dover harbour useful info
TRANSCRIPT
-
7/28/2019 Dover Harbour Useful Info
1/48
Halcrow Group LimitedBurderop Park Swindon Wiltshire SN4 0QD
Tel +44 (0)1793 812479 Fax +44 (0)1793 812089
www.halcrow.com
Halcrow Group Limited has prepared this report in accordance with
the instructions of their client, Dover Harbour Board, for their soleand specific use. Any other persons who use any information
contained herein do so at their own risk.
Halcrow Group Limited 2009
Dover Harbour Board
Port of Dover 30 Year Master Plan
Zoning Report
July 2005
Halcrow
-
7/28/2019 Dover Harbour Useful Info
2/48
Dover Harbour Board
Port of Dover 30 Year Master Plan
Zoning Report
July 2005
Contents Amendment RecordThis report has been issued and amended as follows:
Issue Revision Description Date Signed
1 0 Draft 11.05.05 MBM
1 1 DHB comments - Revised 17.06.05 MBM
2 0 Redraft 29.06.05 RJC
2 1 DHB comments 04.07.05 RJC
2
2
DHB comments 2
08.07.05
RJC
2 3 DHB comments 3 29.07.05 RJC
2 4 DHB comments 4 18.11.05 RJC
-
7/28/2019 Dover Harbour Useful Info
3/48
Issue 2 Rev 4 18 November 2005
Contents
1 Introduction 1
1.1 General 1
1.2 The Issues 2
1.3 Objectives 2
2 Trade Forecasts 4
2.1 General 42.2 Freight Traffic 4
2.3 Car Traffic 5
2.4 Coaches 5
2.5 Fresh Produce (Fruit) 5
2.6 Aggregates 5
2.7 Cruise Liners 5
2.8 Trade Summary 6
2.9 Traffic Growth Beyond 2034 6
3 Eastern Docks Capacity Studies 73.1 General 7
3.2 The Need for a Robust System 8
3.3 Harbour and Marine Capacity 8
3.4 Berth Capacity 9
3.5 Internal and External Access Capacity of Eastern Docks 10
3.6 Overall Capacity Conclusions 11
4 The Environment of Dover Harbour 13
4.1 Introduction 13
4.2 Constraints 134.3 Opportunities 16
5 Development Options 18
5.1 Approach 18
5.2 Exclusion of Stage 1 and Stage 2 Development Options 18
5.3 Choice of Zoning Report Development Options 19
5.4 Zoning Report Development Options 20
5.5 Phasing of Zoning Report Development Options 28
-
7/28/2019 Dover Harbour Useful Info
4/48
Issue 2 Rev 4 18 November 2005
6 Planning Structure 306.1 Introduction 30
6.2 Assessment Criteria 32
6.3 Outline Economic Impact 36
6.4 Planning Findings 38
7 Conclusions 39
8 Zoning Plan 41
8.1 General 41
8.2 Ferry Trade 418.3 Other Trades 43
8.4 Summary 44
Figures
Appendix A Preferred Option Sketches
Appendix B Preferred Option Descriptions Table
Appendix C Phasing of Preferred Options
-
7/28/2019 Dover Harbour Useful Info
5/48
Issue 2 Rev 4 18 November 2005 1
1 Introduction
1.1 GeneralDover is the busiest ferry port in the world and provides a vital link
between the UK road network and the rest of continental Europe. The
port is administered by Dover Harbour Board (DHB) as a Trust Port.
The remit of the port is therefore to operate on a commercial basis to
best serve the interests of the United Kingdom, the surrounding
communities and the users of the port.
In 2003, the DHB decided to draw up a 30 Year Master Plan for the Port.
This master plan was required to set out the pattern of development for
the port so that it could address changes in traffic, continue to contributeto the local economy and minimise the negative impacts on the town of
Dover.
The master plan is being developed using a staged approach. Phase 1 in
2003 included traffic forecasts and assessments of the existing and
potential port capacities. It indicated how each trade sector could develop.
Phase 2 began in 2004 and involved preparing an incremental
development plan, focused on maximising use of the existing harbour
(both Eastern and Western Docks). It analysed investment return and
prioritised conflicting options.
Halcrow is the Engineering Consultant for Phase 2 of the Master Plan,
whilst High Point Rendel (HPR) is the Financial Consultant. Phase 2
includes the following stages, of which we are currently at Stage 3 :
Phase 2 Stage 1 : review port traffic forecasts, outline
development options based on prioritisation of trade;
Phase 2 Stage 2 : undertake capacity study of Eastern Docks,
refine development options based on port trade growthrequirements.
Phase 2 Stage 3 : consultation and further development of
feasible options to create a zoning plan covering both the Eastern
and the Western Docks
Phase 2 Final Report Stage : following further public
consultation.
This report sets out the likely development of the port as the basis forpublic consultation.
-
7/28/2019 Dover Harbour Useful Info
6/48
Issue 2 Rev 4 18 November 2005 2
1.2 The IssuesDover Harbour has always been the historic gateway between the UK and
the Continent and also close to the major shipping lanes into the North
Sea. 80% of trade is ferry related. Operators include P&O, SeaFrance,
Norfolk Line, SpeedFerries and Hoverspeed.
The port has also diversified to include cruise facilities (two berths), a
cargo terminal with temperature controlled storage, an aggregate facility
and the yacht marina. On land are a shopping complex, hotel
development, property and a business park.
The area of land and water in which the port operates is restricted. Ferry
operations are concentrated in the Eastern Docks (shown in Figure 1.1).
While all is running smoothly, the existing port is able to handle the
present levels of traffic without difficulty. The system is complex and any
disruption due to bad weather, breakdowns, labour disputes, political
demonstrations or security issues very quickly clogs the local roads with
traffic. This causes frustration for the port users and disrupts the lives of
the towns residents.
The challenge is to see how the port can handle increasing traffic while
reducing the incidence of these traffic problems. This has to be done
while dealing with ever increasing security and without compromising the
very high safety standards that the port applies.
1.3 ObjectivesThe overall objective is to provide DHB with the foundation for a
workable business plan for the port for the next 30 years, including
recommendations to maximise the commercial and economic potential of
the port and its assets.
The Master Plan will pay particular attention to the following aspects :
Reliable traffic/trade forecasts for ferry, cargo, cruise and marina;
The optimum use of the berthing facilities available;
Take account of cargo terminal capacity, manoeuvring capacity,
internal and external access capacity;
Identify impacts of government policy and environmental
constraints;
Define capacity in each area of port operation;
-
7/28/2019 Dover Harbour Useful Info
7/48
Issue 2 Rev 4 18 November 2005 3
Maximise the commercial and economic potential of the port,
including redevelopment and alternative uses for some or all
areas;
Look carefully at the relationship between the port estate and the
rest of Dover;
Identify the preferred way forward for the Port of Dover.
The master plan will include actions to be taken to improve the
infrastructure and modes of operation, to achieve the vision. The master
plan will not be a static document since it will be subject to regular review
and updating.
Figure 1.1 Port of Dover Layout
N
Southern Breakwater
Admiralty Pier
Eastern Docks
Western Docks
Eastern EntranceWesternEntrance
-
7/28/2019 Dover Harbour Useful Info
8/48
Issue 2 Rev 4 18 November 2005 4
2 Trade Forecasts
2.1 GeneralIn Phase 1 of the master plan, a set of trade forecasts for the port was
developed which was further reviewed in Phase 2.
Trade forecasts for a port are based on a series of assumptions, taking in
the rate of economic growth of the nation, the pattern of trade, changes
in government regulations, the behaviour of shipping lines and the
competition from other modes of transport. All of these factors are
constantly changing and so the forecasts always have an element of doubt
associated with them.
The requirement is that the master plan should set out a series of
forecasts which are as accurate as possible but which can be easily
updated.
2.2 Freight TrafficFreight ferry traffic provides the backbone of Dovers business. Trucks
prefer to use Dover as the frequent sailings allow a turn up and go
system to be operated. Trucks arrive at the port without bookings and are
allocated to the first available ferry by the chosen operator.
The trade between the UK and Europe is growing rapidly although this is
threatened by the increasing relocation of manufacturing capacity to
China and India. The expansion of the EU will encourage trade between
the countries of Eastern Europe. Government legislation throughout
Europe is seeking to control the growth of road traffic, encouraging more
use of sea transport as an alternative. This will tend to shift traffic away
from Dover towards longer ferry crossings from the Humber and Thames
Estuary. Traffic congestion in the South East of England will also tend to
reduce the volume of freight using Dover.
Taking all these factors into account, the master planning team have
produced the forecasts for freight ferry traffic shown in Section 2.8
below. This shows a steady increase in freight traffic with volume almost
doubling by 2034.
The freight traffic is not steady through the day and also shows variations
through the week. The ferry operators set up their service schedules so
that with everything working well there is enough capacity at peak hours.
The same ships are then run through the day with a vessel on the Dover
Calais run typically making 5 round trips per day. This results in theseemingly low deck utilisation (a measure of how full the ships are on
-
7/28/2019 Dover Harbour Useful Info
9/48
Issue 2 Rev 4 18 November 2005 5
average) of around 50%. This low average deck utilisation allows the port
to clear a backlog of waiting trucks quite quickly after a period of
disruption. If the average rose to around 70%, as is usual on longer ferry
crossings, the port would take days to clear a backlog.
2.3 Car TrafficThe number of cars using the Dover Ferry services has been seriously
affected by competition from the Channel Tunnel Shuttle service and also
by low cost airlines offering attractive fly-drive packages. In a more
general level, the holiday traffic has been reduced by a trend to long haul
holidays rather than the more traditional journey to France.
The agreed traffic projections show a reduction in car traffic over the next
few years with a subsequent recovery to give an increase of 15% by 2034.
As with the trucks, car traffic has distinct peaks with low carryings in
winter and more on Bank Holiday weekends. Fortunately the peak car
traffic does not coincide with the truck peak.
2.4 CoachesThe coach trade through Dover is predicted to decline as a result of
changing trends in European holidays. A few years ago it was quite
common for people to use coach travel as part of a holiday package but
the low cost airlines have largely taken this function. Coach tours are still
popular but the average age of the customers is rising except in somespecialist areas. Total coach traffic is expected to halve by 2034. Even if
this projection is wrong, it will not have a large effect on the total ferry
traffic.
2.5 Fresh Produce (Fruit)Dover came into the fruit trade as part of a diversification policy before
the Channel Tunnel opened and the small facility is operated by a third
party, handling cargo for one major importer. Competition in the fruit
market is intense and it is likely that without an improved facility, the fruit
trade will reduce. If improved facilities can be offered, additional userscould be attracted, giving a 50% increase in throughput by 2034.
2.6 AggregatesDover provides a berth and handling facility for marine dredged
aggregates. The materials are for local use and this trade is expected to
stay relatively stable.
2.7 Cruise LinersAnother part of the Dover diversification was to build two cruise liner
berths in the Western Harbour. Dover acts mostly as the start and finishpoint for cruises to Scandinavia and it competes with Harwich in this
-
7/28/2019 Dover Harbour Useful Info
10/48
Issue 2 Rev 4 18 November 2005 6
market. North Sea cruises are a steadily growing market but weather
dictates that it will only have substantial volume in the summer months.
The number of ship calls is expected to double between now and 2034.
2.8 Trade SummaryThe table below sets out a summary of the baseline traffic forecasts up to
2034. The actual trade may vary considerably from the figures given so
that the timing of demand for new facilities may change.
Trade Sector 2003 2014 2024 2034
Freight Million units 1.8 2.2 2.5 2.6 3.3 2.8 3.9
Cars Million units 2.6 2.3 2.6 3.0
Coaches 000 units 130 80-100 60-90 40-80
Fresh Produce 000 tonnes 263 rising to 350 - 400
Aggregates000 tonnes 220 Within the 200-250 range
Cruise Calls 117 140 180-190 200-250
Passengers Million 14.8 14.1 15.6 17.2
2.9 Traffic Growth Beyond 2034Although the present master plan study covers 30 years from the start in
2004, it is sensible to look at general trends beyond that date. It is likely
that the truck traffic will keep growing beyond that date although other
trades may have already changed radically. The master plan should
therefore allow for further growth in ferry demand.
-
7/28/2019 Dover Harbour Useful Info
11/48
Issue 2 Rev 4 18 November 2005 7
3 Eastern Docks Capacity Studies
3.1 GeneralEarlier parts of the master plan study looked at options for the
development of the Eastern Docks and determined the ultimate capacity
of this area to accommodate ferry traffic. The capacity of the existing
fruit and aggregate facilities was also calculated.
A series of capacity aspects were considered, namely marine capacity (ship
movements), berth capacity (berth slots, vessel timetables and berth
throughput), and internal and external access capacity (landside traffic).These are explained in the following section.
To do the capacity calculations, a number of assumptions had to be made.
These can be summarised as follows: -
The ferry services will continue to be operated by a small number
of different companies using modern vessels.
Most traffic will be carried by conventional ferries. The high
speed ferry services will continue but are unlikely to expandsignificantly.
The smaller ferries will be replaced with Dovermax ferries
approximately 185m long with a beam of 28m. The ferry
operators have all stated that they have plans to do this. They
have also looked at using larger ferries but they have decided that
these will take too long to turn around in the Dover context.
Once these larger ferries are operating at around 50% deck
utilisation the operators will increase capacity by providing morefrequent sailings.
If the pattern of services changes from the above assumptions, the dates
on which the various phases of the system reach capacity will change. For
example, the change from the 2004 fleet to an all Dovermax fleet gives a
30% increase in the number of vehicles which the schedule can handle. If
a new operator were to come in and offer an additional service using
smaller ships, this could reduce the capacity of the system by taking up
berth slots and marine capacity, which would not then be available to
larger ships. The legal framework within which the port operates requiresit to offer facilities to new customers. The modelling does not show any
-
7/28/2019 Dover Harbour Useful Info
12/48
Issue 2 Rev 4 18 November 2005 8
constraint on new operators but they are assumed to use large modern
ships.
Dover Harbour is essentially a linear activity with the marine capacity
feeding into the berth capacity which in turn feeds into the landside traffic
capacity. When any one of these areas reaches capacity, the whole system
cannot handle any more traffic. Improvements in one area may not
provide overall increases in capacity if another part of the system is
already at the limit.
3.2 The Need for a Robust SystemIn theory, with everything working to schedule and no problems, the Port
of Dover can handle several times its present throughput. This is
however a theoretical situation and in reality the capacity of the system is
fixed by its capacity to deal with the delays, breakdowns and disruptions
which are part of everyday life. The analyses described below have been
based on quality of service under realistic conditions not the theoretical
maximum capacities.
3.3 Harbour and Marine CapacityThe number of ferry sailings which the Eastern Docks can accommodate
is limited by the space available to manoeuvre ferries seaward of the ferry
berths.
The study of marine capacity was undertaken using ARENA, a simulationmodelling tool. The model was built to closely represent and mimic the
real marine system at the Eastern Entrance and off the Eastern Docks
berths. The rules applied to the ship movements were discussed with the
marine operations staff and ships masters working for the operators. The
model was validated by running the existing shipping schedules and
checking whether it reflected real events. The model was then used to
test a variety of shipping schedules to see how much extra traffic could be
accommodated without a deterioration of service levels.
The construction of Berths 8 and 9 has expanded the area available formarine operations and has improved the service levels. The modelling
showed that the Eastern Docks is able to accept a schedule containing 88
ship movements per day. Building further berths in the Eastern Docks
will not allow additional ship movements as they would use the same
manoeuvring space.
Generating shipping schedules to match the baseline traffic projections
shows that the Eastern Docks runs out of marine capacity in 2024 even
allowing for optimal shipping capacity. At this point more than 88 ship
movements are required. This date will change with varying traffic levels,changes in fleet composition or changes in vessel destinations.
-
7/28/2019 Dover Harbour Useful Info
13/48
Issue 2 Rev 4 18 November 2005 9
3.4 Berth CapacityBerth capacity is the volume of traffic that the berths in the port can
handle. At first sight this may appear trivial as you simply put a new
vessel onto the berth when one departs and the berth capacity is the deck
capacity of the ship times the number of ships per day that the berth can
take. To achieve this capacity there would have to be a queue of ferries
waiting outside the port. This would be uneconomic for the operators
and frustrating for the passengers.
To do a proper analysis of berth capacity you need to look at which ships
will fit which berths and then build a schedule so that the same ships
come back to the same berths. The schedule has to allow for the time at
sea and the time alongside of each ship. The schedule also has to have
some slack in it so that the ship can catch up if she is delayed at any point.
The Dover conventional ferry berths as at the end of 2005 will be as
follows: -
BerthNo
LinkspanType
Max VesselLength (m)
VesselBeam(m)
Depth toSeabed
(m)
YearInstalled
1 Single deckwith stowablefinger ramps
Effectivelyunlimited
21.3 8.6 to 10.3 1987
2 Twin deck .Ramp intovessel. Paxwalkway over
178.5 28.5 7.3 to 9.3 1988
3 Twin deck.Ramp intovessel. Paxwalkway over
178.5 28.5 7.4 to 9.2 1987
5 Twin deck.Ramp intovessel Paxwalkway over
185 22.3 6.3 to 7.4 1980
6 Twin deck.Ramp intovessel. Pax
walkway over
185 27.7 7.7 to 8.3 1980
7 Twin deck.Ramp intovessel. Paxwalkway over
190 28.5 8.0 to 9.2 1993
8 Twin deck.Ramp intovessel. Paxwalkway over
218.8 28.5+ 8.5 2005
9 Twin deck.Ramp intovessel. Paxwalkway over
218.8 28.5+ 8.5 2005
-
7/28/2019 Dover Harbour Useful Info
14/48
Issue 2 Rev 4 18 November 2005 10
In addition, the port has a cars only high speed ferry berth in the Eastern
Docks and a single high speed ferry berth on the hovercraft terminal in
the Western Docks.
Ferry schedules were developed for the years 2014, 2024 and 2034 based
on the traffic predicted for those years. The number of berths required to
handle these schedules was determined based on keeping a reserve berth
to ensure reliability of service. This exercise showed that the berths were
not likely to be the bottleneck given the assumptions made about fleet
mix.
3.5 Internal and External Access Capacity of Eastern DocksThe capacity of the internal and external access to the Eastern Docks was
assessed using VISSIM, a vehicular traffic model that simulates traffic
movements along a road network. A landside traffic micro-simulation
model was set up for this purpose and calibrated against the existing
situation.
Ferry landside capacity includes the capacity of the port internal road
system within the Eastern Docks, as well as the external road network
near the port. Landside capacity is also determined by the processing
capacity of the various control gateways through which traffic passes.
These include security, immigration and customs checks. The practical
capacities of these gateways are determined by operational efficiency,
whereas ultimate capacity is limited by the infrastructure such as howwide the roads are and how many weighbridges are available.
The capacity of the Eastern Docks is also determined by the capacity of
the assembly areas to store outbound traffic prior to departure. This
depends on operational factors, not only in terms of the effective use of
available assembly space, but also in terms of the requirement for such
space. This is in turn a factor of the scheduling and reliability of ferry
operations. If the ferries could operate to a perfectly regular schedule, the
assembly spaces could achieve a very high utilisation but in practice this is
not possible.
With a realistic ferry schedule, the assumed changes in fleet size and
sailing schedules and the baseline projection of traffic growth, the internal
road capacity of the Eastern Docks will be reached by 2020. In practice
this theoretical date may be over-optimistic due to fluctuations which may
occur in traffic arrival patterns and operating conditions. Consequently it
will be important to provide capacity outside the Eastern Docks
considerably in advance of this date. Modifications to the internal road
network and dock exit roundabout will also be needed well before that
date.
-
7/28/2019 Dover Harbour Useful Info
15/48
Issue 2 Rev 4 18 November 2005 11
3.6 Overall Capacity ConclusionsAs can be seen above, the capacity of the Eastern Docks is determined by
its ability to provide good service levels in a number of areas.
The marine capacity of the docks is limited to 88 sailings a day. This will
be achieved by 2024 with all the assumptions made. The most significant
assumption is that all the ships sailing out of Dover will be Dovermax
size. There are a number of new ships on order for ferry routes out of
Dover, but if these are the only changes to the fleet, the marine capacity
will be reached in 2012. Accordingly important decisions will be required
in the near future. This date is very sensitive to changes in assumptions
and the number of sailings required each year will have to be monitored
carefully.
Consideration of berths shows that the number of berths available in
2005 appears sufficient to accommodate a 2034 timetable with predicted
2034 traffic throughput. If the number of operators was to change or the
fleet composition does not change as expected, the date for reaching
capacity will move. The marine capacity is always likely to be reached first
as it reacts to many of the same variables.
Internal and external access (landside) capacity appear theoretically
capable of accommodating traffic levels perhaps as far as 2020, based on
traffic modelling assuming optimal operating conditions and median
freight growth. Capacity is reliant on timetable compliance andoperational use of assembly areas and ticket booths. Outbound traffic
congestion on Townwall Street is a major issue both for the effect on
customers of having to wait so close to the port and for the numerous
ways in which it affects the quality of life of the residents of Dover.
Because of limited waiting capacity within the Eastern Docks, traffic can
build up very quickly on Townwall Street. This congestion can be
triggered by any disruption within the Docks and ferry system or by an
unusual arrival pattern in the traffic as a result of motorway congestion.
The other critical issue in the customers perception of Dover is the timebetween the lowering of the ships ramp and the vehicle being on the
open road outside the town. Any congestion within the Docks or the
town has a major effect on this.
To allow an increase in the traffic through the Eastern Docks, the whole
system must be examined carefully to improve the reliability of the
process and to make maximum use of the vehicle parking areas within the
port area. Even with all such measures taken, the capacity will never be
truly robust. With traffic well below the theoretical capacity of the
system, disruptions are still likely to cause congestion on Townwall Street.
-
7/28/2019 Dover Harbour Useful Info
16/48
Issue 2 Rev 4 18 November 2005 12
The only other way to control traffic queuing on Townwall Street is to
control the flow of traffic leaving the M20. A proposal to build a holding
area to the west of Dover is discussed later in this document. In the light
of the Highways Agencys dislike of controlled signage on main routes, a
holding area used by all freight traffic would seem to be the only option.
A small change in traffic growth rates can change the date at which
capacity is reached. For example, changing from the baseline traffic
projection to the upside projection will bring the theoretical capacity date
forward by five or six years. It is important for DHB to be aware of the
issues which will affect the dates and to monitor these parameters. The
master plan study will leave DHB with a series of tools to model the
effects of changes as they occur.
A product of the master plan will be a description of the trigger points to
initiate the provision of new facilities. These trigger points will be in two
forms based on a theoretical look ahead and on the levels of service
actually being achieved. To determine the theoretical trigger points, it will
be necessary to estimate the time taken to procure each element of the
development and then calculate the traffic levels at the time when
procurement has to start. This calculation will have to take into account
both the traffic level and the rate at which the traffic is increasing.
It is much more difficult to establish the level of service thresholds as it
will be necessary to plot a number of key performance indicators such asthe number of times per year that queues develop outside the docks, the
number of ships which are delayed by more than 10 minutes each year
and the average time from ramp down to the last vehicle leaving the
docks. The rate at which these key performance indicators are changing
can then be used to determine the date on which they will pass the
threshold of acceptability.
-
7/28/2019 Dover Harbour Useful Info
17/48
Issue 2 Rev 4 18 November 2005 13
4 The Environment of Dover Harbour
4.1 IntroductionThroughout history, the development of the town of Dover and the port
have been very closely related. As the port traffic has built up, the effects
on the town have increased so that now the interaction between the two
has become a major issue. In particular the road network to the port is
prone to congestion, affecting the environment of the town. Options for
the future are considered in this section.
4.2 ConstraintsThe constraints preventing the development of new projects within the
port are illustrated in Figure 4.1 and discussed below.
4.2.1 Cliff TopographySettlement patterns and port development over the centuries have been
influenced by the physical topography of the town, with future port
expansion beyond existing boundaries constrained by the cliffs and the
built development of the town.
4.2.2 Public Access, Recreational Facilities and Limited Water DepthPublic access to the sea and beach is confined to the stretch of coastline
between the Eastern and Western Docks and it is desirable that this isretained as a valuable local asset. This splits the operations of the Port of
Dover into two separate and distinct areas of the Eastern and Western
Docks.
Water sports and recreational boating take place in the waters fronting the
Marine Parade, again dividing the two distinct areas of port activity.
To retain the recreational use of the beach and foreshore requires care in
the design of the limits of dredging. The situation must be avoided where
a person can be standing on the bottom and then find themselvessuddenly in deep water as this is extremely dangerous. Similarly the
propeller wash from commercial shipping should not reach the areas
where people are wading. These constraints may affect the layout of
future developments.
4.2.3 Sites of Special Scientific InterestThe coastline from Port of Dover to Kingsdown is of national
importance due to its geology, geomorphology and varied flora and fauna,
including many rare species. The cliffs, from Shakespeare Cliff to behind
the Eastern Docks, are designated as Sites of Special Scientific Interestand include the sheer cliff faces and the wave cut platform at the base of
-
7/28/2019 Dover Harbour Useful Info
18/48
Issue 2 Rev 4 18 November 2005 14
the cliffs. These sites provide the habitat for rare species and migrating
birds.
4.2.4 Recreational FishingAdmiralty Pier is a nationally recognised site for sea anglers with the area
adjacent to the Western Docks also used by local fishermen.
4.2.5 Access Road Frontage DevelopmentPort traffic to the Eastern Docks from the M20 uses Townwall Street
(A20). From the York Street Roundabout to the junction with East Cliff
the road is developed on both sides with flats, hotels, a leisure centre and
other town centre related development. This section of the route is within
an Air Quality Management Area. From East Cliff to the Eastern Docks
the route is adjacent to the East Cliff and Athol Terrace Conservation
Area. At times when the rate at which trucks arrive exceeds the capacity
of the Eastern Docks the traffic queues along the A20, which interferes
with local traffic and pedestrian movements. The Eastern Docks
roundabout has capacity constraints which can cause peak period
congestion. Even when traffic is flowing freely, port traffic combines
with local traffic to create the general noise, vibration and air quality
effects of traffic in the town centre.
The effects of local and port traffic cannot be separated and it is
important that the Dover traffic issues are considered as a whole. New
developments in the town will contribute to congestion in just the sameway that port traffic will. It is vital that all organisations in the Dover area
work together to minimise the problems on the towns roads. This can
only be achieved by sharing information and setting up an agreed model
of the traffic flows so that the effects of changes can be reviewed
dispassionately.
4.2.6 Listed Buildings and Ancient MonumentsWithin the port itself there are various Listed Buildings, which are
highlighted below. Any works requiring demolition or negatively
affecting the setting of these features will require consents. Very oftenthe effects of changes can be mitigated by finding alternative uses for
buildings or similar.
(a) Former Dover Marine Rail station
This is currently in use as a Cruise liner terminal, with one end converted
into a passenger facility, and a large portion of its remaining internal space
is used for car parking. The brick walling on the western elevation has
seen some modern alteration. Any major changes proposed here (e.g.
creation of new openings) are likely to require a detailed building
assessment to be carried out to establish the history of alteration to the
-
7/28/2019 Dover Harbour Useful Info
19/48
Issue 2 Rev 4 18 November 2005 15
structure. This would allow a full consideration of its future conservation
requirements.
Connected to the main building is an overhead walkway with its own
entrance building, which is currently used by the local angling group to
access the Admiralty Pier for fishing. The presence of this structure
imposes constraints on manoeuvring and vehicle movements within the
Western Docks which may impact future port options. Safe pedestrian
access to Admiralty Pier can be provided in a number of ways and the
walkway will only be removed if no other viable solutions can be found at
reasonable cost. Part of the change may include the refurbishment of part
of the walkway so that its historical context can still be appreciated.
(b) The Prince of Wales Pier
The length of the pier imposes a constraint on shipping movements to
and from Admiralty Pier. The pier is perceived to have group value with
other pier and lighthouse features and to contribute to the whole
appearance of the harbour.
It is very likely that the outer end of the Prince of Wales Pier will form a
major obstruction to the development of the Western Docks and there
will be a strong case for its removal. It is possible that part of the pier
could be reassembled as part of a revised Western Docks layout but this
would need considerable further study. The layout of Dover Harbour has
been changed continuously to accommodate changes in circumstances.The modification of the Prince of Wales Pier would be a continuation of
this pattern.
(c) Other
Lord Warden House is currently used to provide offices. The building has
had substantial expenditure to preserve its basic fabric but it has lost its
original setting and is not well suited to its present use.
A crane structure which is an ancient monument has been retained within
the Wellington Dock area. The use of this area for the marina providesprotection for this structure.
Just outside the Western Docks, Waterloo Crescent comprises a row of
Regency town houses within the conservation area on the beach front,
which includes the DHB offices. These buildings are maintained to a high
standard and well used.
A section of the Western Docks falls within an area of defined
archaeological importance, including the Tidal Harbour and Granville
Dock. The potential of this area for marine archaeology has beenunderlined by the discovery of features of marine archaeological interest.
-
7/28/2019 Dover Harbour Useful Info
20/48
Issue 2 Rev 4 18 November 2005 16
Whilst this does not necessarily preclude development, it does increase
the requirements for site investigations and excavations prior to any
development being allowed to commence.
4.3 OpportunitiesThe opportunities to develop new projects within the port, which could
involve both further expansion of existing uses and the development of
new facilities, are illustrated in Figure 4.2.
4.3.1 Space PotentialThe Eastern Docks is the main focus for passenger ferries and is the most
heavily utilised area of the port. Capacity of the Eastern Docks could be
improved by relocating a number of buildings within the port boundaries
to outside the port, and converting single/low-storey buildings to multi-
storey for further intensification. The space potential created and the
relevant cost involved would determine the attractiveness.
Another option is relocation of the coach interchange area outside the
port, although a major concern is the potential impact on the coach trade.
4.3.2 Underutilised Port Land and Water AreaThe Western Docks contain large buildings and spaces which are only
partially used. There is also a large area of underutilised water around the
Prince of Wales Pier and expansion of port operations here needs to be
reconciled with the historic interest of this part of the site.
Future options for large scale port expansion towards Shakespeare Cliff
have been discussed for some years. In an early part of the study, these
options were carefully reviewed and ruled out for the foreseeable future.
The cost of the breakwater system is simply too high to obtain an
economic return.
4.3.3 Wellington Dock areaThe Wellington Dock is a relatively small water area surrounded by a
number of historic buildings and port features. The entrance toWellington Dock is narrow and spanned by a swing bridge which gives
access to the Hovercraft Terminal area of the Western Docks. The dock
is too small for modern shipping but it provides the ideal site for
waterfront development, linking the town and the beach. This link could
include improved footpaths and cycle ways. It could also be used to
improve the appearance of the river Dour which discharges into the
basin.
The successful De Bradelei Wharf has provided a much used facility
which is in keeping with the surroundings. Further property developmentis possible without detracting from the area and without losing this
-
7/28/2019 Dover Harbour Useful Info
21/48
Issue 2 Rev 4 18 November 2005 17
section of the marina. Options under consideration include an extension
to De Bradelei Wharf and an hotel on the seaward side of the dock.
4.3.4 Potential to Re-establish the Rail LinkTraditionally the Western Docks was served by a rail link which delivered
passengers and freight to the quay edge and to the Train Ferry Berth.
In the absence of a rail ferry service, it is difficult to see what cargo such a
service would carry and if passengers wish to use a rail link to the
Continent, they are likely to use the Eurostar service.
-
7/28/2019 Dover Harbour Useful Info
22/48
Issue 2 Rev 4 18 November 2005 18
5 Development Options
5.1 ApproachThe overall approach to the initial development options was to show a
number of possibilities which fulfil individual trade growth requirements
or some limited combinations of them. This was so that a range of costs
for development for each trade could be shown. These then assisted in
prioritisation of trades and development options, taking account of the
revenue associated with each development option.
Following the trade prioritisation process, the development options were
re-assessed from a different viewpoint. Options were refined by varying
them, combining them and in some cases by phasing the development ina different manner. For each variant the outcome of the study
undertaken to determine the capacity of the existing port was taken into
account. This allowed the most feasible solutions to be determined and
put forward, whilst still taking the individual trade growth requirements of
the port as well as its capacity into consideration.
The main conclusion of the trade prioritisation is that the ferry business
generates considerably more revenue per berth and per unit of area
occupied than any of the other trades using the Port of Dover. The
cruise business has received considerable investment and this will allowDover to hold its position in a limited market place. Major investment
would also be required to maintain or improve the position of the fruit
trade and this would need strong justification. The aggregates business
shows a good return on its existing facilities but it would be difficult to
justify new construction. The Marina has never operated at capacity and
it struggles to cover its operating costs.
In this Zoning Report, feasible options contributing towards a preferred
zoning plan are described. The preferred options are outlined in greater
detail providing better information as to their economic andenvironmental feasibility and their appropriateness in meeting the capacity
requirements of the Port.
5.2 Exclusion of Stage 1 and Stage 2 Development OptionsThe development options from Stage 1 and Stage 2 of the Master Plan
Study were amended taking account of financial viability and overall
feasibility while satisfying the trade growth requirements of the port. An
explanation as to the reasons for the exclusion of some of the
development options raised at Stage 1 and 2 of the study, are given below.
-
7/28/2019 Dover Harbour Useful Info
23/48
Issue 2 Rev 4 18 November 2005 19
5.2.1 Eastern DocksThe existing berth capacity of the Eastern Docks is sufficient to cope with
an increase in marine traffic based on a developed timetable for 2034.
The overall capacity of the Eastern Docks is determined by the ability to
get ships to the berths and the road traffic in and out of the port. Neither
of these problems can be solved without dramatic changes to the port and
the town. It would not be possible to keep the port operating at capacity
during such changes. Development options including additional berths in
the Eastern Docks have therefore been excluded.
5.2.2 Western DocksSeveral of the possible schemes for the Western Docks provide very large
capacity increases at a single stroke but they also carry very large costs and
they will not be commercially viable.
Developments resulting in the displacement of the aggregates facility in
favour of cruise or other cargo berths appear not to be financially viable.
This is mainly due to there being no added benefit from removing an
income generating trade to make way for other options that are not as
financially rewarding.
Alterations to the port entrance either by extending the Admiralty Pier or
removing the existing entrances and creating a single entrance are not
financially feasible. The only benefit is the reduction in wave exposure
for Western Docks development options, which when valued against thecosts involved cannot be financially justified. Further, a single port
entrance may increase downtime in parts of the Eastern Docks which is
unacceptable due to the effects this will have on the ferry trade,
specifically in terms of congestion and delays. These options have
therefore been discounted.
5.2.3 Outside the PortAs already discussed, the costs to develop berths outside the existing port
are very high and could never show a reasonable financial return at
present tariff rates. Some time in the future, such a development may bepossible but certainly not until the capacity of the existing port has been
maximised.
5.3 Choice of Zoning Report Development OptionsThe various factors contributing towards the choice of development
options are outlined below. Only options that comply with these
requirements have been considered further.
5.3.1 Ferry DevelopmentThe ferry trade remains by far the most important trade to the port and itis important to cater for its future growth. The baseline demand forecast
-
7/28/2019 Dover Harbour Useful Info
24/48
Issue 2 Rev 4 18 November 2005 20
calls for three new ferry berths in the Western Docks with a fourth berth
if traffic growth follows the high end scenario. If traffic grows in line
with the low end scenario, the requirement for new berths within the
study period will reduce. All the forecasts show the need for a number of
new ferry berths in the Western Docks, the only difference between the
scenarios being timing.
Based on the above, it is important to make space provision for new
facilities while carefully monitoring traffic growth to determine the
phasing and timing of developments.
An added consideration in the expansion of the ferry trade is that it
creates far greater employment and secondary benefits than any of the
other trade options. It is clear that the choice of such a development is
far superior economically to the other options.
In theory it would be possible to gain landside capacity in the Eastern
Docks by making more dramatic changes to the internal road layout but
the costs would be considerable and relatively soon after the predicted
saturation date, the Eastern Docks runs out of marine capacity. Such
internal improvements would only exacerbate the congestion problems on
Townwall Street. The service provided by a port which is very close to
the limit on both landside and marine operations is going to be unreliable
and bad for the long term future of the port.
5.3.2 Cargo DevelopmentThe costs of providing completely new facilities for the fruit trade would
be substantial. These could only be justified by obtaining suitable
guarantees and long-term contractual commitments.
5.3.3 Cruise Terminal DevelopmentThe traffic projections show the number of cruise liner calls increasing to
200-250 at the end of the study period. Each cruise call occupies the
berth for a day so how many calls can be accommodated at each berth
depends on the length of the season and the exact pattern of calls withinthe season. It is possible to provide a longer berth to meet the growing
market for ships of over 300m or a third cruise berth for the smaller
cruise liners by removing the spur pier which forms the Jetfoil Basin. Any
other location for an extra cruise berth is likely to restrict ferry operations
and DHB will have to decide which trade will take precedence.
5.4 Zoning Report Development Options5.4.1 General
The chosen options for development are shown in the sketches in
Appendix Aand discussed in more detail below. Appendix B
-
7/28/2019 Dover Harbour Useful Info
25/48
Issue 2 Rev 4 18 November 2005 21
summarises the options descriptions, advantages, disadvantages and any
relevant comments.
5.4.2 Option I : Do MinimumThis option is based on carrying out minimal improvements, at relatively
low cost and minimising disruption to existing services. In the short
term, these measures can improve the quality of service offered but
pressure of traffic will steadily erode this gain. In the longer term,
congestion and delays will increase, if this option is used in isolation,
progressively reducing the quality of service offered by Dover.
Elements which could be included are as follows:
Revised A20 dock exit and dock exit roundabout improvements
(initial studies in progress)
Lane width and weighbridge improvements inside the Eastern
Docks
Revised ferry fleet (increasing carrying capacity)
Extend ticketing area
Green transport measures to reduce car parking spaces and
reduce staff car traffic impacts
Consider reduction in the unaccompanied trailer park size and
relocation to reclamation in the East Catamaran Berth area,
between Berths 6 and 7
Consider relocating coach interchange area out of port, with area
being used for either marshalling/assembly area, increasing
queuing area in front of ticketing or for Dover Cargo Terminal
Upgrade Berth 5 to accommodate wider beam vessels (ongoingupgrading of vessels in future will increase berthing difficulty at
this berth otherwise)
These measures are fairly self explanatory. Each produces a small
incremental increase in capacity or an increase in reliability at fixed
throughput. None of them however addresses the specific issue of traffic
congestion on Townwall Street. The following concepts do have a direct
impact on Townwall Street and therefore demand closer inspection.
-
7/28/2019 Dover Harbour Useful Info
26/48
Issue 2 Rev 4 18 November 2005 22
Compactor Corner Improvements
Compactor Corner is the point at which the traffic going to the
berths in the Eastern Docks turns seaward at the base of the
cliffs, heading towards Berth 1. A key constraint on the landside
capacity of the Eastern Docks arises due to the fact that upstream
of Compactor Corner, the approach route consists of only 3
lanes. If there is a queue caused by one operator being unable to
process traffic through the check-ins, traffic builds back to
Compactor Corner where it then blocks vehicles intending to use
other operators from reaching the check-ins. Once this happens,
the rest of the Eastern Docks road system rapidly chokes, causing
a tail back onto Townwall Street. A review of alternative highway
layouts through Compactor Corner has been undertaken in order
to assess the scope for providing additional operator specific
storage capacity. This will delay the point at which one
operators traffic disrupts the entire operation.
Four preliminary options have been considered. Three of the
options are based on an alignment north of Easter Camber
Office building and the fourth on an alignment south of the
building. Some options involve significant demolition and
relocation of buildings and the replacement of weighbridges.
Additional capacity of up to 60 lorry spaces can be provided and
would lead to a reduction in the incidence of outbound traffic
queuing outside the Eastern Docks.
At best, this work at Compactor Corner simply delays the
moment at which queues spread outside the port and there could
be substantial expense and disruption involved. It is a useful idea
but in itself it has only a small effect.
Buffer Zone Concept
This concept is based on the very simple idea that it is possible to
monitor and predict the rate at which the ferries can load vehicles
from the Eastern Docks. It is also possible to monitor the rate atwhich vehicles are arriving at the south edge of Dover heading
for the Eastern Docks. If the rate of arrivals exceeds the rate of
ferry loading, the result can only be stationary traffic on
Townwall Street. The factors determining the uplift rate by the
ferries are not easily controlled in the short term but it is possible
to take off the peaks in the traffic arriving into Dover by holding
some vehicles until the peak has passed. This would allow
Townwall Street to run more consistently, reducing the tendency
to congestion.
-
7/28/2019 Dover Harbour Useful Info
27/48
Issue 2 Rev 4 18 November 2005 23
The analysis of landside capacity in the Eastern Docks has
demonstrated that the key constraint on capacity, assuming that
inbound capacity problems are largely dealt with by the
construction of the Dock Exit Scheme, is the amount of space
available to accommodate outbound traffic waiting to embark on
a ferry. The need for substantial storage largely applies to non-
pre-booked freight traffic although the same thinking can be
applied to all traffic. Given the space constraints within the
Eastern Docks, consideration has been given to the possibility of
creating a secondary queuing area outside the Eastern Docks so
as to reduce the need for pre-embarkation storage within the
Eastern Docks.
A number of options for the location of such a secondary
queuing area have been considered, with one option having
considerable advantages in terms of potential size and ease of
access.
As an alternative, DHB is having preliminary discussions with
landowners in relation to an off-road site accessed from the
A20 west of Aycliffe Roundabout to locate a buffer zone. The
advantages of a buffer zone in this location compared to one
on the Granville Dock site are twofold. Firstly, the area of land
available is potentially larger and secondly access to the site
would not be via the existing busy roundabout junctions withinDover.
A site west of Aycliffe roundabout would be suitably located
for M20 port-bound traffic. This is the Highways Agency
strategic route for traffic to Dover. If the Highways Agency
were to change the strategic route to use the A2, the preferred
site would be to the north of that road. With a single buffer
zone, the traffic using the other route would have to be co-
ordinated with the main flow of traffic. This is done by the
port police under the present system and seems to work well.The best solution would be waiting areas on both the
approaches, co-ordinated from a central control in the port.
Whichever option is chosen, consideration has to be given to the
way a secondary queuing area would operate in practice. The key
issues to be considered include:
The need for the route from the buffer zone site to the
Eastern Docks to be free from congestion and for the
operators to have good IT links, including links to trafficinformation, to be able to manage the facility efficiently
-
7/28/2019 Dover Harbour Useful Info
28/48
Issue 2 Rev 4 18 November 2005 24
Whether checking-in will take place in the buffer zone site
Whether the buffer zone would be used all the time or just in
peak hours
The type of traffic that will use the facility. Initially it is
assumed that non-pre-booked freight traffic will be the main
user although it could handle cars as well
How traffic approaching on the M2 corridor will be co-
ordinated with the main flow along the M20
Who will operate the buffer zone and whether one or all
ferry operators will use it
The size of the freight buffer zone
Traffic implications at the turn into and out of the zone.
Port Expressway Concept
A review of the Highway Agencys Port Expressway concept has
been undertaken. The concept is to segregate Port traffic and local
traffic on the A20 between Aycliffe Roundabout and the Eastern
Docks entrance by converting the eastbound carriageway to two-
way for local traffic only, and converting the westboundcarriageway to two-way port traffic only.
While this idea seems at first sight to separate the two flows well, it
suffers from the inherent fault that two way roads are much more
prone to disruption than dual carriageways. It will also lead to
some complex junctions.
The conclusion is that the concept provides an alternative approach
but it does not solve the basic problem of more traffic arriving in
the port than the facility can handle.
A number of alternative layouts have been considered during Phase
2 Stage 2 of the study, including a modified Aycliffe Roundabout,
traffic signals and a flyover arrangement. Further work is required
before any firm conclusions on feasibility or capacity can be
reached.
Recommended Elements
The recommended elements of Option I are as follows:
Revised A20 dock exit and dock exit roundabout improvements
-
7/28/2019 Dover Harbour Useful Info
29/48
Issue 2 Rev 4 18 November 2005 25
Compactor Corner improvements
Lane width and weighbridge improvements as outlined in Phase 1
Green transport measures to reduce car parking spaces and
reduce staff car traffic impacts
The establishment of a buffer zone.
5.4.3 Option F : Convert Hoverport High Speed to Conventional FerryThis scenario creates one new double deck conventional ferry berth for
minimal cost in the Western Docks, at the expense of the fast ferry berth.
The fast ferry operations out of Dover have never really thrived in the
same way as the conventional ferries and they would seem to be under
increasing threat from fly-drive services provided by the low cost airlines.
The throughput of the existing high speed ferry service out of the
Hoverport does not really justify the space that it occupies and there is
the option to move it to Berth 1 in the Eastern Docks.
The option of building a single conventional berth in the Western Docks
is not particularly attractive as all of the existing operators require more
than one berth and would almost certainly not be willing to split their
operation.
Any Western Docks development will require some investment in
facilities for the regulatory authorities to handle freight vehicles and this
will be more attractive if used to service several berths.
The land area available on the Hoverport is adequate for conventional
ferry operations. The local highway network including the Prince of Wales
roundabout and the swing bridge are adequate to accommodate the
higher ferry discharges and loads although a greater number of freight
vehicles making a right turn at the roundabout carries a safety risk. The
right turn traffic could also create a major problem if the swing bridgewere to open, closing the road to traffic, when there is already stationary
traffic on the inside lane of Townwall Street. This has the potential to
gridlock the road system until the bridge re-opens to road traffic. If the
swing bridge were to open just at the point where the traffic from a large
ferry was exiting the Hoverport area this would lead to congestion within
the terminal and frustration for the drivers. The conclusion has to be that
it is not practical to operate large conventional ferries into the Hoverport
area while the swing bridge is still in operation.
This variation can form part of an overall development strategy for theWestern Docks but it has problems as a stand-alone development.
-
7/28/2019 Dover Harbour Useful Info
30/48
Issue 2 Rev 4 18 November 2005 26
The sketch showing the joint development of Options F and G2 (Phase
1) relative to the entire Port is shown in Figure 5.1.
5.4.4 Option G2 : Add One Ferry Berth (Saw-tooth) - HoverportThis option involves reclamation on the northern side of the Prince of
Wales Pier, creating one ferry berth in saw-tooth configuration in the
Western Docks. One new double deck conventional ferry berth is
created. This is at the expense of the fast ferry berth as its vehicle storage
area is needed. The aggregates facility is retained but the freight clearance
facility is reduced. This option is medium term and does not convert
easily to a long term solution for an increasing ferry trade. However, a
change in formation of the reclaimed area to the north of the Prince of
Wales Pier would allow for long-term development.
Exposure to excessive wave action is a possibility for the new berth being
near the Western Entrance. This will need detailed investigation using the
existing wave models of Dover. This modelling is reasonably expensive
and the schemes need to be refined before the modelling is done.
The new berth would affect the views from the beach area. The physical
impact on the beach area must be confirmed and mitigated, where
necessary. It would restrict the use of the water area off the beach and the
associated impact of dredging for ferry access also needs to be checked.
Increased land space would be required towards Lord Warden House aswell as towards the Town Yard area. For two berths, road access via
Prince of Wales or Limekiln roundabout or a combination is acceptable.
This option has the advantage of keeping the majority of the existing
Prince of Wales Pier in place subject to a structural load analysis, but cuts
off public access.
Access via Limekiln roundabout may allow a longer internal road system,
to provide queuing lengths in front of control agencies and ticketing, as
well as assembly areas. To ensure separation from the non-port roads, aseparate swing bridge would be required across the entrance to
Wellington Dock. There would be a loss of car parking (Union Street), the
marina yard near Prince of Wales roundabout and a reduction in the
Freight Clearance Facility area. Access to the RNLI/tugs/marina berths
has to be maintained and may be constrained. Use of the marina would
be affected, with a need for replacement parking further away, restricted
or impeded access, no marine yard and possibly surrounded by a freight
buffer zone.
On a positive note however, the Dover Pride Project is considering apotential marina development at the eastern end of the beach. If it
-
7/28/2019 Dover Harbour Useful Info
31/48
Issue 2 Rev 4 18 November 2005 27
happens, this replacement marina would decrease the impact and effect
the ferry trade development has on marina use within Granville Dock and
the Tidal Harbour.
Again Figure 5.1 shows the development of Options F and G2 (Phase 1)
relative to the entire Port.
5.4.5 Option G4 : Add Two Ferry Berths (Jetty) - HoverportAs with Option G2, this option also involves reclamation on the northern
side of the Prince of Wales Pier creating one ferry berth in saw-tooth
configuration. However, in addition to this, this option also involves
creating two ferry berths in jetty configuration in the Western Docks.
The two ferry berths would be on the northern side of the Prince of
Wales Pier (that is, on the reclamation-side south of the single berth in
saw-tooth configuration). One new double deck conventional ferry berth
for minimal costs is created. This is at the expense of the fast ferry berth.
This option caters for long-term development.
As for Option G2, increased on-land space would be required towards
Lord Warden House and the Town Yard area. However, on-land space in
this area is limited so for this 4-berth option additional land is required
and is provided by reclaiming the existing marina outer basins (Granville
Dock and Tidal Harbour), with a replacement marina proposed on the
northern side of the Prince of Wales Pier. In terms of capacity, the new
marina caters for the 200 to 250 berths lost so together with theWellington Dock marina provides the 400 to 450 berths currently
available at the Western Docks. Access to the Wellington Dock basin is
achieved through the new marina as entrance via the marina outer basins
will not be possible.
Filling in the basins is not a particularly attractive option and an alternate
is possible by reclaiming off Shakespeare Beach to provide the additional
space required for the fourth berth. This land space would however be a
long way from the berths, causing operational difficulties.
Exposure to excessive wave action is a possibility for the two berths in
jetty configuration and the one berth in saw-tooth configuration, as with
Option G2 and will need to be investigated. Wave exposure at the marina
entrance will also need to be investigated.
The associated landside issues linked to this development are similar to
those in Option G2, including the minor works required to the Prince of
Wales Pier.
The sketch showing the development of Option G4 (Phase 2) relative tothe entire Port is shown in Figure 5.2.
-
7/28/2019 Dover Harbour Useful Info
32/48
Issue 2 Rev 4 18 November 2005 28
5.5 Phasing of Zoning Report Development Options5.5.1 Ferry Development
The ferry development options outlined in Section 5.3 include the
introduction of the conventional ferry trade at the Western Docks to cater
for any traffic overflow from the Eastern Docks, based on the Ports
forecast traffic.
The capacity study of the Eastern Docks indicates that the limit in terms
of meeting the forecast traffic, based on the landside capacity results, is
likely to be reached within the next few years. Therefore the Western
Docks is required to accommodate the remaining forecast traffic overflow
from the Eastern Docks thereafter.
In terms of meeting the traffic overflow from the Eastern Docks, it is not
necessary for all berths in the Western Docks to be provided at once
when the capacity at the Eastern Docks is reached. The provision of the
berths could occur in three phases as and when the forecast overflow
traffic increases to levels the current berths are unable to accommodate.
Therefore the development options outlined in the sections above can
effectively be considered different phases of a single expansion
development to be embarked on over the next 30 years, in line with the
ports master plan.
For this phased implementation, Phase 1 would include the provision of a
single berth by converting the existing Hoverport fast ferry berth to aconventional double deck ferry berth (as for Option F in Section 5.4.3).
A second berth (similar to Option G2 in Section 5.4.4) would also be
provided. This involves reclamation on the northern side of the Prince of
Wales Pier creating one ferry berth in saw-tooth configuration in the
Western Docks. Following on from this Phase 2 involves the provision
of two ferry berths in jetty configuration created on the reclamation on
the northern side of the Prince of Wales Pier. This development is similar
to Option G4 (see Section 5.4.5).
The sketches showing potential phasing of conventional ferry berths inthe Western Docks are shown inAppendix C.
5.5.2 Roundabout AssessmentThe traffic performance of Limekiln and Prince of Wales Roundabouts
has been assessed for 2020 and 2034 in relation to the proposed
development of two berths at Western Docks. A number of access
options using Limekiln and Prince of Wales roundabouts were considered
and the capacities of the roundabouts were checked for each of these
scenarios.
-
7/28/2019 Dover Harbour Useful Info
33/48
Issue 2 Rev 4 18 November 2005 29
The results show, in theory, the Limekiln roundabout operates
satisfactorily in all scenarios in 2020 and is marginally over desirable
design parameters in 2034 in the AM peak on one approach for one of
the access options.
Similarly the modelling shows that Prince of Wales roundabout will be
operating below its design parameters in 2014 and after the development
of berths in the Western Docks in both AM and PM peaks. However,
capacity will be exceeded in 2034 in both AM and PM peaks in all three
access options. This means that the roundabout junction will need to be
amended or improved before 2034 with the two berth Western Docks
development scenario.
This modelling is based on the through traffic being free flowing and of
course this does not happen at present with regular queuing on the inside
lane of the roundabout. Improvements will be required much earlier at
both roundabouts if their eastbound approaches continue to be blocked
by traffic queuing back from Eastern Docks.
The introduction of the buffer area will greatly increase the practical
capacity of the roundabouts by reducing or eliminating the queuing
traffic.
-
7/28/2019 Dover Harbour Useful Info
34/48
Issue 2 Rev 4 18 November 2005 30
6 Planning Structure
6.1 IntroductionThe criteria developed for the assessment of planning issues for the
options are based on trying to ensure that the needs of relevant policy
principles are met. The principal focus is on the need to protect the
environment and heritage aspects of the site and its environs and to
ensure that future development helps to diversify and support the wider
economy of the town as a whole.
6.1.1 Strategic Planning ContextThe Planning and Compulsory Purchase Act, 2004 has fundamentally changed
the structure of plan making in the UK. Regional Spatial Strategies willreplace Structure Plans and Local Development Documents will replace
Local Plans.
The Kent and Medway Structure Plan (Deposit Plan September 2003) provides
the current strategic planning context for the Kent and Medway area.
Policy TP20 of the Structure Plandefines Dover as a Core Port, with
those in Sheerness, Thamesport and Ramsgate. This definition indicates
the safeguarding of the port function, and support for further
development, provided it meets with transport, access, design and
sustainability requirements.
The Structure Planhighlights Dovers ability to expand its current
operations within existing port boundaries, and particularly within the
Western section of the port. It also promotes the reintroduction of rail
services to the port, the upgrading of the A2 to dual carriageway, and
improved traffic management on the A20, in order to facilitate increased
activity.
The Structure Planwill ultimately be replaced by the Regional Spatial Strategy
and a consultation draft of the South East Planhas recently been publishedfor public consultation. Policies T7 and T8 support maintenance and
encouragement of further ro-ro services, niche market and short sea
services at Dover. The supporting text for these policies refers to Dover
in the following terms:
The primary focus for ro-ro services will continue to be across the
Dover Straits, using either cross-Channel ferry services operating via the
Port of Dover or shuttle services operating through the Channel Tunnel.
Restoration of a rail connection into the Port of Dover, together with
improvements to road access along the A2 corridor should be givenpriority in the medium term. In the longer term consideration will need to
-
7/28/2019 Dover Harbour Useful Info
35/48
Issue 2 Rev 4 18 November 2005 31
be given to the capacity of the road and rail corridors serving both the
Port of Dover and the Channel Tunnel and to the need for a Thames
Crossing east of Dartford.
6.1.2 Local Planning ContextThe provisions of the Dover Local Planin respect of new developments at
the port are now several years out of date and have been overtaken by
recent developments at the port and by work on the Dover Pride Vision.
The Dover Local Development Framework is currently under preparation and a
consultation document on Issues and Options is expected shortly. The
provisions of the Local Planin respect of heritage and conservation issues
are not expected to change significantly, as these reflect national planning
policy.
The Dover Pride Strategy and Action Plansets an ambitious framework for
regeneration of the town. The Strategy asserts that the local economy is
dominated by the port, which accounts for about 25% of employment in
the town, although there are few high value local jobs and its drive
through operations limit the benefits which are realised within the local
economy (staying visitors on average spend 400 as opposed to the 26
spent by day visitors). It recognises that the port is sensitive to changes in
Channel Tunnel operations and the European economy but its long term
growth prospects are positive.
One of the strategic objectives of the study relates to realisation of thepotential of port expansion and it is recognised that this could create a
variety of new opportunities for the town. It asserts that Dover could
become a true gateway port for the South East region within the East
Kent Pas de Calais sub-region. Possibilities include the development of
port related activities (such as marine and road transport instrumentation
and ship docking systems), import-export processing activities to add
value to freight which currently passes through the port (such as food
processing and packaging) and logistics activities (including groupage,
freight forwarding and transport fleet management). The Strategy asserts
that some of these activities could be located within the port itself (mainlywithin the Western Docks) but other activities would need to be located
in the Port Zone and the White Cliffs Business Park at Whitfield (100
acres of which remain undeveloped).
The Strategy also raises the possibility of the creation of a new waterfront
destination at the eastern end of the waterfront, which would create an
opportunity to relocate the marina from the Western Docks. It is unclear
what implications, if any, this would have for the operation of the Eastern
Docks and it is acknowledged that the idea needs further investigation
and testing.
-
7/28/2019 Dover Harbour Useful Info
36/48
Issue 2 Rev 4 18 November 2005 32
The Strategy also suggests that the problems of heavy through traffic
along the A20 Townwall Street between the town centre and the seafront
could be addressed in part by a strategic routing of port traffic; along the
M20 to the Western Docks and the A2/M2 to the Eastern Docks,
together with sophisticated traffic light control to pulse traffic along the
A20 to the Eastern Docks between pedestrian and local traffic
movements. This may well have implications for passing trade from
which Dover currently benefits and needs investigation.
6.1.3 EnvironmentEnvironmental changes to air and water quality and sediment movement
are an inevitable part of intensification of port uses. These are discussed
in Section 6.2 below together with any mitigation measures that should
be undertaken to relieve environmental impacts. In the assessment
criteria described in Section 6.2 below, environmental issues are
subsumed as necessary within the criteria dealing with port boundary,
reclamation, traffic and policy criteria.
6.2 Assessment CriteriaBelow is a brief description of the different criteria adopted in the
assessment criteria table. The options are evaluated qualitatively using a
five point scale as follows:
Significantly Negative
Negative
Neutral
Positive
Significantly Positive
Table 6.1 includes a number of comments that are specific to the
development options.
6.2.1 Port BoundaryThe Structure Plan focuses on the need to confine new development
within the existing port boundary. This is particularly related to the effects
on environmentally sensitive areas to the east and west of the site.
6.2.2 Reclamation, Dredging, and Marine Flora and FaunaThe ferry development includes significant land reclamation within the
port boundary and will change the view to seaward from the beach area.
Archaeological interests may also be affected but given sufficient leadtime and funding, the archaeology of the area can be fully explored.
-
7/28/2019 Dover Harbour Useful Info
37/48
Issue 2 Rev 4 18 November 2005 33
The dredging and reclamation will cause a short term increase in turbidity
and this should be carried out at a time of year when the impact on
bottom dwelling fish will be minimised. In all consideration of the marine
environment of Dover Harbour, it should be remembered that the whole
environment is artificial and it cannot be viewed in the same light as
undisturbed natural habitats.
The base of the Prince of Wales Pier is a good habitat for lobsters, hermit
crabs, edible crabs, prawns and whelks. Reclamation along this pier will
have a significant detrimental affect on these populations but this can be
compensated by recreating the same environment elsewhere in the
harbour.
6.2.3 Hydrodynamic RegimeAlterations to the current berth configuration at Western Docks will have
some effect on the hydrodynamics of the port. Modelling will have to be
undertaken to ensure that there are no unexpected effects.
6.2.4 HeritageThere are a number of listed buildings/structures and ancient monuments
within the port boundary. The way in which each structure is affected by
the development must be reviewed and agreement reached on what
actions are needed.
6.2.5 PolicyThere are a number of current policy documents which are relevant in
relation to the port. These are described in the previous introductory
section. Positive responses to these criteria are recorded by retaining
development within the existing port boundaries such as Phase 1 of the
ferry development, and increasing the provision of port specific
businesses, such as facilities for cruise services.
6.2.6 PublicThere are currently a number of public access points and amenities withinthe Port. Options are assessed on their impact on facilities such as the
water sports centres and the marina, and on access such as the public
promenade and beach, and the fishing area provided on Admiralty Pier.
6.2.7 TrafficPort traffic can have impacts both within and outside the port boundary.
Options are assessed from a strategic standpoint, looking at overall impact
on both internal features (requiring access across the swing bridge) and on
the transport network outside the Docks. This is particularly important
for the junctions along the A20, (which runs parallel to the portboundary) where there are already significant levels of traffic.
-
7/28/2019 Dover Harbour Useful Info
38/48
Issue 2 Rev 4 18 November 2005 34
6.2.8 Pollution(a) Noise Pollution
During the phased construction of the development, construction
vehicles may generate increased levels of noise. The general operation of
the berths will only slightly increase the noise levels over and above those
already existing in the Western Docks.
(b) Air Quality
Air quality monitoring currently takes place within the Port of Dover to
ensure compliance with Health and Safety Legislation and codes of
practice. If levels are dramatically increased due to the development then
the Western Docks could become an Air Quality Management Area
(AQMA). The two major sources of poor air quality are emissions from
the ships engines and generators and emissions from stationary vehicles.
The former is being addressed by the ferry operators introducing scrubber
systems on the vessels. The best way to address vehicle emissions is to
keep the traffic moving. Introducing the buffer zone is the best
approach to preventing port traffic queuing on Townwall Street.
(c) Water Quality
With the development in the Western Docks the probability of water
pollution incidents within the Western Docks water area would be
increased marginally. The water quality of the Wellington Dock will have
to be carefully monitored. There are a range of remedial techniques
available if problems are detected.
(d) Light Pollution
Levels of light pollution may increase following the completion of the
development although the replacement of older style light fittings with
modern low spill types will compensate.
-
7/28/2019 Dover Harbour Useful Info
39/48
Issue 2 Rev 4 18 November 2005
Option
Port
Boundary
Reclamation
Dredging,
Marine
Flora
andFauna
Heritage
Polic
y
Public
Traffic
Nois
ePollution
AirQ
uality
Wate
rQuality
UseofGreenland
Comments
F 0 0 - ++ + 0 - - 0 0 0 This option does not impactreclamation or development removing the fast ferry optioprovision it does not contribthe port.
G2 0 - - - + - - - - - - This option involving land rehave a significant impact on the beach front, although thireclamation. However, there Wales Pier.
G4 0 - - - + - - - - - - This option involving land rehave a significant impact on the beach front, this could hawater sports facilities on the significant impact on the listeGranville Dock and the Tidaissues.
I 0 0 0 0 + + 0 0 0 0 0 -
Assessment Key:
-- Significantly Negative- Negative0 Neutral+ Positive
++ Significantly Positive
Table 6.1: Assessment Criteria without Mitigation Measures
-
7/28/2019 Dover Harbour Useful Info
40/48
Issue 2 Rev 4 18 November 2005 36
6.3 Outline Economic ImpactThis outline economic impact of the various development options for the
Port of Dover is based upon a classification of five primary sources of
benefit/cost. These are briefly outlined below.
Construction Phase these effects relate to the benefits and
costs associated with the construction phase of the project and as
such are likely to be transitory;
Direct employment and GDP arising directly from port
operations and dependant activities (includes shipping
agents/brokers);
Indirect employment and GDP arising from suppliers to and
activities arising from port activities but not directly dependant
upon port activities;
Induced employment and GDP resulting from direct and
indirect spending and also economic activity generated by port
visitors;
Wider Economic Effects ports effect on social, economic
and physical conditions (related to attractiveness to non-port
businesses, regeneration, tourism etc).
Table 6.2 illustrates the impacts associated with each development option
described in Section 5. Port development generally will have positive
direct and indirect economic benefits, induce higher port employment and
local spend and add to the ports ability to attract clustered economic
activity.
In general, the cargo related option boosts economic benefits arising from
cargo and aids the retention of the business. The ferry development
options allow increases in ferry related economic benefits but may impact
on leisure and tourism near the Port.
-
7/28/2019 Dover Harbour Useful Info
41/48
Issue 2 Rev 4 18 November 2005
F G2 G4 I
Construction Phase Minor benefits Some benefits Few benefits
DirectFerry benefits
Fast ferry lossMore than F More than G2 Minor ferry ben
Indirect Small rise More than F More than G2 Minimal rise
Induced Will rise More than F More than G2 Will rise
Wider Economic
EffectsWill add marginally More than F More than G2 Limited
Table 6.2: Economic Impact of Development Options
-
7/28/2019 Dover Harbour Useful Info
42/48
Issue 2 Rev 4 18 November 2005 38
6.4 Planning FindingsIn general terms the planning policy context is supportive of further port
growth, provided impacts on the environment and the wider Dover area
are beneficial. However, there are some important heritage/conservation
issues which apply at the local level, and because of these those options
which imply a smaller scale of growth appear more positive in terms of
the planning assessment. However, whilst it is relatively straightforward to
identify local constraints to development, it is much harder to predict
wider economic benefits. This may require some difficult choices, given
the range of environmental and heritage issues which apply and the need
for the port to grow and adapt to changing commercial requirements.
Whilst the options may appear to have negative implications, the detailed
design of these options will have a significant effect on the overall
evaluation. For example, issues of public access and loss of amenity can
be solved through working solutions into the options. Likewise heritage
issues, whilst serious, are not an absolute constraint to future
development, but they do require that there is a clear operational need for
development, and that least damaging options have been thoroughly
evaluated and ruled out for genuine reasons. The value of heritage
buildings is important and whilst they should wherever possible be
preserved, it is important to understand that a building is better retained
in a slightly changed format, whilst providing a viable modern function,
than saved purely as an inconvenient museum piece.
The planning assessment clearly indicates that encroachment into areas
outside the current port boundary would be undesirable, particularly in
terms of environmental protection of the important habitats to both the
east and west of the port, and this issue is clearly identified by the relevant
local authorities as likely to be unacceptable.
In conclusion the options provide a range of opportunities, some of
which raise significant planning issues. However, the options do offer
ways of combining the business needs of the port with the wider needs of
the communities as a whole. In the longer term, if the port continues toexpand and large areas of new reclamation are required, the conflict with
planning policies is likely to become more pronounced.
-
7/28/2019 Dover Harbour Useful Info
43/48
Issue 2 Rev 4 18 November 2005 39
7 Conclusions
The conclusions set out below are a summary and the reader should look
at the text of the report for details of each issue: -
1. The present operation of Dover Harbour