7An-Najah National UniversityCivi l Engineering Department
Management engineeringprepared by : Mariam Al-Qarow
Hala Harb Amani Saleh
Submitted to: Dr. Barraq JumaaWelcome to our presentat ion
![Page 2: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/2.jpg)
7
What is a Project?
is a work eff ort made over period of time to create a unique
product, or a service. & because it has a start and a fi nish, it is
also called a temporary eff ort or endeavor .
![Page 3: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/3.jpg)
7
* Pro ject L i fecyc le
f rom the beg inning o f the pro ject to the end , i t s go through steps such:1- defi ning the project object ives2- Planning the work to achieve those object ives 3- performing the work4- monitor ing and control l ing al l those steps careful ly 5-c losing the project after receiving product acceptance .
![Page 4: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/4.jpg)
7
![Page 5: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/5.jpg)
7* Project management
Its the usage of knowledge, skills, and tools to manage a project from start to fi nish with the goal of meeting the project requirements, and its divided to main 9 issues which are :
![Page 6: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/6.jpg)
7
1-Managing scope : it includes the processes required to ensure that the project includes all the work required to complete the project successfully
2- Managing Time : The project schedule is the organization of all project activities by time and by their logical dependencies and each with a start date and a finish date.
![Page 7: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/7.jpg)
7
3-Managing Cost : includes the processes involved in planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget
![Page 8: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/8.jpg)
74-Managing Human Resources :
processes required to coordinate the human resources on a project, such processes include those needed to plan, obtain, orient, assign, and release staff over the l i fe of the project .
![Page 9: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/9.jpg)
7
5- Managing Risk : identifi cation and treatment of these r isks. I ts object ive is to add maximum sustainable value to al l the activi t ies of the organization
6-Managing Quality : "Qual i ty" refers to the abi l i ty of product to satisfy both stated and impl ied needs requirements
![Page 10: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/10.jpg)
7
7-Managing Integration:
The need for integration in project management becomes evident in situations where individual processes interact, and the picture below samurais the whole process
![Page 11: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/11.jpg)
7
8-Managing Communication : Any project requires good communicat ions to manage day-to -day act iv it ies and ensure success of the project
9- Procurement managing:
includes the processes required to acquire goods and services from outside the performing organization.
![Page 12: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/12.jpg)
7
C a s e s t u d y Pa r t t w o
S h o r t D e s c r i p t i o n
a l - mo q a t a ’ a l o c a t e s i n Tu l ka re m c i t yTo t a l a re a o f t h e b u i l d i n g e q u a l 42 65 .9 3 m 2 a n d c o n s i s t o f fi v e fl o o r co n t a i n k i t c h e n , re ce p t i o n a n d d o rm i t o r y.
![Page 13: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/13.jpg)
Description Unit
No. of floor NO. 5
Basement floor area m2 840.6
Ground floor area m2 842.62
1st floor area m2 834.83
2nd floor area m2 831.07
3rd floor area m2 831.07
Stair area m2 85.73
![Page 14: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/14.jpg)
7
Objective
The purpose of our study is to obtain the fi nal cost, and duration
for al-moqata’a building and information are shown below .
![Page 15: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/15.jpg)
71-WBS
![Page 16: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/16.jpg)
7
2- Quant i ty and durat ion for each act iv i ty
Example : i n t e rna l p l a s te r i ng f o r t he ( ba s ement fl o o r )
Q ty. = 1 7 0 0 m 2
Du ra t i o n = Q ty / p ro duc t i v i t y ( 3 ma s on = 1 2 0 m 2 / d )
= 1 7 0 0 / 1 2 0 = 1 3 day
![Page 17: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/17.jpg)
73-Total cost
description unit Qty. Unit price(NIS)
Tot.(NIS)
Internal plastering
M2 1700 29 49300
![Page 18: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/18.jpg)
4- check design using sap
D.L= 0.5 ton/m2 L.L= 0.6 ton/m2
The design appear to be ok
![Page 19: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/19.jpg)
7
5- Analysis of the project
using primavera 6.1 Calendar: 6day work/ week
![Page 20: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/20.jpg)
7
6- Result
Total project cost = 7314479 NIS
Profi t = 30% from total cost
Project duration 248 work day
![Page 21: 7 An-Najah National University Civil Engineering Department Management engineering prepared by : Mariam Al-Qarow Hala Harb Amani Saleh Submitted to: Dr](https://reader035.vdocuments.net/reader035/viewer/2022070415/5697bf901a28abf838c8dc88/html5/thumbnails/21.jpg)
7
Earned value
analysis
ACWPBCWPCV = 7318479 - 8167433
= -848954 NIS
CPI = BCWP / ACWP = 7318479/8167433 = 0.89 < 1 over budget