April 5, 2007
Networks Integration Management Office
Mission Support Process
Networks Integration Management
Office; Code 450.1
Page 2NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
Network Integration Management Office Functions
The Network Integration Management Office (NIMO) provides its spacecraft and scientific customers with a complement of mission
services. The group provides best value tracking and data acquisition options, assistance with mission-unique communications requirements, and assistance in requirements definition.
The NIMO provides Principal Investigators and Mission Formulation Managers with options and planning assistance to effectively meet the
mission tracking and data acquisition (T&DA) needs. The NIMO also supports the mission throughout the life cycle for its T&DA needs - from trade studies and cost analysis during the formulation phase, to project
management during development and operations. In addition, the NIMO provides Network Integration Managers (NIM) with the ability to secure
contract vehicles and services to implement and operate their mission most effectively.
Page 3NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Personnel & Assignments
Direct Civil ServantsLeslie Ambrose – Space Science
Mark Ambrose – Agreements & Reimbursable Manager
Jim Bangerter – Human Space Flight
Evette Brown-Conwell – ELV
Dick Harris – Contracts
Al Levine – Loading & Feasibility
Lynn Myers – Earth Sciences
Tammy Wang – Resource Analyst
Matrixed Civil ServantsJohn Weiss – Estimation
Dick Nefzger – Video
YY Bae – Compatibility
Chris Schwartz – L&F & ELV
Page 4NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
Networks Integration Manager (NIM) Assignments
Designations: (C) Proposed Funding Cancellation; (D) Demo; (E) Engineering; (H) JSC Lead; (J) JPL Lead; (K) KSC Lead; (M) MSFC Lead; (P) Post-Science; (X) Information only; (Z) Pre-Formulation; * DAS candidate
Science Mission Directorate Space Operations Mission Directorate - Human Space Flight -
Jim Bangerter 301-286-7306
Space Sciences Leslie Ambrose/301-286-7767 [email protected]
Earth Sciences Lynn Myers/301-286-6343
Space Ops Mission Directorate Evette Conwell
301-286-9809 [email protected]
Operational International Space Station (Core(H)_Utilization)
(M) MeteoSat-7 (H) MeteoSat-8 (MSG-1) (H) Space Transportation System (H)
Implementation ATV (ESA (H)) HTV (JAXA) (H)
Formulation CEV (M) (study)
ARES-1
Space Ops Mission Directorate Mark Ambrose
301-286-7433 [email protected]
Non-Reimbursable - Implementation SBR (F-15 Aircraft) (D) (E) SBR (NSR-Terrier MK70) (D) (E)
Reimbursable - Formulation
Note: Mission name in ITALICS (no PSLA generated)
Operational ACE Balloons Project Chandra XRO (J) CHIPsat (UNEX-1) Cluster-II FAST (SMEX-2) FUSE (MIDEX-0) GALEX (SMEX-7) GeoTail Gravity Probe-B HST IMP-8 Polar
RHESSI (SMEX-6)
Rossi XTE SAMPEX (SMEX-1) (P) SOHO Spitzer (SIRTF) (J) SWAS (SMEX-3) (E) Swift* (MIDEX-3) TIMED (STP) TRACE (SMEX-4) WIND WIRE (SMEX-5) (P) WMAP (MIDEX-2)
Implementation AIM (SMEX-9) C/NOFS (CINDI)* GLAST* IBEX (SMEX-10) LRO SDO Solar-B (M) STEREO (STP) (J) TACSat-2 (Roadrunner)
TASS Demo (E) THEMIS (MIDEX-5)
Formulation Constellation-X (Z) GEC (STP) (C) (Z) GM-RBM JWST (J) MMS (STP) WISE (MIDEX-6)
Operational ACRIMSAT (J) CALIPSO CHAMP COBE (E) EO-1 EOS-Aqua EOS-Aura EOS-IceSat EOS-Terra ERS-2 GOES (9 thru 13) GRACE-1, -2 Jason-1 (J) Landsat-5, -7 NOAA-15, -16, -17 -18 Orbview-2 QuikScat
RadarSat-1 (J)
SAC-C SciSat-1 SORCE TOMS/EP TRMM
Implementation Glory GOES-O, -P NOAA -N Prime NPP OCO SAC-D/Aquarius
Formulation GOES-R GPM* NPOESS-1
Reimbursable - Implementation Atlas DoD (ELV) Atlas ER (ELV) (Lockheed) Atlas WR (ELV) (Lockheed) DARPA/Orbital Express (Boeing)* H-IIA ETS VIII (ELV) (JAXA) Minotaur (OSP SLV ELV) P-3 (USNavy/DoD) Pegasus (ELV) (OSC) Sea Launch (Boeing) SELENE (JAXA) Textron/Minuteman III (USAF)
Reimbursable - Formulation MDA (DST) MDA (LeClair)
Non-Reimbursable - Operations Delta NLS (K)
Atlas NLS (K) Non-Reimbursable - Implementation Demosat MPE SOAREX (D)
Non-Reimbursable - Formulation
Page 5NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Access Methods
ProjectsProposal Teams
Telephone E-mail Walk in
NIMO
Page 6NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
External Interface to the Infrastructure
ESCDGSFC
Spac
e N
etw
ork
Gro
und
Net
wor
k
Luna
r Net
wor
k
NIS
N
Flig
ht D
yn. F
ac.
Dee
p Sp
ace
Net
NIMO
NA
SA
Non
-NA
SA NASA
Page 7NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Major Process Steps
Customer & Code 450
agree to work together
GSFC Code 450 Network Integration ManagementMajor Steps
Define requirements
Configure
Test
Provide services
Evaluate
START
END
Formulation
Implementation
Operations
Page 8NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Major Process Steps Details - Example
Receive/compile high-level customer
requirements
START
Create new or revise existing
MOA (if needed)
Preliminary feasibility assessment
Capableof meeting
req’ts.?
Negotiate with customer to refine
requirements
Yes
No
Yes
Customer requests network services
2 5 2 3
22
1
Conduct preliminary feasibility
assessment
Feasible? Negotiate requirements
Reach satisfactory agreement?
No
NoYes
6
6
2
1§ Prepare RF ICD§ Assess loading§ Assess coverage§ Prepare initial link
budgets (ELV)
6
8 3
Analyze requirements
8 6
DOCUMENTS
Memorandum of Agreement (MOA)
RFICD
Need MOA?
Needed for reimbursables, exchange of svcs., or collaboration
between orgs. or agencies
Yes
No
Receive funds (reimbursable missions only)
Military Interagency Purchase Request
(MIPR) or Purchase Order (PO); WBS
2
2
Reimbursable?
Yes
2
Formulation
2A 2B
NASA customer?
Yes
ANo
A
No
1
2
1
1
Coverage, Analysis, &
Loading Report
2
21
2C
2 NIMO Network Integration Manager
4 NENS Compatibility Test Engineer
5 PAAC II Agreements Coordinator
6 Network Loading & Scheduling
PROCESS LEGEND
7 NENS Network Operations Manager
8 RF Interface Manager
1 Customer
3 NENS Mission Commitment Engineer
9 PAAC II Support
S Service Providers
4
2
2
Code 450 Configuration-Controlled
Report
DOCUMENT LEGENDCustomer-Supplied
NENS-Controlled
1
23
4
Updated: 12/1/06
※ ※
Page 9NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Mission Process Products
Memorandum of Agreement
Visibility and Loading Analysis - 1
Project Support Level Agreement
Visibility and Loading Analysis - 2
Networks Requirements Document
Networks Requirements Review
Radio Frequency ICD
Compatibility Test
Plan
Test
Quick Look Report
Final Report
Compat. Test Review
Customer Integration Test
Plan
Testing
Network Operations Support Plan
Customer Data Flows & Simulations
Visibility and Loading Analysis - 3
Mission Operations Readiness Review
Mission Operations
Post Launch Report/Lessons Learned
The NIMO mission development process exists, and is constructed, to assure, to
the maximum extent possible, communications connectivity and data
delivery to every mission on every contact.
Page 10NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Process Timeline
ID Task Name Duration Start Finish Predecessors
1 Start 0 days Mon 1/1/07 Mon 1/1/07
2 RF Link Analysis 4 wks Mon 1/1/07 Fri 1/26/07 1
3 Feasibility Assessment 1 2 wks Mon 1/29/07 Fri 2/9/07 2
4 MOA 0 days Thu 3/1/07 Thu 3/1/07 2,3
5 Project CDR 0 days Fri 2/9/07 Fri 2/9/07 2,3
6 DMR 0 days Fri 2/9/07 Fri 2/9/07 2,3
7 PSLA 4 wks Mon 8/6/07 Fri 8/31/07 6
8 RF ICD 1 12 wks Mon 6/11/07 Fri 8/31/07 5
9 Feasibility Assessment 2 2 wks Mon 2/18/08 Fri 2/29/08 8
10 NRD 44 days Mon 3/3/08 Thu 5/1/08 6,8,9,711 Draft 4 wks Mon 3/3/08 Fri 3/28/08
12 Review (NRR) 0 days Fri 3/28/08 Fri 3/28/08 11
13 Update 1 wk Mon 3/31/08 Fri 4/4/08 12
14 Approve 0 wks Thu 5/1/08 Thu 5/1/08 13
15 Compatibility Test 175 days Fri 5/2/08 Thu 1/1/09 8,9,1016 CTV Test Plan 2 wks Fri 5/2/08 Thu 5/15/08
17 CTV Testing 2 wks Tue 10/21/08 Mon 11/3/08 16
18 Compatibility Test Report 4 wks Fri 12/5/08 Thu 1/1/09 17
19 RF ICD 2 (DCN) 4 wks Fri 1/2/09 Thu 1/29/09 15
20 Customer Integration Test 142 days Fri 1/2/09 Mon 7/20/09 1521 Customer Integration Test Plan 4 wks Fri 1/2/09 Thu 1/29/09
22 Customer Integration Testing 12 wks Tue 3/31/09 Mon 6/22/09 21
23 Customer Integration Test Report 4 wks Tue 6/23/09 Mon 7/20/09 22
24 NOSP 4 wks Mon 7/6/09 Fri 7/31/09 20FF
25 MORR 0 wks Fri 7/31/09 Fri 7/31/09 24
26 Launch 0 days Tue 9/1/09 Tue 9/1/09 25
27 Lessons Learned/Post-Mission Report 3 wks Mon 10/12/09 Fri 10/30/09 26
1/1
3/12/92/9
3/28
5/1
7/319/1
Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22006 2007 2008 2009 2010
Page 11NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
Backup
Page 12NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Process Flow (cont.)
DOCUMENTSImplementation
Establish contract (PSLA) & project
schedule
§ Complete RF ICD
Execute compatibility
test
3
2 3
Decline service
2
Reach satisfactory agreement
?2
Yes
No
4
END
Customer provides detailed
requirements1
9
2A 2C
Networks Requirements
Document (NRD)
Project Service Level Agreement
(PSLA)
1
1 27 8
2B
1
New capability?
No
Coordinate implementation of
new capability
Yes
2 NIMO Network Integration Manager
4 NENS Compatibility Test Engineer
5 PAAC II Agreements Coordinator
6 Network Loading & Scheduling
PROCESS LEGEND
7 NENS Network Operations Manager
8 RF Interface Manager
1 Customer
3 NENS Mission Commitment Engineer
9 PAAC II Support
S Service Providers
S
2
Code 450 Configuration-Controlled
Report
DOCUMENT LEGENDCustomer-Supplied
NENS-Controlled
1
234
2
Compatibility Test Report
Compatibility Test Plan
3
4
2 3
2
Assign priority
1 6
S1
9
9
Create NRD(due L-1 year)
2 39
1S
Plan compatibility test to
demonstrate RF compatibility &
capability
Generate quick look report
Prepare Compatibility Test
Report
Review test results
2 3 4 8
4
4
3Updated: 12/1/06
Page 13NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO Process Flow (cont.)
※※ ※※
Operations Launch and/or commence operations
Closeout
END
2 3
7 § Assess lessons learned
§ Prepare post-mission report (ELV only)
§ Submit final invoice (reimbursable only)
9
DOCUMENTS
Lessons Learned report
Post-launch report (ELV only)
2 NIMO Network Integration Manager
4 NENS Compatibility Test Engineer
5 PAAC II Agreements Coordinator
6 Network Loading & Scheduling
PROCESS LEGEND
7 NENS Network Operations Manager
8 RF Interface Manager
1 Customer
3 NENS Mission Commitment Engineer
9 PAAC II Support
S Service Providers
3 S
S
Code 450 Configuration-Controlled
Report
DOCUMENT LEGENDCustomer-Supplied
NENS-Controlled
1234
44
Perform customer
integration test
Configure customer & NIMO data & systems
Yes
Config. test successful/complete?
Resolve configuration
issues
No
Yes
1
3
Re-test
2 31
37
7
7
4
Validate (Operations
Readiness Review, other reviews as
required)
7
Prepare NOSP
7
9
9
S
SS
S 7 S 1 32S
7 S
(May be parallel activities)
Capability/compatibility confirmed?
Negotiate with customer to refine req’ts., equipment,
methods
No
2 3 4
2 34 8
1
Operations Readiness Review
(ORR) Package
Network Test Report
Network Test Plan
3
4
Customer reviews
1
2
Network Operations
Support Plan (NOSP)
2
3
Updated: 12/1/06
Page 14NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO PSLA Contents (Present)
Section A. Customer Information
Section B. Customer Requirements and Standard Services
B.1 GSFC Networks/Data Services
B.1.1 Ground Network Services
B.1.1.1 Customer Requirements
B.1.1.2 Services Provided
B.1.2 Space Network (SN) Services
B.1.2.1 Customer Requirements
B.1.2.2 SN Data Formatting and Interface
B.1.2.3 Services Provided
B.1.3 Customer Integration and Test
B.1.4 Satellite Laser Ranging (SLR) Services
B.1.5 Radio Frequency (RF) Interface Control Document (ICD)
B.2 Deep Space Network (DSN) Services
B.3 Flight Dynamics Services
B.3.1 Customer Requirements
B.3.2 Services Provided
B.4 Range Services – Not Applicable
B.5 NASA Integrated Services Network (NISN) Services
Section C. Unique Customer Requirements for Non-Standard Services
Section D. Service and Schedule Summary
D.1 Funding Responsibility
D.2 Estimated Services for Future Years
Section E. Projected Documentation Set
Page 15NIMO MSR (September 1 – September 30, 2006)
NETWORKS INTEGRATION MANAGEMENT OFFICE
NIMO PSLA Contents (Future)
SECTION A. Customer Information
SECTION B. Customer Requirements And Standard Services
B.1 GSFC Networks/Data Services
B.1.1 Ground Network Services
B.1.2 Space Network Services
B.1.3 Customer Integration And Test
B.1.4 Satellite Laser Ranging (SLR) Services
B.1.5 Radio Frequency (RF) Interface Control Document (ICD)
B.2 Deep Space Network (DSN) Services
B.3 Flight Dynamics Services
B.4 Range Services
B.5 NASA Integrated Services Network (NISN) Services
SECTION C. Unique Customer Requirements For Non-Standard Services
C.1 AFSCN Requirements
SECTION D. Service And Schedule Summary
D.1 Funding Responsibility
D.2 Estimated Services For Future Years
D.2.1 Project Schedule
SECTION E. Network Integration Documentation Set