Download - Assignment 3 Unit 21Kyle Barrass
![Page 1: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/1.jpg)
Assignment 3 Unit 21 Kyle Barrass
Presentation of a Construction Project
![Page 2: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/2.jpg)
First Stage of the Construction Building
• The first step was to design a drawing of the building to give the client an idea of what he wanted.
![Page 3: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/3.jpg)
First Stage of the Construction Building
• The client decides on what he wants.
![Page 4: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/4.jpg)
First stage of the construction Building
• Before the building was even started there was a Gant chart make to know what was going to happen, when it was going to happen and how long it should take.
![Page 5: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/5.jpg)
Designing the Building
• After the design on the building was chosen I designed a mini version of the timber frame.
![Page 6: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/6.jpg)
Designing the Building
• Before the brick walls started the timber frame flooring was put into place.
![Page 7: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/7.jpg)
Designing the Building
• After the mini model of the timber frame was done the work on the foundations had already been done so work on the brick and block walls was started.
![Page 8: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/8.jpg)
Designing the Building
• The work on the building was set back down to the bad weather, it was set back by a few weeks.
![Page 9: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/9.jpg)
Designing the Building
• As the brick walls had been held back the timber frame walls were being put together.
![Page 10: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/10.jpg)
Designing the Building
• After the timber frame walls were built the work on the window frames and door frames started.
![Page 11: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/11.jpg)
Designing the Building
• The Gant chart had to be changed as the bad weather set the building back by a few weeks, as you can see in the photo below.
![Page 12: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/12.jpg)
Designing the Building
• As you can see the brick walls had been kicked down by someone coming onto the site, so the brick and block building was set back even more.
![Page 13: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/13.jpg)
Designing the Building
• Here are the students putting the plywood on the timber floor.
![Page 14: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/14.jpg)
Designing the Building
• The timber framed walls were put up and as you can see we ran into a little problem that was easily solved.
![Page 15: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/15.jpg)
Designing the Building
• The first timber roof trust was built and the only thing that needed changing was the length of the overhang.
![Page 16: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/16.jpg)
Designing the Building
• The plywood was put onto the timber walls and the roof trusts were constructed with more overhang.
![Page 17: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/17.jpg)
Designing the Building
• The work on the brick and block building was started again and the block work was started on the timber and block building.
![Page 18: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/18.jpg)
Designing the Building
• The rest of the roof trusts were put in place and then the ply wood was put in place.
![Page 19: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/19.jpg)
Designing the Building
• The work on the tiling being done and the rest of the brick and block building is being done at the same time.
![Page 20: Assignment 3 Unit 21Kyle Barrass](https://reader035.vdocuments.net/reader035/viewer/2022062518/5681449f550346895db15b8d/html5/thumbnails/20.jpg)
Summary
• Timber frame construction was erected quicker than traditional building
• Adverse weather had little impact on timber frame construction
• Quality issues with some of the timber walls and roof construction – to improve inspection off-site