Download - Сооружение атомного реактора EPR
-
8/6/2019 EPR
1/30
-
8/6/2019 EPR
2/30
EPRTMreactor: the path to certainty
-
8/6/2019 EPR
3/30
> EPRTM: the path to certainty Andreas Goebel3 3
1950 1970 1988 2010 2040
Generation I Generation II
PWR, BWR, PHWR, RBMK, AGRFirst prototypes
of reactors
Chooz,
Brennilis,
Kahl, MZFR
PWR, BWR
< 1,400 MWe
N4, KONVOI
1,300 to 1,500 MWe
R&D on
Innovative systems
EPR, ATMEA1,
KERENA
1100 to 1,600 MWe
Generation III+
PWR, BWR
PHWR
An evolutionary approach to Gen III+ reactors
-
8/6/2019 EPR
4/30
> EPRTM: the path to certainty Andreas Goebel4 4
A complete range of Gen III+ reactors
TM
X High power output (1600+MWe)
X Evolutionary design(Konvoi/N4)
X Construction permits inFinland and France, China2009. On-going construction
in these countriesX Low global powergeneration costs
X Outstanding safety level
XMinimal environmentalimpact
XMaximized benefit from sizeeffect
XMedium power output(1100+ MWe)
X Evolutionary design(AREVA/MHI)
X Design based on EPR andMHI model
X Outstanding safety level
XMinimal environmentalimpact
XMedium power output(1250+ MWe)
X Evolutionary design(Gundremingen referenceplant) with use of passivefeatures in some safety
systemsXOutstanding safety level
XMinimal environmentalimpact
-
8/6/2019 EPR
5/30
> EPRTM: the path to certainty Andreas Goebel5 5
Competitive
The EPR reactor: performance with certitude
Evolutionary
Safe
Proven technology based on 87 PWRs builtthroughout the world, integrating numeroustechnological innovations
Core meltdown prevention with 4 times 100% redundant safeguardsystems, mitigation of severe accidents consequences, radiological
protection, functional diversity of safety systems, robustness
against external hazards such as airplane crash
High power output (1600+ MWe), efficiency and availability, reduced powergeneration costs, extended life service
Double concrete shell designed to
withstand the impact of a largeairplane crash
-
8/6/2019 EPR
6/30
> EPRTM: the path to certainty Andreas Goebel6 6
Projects
Flamanville 3
Olkiluoto 3
Taishan 1&2
4 EPR under construction
-
8/6/2019 EPR
7/30
> EPRTM: the path to certainty Andreas Goebel7 7
Where Olkiluoto, Finland
Contract signed Dec 18, 2003
Customer Teollisuuden Voima Oy (TVO)
Supplier Consortium formed by AREVA and Siemens AG
(73% / 27%) and led by AREVA
Supply scope 1 EPR unit in turnkey construction
First Concrete Jul, 2005
Net electric output 1,600 MWe
Reactor thermal output 4,300 MWth
Target delivery date 2012
Olkiluoto 3 Fast Facts
For internal use only
The EPR Olkiluoto 3 Project
-
8/6/2019 EPR
8/30
> EPRTM: the path to certainty Andreas Goebel8 8
July 2007 FLASHBACK - General view
-
8/6/2019 EPR
9/30
> EPRTM: the path to certainty Andreas Goebel9 9For internal use only
2009 20102008
February 08Steam GeneratorBlowdown Tankinstallation
May 08Reactor
Compartment PoolFrame-work installed
July 08EDG tanks installationin Nuclear AuxiliaryBuilding
June 08Erection started:First pipe installedin Fuel Building
October 08Start of electro-mechanical activities
November 08Next-to-last double ring linerinstalled in Reactor Building
First heat exchanger liftedinto Safeguard Building
Installation of first
accumulator in ReactorBuilding
Olkiluoto 3 Milestones
January 09RPV and itshead deliveryat OL3
Temporary
Control Roomready foroperation
March 09Start of electro-mechanicalactivities in thespreading area
The EPR Olkiluoto 3 Project
May 09Reactor domedelivered on site
Completion of thecooling elementsinstallation in thecore catcher
-
8/6/2019 EPR
10/30
> EPRTM: the path to certainty Andreas Goebel10 10
Civil construction status reactor building
Reinforcement ongoing
Concreted
April 2009
July 2007
-
8/6/2019 EPR
11/30
> EPRTM: the path to certainty Andreas Goebel11 11
The EPR Olkiluoto 3 Project May 2009
OL3, the 1stof the EPR worldwide fleet
-
8/6/2019 EPR
12/30
> EPRTM: the path to certainty Andreas Goebel12 12
The EPR Olkiluoto 3 ProjectNuclear Island - May 2009
-
8/6/2019 EPR
13/30
> EPRTM: the path to certainty Andreas Goebel13 13
The EPR Olkiluoto 3 ProjectTurbine Island - May 2009
-
8/6/2019 EPR
14/30
> EPRTM: the path to certainty Andreas Goebel14 14
The EPR Olkiluoto 3 ProjectReactor Dome Delivery on site May 4
-
8/6/2019 EPR
15/30
> EPRTM: the path to certainty Andreas Goebel15 15
The EPR Olkiluoto 3 ProjectInstallations completed at the Spreading area - May 2009
3D view of IRWST and Spreading Area
Incontainment
RefuelingWater
Storage Tank(IRWST)
Spreadingarea
-
8/6/2019 EPR
16/30
> EPRTM: the path to certainty Andreas Goebel16 16
Transfer of activities from civil constructionto electro-mechanical installation
-
8/6/2019 EPR
17/30
> EPRTM: the path to certainty Andreas Goebel17 17
The EPRTMFlamanville 3 Project
-
8/6/2019 EPR
18/30
> EPRTM: the path to certainty Andreas Goebel18 18
Flamanville 3 Fast Facts
General Presentation Market and OutlookProducts and Projects
Copyright EDF March 2009
Where Flamanville, France
Contract signed Apr 11, 2007
Customer Electricit de France (EDF)
Supplier AREVA
Supply scope 1 EPR unit
- Nuclear Island Nuclear Steam Supply System (NSSS)- Nuclear Island Engineering & Procurement (NI EP)
First Concrete Dec 2007
Net electric output 1,630 MWe
Reactor thermal output 4,300 MWth
Target delivery date 2012
For internal use only
The EPRTMFlamanville 3 Project
-
8/6/2019 EPR
19/30
> EPRTM: the path to certainty Andreas Goebel19 19
The EPR Flamanville 3 ProjectView of the site May 2009
-
8/6/2019 EPR
20/30
> EPRTM: the path to certainty Andreas Goebel20 20
The EPR Flamanville 3 ProjectView of the site May 2009
COPYRIGHT EDF
-
8/6/2019 EPR
21/30
> EPRTM: the path to certainty Andreas Goebel21 21
The EPR Flamanville 3 ProjectReactor Building May 2009
-
8/6/2019 EPR
22/30
> EPRTM: the path to certainty Andreas Goebel22 22
The EPR Flamanville 3 ProjectTurbine Building May 2009
-
8/6/2019 EPR
23/30
> EPRTM: the path to certainty Andreas Goebel23 23
The EPR Taishan 1&2 Project
-
8/6/2019 EPR
24/30
> EPRTM: the path to certainty Andreas Goebel24 24
Where Taishan, China
Contract signed Nov 26, 2007
Customer Taishan Nuclear Power Company (TSNPC)
Supplier AREVA in consortium with 2 subsidiaries of CGNPC
Supply scope 2 EPR units and the materials and services to operate them:
-Nuclear Island Engineering & Procurement (NI EP)- Nuclear Steam Supply System (NSSS)- Balance of Nuclear Island (BNI)
-Supply fuel and enriched uranium for 15 years
First concrete Aug 2009
Net electric output 1,660 MWe
Reactor thermal output 4,590 MWth
Target delivery date 2013-14
Taishan 1&2 Fast Facts
The EPR Taishan 1&2 Project
2008
-
8/6/2019 EPR
25/30
> EPRTM: the path to certainty Andreas Goebel25 25
Site location
TAISHAN
Daya Bay
-
8/6/2019 EPR
26/30
> EPRTM: the path to certainty Andreas Goebel26 26For internal use only
The EPR Taishan 1&2 ProjectView of the site - May 2009
-
8/6/2019 EPR
27/30
> EPRTM: the path to certainty Andreas Goebel27 27For internal use only
The EPR Taishan 1&2 ProjectExcavation - May 2009
-
8/6/2019 EPR
28/30
> EPRTM: the path to certainty Andreas Goebel28 28
Future developments of the EPR reactor
EMIRATES
X EPR projectunderpreparation withSuez and Total
X MoU for 2 EPRreactors
INDIA
FRANCE
X 2nd EPRTM inPenly launchedin March 2009
USA
X EPRtechnologyselected by fiveutilities
X Certificationsubmitted in
Dec. 2007
X Detailed Designunderway
UK
X EPR design
pre-certificationunderway
X EPRtechnologyselected by EDFand E.ON
-
8/6/2019 EPR
29/30
We are building the new generation
for power generation
> Plants Business Unit - May 2009
-
8/6/2019 EPR
30/30