    Figure 1.1 Port of Dover Layout

    N

    Southern Breakwater

    Admiralty Pier

    Eastern Docks

    Western Docks

    Eastern EntranceWesternEntrance

  • 7/28/2019 Dover Harbour Useful Info

    8/48

    Issue 2 Rev 4 18 November 2005 4

    2 Trade Forecasts

    2.1 GeneralIn Phase 1 of the master plan, a set of trade forecasts for the port was

    developed which was further reviewed in Phase 2.

    Trade forecasts for a port are based on a series of assumptions, taking in

    the rate of economic growth of the nation, the pattern of trade, changes

    in government regulations, the behaviour of shipping lines and the

    competition from other modes of transport. All of these factors are

    constantly changing and so the forecasts always have an element of doubt

    associated with them.

    The requirement is that the master plan should set out a series of

    forecasts which are as accurate as possible but which can be easily

    updated.

    2.2 Freight TrafficFreight ferry traffic provides the backbone of Dovers business. Trucks

    prefer to use Dover as the frequent sailings allow a turn up and go

    system to be operated. Trucks arrive at the port without bookings and are

    allocated to the first available ferry by the chosen operator.

    The trade between the UK and Europe is growing rapidly although this is

    threatened by the increasing relocation of manufacturing capacity to

    China and India. The expansion of the EU will encourage trade between

    the countries of Eastern Europe. Government legislation throughout

    Europe is seeking to control the growth of road traffic, encouraging more

    use of sea transport as an alternative. This will tend to shift traffic away

    from Dover towards longer ferry crossings from the Humber and Thames

    Estuary. Traffic congestion in the South East of England will also tend to

    reduce the volume of freight using Dover.

    Taking all these factors into account, the master planning team have

    produced the forecasts for freight ferry traffic shown in Section 2.8

    below. This shows a steady increase in freight traffic with volume almost

    doubling by 2034.

    The freight traffic is not steady through the day and also shows variations

    through the week. The ferry operators set up their service schedules so

    that with everything working well there is enough capacity at peak hours.

    The same ships are then run through the day with a vessel on the Dover

    Calais run typically making 5 round trips per day. This results in theseemingly low deck utilisation (a measure of how full the ships are on

  • 7/28/2019 Dover Harbour Useful Info

    9/48

    Issue 2 Rev 4 18 November 2005 5

    average) of around 50%. This low average deck utilisation allows the port

    to clear a backlog of waiting trucks quite quickly after a period of

    disruption. If the average rose to around 70%, as is usual on longer ferry

    crossings, the port would take days to clear a backlog.

    2.3 Car TrafficThe number of cars using the Dover Ferry services has been seriously

    affected by competition from the Channel Tunnel Shuttle service and also

    by low cost airlines offering attractive fly-drive packages. In a more

    general level, the holiday traffic has been reduced by a trend to long haul

    holidays rather than the more traditional journey to France.

    The agreed traffic projections show a reduction in car traffic over the next

    few years with a subsequent recovery to give an increase of 15% by 2034.

    As with the trucks, car traffic has distinct peaks with low carryings in

    winter and more on Bank Holiday weekends. Fortunately the peak car

    traffic does not coincide with the truck peak.

    2.4 CoachesThe coach trade through Dover is predicted to decline as a result of

    changing trends in European holidays. A few years ago it was quite

    common for people to use coach travel as part of a holiday package but

    the low cost airlines have largely taken this function. Coach tours are still

    popular but the average age of the customers is rising except in somespecialist areas. Total coach traffic is expected to halve by 2034. Even if

    this projection is wrong, it will not have a large effect on the total ferry

    traffic.

    2.5 Fresh Produce (Fruit)Dover came into the fruit trade as part of a diversification policy before

    the Channel Tunnel opened and the small facility is operated by a third

    party, handling cargo for one major importer. Competition in the fruit

    market is intense and it is likely that without an improved facility, the fruit

    trade will reduce. If improved facilities can be offered, additional userscould be attracted, giving a 50% increase in throughput by 2034.

    2.6 AggregatesDover provides a berth and handling facility for marine dredged

    aggregates. The materials are for local use and this trade is expected to

    stay relatively stable.

    2.7 Cruise LinersAnother part of the Dover diversification was to build two cruise liner

    berths in the Western Harbour. Dover acts mostly as the start and finishpoint for cruises to Scandinavia and it competes with Harwich in this

  • 7/28/2019 Dover Harbour Useful Info

    10/48

    Issue 2 Rev 4 18 November 2005 6

    market. North Sea cruises are a steadily growing market but weather

    dictates that it will only have substantial volume in the summer months.

    The number of ship calls is expected to double between now and 2034.

    2.8 Trade SummaryThe table below sets out a summary of the baseline traffic forecasts up to

    2034. The actual trade may vary considerably from the figures given so

    that the timing of demand for new facilities may change.

    Trade Sector 2003 2014 2024 2034

    Freight Million units 1.8 2.2 2.5 2.6 3.3 2.8 3.9

    Cars Million units 2.6 2.3 2.6 3.0

    Coaches 000 units 130 80-100 60-90 40-80

    Fresh Produce 000 tonnes 263 rising to 350 - 400

    Aggregates000 tonnes 220 Within the 200-250 range

    Cruise Calls 117 140 180-190 200-250

    Passengers Million 14.8 14.1 15.6 17.2

    2.9 Traffic Growth Beyond 2034Although the present master plan study covers 30 years from the start in

    2004, it is sensible to look at general trends beyond that date. It is likely

    that the truck traffic will keep growing beyond that date although other

    trades may have already changed radically. The master plan should

    therefore allow for further growth in ferry demand.

  • 7/28/2019 Dover Harbour Useful Info

    11/48

    Issue 2 Rev 4 18 November 2005 7

    3 Eastern Docks Capacity Studies

    3.1 GeneralEarlier parts of the master plan study looked at options for the

    development of the Eastern Docks and determined the ultimate capacity

    of this area to accommodate ferry traffic. The capacity of the existing

    fruit and aggregate facilities was also calculated.

    A series of capacity aspects were considered, namely marine capacity (ship

    movements), berth capacity (berth slots, vessel timetables and berth

    throughput), and internal and external access capacity (landside traffic).These are explained in the following section.

    To do the capacity calculations, a number of assumptions had to be made.

    These can be summarised as follows: -

    The ferry services will continue to be operated by a small number

    of different companies using modern vessels.

    Most traffic will be carried by conventional ferries. The high

    speed ferry services will continue but are unlikely to expandsignificantly.

    The smaller ferries will be replaced with Dovermax ferries

    approximately 185m long with a beam of 28m. The ferry

    operators have all stated that they have plans to do this. They

    have also looked at using larger ferries but they have decided that

    these will take too long to turn around in the Dover context.

    Once these larger ferries are operating at around 50% deck

    utilisation the operators will increase capacity by providing morefrequent sailings.

    If the pattern of services changes from the above assumptions, the dates

    on which the various phases of the system reach capacity will change. For

    example, the change from the 2004 fleet to an all Dovermax fleet gives a

    30% increase in the number of vehicles which the schedule can handle. If

    a new operator were to come in and offer an additional service using

    smaller ships, this could reduce the capacity of the system by taking up

    berth slots and marine capacity, which would not then be available to

    larger ships. The legal framework within which the port operates requiresit to offer facilities to new customers. The modelling does not show any

  • 7/28/2019 Dover Harbour Useful Info

    12/48

    Issue 2 Rev 4 18 November 2005 8

    constraint on new operators but they are assumed to use large modern

    ships.

    Dover Harbour is essentially a linear activity with the marine capacity

    feeding into the berth capacity which in turn feeds into the landside traffic

    capacity. When any one of these areas reaches capacity, the whole system

    cannot handle any more traffic. Improvements in one area may not

    provide overall increases in capacity if another part of the system is

    already at the limit.

    3.2 The Need for a Robust SystemIn theory, with everything working to schedule and no problems, the Port

    of Dover can handle several times its present throughput. This is

    however a theoretical situation and in reality the capacity of the system is

    fixed by its capacity to deal with the delays, breakdowns and disruptions

    which are part of everyday life. The analyses described below have been

    based on quality of service under realistic conditions not the theoretical

    maximum capacities.

    3.3 Harbour and Marine CapacityThe number of ferry sailings which the Eastern Docks can accommodate

    is limited by the space available to manoeuvre ferries seaward of the ferry

    berths.

    The study of marine capacity was undertaken using ARENA, a simulationmodelling tool. The model was built to closely represent and mimic the

    real marine system at the Eastern Entrance and off the Eastern Docks

    berths. The rules applied to the ship movements were discussed with the

    marine operations staff and ships masters working for the operators. The

    model was validated by running the existing shipping schedules and

    checking whether it reflected real events. The model was then used to

    test a variety of shipping schedules to see how much extra traffic could be

    accommodated without a deterioration of service levels.

    The construction of Berths 8 and 9 has expanded the area available formarine operations and has improved the service levels. The modelling

    showed that the Eastern Docks is able to accept a schedule containing 88

    ship movements per day. Building further berths in the Eastern Docks

    will not allow additional ship movements as they would use the same

    manoeuvring space.

    Generating shipping schedules to match the baseline traffic projections

    shows that the Eastern Docks runs out of marine capacity in 2024 even

    allowing for optimal shipping capacity. At this point more than 88 ship

    movements are required. This date will change with varying traffic levels,changes in fleet composition or changes in vessel destinations.

  • 7/28/2019 Dover Harbour Useful Info

    13/48

    Issue 2 Rev 4 18 November 2005 9

    3.4 Berth CapacityBerth capacity is the volume of traffic that the berths in the port can

    handle. At first sight this may appear trivial as you simply put a new

    vessel onto the berth when one departs and the berth capacity is the deck

    capacity of the ship times the number of ships per day that the berth can

    take. To achieve this capacity there would have to be a queue of ferries

    waiting outside the port. This would be uneconomic for the operators

    and frustrating for the passengers.

    To do a proper analysis of berth capacity you need to look at which ships

    will fit which berths and then build a schedule so that the same ships

    come back to the same berths. The schedule has to allow for the time at

    sea and the time alongside of each ship. The schedule also has to have

    some slack in it so that the ship can catch up if she is delayed at any point.

    The Dover conventional ferry berths as at the end of 2005 will be as

    follows: -

    BerthNo

    LinkspanType

    Max VesselLength (m)

    VesselBeam(m)

    Depth toSeabed

    (m)

    YearInstalled

    1 Single deckwith stowablefinger ramps

    Effectivelyunlimited

    21.3 8.6 to 10.3 1987

    2 Twin deck .Ramp intovessel. Paxwalkway over

    178.5 28.5 7.3 to 9.3 1988

    3 Twin deck.Ramp intovessel. Paxwalkway over

    178.5 28.5 7.4 to 9.2 1987

    5 Twin deck.Ramp intovessel Paxwalkway over

    185 22.3 6.3 to 7.4 1980

    6 Twin deck.Ramp intovessel. Pax

    walkway over

    185 27.7 7.7 to 8.3 1980

    7 Twin deck.Ramp intovessel. Paxwalkway over

    190 28.5 8.0 to 9.2 1993

    8 Twin deck.Ramp intovessel. Paxwalkway over

    218.8 28.5+ 8.5 2005

    9 Twin deck.Ramp intovessel. Paxwalkway over

    218.8 28.5+ 8.5 2005

  • 7/28/2019 Dover Harbour Useful Info

    14/48

    Issue 2 Rev 4 18 November 2005 10

    In addition, the port has a cars only high speed ferry berth in the Eastern

    Docks and a single high speed ferry berth on the hovercraft terminal in

    the Western Docks.

    Ferry schedules were developed for the years 2014, 2024 and 2034 based

    on the traffic predicted for those years. The number of berths required to

    handle these schedules was determined based on keeping a reserve berth

    to ensure reliability of service. This exercise showed that the berths were

    not likely to be the bottleneck given the assumptions made about fleet

    mix.

    3.5 Internal and External Access Capacity of Eastern DocksThe capacity of the internal and external access to the Eastern Docks was

    assessed using VISSIM, a vehicular traffic model that simulates traffic

    movements along a road network. A landside traffic micro-simulation

    model was set up for this purpose and calibrated against the existing

    situation.

    Ferry landside capacity includes the capacity of the port internal road

    system within the Eastern Docks, as well as the external road network

    near the port. Landside capacity is also determined by the processing

    capacity of the various control gateways through which traffic passes.

    These include security, immigration and customs checks. The practical

    capacities of these gateways are determined by operational efficiency,

    whereas ultimate capacity is limited by the infrastructure such as howwide the roads are and how many weighbridges are available.

    The capacity of the Eastern Docks is also determined by the capacity of

    the assembly areas to store outbound traffic prior to departure. This

    depends on operational factors, not only in terms of the effective use of

    available assembly space, but also in terms of the requirement for such

    space. This is in turn a factor of the scheduling and reliability of ferry

    operations. If the ferries could operate to a perfectly regular schedule, the

    assembly spaces could achieve a very high utilisation but in practice this is

    not possible.

    With a realistic ferry schedule, the assumed changes in fleet size and

    sailing schedules and the baseline projection of traffic growth, the internal

    road capacity of the Eastern Docks will be reached by 2020. In practice

    this theoretical date may be over-optimistic due to fluctuations which may

    occur in traffic arrival patterns and operating conditions. Consequently it

    will be important to provide capacity outside the Eastern Docks

    considerably in advance of this date. Modifications to the internal road

    network and dock exit roundabout will also be needed well before that

    date.

  • 7/28/2019 Dover Harbour Useful Info

    15/48

    Issue 2 Rev 4 18 November 2005 11

    3.6 Overall Capacity ConclusionsAs can be seen above, the capacity of the Eastern Docks is determined by

    its ability to provide good service levels in a number of areas.

    The marine capacity of the docks is limited to 88 sailings a day. This will

    be achieved by 2024 with all the assumptions made. The most significant

    assumption is that all the ships sailing out of Dover will be Dovermax

    size. There are a number of new ships on order for ferry routes out of

    Dover, but if these are the only changes to the fleet, the marine capacity

    will be reached in 2012. Accordingly important decisions will be required

    in the near future. This date is very sensitive to changes in assumptions

    and the number of sailings required each year will have to be monitored

    carefully.

    Consideration of berths shows that the number of berths available in

    2005 appears sufficient to accommodate a 2034 timetable with predicted

    2034 traffic throughput. If the number of operators was to change or the

    fleet composition does not change as expected, the date for reaching

    capacity will move. The marine capacity is always likely to be reached first

    as it reacts to many of the same variables.

    Internal and external access (landside) capacity appear theoretically

    capable of accommodating traffic levels perhaps as far as 2020, based on

    traffic modelling assuming optimal operating conditions and median

    freight growth. Capacity is reliant on timetable compliance andoperational use of assembly areas and ticket booths. Outbound traffic

    congestion on Townwall Street is a major issue both for the effect on

    customers of having to wait so close to the port and for the numerous

    ways in which it affects the quality of life of the residents of Dover.

    Because of limited waiting capacity within the Eastern Docks, traffic can

    build up very quickly on Townwall Street. This congestion can be

    triggered by any disruption within the Docks and ferry system or by an

    unusual arrival pattern in the traffic as a result of motorway congestion.

    The other critical issue in the customers perception of Dover is the timebetween the lowering of the ships ramp and the vehicle being on the

    open road outside the town. Any congestion within the Docks or the

    town has a major effect on this.

    To allow an increase in the traffic through the Eastern Docks, the whole

    system must be examined carefully to improve the reliability of the

    process and to make maximum use of the vehicle parking areas within the

    port area. Even with all such measures taken, the capacity will never be

    truly robust. With traffic well below the theoretical capacity of the

    system, disruptions are still likely to cause congestion on Townwall Street.

  • 7/28/2019 Dover Harbour Useful Info

    16/48

    Issue 2 Rev 4 18 November 2005 12

    The only other way to control traffic queuing on Townwall Street is to

    control the flow of traffic leaving the M20. A proposal to build a holding

    area to the west of Dover is discussed later in this document. In the light

    of the Highways Agencys dislike of controlled signage on main routes, a

    holding area used by all freight traffic would seem to be the only option.

    A small change in traffic growth rates can change the date at which

    capacity is reached. For example, changing from the baseline traffic

    projection to the upside projection will bring the theoretical capacity date

    forward by five or six years. It is important for DHB to be aware of the

    issues which will affect the dates and to monitor these parameters. The

    master plan study will leave DHB with a series of tools to model the

    effects of changes as they occur.

    A product of the master plan will be a description of the trigger points to

    initiate the provision of new facilities. These trigger points will be in two

    forms based on a theoretical look ahead and on the levels of service

    actually being achieved. To determine the theoretical trigger points, it will

    be necessary to estimate the time taken to procure each element of the

    development and then calculate the traffic levels at the time when

    procurement has to start. This calculation will have to take into account

    both the traffic level and the rate at which the traffic is increasing.

    It is much more difficult to establish the level of service thresholds as it

    will be necessary to plot a number of key performance indicators such asthe number of times per year that queues develop outside the docks, the

    number of ships which are delayed by more than 10 minutes each year

    and the average time from ramp down to the last vehicle leaving the

    docks. The rate at which these key performance indicators are changing

    can then be used to determine the date on which they will pass the

    threshold of acceptability.

  • 7/28/2019 Dover Harbour Useful Info

    17/48

    Issue 2 Rev 4 18 November 2005 13

    4 The Environment of Dover Harbour

    4.1 IntroductionThroughout history, the development of the town of Dover and the port

    have been very closely related. As the port traffic has built up, the effects

    on the town have increased so that now the interaction between the two

    has become a major issue. In particular the road network to the port is

    prone to congestion, affecting the environment of the town. Options for

    the future are considered in this section.

    4.2 ConstraintsThe constraints preventing the development of new projects within the

    port are illustrated in Figure 4.1 and discussed below.

    4.2.1 Cliff TopographySettlement patterns and port development over the centuries have been

    influenced by the physical topography of the town, with future port

    expansion beyond existing boundaries constrained by the cliffs and the

    built development of the town.

    4.2.2 Public Access, Recreational Facilities and Limited Water DepthPublic access to the sea and beach is confined to the stretch of coastline

    between the Eastern and Western Docks and it is desirable that this isretained as a valuable local asset. This splits the operations of the Port of

    Dover into two separate and distinct areas of the Eastern and Western

    Docks.

    Water sports and recreational boating take place in the waters fronting the

    Marine Parade, again dividing the two distinct areas of port activity.

    To retain the recreational use of the beach and foreshore requires care in

    the design of the limits of dredging. The situation must be avoided where

    a person can be standing on the bottom and then find themselvessuddenly in deep water as this is extremely dangerous. Similarly the

    propeller wash from commercial shipping should not reach the areas

    where people are wading. These constraints may affect the layout of

    future developments.

    4.2.3 Sites of Special Scientific InterestThe coastline from Port of Dover to Kingsdown is of national

    importance due to its geology, geomorphology and varied flora and fauna,

    including many rare species. The cliffs, from Shakespeare Cliff to behind

    the Eastern Docks, are designated as Sites of Special Scientific Interestand include the sheer cliff faces and the wave cut platform at the base of

  • 7/28/2019 Dover Harbour Useful Info

    18/48

    Issue 2 Rev 4 18 November 2005 14

    the cliffs. These sites provide the habitat for rare species and migrating

    birds.

    4.2.4 Recreational FishingAdmiralty Pier is a nationally recognised site for sea anglers with the area

    adjacent to the Western Docks also used by local fishermen.

    4.2.5 Access Road Frontage DevelopmentPort traffic to the Eastern Docks from the M20 uses Townwall Street

    (A20). From the York Street Roundabout to the junction with East Cliff

    the road is developed on both sides with flats, hotels, a leisure centre and

    other town centre related development. This section of the route is within

    an Air Quality Management Area. From East Cliff to the Eastern Docks

    the route is adjacent to the East Cliff and Athol Terrace Conservation

    Area. At times when the rate at which trucks arrive exceeds the capacity

    of the Eastern Docks the traffic queues along the A20, which interferes

    with local traffic and pedestrian movements. The Eastern Docks

    roundabout has capacity constraints which can cause peak period

    congestion. Even when traffic is flowing freely, port traffic combines

    with local traffic to create the general noise, vibration and air quality

    effects of traffic in the town centre.

    The effects of local and port traffic cannot be separated and it is

    important that the Dover traffic issues are considered as a whole. New

    developments in the town will contribute to congestion in just the sameway that port traffic will. It is vital that all organisations in the Dover area

    work together to minimise the problems on the towns roads. This can

    only be achieved by sharing information and setting up an agreed model

    of the traffic flows so that the effects of changes can be reviewed

    dispassionately.

    4.2.6 Listed Buildings and Ancient MonumentsWithin the port itself there are various Listed Buildings, which are

    highlighted below. Any works requiring demolition or negatively

    affecting the setting of these features will require consents. Very oftenthe effects of changes can be mitigated by finding alternative uses for

    buildings or similar.

    (a) Former Dover Marine Rail station

    This is currently in use as a Cruise liner terminal, with one end converted

    into a passenger facility, and a large portion of its remaining internal space

    is used for car parking. The brick walling on the western elevation has

    seen some modern alteration. Any major changes proposed here (e.g.

    creation of new openings) are likely to require a detailed building

    assessment to be carried out to establish the history of alteration to the

  • 7/28/2019 Dover Harbour Useful Info

    19/48

    Issue 2 Rev 4 18 November 2005 15

    structure. This would allow a full consideration of its future conservation

    requirements.

    Connected to the main building is an overhead walkway with its own

    entrance building, which is currently used by the local angling group to

    access the Admiralty Pier for fishing. The presence of this structure

    imposes constraints on manoeuvring and vehicle movements within the

    Western Docks which may impact future port options. Safe pedestrian

    access to Admiralty Pier can be provided in a number of ways and the

    walkway will only be removed if no other viable solutions can be found at

    reasonable cost. Part of the change may include the refurbishment of part

    of the walkway so that its historical context can still be appreciated.

    (b) The Prince of Wales Pier

    The length of the pier imposes a constraint on shipping movements to

    and from Admiralty Pier. The pier is perceived to have group value with

    other pier and lighthouse features and to contribute to the whole

    appearance of the harbour.

    It is very likely that the outer end of the Prince of Wales Pier will form a

    major obstruction to the development of the Western Docks and there

    will be a strong case for its removal. It is possible that part of the pier

    could be reassembled as part of a revised Western Docks layout but this

    would need considerable further study. The layout of Dover Harbour has

    been changed continuously to accommodate changes in circumstances.The modification of the Prince of Wales Pier would be a continuation of

    this pattern.

    (c) Other

    Lord Warden House is currently used to provide offices. The building has

    had substantial expenditure to preserve its basic fabric but it has lost its

    original setting and is not well suited to its present use.

    A crane structure which is an ancient monument has been retained within

    the Wellington Dock area. The use of this area for the marina providesprotection for this structure.

    Just outside the Western Docks, Waterloo Crescent comprises a row of

    Regency town houses within the conservation area on the beach front,

    which includes the DHB offices. These buildings are maintained to a high

    standard and well used.

    A section of the Western Docks falls within an area of defined

    archaeological importance, including the Tidal Harbour and Granville

    Dock. The potential of this area for marine archaeology has beenunderlined by the discovery of features of marine archaeological interest.

  • 7/28/2019 Dover Harbour Useful Info

    20/48

    Issue 2 Rev 4 18 November 2005 16

    Whilst this does not necessarily preclude development, it does increase

    the requirements for site investigations and excavations prior to any

    development being allowed to commence.

    4.3 OpportunitiesThe opportunities to develop new projects within the port, which could

    involve both further expansion of existing uses and the development of

    new facilities, are illustrated in Figure 4.2.

    4.3.1 Space PotentialThe Eastern Docks is the main focus for passenger ferries and is the most

    heavily utilised area of the port. Capacity of the Eastern Docks could be

    improved by relocating a number of buildings within the port boundaries

    to outside the port, and converting single/low-storey buildings to multi-

    storey for further intensification. The space potential created and the

    relevant cost involved would determine the attractiveness.

    Another option is relocation of the coach interchange area outside the

    port, although a major concern is the potential impact on the coach trade.

    4.3.2 Underutilised Port Land and Water AreaThe Western Docks contain large buildings and spaces which are only

    partially used. There is also a large area of underutilised water around the

    Prince of Wales Pier and expansion of port operations here needs to be

    reconciled with the historic interest of this part of the site.

    Future options for large scale port expansion towards Shakespeare Cliff

    have been discussed for some years. In an early part of the study, these

    options were carefully reviewed and ruled out for the foreseeable future.

    The cost of the breakwater system is simply too high to obtain an

    economic return.

    4.3.3 Wellington Dock areaThe Wellington Dock is a relatively small water area surrounded by a

    number of historic buildings and port features. The entrance toWellington Dock is narrow and spanned by a swing bridge which gives

    access to the Hovercraft Terminal area of the Western Docks. The dock

    is too small for modern shipping but it provides the ideal site for

    waterfront development, linking the town and the beach. This link could

    include improved footpaths and cycle ways. It could also be used to

    improve the appearance of the river Dour which discharges into the

    basin.

    The successful De Bradelei Wharf has provided a much used facility

    which is in keeping with the surroundings. Further property developmentis possible without detracting from the area and without losing this

  • 7/28/2019 Dover Harbour Useful Info

    21/48

    Issue 2 Rev 4 18 November 2005 17

    section of the marina. Options under consideration include an extension

    to De Bradelei Wharf and an hotel on the seaward side of the dock.

    4.3.4 Potential to Re-establish the Rail LinkTraditionally the Western Docks was served by a rail link which delivered

    passengers and freight to the quay edge and to the Train Ferry Berth.

    In the absence of a rail ferry service, it is difficult to see what cargo such a

    service would carry and if passengers wish to use a rail link to the

    Continent, they are likely to use the Eurostar service.

  • 7/28/2019 Dover Harbour Useful Info

    22/48

    Issue 2 Rev 4 18 November 2005 18

    5 Development Options

    5.1 ApproachThe overall approach to the initial development options was to show a

    number of possibilities which fulfil individual trade growth requirements

    or some limited combinations of them. This was so that a range of costs

    for development for each trade could be shown. These then assisted in

    prioritisation of trades and development options, taking account of the

    revenue associated with each development option.

    Following the trade prioritisation process, the development options were

    re-assessed from a different viewpoint. Options were refined by varying

    them, combining them and in some cases by phasing the development ina different manner. For each variant the outcome of the study

    undertaken to determine the capacity of the existing port was taken into

    account. This allowed the most feasible solutions to be determined and

    put forward, whilst still taking the individual trade growth requirements of

    the port as well as its capacity into consideration.

    The main conclusion of the trade prioritisation is that the ferry business

    generates considerably more revenue per berth and per unit of area

    occupied than any of the other trades using the Port of Dover. The

    cruise business has received considerable investment and this will allowDover to hold its position in a limited market place. Major investment

    would also be required to maintain or improve the position of the fruit

    trade and this would need strong justification. The aggregates business

    shows a good return on its existing facilities but it would be difficult to

    justify new construction. The Marina has never operated at capacity and

    it struggles to cover its operating costs.

    In this Zoning Report, feasible options contributing towards a preferred

    zoning plan are described. The preferred options are outlined in greater

    detail providing better information as to their economic andenvironmental feasibility and their appropriateness in meeting the capacity

    requirements of the Port.

    5.2 Exclusion of Stage 1 and Stage 2 Development OptionsThe development options from Stage 1 and Stage 2 of the Master Plan

    Study were amended taking account of financial viability and overall

    feasibility while satisfying the trade growth requirements of the port. An

    explanation as to the reasons for the exclusion of some of the

    development options raised at Stage 1 and 2 of the study, are given below.

  • 7/28/2019 Dover Harbour Useful Info

    23/48

    Issue 2 Rev 4 18 November 2005 19

    5.2.1 Eastern DocksThe existing berth capacity of the Eastern Docks is sufficient to cope with

    an increase in marine traffic based on a developed timetable for 2034.

    The overall capacity of the Eastern Docks is determined by the ability to

    get ships to the berths and the road traffic in and out of the port. Neither

    of these problems can be solved without dramatic changes to the port and

    the town. It would not be possible to keep the port operating at capacity

    during such changes. Development options including additional berths in

    the Eastern Docks have therefore been excluded.

    5.2.2 Western DocksSeveral of the possible schemes for the Western Docks provide very large

    capacity increases at a single stroke but they also carry very large costs and

    they will not be commercially viable.

    Developments resulting in the displacement of the aggregates facility in

    favour of cruise or other cargo berths appear not to be financially viable.

    This is mainly due to there being no added benefit from removing an

    income generating trade to make way for other options that are not as

    financially rewarding.

    Alterations to the port entrance either by extending the Admiralty Pier or

    removing the existing entrances and creating a single entrance are not

    financially feasible. The only benefit is the reduction in wave exposure

    for Western Docks development options, which when valued against thecosts involved cannot be financially justified. Further, a single port

    entrance may increase downtime in parts of the Eastern Docks which is

    unacceptable due to the effects this will have on the ferry trade,

    specifically in terms of congestion and delays. These options have

    therefore been discounted.

    5.2.3 Outside the PortAs already discussed, the costs to develop berths outside the existing port

    are very high and could never show a reasonable financial return at

    present tariff rates. Some time in the future, such a development may bepossible but certainly not until the capacity of the existing port has been

    maximised.

    5.3 Choice of Zoning Report Development OptionsThe various factors contributing towards the choice of development

    options are outlined below. Only options that comply with these

    requirements have been considered further.

    5.3.1 Ferry DevelopmentThe ferry trade remains by far the most important trade to the port and itis important to cater for its future growth. The baseline demand forecast

  • 7/28/2019 Dover Harbour Useful Info

    24/48

    Issue 2 Rev 4 18 November 2005 20

    calls for three new ferry berths in the Western Docks with a fourth berth

    if traffic growth follows the high end scenario. If traffic grows in line

    with the low end scenario, the requirement for new berths within the

    study period will reduce. All the forecasts show the need for a number of

    new ferry berths in the Western Docks, the only difference between the

    scenarios being timing.

    Based on the above, it is important to make space provision for new

    facilities while carefully monitoring traffic growth to determine the

    phasing and timing of developments.

    An added consideration in the expansion of the ferry trade is that it

    creates far greater employment and secondary benefits than any of the

    other trade options. It is clear that the choice of such a development is

    far superior economically to the other options.

    In theory it would be possible to gain landside capacity in the Eastern

    Docks by making more dramatic changes to the internal road layout but

    the costs would be considerable and relatively soon after the predicted

    saturation date, the Eastern Docks runs out of marine capacity. Such

    internal improvements would only exacerbate the congestion problems on

    Townwall Street. The service provided by a port which is very close to

    the limit on both landside and marine operations is going to be unreliable

    and bad for the long term future of the port.

    5.3.2 Cargo DevelopmentThe costs of providing completely new facilities for the fruit trade would

    be substantial. These could only be justified by obtaining suitable

    guarantees and long-term contractual commitments.

    5.3.3 Cruise Terminal DevelopmentThe traffic projections show the number of cruise liner calls increasing to

    200-250 at the end of the study period. Each cruise call occupies the

    berth for a day so how many calls can be accommodated at each berth

    depends on the length of the season and the exact pattern of calls withinthe season. It is possible to provide a longer berth to meet the growing

    market for ships of over 300m or a third cruise berth for the smaller

    cruise liners by removing the spur pier which forms the Jetfoil Basin. Any

    other location for an extra cruise berth is likely to restrict ferry operations

    and DHB will have to decide which trade will take precedence.

    5.4 Zoning Report Development Options5.4.1 General

    The chosen options for development are shown in the sketches in

    Appendix Aand discussed in more detail below. Appendix B

  • 7/28/2019 Dover Harbour Useful Info

    25/48

    Issue 2 Rev 4 18 November 2005 21

    summarises the options descriptions, advantages, disadvantages and any

    relevant comments.

    5.4.2 Option I : Do MinimumThis option is based on carrying out minimal improvements, at relatively

    low cost and minimising disruption to existing services. In the short

    term, these measures can improve the quality of service offered but

    pressure of traffic will steadily erode this gain. In the longer term,

    congestion and delays will increase, if this option is used in isolation,

    progressively reducing the quality of service offered by Dover.

    Elements which could be included are as follows:

    Revised A20 dock exit and dock exit roundabout improvements

    (initial studies in progress)

    Lane width and weighbridge improvements inside the Eastern

    Docks

    Revised ferry fleet (increasing carrying capacity)

    Extend ticketing area

    Green transport measures to reduce car parking spaces and

    reduce staff car traffic impacts

    Consider reduction in the unaccompanied trailer park size and

    relocation to reclamation in the East Catamaran Berth area,

    between Berths 6 and 7

    Consider relocating coach interchange area out of port, with area

    being used for either marshalling/assembly area, increasing

    queuing area in front of ticketing or for Dover Cargo Terminal

    Upgrade Berth 5 to accommodate wider beam vessels (ongoingupgrading of vessels in future will increase berthing difficulty at

    this berth otherwise)

    These measures are fairly self explanatory. Each produces a small

    incremental increase in capacity or an increase in reliability at fixed

    throughput. None of them however addresses the specific issue of traffic

    congestion on Townwall Street. The following concepts do have a direct

    impact on Townwall Street and therefore demand closer inspection.

  • 7/28/2019 Dover Harbour Useful Info

    26/48

    Issue 2 Rev 4 18 November 2005 22

    Compactor Corner Improvements

    Compactor Corner is the point at which the traffic going to the

    berths in the Eastern Docks turns seaward at the base of the

    cliffs, heading towards Berth 1. A key constraint on the landside

    capacity of the Eastern Docks arises due to the fact that upstream

    of Compactor Corner, the approach route consists of only 3

    lanes. If there is a queue caused by one operator being unable to

    process traffic through the check-ins, traffic builds back to

    Compactor Corner where it then blocks vehicles intending to use

    other operators from reaching the check-ins. Once this happens,

    the rest of the Eastern Docks road system rapidly chokes, causing

    a tail back onto Townwall Street. A review of alternative highway

    layouts through Compactor Corner has been undertaken in order

    to assess the scope for providing additional operator specific

    storage capacity. This will delay the point at which one

    operators traffic disrupts the entire operation.

    Four preliminary options have been considered. Three of the

    options are based on an alignment north of Easter Camber

    Office building and the fourth on an alignment south of the

    building. Some options involve significant demolition and

    relocation of buildings and the replacement of weighbridges.

    Additional capacity of up to 60 lorry spaces can be provided and

    would lead to a reduction in the incidence of outbound traffic

    queuing outside the Eastern Docks.

    At best, this work at Compactor Corner simply delays the

    moment at which queues spread outside the port and there could

    be substantial expense and disruption involved. It is a useful idea

    but in itself it has only a small effect.

    Buffer Zone Concept

    This concept is based on the very simple idea that it is possible to

    monitor and predict the rate at which the ferries can load vehicles

    from the Eastern Docks. It is also possible to monitor the rate atwhich vehicles are arriving at the south edge of Dover heading

    for the Eastern Docks. If the rate of arrivals exceeds the rate of

    ferry loading, the result can only be stationary traffic on

    Townwall Street. The factors determining the uplift rate by the

    ferries are not easily controlled in the short term but it is possible

    to take off the peaks in the traffic arriving into Dover by holding

    some vehicles until the peak has passed. This would allow

    Townwall Street to run more consistently, reducing the tendency

    to congestion.

  • 7/28/2019 Dover Harbour Useful Info

    27/48

    Issue 2 Rev 4 18 November 2005 23

    The analysis of landside capacity in the Eastern Docks has

    demonstrated that the key constraint on capacity, assuming that

    inbound capacity problems are largely dealt with by the

    construction of the Dock Exit Scheme, is the amount of space

    available to accommodate outbound traffic waiting to embark on

    a ferry. The need for substantial storage largely applies to non-

    pre-booked freight traffic although the same thinking can be

    applied to all traffic. Given the space constraints within the

    Eastern Docks, consideration has been given to the possibility of

    creating a secondary queuing area outside the Eastern Docks so

    as to reduce the need for pre-embarkation storage within the

    Eastern Docks.

    A number of options for the location of such a secondary

    queuing area have been considered, with one option having

    considerable advantages in terms of potential size and ease of

    access.

    As an alternative, DHB is having preliminary discussions with

    landowners in relation to an off-road site accessed from the

    A20 west of Aycliffe Roundabout to locate a buffer zone. The

    advantages of a buffer zone in this location compared to one

    on the Granville Dock site are twofold. Firstly, the area of land

    available is potentially larger and secondly access to the site

    would not be via the existing busy roundabout junctions withinDover.

    A site west of Aycliffe roundabout would be suitably located

    for M20 port-bound traffic. This is the Highways Agency

    strategic route for traffic to Dover. If the Highways Agency

    were to change the strategic route to use the A2, the preferred

    site would be to the north of that road. With a single buffer

    zone, the traffic using the other route would have to be co-

    ordinated with the main flow of traffic. This is done by the

    port police under the present system and seems to work well.The best solution would be waiting areas on both the

    approaches, co-ordinated from a central control in the port.

    Whichever option is chosen, consideration has to be given to the

    way a secondary queuing area would operate in practice. The key

    issues to be considered include:

    The need for the route from the buffer zone site to the

    Eastern Docks to be free from congestion and for the

    operators to have good IT links, including links to trafficinformation, to be able to manage the facility efficiently

  • 7/28/2019 Dover Harbour Useful Info

    28/48

    Issue 2 Rev 4 18 November 2005 24

    Whether checking-in will take place in the buffer zone site

    Whether the buffer zone would be used all the time or just in

    peak hours

    The type of traffic that will use the facility. Initially it is

    assumed that non-pre-booked freight traffic will be the main

    user although it could handle cars as well

    How traffic approaching on the M2 corridor will be co-

    ordinated with the main flow along the M20

    Who will operate the buffer zone and whether one or all

    ferry operators will use it

    The size of the freight buffer zone

    Traffic implications at the turn into and out of the zone.

    Port Expressway Concept

    A review of the Highway Agencys Port Expressway concept has

    been undertaken. The concept is to segregate Port traffic and local

    traffic on the A20 between Aycliffe Roundabout and the Eastern

    Docks entrance by converting the eastbound carriageway to two-

    way for local traffic only, and converting the westboundcarriageway to two-way port traffic only.

    While this idea seems at first sight to separate the two flows well, it

    suffers from the inherent fault that two way roads are much more

    prone to disruption than dual carriageways. It will also lead to

    some complex junctions.

    The conclusion is that the concept provides an alternative approach

    but it does not solve the basic problem of more traffic arriving in

    the port than the facility can handle.

    A number of alternative layouts have been considered during Phase

    2 Stage 2 of the study, including a modified Aycliffe Roundabout,

    traffic signals and a flyover arrangement. Further work is required

    before any firm conclusions on feasibility or capacity can be

    reached.

    Recommended Elements

    The recommended elements of Option I are as follows:

    Revised A20 dock exit and dock exit roundabout improvements

  • 7/28/2019 Dover Harbour Useful Info

    29/48

    Issue 2 Rev 4 18 November 2005 25

    Compactor Corner improvements

    Lane width and weighbridge improvements as outlined in Phase 1

    Green transport measures to reduce car parking spaces and

    reduce staff car traffic impacts

    The establishment of a buffer zone.

    5.4.3 Option F : Convert Hoverport High Speed to Conventional FerryThis scenario creates one new double deck conventional ferry berth for

    minimal cost in the Western Docks, at the expense of the fast ferry berth.

    The fast ferry operations out of Dover have never really thrived in the

    same way as the conventional ferries and they would seem to be under

    increasing threat from fly-drive services provided by the low cost airlines.

    The throughput of the existing high speed ferry service out of the

    Hoverport does not really justify the space that it occupies and there is

    the option to move it to Berth 1 in the Eastern Docks.

    The option of building a single conventional berth in the Western Docks

    is not particularly attractive as all of the existing operators require more

    than one berth and would almost certainly not be willing to split their

    operation.

    Any Western Docks development will require some investment in

    facilities for the regulatory authorities to handle freight vehicles and this

    will be more attractive if used to service several berths.

    The land area available on the Hoverport is adequate for conventional

    ferry operations. The local highway network including the Prince of Wales

    roundabout and the swing bridge are adequate to accommodate the

    higher ferry discharges and loads although a greater number of freight

    vehicles making a right turn at the roundabout carries a safety risk. The

    right turn traffic could also create a major problem if the swing bridgewere to open, closing the road to traffic, when there is already stationary

    traffic on the inside lane of Townwall Street. This has the potential to

    gridlock the road system until the bridge re-opens to road traffic. If the

    swing bridge were to open just at the point where the traffic from a large

    ferry was exiting the Hoverport area this would lead to congestion within

    the terminal and frustration for the drivers. The conclusion has to be that

    it is not practical to operate large conventional ferries into the Hoverport

    area while the swing bridge is still in operation.

    This variation can form part of an overall development strategy for theWestern Docks but it has problems as a stand-alone development.

  • 7/28/2019 Dover Harbour Useful Info

    30/48

    Issue 2 Rev 4 18 November 2005 26

    The sketch showing the joint development of Options F and G2 (Phase

    1) relative to the entire Port is shown in Figure 5.1.

    5.4.4 Option G2 : Add One Ferry Berth (Saw-tooth) - HoverportThis option involves reclamation on the northern side of the Prince of

    Wales Pier, creating one ferry berth in saw-tooth configuration in the

    Western Docks. One new double deck conventional ferry berth is

    created. This is at the expense of the fast ferry berth as its vehicle storage

    area is needed. The aggregates facility is retained but the freight clearance

    facility is reduced. This option is medium term and does not convert

    easily to a long term solution for an increasing ferry trade. However, a

    change in formation of the reclaimed area to the north of the Prince of

    Wales Pier would allow for long-term development.

    Exposure to excessive wave action is a possibility for the new berth being

    near the Western Entrance. This will need detailed investigation using the

    existing wave models of Dover. This modelling is reasonably expensive

    and the schemes need to be refined before the modelling is done.

    The new berth would affect the views from the beach area. The physical

    impact on the beach area must be confirmed and mitigated, where

    necessary. It would restrict the use of the water area off the beach and the

    associated impact of dredging for ferry access also needs to be checked.

    Increased land space would be required towards Lord Warden House aswell as towards the Town Yard area. For two berths, road access via

    Prince of Wales or Limekiln roundabout or a combination is acceptable.

    This option has the advantage of keeping the majority of the existing

    Prince of Wales Pier in place subject to a structural load analysis, but cuts

    off public access.

    Access via Limekiln roundabout may allow a longer internal road system,

    to provide queuing lengths in front of control agencies and ticketing, as

    well as assembly areas. To ensure separation from the non-port roads, aseparate swing bridge would be required across the entrance to

    Wellington Dock. There would be a loss of car parking (Union Street), the

    marina yard near Prince of Wales roundabout and a reduction in the

    Freight Clearance Facility area. Access to the RNLI/tugs/marina berths

    has to be maintained and may be constrained. Use of the marina would

    be affected, with a need for replacement parking further away, restricted

    or impeded access, no marine yard and possibly surrounded by a freight

    buffer zone.

    On a positive note however, the Dover Pride Project is considering apotential marina development at the eastern end of the beach. If it

  • 7/28/2019 Dover Harbour Useful Info

    31/48

    Issue 2 Rev 4 18 November 2005 27

    happens, this replacement marina would decrease the impact and effect

    the ferry trade development has on marina use within Granville Dock and

    the Tidal Harbour.

    Again Figure 5.1 shows the development of Options F and G2 (Phase 1)

    relative to the entire Port.

    5.4.5 Option G4 : Add Two Ferry Berths (Jetty) - HoverportAs with Option G2, this option also involves reclamation on the northern

    side of the Prince of Wales Pier creating one ferry berth in saw-tooth

    configuration. However, in addition to this, this option also involves

    creating two ferry berths in jetty configuration in the Western Docks.

    The two ferry berths would be on the northern side of the Prince of

    Wales Pier (that is, on the reclamation-side south of the single berth in

    saw-tooth configuration). One new double deck conventional ferry berth

    for minimal costs is created. This is at the expense of the fast ferry berth.

    This option caters for long-term development.

    As for Option G2, increased on-land space would be required towards

    Lord Warden House and the Town Yard area. However, on-land space in

    this area is limited so for this 4-berth option additional land is required

    and is provided by reclaiming the existing marina outer basins (Granville

    Dock and Tidal Harbour), with a replacement marina proposed on the

    northern side of the Prince of Wales Pier. In terms of capacity, the new

    marina caters for the 200 to 250 berths lost so together with theWellington Dock marina provides the 400 to 450 berths currently

    available at the Western Docks. Access to the Wellington Dock basin is

    achieved through the new marina as entrance via the marina outer basins

    will not be possible.

    Filling in the basins is not a particularly attractive option and an alternate

    is possible by reclaiming off Shakespeare Beach to provide the additional

    space required for the fourth berth. This land space would however be a

    long way from the berths, causing operational difficulties.

    Exposure to excessive wave action is a possibility for the two berths in

    jetty configuration and the one berth in saw-tooth configuration, as with

    Option G2 and will need to be investigated. Wave exposure at the marina

    entrance will also need to be investigated.

    The associated landside issues linked to this development are similar to

    those in Option G2, including the minor works required to the Prince of

    Wales Pier.

    The sketch showing the development of Option G4 (Phase 2) relative tothe entire Port is shown in Figure 5.2.

  • 7/28/2019 Dover Harbour Useful Info

    32/48

    Issue 2 Rev 4 18 November 2005 28

    5.5 Phasing of Zoning Report Development Options5.5.1 Ferry Development

    The ferry development options outlined in Section 5.3 include the

    introduction of the conventional ferry trade at the Western Docks to cater

    for any traffic overflow from the Eastern Docks, based on the Ports

    forecast traffic.

    The capacity study of the Eastern Docks indicates that the limit in terms

    of meeting the forecast traffic, based on the landside capacity results, is

    likely to be reached within the next few years. Therefore the Western

    Docks is required to accommodate the remaining forecast traffic overflow

    from the Eastern Docks thereafter.

    In terms of meeting the traffic overflow from the Eastern Docks, it is not

    necessary for all berths in the Western Docks to be provided at once

    when the capacity at the Eastern Docks is reached. The provision of the

    berths could occur in three phases as and when the forecast overflow

    traffic increases to levels the current berths are unable to accommodate.

    Therefore the development options outlined in the sections above can

    effectively be considered different phases of a single expansion

    development to be embarked on over the next 30 years, in line with the

    ports master plan.

    For this phased implementation, Phase 1 would include the provision of a

    single berth by converting the existing Hoverport fast ferry berth to aconventional double deck ferry berth (as for Option F in Section 5.4.3).

    A second berth (similar to Option G2 in Section 5.4.4) would also be

    provided. This involves reclamation on the northern side of the Prince of

    Wales Pier creating one ferry berth in saw-tooth configuration in the

    Western Docks. Following on from this Phase 2 involves the provision

    of two ferry berths in jetty configuration created on the reclamation on

    the northern side of the Prince of Wales Pier. This development is similar

    to Option G4 (see Section 5.4.5).

    The sketches showing potential phasing of conventional ferry berths inthe Western Docks are shown inAppendix C.

    5.5.2 Roundabout AssessmentThe traffic performance of Limekiln and Prince of Wales Roundabouts

    has been assessed for 2020 and 2034 in relation to the proposed

    development of two berths at Western Docks. A number of access

    options using Limekiln and Prince of Wales roundabouts were considered

    and the capacities of the roundabouts were checked for each of these

    scenarios.

  • 7/28/2019 Dover Harbour Useful Info

    33/48

    Issue 2 Rev 4 18 November 2005 29

    The results show, in theory, the Limekiln roundabout operates

    satisfactorily in all scenarios in 2020 and is marginally over desirable

    design parameters in 2034 in the AM peak on one approach for one of

    the access options.

    Similarly the modelling shows that Prince of Wales roundabout will be

    operating below its design parameters in 2014 and after the development

    of berths in the Western Docks in both AM and PM peaks. However,

    capacity will be exceeded in 2034 in both AM and PM peaks in all three

    access options. This means that the roundabout junction will need to be

    amended or improved before 2034 with the two berth Western Docks

    development scenario.

    This modelling is based on the through traffic being free flowing and of

    course this does not happen at present with regular queuing on the inside

    lane of the roundabout. Improvements will be required much earlier at

    both roundabouts if their eastbound approaches continue to be blocked

    by traffic queuing back from Eastern Docks.

    The introduction of the buffer area will greatly increase the practical

    capacity of the roundabouts by reducing or eliminating the queuing

    traffic.

  • 7/28/2019 Dover Harbour Useful Info

    34/48

    Issue 2 Rev 4 18 November 2005 30

    6 Planning Structure

    6.1 IntroductionThe criteria developed for the assessment of planning issues for the

    options are based on trying to ensure that the needs of relevant policy

    principles are met. The principal focus is on the need to protect the

    environment and heritage aspects of the site and its environs and to

    ensure that future development helps to diversify and support the wider

    economy of the town as a whole.

    6.1.1 Strategic Planning ContextThe Planning and Compulsory Purchase Act, 2004 has fundamentally changed

    the structure of plan making in the UK. Regional Spatial Strategies willreplace Structure Plans and Local Development Documents will replace

    Local Plans.

    The Kent and Medway Structure Plan (Deposit Plan September 2003) provides

    the current strategic planning context for the Kent and Medway area.

    Policy TP20 of the Structure Plandefines Dover as a Core Port, with

    those in Sheerness, Thamesport and Ramsgate. This definition indicates

    the safeguarding of the port function, and support for further

    development, provided it meets with transport, access, design and

    sustainability requirements.

    The Structure Planhighlights Dovers ability to expand its current

    operations within existing port boundaries, and particularly within the

    Western section of the port. It also promotes the reintroduction of rail

    services to the port, the upgrading of the A2 to dual carriageway, and

    improved traffic management on the A20, in order to facilitate increased

    activity.

    The Structure Planwill ultimately be replaced by the Regional Spatial Strategy

    and a consultation draft of the South East Planhas recently been publishedfor public consultation. Policies T7 and T8 support maintenance and

    encouragement of further ro-ro services, niche market and short sea

    services at Dover. The supporting text for these policies refers to Dover

    in the following terms:

    The primary focus for ro-ro services will continue to be across the

    Dover Straits, using either cross-Channel ferry services operating via the

    Port of Dover or shuttle services operating through the Channel Tunnel.

    Restoration of a rail connection into the Port of Dover, together with

    improvements to road access along the A2 corridor should be givenpriority in the medium term. In the longer term consideration will need to

  • 7/28/2019 Dover Harbour Useful Info

    35/48

    Issue 2 Rev 4 18 November 2005 31

    be given to the capacity of the road and rail corridors serving both the

    Port of Dover and the Channel Tunnel and to the need for a Thames

    Crossing east of Dartford.

    6.1.2 Local Planning ContextThe provisions of the Dover Local Planin respect of new developments at

    the port are now several years out of date and have been overtaken by

    recent developments at the port and by work on the Dover Pride Vision.

    The Dover Local Development Framework is currently under preparation and a

    consultation document on Issues and Options is expected shortly. The

    provisions of the Local Planin respect of heritage and conservation issues

    are not expected to change significantly, as these reflect national planning

    policy.

    The Dover Pride Strategy and Action Plansets an ambitious framework for

    regeneration of the town. The Strategy asserts that the local economy is

    dominated by the port, which accounts for about 25% of employment in

    the town, although there are few high value local jobs and its drive

    through operations limit the benefits which are realised within the local

    economy (staying visitors on average spend 400 as opposed to the 26

    spent by day visitors). It recognises that the port is sensitive to changes in

    Channel Tunnel operations and the European economy but its long term

    growth prospects are positive.

    One of the strategic objectives of the study relates to realisation of thepotential of port expansion and it is recognised that this could create a

    variety of new opportunities for the town. It asserts that Dover could

    become a true gateway port for the South East region within the East

    Kent Pas de Calais sub-region. Possibilities include the development of

    port related activities (such as marine and road transport instrumentation

    and ship docking systems), import-export processing activities to add

    value to freight which currently passes through the port (such as food

    processing and packaging) and logistics activities (including groupage,

    freight forwarding and transport fleet management). The Strategy asserts

    that some of these activities could be located within the port itself (mainlywithin the Western Docks) but other activities would need to be located

    in the Port Zone and the White Cliffs Business Park at Whitfield (100

    acres of which remain undeveloped).

    The Strategy also raises the possibility of the creation of a new waterfront

    destination at the eastern end of the waterfront, which would create an

    opportunity to relocate the marina from the Western Docks. It is unclear

    what implications, if any, this would have for the operation of the Eastern

    Docks and it is acknowledged that the idea needs further investigation

    and testing.

  • 7/28/2019 Dover Harbour Useful Info

    36/48

    Issue 2 Rev 4 18 November 2005 32

    The Strategy also suggests that the problems of heavy through traffic

    along the A20 Townwall Street between the town centre and the seafront

    could be addressed in part by a strategic routing of port traffic; along the

    M20 to the Western Docks and the A2/M2 to the Eastern Docks,

    together with sophisticated traffic light control to pulse traffic along the

    A20 to the Eastern Docks between pedestrian and local traffic

    movements. This may well have implications for passing trade from

    which Dover currently benefits and needs investigation.

    6.1.3 EnvironmentEnvironmental changes to air and water quality and sediment movement

    are an inevitable part of intensification of port uses. These are discussed

    in Section 6.2 below together with any mitigation measures that should

    be undertaken to relieve environmental impacts. In the assessment

    criteria described in Section 6.2 below, environmental issues are

    subsumed as necessary within the criteria dealing with port boundary,

    reclamation, traffic and policy criteria.

    6.2 Assessment CriteriaBelow is a brief description of the different criteria adopted in the

    assessment criteria table. The options are evaluated qualitatively using a

    five point scale as follows:

    Significantly Negative

    Negative

    Neutral

    Positive

    Significantly Positive

    Table 6.1 includes a number of comments that are specific to the

    development options.

    6.2.1 Port BoundaryThe Structure Plan focuses on the need to confine new development

    within the existing port boundary. This is particularly related to the effects

    on environmentally sensitive areas to the east and west of the site.

    6.2.2 Reclamation, Dredging, and Marine Flora and FaunaThe ferry development includes significant land reclamation within the

    port boundary and will change the view to seaward from the beach area.

    Archaeological interests may also be affected but given sufficient leadtime and funding, the archaeology of the area can be fully explored.

  • 7/28/2019 Dover Harbour Useful Info

    37/48

    Issue 2 Rev 4 18 November 2005 33

    The dredging and reclamation will cause a short term increase in turbidity

    and this should be carried out at a time of year when the impact on

    bottom dwelling fish will be minimised. In all consideration of the marine

    environment of Dover Harbour, it should be remembered that the whole

    environment is artificial and it cannot be viewed in the same light as

    undisturbed natural habitats.

    The base of the Prince of Wales Pier is a good habitat for lobsters, hermit

    crabs, edible crabs, prawns and whelks. Reclamation along this pier will

    have a significant detrimental affect on these populations but this can be

    compensated by recreating the same environment elsewhere in the

    harbour.

    6.2.3 Hydrodynamic RegimeAlterations to the current berth configuration at Western Docks will have

    some effect on the hydrodynamics of the port. Modelling will have to be

    undertaken to ensure that there are no unexpected effects.

    6.2.4 HeritageThere are a number of listed buildings/structures and ancient monuments

    within the port boundary. The way in which each structure is affected by

    the development must be reviewed and agreement reached on what

    actions are needed.

    6.2.5 PolicyThere are a number of current policy documents which are relevant in

    relation to the port. These are described in the previous introductory

    section. Positive responses to these criteria are recorded by retaining

    development within the existing port boundaries such as Phase 1 of the

    ferry development, and increasing the provision of port specific

    businesses, such as facilities for cruise services.

    6.2.6 PublicThere are currently a number of public access points and amenities withinthe Port. Options are assessed on their impact on facilities such as the

    water sports centres and the marina, and on access such as the public

    promenade and beach, and the fishing area provided on Admiralty Pier.

    6.2.7 TrafficPort traffic can have impacts both within and outside the port boundary.

    Options are assessed from a strategic standpoint, looking at overall impact

    on both internal features (requiring access across the swing bridge) and on

    the transport network outside the Docks. This is particularly important

    for the junctions along the A20, (which runs parallel to the portboundary) where there are already significant levels of traffic.

  • 7/28/2019 Dover Harbour Useful Info

    38/48

    Issue 2 Rev 4 18 November 2005 34

    6.2.8 Pollution(a) Noise Pollution

    During the phased construction of the development, construction

    vehicles may generate increased levels of noise. The general operation of

    the berths will only slightly increase the noise levels over and above those

    already existing in the Western Docks.

    (b) Air Quality

    Air quality monitoring currently takes place within the Port of Dover to

    ensure compliance with Health and Safety Legislation and codes of

    practice. If levels are dramatically increased due to the development then

    the Western Docks could become an Air Quality Management Area

    (AQMA). The two major sources of poor air quality are emissions from

    the ships engines and generators and emissions from stationary vehicles.

    The former is being addressed by the ferry operators introducing scrubber

    systems on the vessels. The best way to address vehicle emissions is to

    keep the traffic moving. Introducing the buffer zone is the best

    approach to preventing port traffic queuing on Townwall Street.

    (c) Water Quality

    With the development in the Western Docks the probability of water

    pollution incidents within the Western Docks water area would be

    increased marginally. The water quality of the Wellington Dock will have

    to be carefully monitored. There are a range of remedial techniques

    available if problems are detected.

    (d) Light Pollution

    Levels of light pollution may increase following the completion of the

    development although the replacement of older style light fittings with

    modern low spill types will compensate.

  • 7/28/2019 Dover Harbour Useful Info

    39/48

    Issue 2 Rev 4 18 November 2005

    Option

    Port

    Boundary

    Reclamation

    Dredging,

    Marine

    Flora

    andFauna

    Heritage

    Polic

    y

    Public

    Traffic

    Nois

    ePollution

    AirQ

    uality

    Wate

    rQuality

    UseofGreenland

    Comments

    F 0 0 - ++ + 0 - - 0 0 0 This option does not impactreclamation or development removing the fast ferry optioprovision it does not contribthe port.

    G2 0 - - - + - - - - - - This option involving land rehave a significant impact on the beach front, although thireclamation. However, there Wales Pier.

    G4 0 - - - + - - - - - - This option involving land rehave a significant impact on the beach front, this could hawater sports facilities on the significant impact on the listeGranville Dock and the Tidaissues.

    I 0 0 0 0 + + 0 0 0 0 0 -

    Assessment Key:

    -- Significantly Negative- Negative0 Neutral+ Positive

    ++ Significantly Positive

    Table 6.1: Assessment Criteria without Mitigation Measures

  • 7/28/2019 Dover Harbour Useful Info

    40/48

    Issue 2 Rev 4 18 November 2005 36

    6.3 Outline Economic ImpactThis outline economic impact of the various development options for the

    Port of Dover is based upon a classification of five primary sources of

    benefit/cost. These are briefly outlined below.

    Construction Phase these effects relate to the benefits and

    costs associated with the construction phase of the project and as

    such are likely to be transitory;

    Direct employment and GDP arising directly from port

    operations and dependant activities (includes shipping

    agents/brokers);

    Indirect employment and GDP arising from suppliers to and

    activities arising from port activities but not directly dependant

    upon port activities;

    Induced employment and GDP resulting from direct and

    indirect spending and also economic activity generated by port

    visitors;

    Wider Economic Effects ports effect on social, economic

    and physical conditions (related to attractiveness to non-port

    businesses, regeneration, tourism etc).

    Table 6.2 illustrates the impacts associated with each development option

    described in Section 5. Port development generally will have positive

    direct and indirect economic benefits, induce higher port employment and

    local spend and add to the ports ability to attract clustered economic

    activity.

    In general, the cargo related option boosts economic benefits arising from

    cargo and aids the retention of the business. The ferry development

    options allow increases in ferry related economic benefits but may impact

    on leisure and tourism near the Port.

  • 7/28/2019 Dover Harbour Useful Info

    41/48

    Issue 2 Rev 4 18 November 2005

    F G2 G4 I

    Construction Phase Minor benefits Some benefits Few benefits

    DirectFerry benefits

    Fast ferry lossMore than F More than G2 Minor ferry ben

    Indirect Small rise More than F More than G2 Minimal rise

    Induced Will rise More than F More than G2 Will rise

    Wider Economic

    EffectsWill add marginally More than F More than G2 Limited

    Table 6.2: Economic Impact of Development Options

  • 7/28/2019 Dover Harbour Useful Info

    42/48

    Issue 2 Rev 4 18 November 2005 38

    6.4 Planning FindingsIn general terms the planning policy context is supportive of further port

    growth, provided impacts on the environment and the wider Dover area

    are beneficial. However, there are some important heritage/conservation

    issues which apply at the local level, and because of these those options

    which imply a smaller scale of growth appear more positive in terms of

    the planning assessment. However, whilst it is relatively straightforward to

    identify local constraints to development, it is much harder to predict

    wider economic benefits. This may require some difficult choices, given

    the range of environmental and heritage issues which apply and the need

    for the port to grow and adapt to changing commercial requirements.

    Whilst the options may appear to have negative implications, the detailed

    design of these options will have a significant effect on the overall

    evaluation. For example, issues of public access and loss of amenity can

    be solved through working solutions into the options. Likewise heritage

    issues, whilst serious, are not an absolute constraint to future

    development, but they do require that there is a clear operational need for

    development, and that least damaging options have been thoroughly

    evaluated and ruled out for genuine reasons. The value of heritage

    buildings is important and whilst they should wherever possible be

    preserved, it is important to understand that a building is better retained

    in a slightly changed format, whilst providing a viable modern function,

    than saved purely as an inconvenient museum piece.

    The planning assessment clearly indicates that encroachment into areas

    outside the current port boundary would be undesirable, particularly in

    terms of environmental protection of the important habitats to both the

    east and west of the port, and this issue is clearly identified by the relevant

    local authorities as likely to be unacceptable.

    In conclusion the options provide a range of opportunities, some of

    which raise significant planning issues. However, the options do offer

    ways of combining the business needs of the port with the wider needs of

    the communities as a whole. In the longer term, if the port continues toexpand and large areas of new reclamation are required, the conflict with

    planning policies is likely to become more pronounced.

  • 7/28/2019 Dover Harbour Useful Info

    43/48

    Issue 2 Rev 4 18 November 2005 39

    7 Conclusions

    The conclusions set out below are a summary and the reader should look

    at the text of the report for details of each issue: -

    1. The present operation of Dover Harbour