Transcript
Page 1: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

DRAPP 2012

Page 2: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

Agenda Progress Report Delivery Information WMS Stats WMS Tips and Tricks Presentation

Page 3: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

DRAPP ScheduleMilestone Goal Date Actual DateComplete Spring Flights April 15 March 30

Complete Summer Flights June 30 June 30

All Interim Imagery in WMS August 1 July 31

All Pilot Imagery DAT-Approved August 30 September 25

All Final Imagery DAT-Approved November 30

All Final Imagery in WMS December 31

Delivery of Final Imagery to Partners

January 15

Page 4: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

Details on the Final Orthos

Area 1 – Denver 6 Shipments – Majority have been DAT reviewed but not

approved yet. Area 2 – Eastern Plains

Accepted on September 4 Loaded to Final WMS on October 1

Area 3 – Mountains Last area to be processed. In progress right now. Expected to be sent for DAT by November 30

Area 4 – Weld Accepted on November 8 Loaded to Final WMS on November 19

Page 5: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

Final OrthosDAT-Reviewed Area(blue) contains 6subgroups. Four areas(79%) were sent toIntraSearch fora final time on 11/27.

The DAT-approved areas(red) are final and can beviewed in the WMS now.Metadata will be includedsoon.

Page 6: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

Details on Delivery Shipments will be in 3 Waves

40% of the Orders Delivered by December 15 80% of the Orders Delivered by December 30 100% of the Orders Delivered by January 15

Order Processing Criteria: Location of the area of interest

areas completed first will be shipped first. Extent

smaller orders will be shipped before larger orders. Funding contingencies

jurisdictions that must receive their order by a certain date to release funding will be prioritized. Orders may also be de-prioritized if the partner's paperwork is not finalized.

Page 7: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

Hard Drive Notice An external hard drive(s) containing your custom aerial

imagery order will be delivered to you as part of DRAPP 2012. This hardware has been purchased by DRCOG and may be used in future Data Consortium initiatives, including future aerial photography projects.

DRAPP 2012 participants that return the external hard drive(s) by March 29, 2013 will receive a $200 discount on the next project, if they choose to participate again. The value of this discount is more than the drive itself.

Page 8: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

WMS Stats

22 Partners have 1 user 12 Partners have between 2 and 7 users 3 Partners have over 10 users

Who’s accessingthe WMS?

37 Partners129 Users

Page 9: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

WMS Feedback How has your experience with the WMS been?

How often do you use the WMS?

Is the WMS a substitute for using the actual tiles?

What other features do you wish the WMS would offer?

What other services would you find useful?

Have you been affected by downtime?

Page 10: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

WMS Tips and Tricks Presentation

Page 11: Progress Report  Delivery Information  WMS Stats  WMS Tips and Tricks Presentation

For more information, contact Ashley Summers at [email protected] or 303-

480-6746.


Top Related