Transcript
Page 1: 1 Technical Advice from Architectural Services Department

1

Technical Advice from Architectural Services

Department

Page 2: 1 Technical Advice from Architectural Services Department

2

I. Processing of Applications

II.Consultant Appointment after Budget Approval

Page 3: 1 Technical Advice from Architectural Services Department

1. Steps of Processing 2. Drawings and Estimates3. Common Problems

3

I. Processing of Applications

Page 4: 1 Technical Advice from Architectural Services Department

1. Five Steps of ProcessingStep 1: Preliminary Assessment

Step 2: Arrangement for Joint Site Inspection

Step 3: Joint Site Inspection

Step 4: Budgetary Assessment

Step 5: Differences/Objections from Schools

4

Page 5: 1 Technical Advice from Architectural Services Department

Step 1: Preliminary Assessment EDB to complete Initial Screening.

EDB to forward to ArchSD the DSS applications in batches.

ArchSD to advise EDB of preliminary assessment.

5

Page 6: 1 Technical Advice from Architectural Services Department

Step 2: Arrangement for Joint Site

Inspection

EDB to arrange joint site inspection upon receipt of ArchSD’s preliminary assessment.

Outstanding information to be provided by the school 3 days prior to the joint site inspection.

6

Page 7: 1 Technical Advice from Architectural Services Department

Step 3: Joint Site Inspection

EDB to lead the joint inspection and decide on supportability of items as required.

Schools’ representative to answer queries raised during site walk and provide further information immediately afterwards.

7

Page 8: 1 Technical Advice from Architectural Services Department

Step 4: Budgetary Assessment by

ArchSD

Based on the available information from schools and policy decision on supportability of items from EDB, ArchSD to proceed with detailed budgetary assessment.

ArchSD to report on the technically supported amount to EDB.

8

Page 9: 1 Technical Advice from Architectural Services Department

Step 5: Differences/ Objections from

SchoolsSchools to provide justification/

substantiation in respect of each disputed item within reasonable time after receipt of EDB’s advice.

EDB/ ArchSD to further assess and decide on the final supportable level.

ArchSD to complete within reasonable time.

May repeat the above process once more, where necessary, as the final round.

9

Page 10: 1 Technical Advice from Architectural Services Department

2. Drawings and Estimates

Drawings for each application item:

1) Layout plans with dimensions and location

2) Layout plans to scale3) Highlight changes on plans

10

Drawings

Page 11: 1 Technical Advice from Architectural Services Department

Details of the proposed works items should be clear and sufficient to facilitate cost estimates

11

Estimates

ARCHITECTURAL SERVICES DEPARTMENTSUBVENTED PROJECTS DIVISION

Estimate for DSS Major Repair Works(Building Work)

Item No.

Details of Works Items (description, locations, etc.)

Work Type

Justification Qty Unit RateApplied Amount

To be completed by EDB/ArchSD

Supported Amount

($)

Sub-total ($)

Remarks

(1)Waterproofing works for main roof, roof and upper roof floor (remedial and improvement):

                 

1.1Demolition of existing roof finishes and waterproofing membrane

    1 Sup. 0 0      

1.2Cement sand screeding to fall     1 Sup. 0 0      

1.3Laying of new waterproofing membrane

    1 Sup. 0 0      

1.4Laying of new polystrene insulation board

    1 Sup. 0 0      

1.5Paving of new roof tiles     1 Sup. 0 0      

1.6Pond test     1 Sum 0 0      

      Sub-total and carried to summary

    0      

Page 12: 1 Technical Advice from Architectural Services Department

3. Common problems

1. Unclear or ambiguous description of the scope of works

2. Estimates combined into a lump sum without relevant breakdowns

12

Page 13: 1 Technical Advice from Architectural Services Department

3. Inclusion of non/above-standard items

4. Inclusion of furniture and equipment (F & E) items

5. Slope repair works

13

Page 14: 1 Technical Advice from Architectural Services Department

Example:

Arch SD’s comment: Layout plan with indication of the exact

locations of the air-conditioner and detailed work scope (e.g. the cooling capacity and type of air-conditioner) should be provided.

Description Unit Unit Rate

Amount

Replacement of existing air-conditioners in the Offices

5nos $4,100 $20,500

14

1. Unclear or ambiguous description of the scope of works

Page 15: 1 Technical Advice from Architectural Services Department

Proper Submission:Provide clear description of the scope of

works

15

Description Unit Unit Rate

Amount

(i)To replace the existing air-conditioners in the Staff Room on 2/F with window type A/C units (cooling only with cooling capacity @5.3kW) c/w all necessary supports, condensate drip pan, power supply connection and condensate drain pipe connected to nearest drain

3nos $4,500 $13,500

Page 16: 1 Technical Advice from Architectural Services Department

Proper Submission:Provide clear description of the scope of

works (cont’d)

16

Description Unit Unit Rate

Amount

(ii)To replace the existing air-conditioners in the General Office on G/F with window type A/C units (cooling only with cooling capacity @3.5kW) c/w all necessary supports, condensate drip pan, power supply connection and condensate drain pipe connected to nearest drain

2nos

$3,500 $7,000

Total $20,500

Page 17: 1 Technical Advice from Architectural Services Department

Submit relevant layout plans to indicate locations of the air-conditioners.

17

Page 18: 1 Technical Advice from Architectural Services Department

2. Estimates combined into a lump sum without relevant breakdown

Example:

Arch SD’s comment: Schools/AP should provide the cost

breakdown for waterproof coat.

Description Unit Unit Rate

Amount

Application of roof waterproof coat

1sum

$890,000

$890,000

18

Page 19: 1 Technical Advice from Architectural Services Department

Proper Submission:Schools should provide roof warranty to show expiry of guarantee period.

19

Page 20: 1 Technical Advice from Architectural Services Department

20

Description Unit Unit Rate Amount RemarksDemolition of existing roof finishes and waterproofing membrane

1000 m2 $150 $150,000 Water seepage and weathering of roof-top.

Cement sand screeding to fall

1000 m2 $200 $200,000

Laying of new waterproofing membrane

1000 m2 $250 $250,000

Laying of new polystrene insulation board

1000 m2 $100 $100,000

Paving of new roof tiles

1000 m2 $180 $180,000

Pond test 1 sum $10000 $10,000

Total $890,000

• Example:

Page 21: 1 Technical Advice from Architectural Services Department

3. Inclusion of non/above-standard itemsExamples:

CCTV System;Air-conditioning system/units in

Dining Hall, etc.

Proper Submissions:Schools should follow the standard

provision according to EDB’s requirements

21

Page 22: 1 Technical Advice from Architectural Services Department

4. Inclusion of furniture and equipment ( F&E) items

Examples:Audio/ Visual equipment;LAN cable and computing equipment;Overhead projector, etc.

Proper Submission:F&E items should not be included in

the works.

22

Page 23: 1 Technical Advice from Architectural Services Department

5. Slope repair works

23

Page 24: 1 Technical Advice from Architectural Services Department

DSS Application for non-recurrent assistance – Slope Repairs (SR)

24

Page 25: 1 Technical Advice from Architectural Services Department

25

Types of Works Not Supported under Non-recurrent Assistance Routine slope maintenance works (e.g. Repair cracked / damaged chunam / shotcrete surface, remove unplanned vegetations, clearance of blocked drainage channels / catchpits, repair damaged channels / catchpits, clear blocked weepholes in retaining walls etc.)

Engineer Inspection (EI) of slopes / retaining walls located within school boundaries to be carried out by Registered Geotechnical Engineers

Page 26: 1 Technical Advice from Architectural Services Department

26

Types of Works / Studies Supported under Non-recurrent Assistance

Stability Assessment by Registered Geotechnical Engineer + Slope stabilization works Preventive maintenance works

• Soil slopes – improved surface protection on slope and upslope, surface drainage channels, subsoil drainage, soil nails etc.

• Rock slopes – concrete buttress, rock dowels, steel wire meshes, scaling or dentition etc.

Page 27: 1 Technical Advice from Architectural Services Department

27

II. Consultant Appointment after Budget Approval

1.Procedures for Consultant Selection

2.Number of Tenderers 3.List of Tenderers 4.Expression of Interest (EOI)5.Consultant’s Invitation

Document 6.Evaluation of Consultant’s

Proposal

Page 28: 1 Technical Advice from Architectural Services Department

28

1. Procedures for Consultant Selection • Guidelines on Consultant Selection

for Architectural and Associated Consultancy Services

• Guidelines on Consultant Selection for Quantity Surveying Consultancy Services

Page 29: 1 Technical Advice from Architectural Services Department

29

2. Number of Tenderers

• Invite at least 5 consultants of appropriate band

• If less than 3 valid tender returns are received, the tender exercise is abortive.

• Therefore, schools preferably invite 6-8 consultants

Page 30: 1 Technical Advice from Architectural Services Department

30

3. List of Tenderers

• From the list of approved Architectural and Associated Consultants

• If estimated fee more than HK 1.43 million > Band 1

• If estimated fee not more than HK $1.43 million > Band 2 and Band 3

Page 31: 1 Technical Advice from Architectural Services Department

31

• Website: http://www.archsd.gov.hk> Consultants & Contractors >(a) List of Consultants of AACSB OR (b) List of Band 3 Architectural Consultants

(a) List of Consultants of AACSB>Who have been included?>Choose: Category: “Architectural Category/ Quantity Surveying Category”; and Band: “Band 1/ Band 2”>Search

Page 32: 1 Technical Advice from Architectural Services Department

32

(b) List of Band 3 Architectural Consultants >Yes and Proceed>(1)The Associated of Architectural Practices (AAP) and (2) The Hong Kong Institute of Architects (HKIA)

Page 33: 1 Technical Advice from Architectural Services Department

33

4. Expression of Interest (EOI)

• To ensure obtaining 6-8 consultant’s proposals, EOI should be carried out.

• Invitation letter>Scope of the Works>Estimate Cost of the Works>Period of Time for Services

• Sample for reference

Page 34: 1 Technical Advice from Architectural Services Department

34

Page 35: 1 Technical Advice from Architectural Services Department

35

Statement for Expression of Interest to Tender

Date : ____________

To : [name and address of NGO]

Fax No. : [ ]

Dear Sir/Madam,

Architectural and Associated Consultancy Services for

[TITLE OF PROJECT]

I *wish/do not wish to be invited to tender for the captioned Services.

Yours faithfully,

________________________________

(Authorized Signature for and on behalf of the

Consultant)

Name of Consultant : __________________

* Delete as appropriate.

Page 36: 1 Technical Advice from Architectural Services Department

36

Annex

Architectural and Associated Consultancy Services for

[TITLE OF PROJECT]

(1) Scope of the Works

Item No. Work Description Location

1 External texture paint to wall and soffit All elevations and Staircases 2 Replacement of existing waterproofing works Main roof and upper roof 3 Demolish existing floor finish, relay waterproofing and floor tile finish for

toilets

Boy's and Girl's toilets 1/F to 7/F

4 Repaint anti-mould emulsion paint to internal wall All Classrooms and Offices 5 Replacement of existing door and frames including new ironmongery and

painting

Rooms 105, 106, 203, 302, 403, 405,

502, 602, 603 6 Replace existing all pipes of drainage and plumbing system entire building 7 Replacement of existing air conditioners with 3 new 22900 BTU

window-type air conditioners

Chemistry Laboratory 6/F

8 Supply and install wiring, G.I. conduit and trunking for:

a. 14 nos. lighting point and 6 nos. power point per classroom(total 24

classroom and 20 special room)

b. 5 nos. lighting point per toilet (total 16 toilets/changing rooms).

c. 60 nos. lighting point and 20 nos. power point for Hall.

d. Wiring from main switch room to sub-main switch room and MCB

board.

Old wing of school premises

(2) Estimated Cost of the Works

Approved project cost $

Preliminaries $

_______________________

$

Contingencies $

________________________

Estimated Cost (in September 2011 prices) $

Page 37: 1 Technical Advice from Architectural Services Department

37

5. Consultant’s Invitation Document• Refer to Guidelines

> “NGO Note” in blue colour

• Technical and Fee Proposal>Appendix 4 for Technical proposal

• Fee Proposal Only (Annex I)>(optional) for estimated fee not more than HK $1.43 million

Page 38: 1 Technical Advice from Architectural Services Department

38

6. Evaluation of Consultant’s Proposal

• Technical Assessment and Approval

• Commence Technical and Fee Assessment after EDB’s Approval of Technical Assessment

Page 39: 1 Technical Advice from Architectural Services Department

39

Questions & Answers

Page 40: 1 Technical Advice from Architectural Services Department

40

Thank You


Top Related