Transcript
Page 1: Barranca Median Asphalt Patch Back - SOCCCD...Barranca Parkway Access Road IRVINE VALLEY COLLEGE South Orange County Community College District Bi-Weekly Progress Update Through November

Barranca Parkway Access Road

IRVINE VALLEY COLLEGE South Orange County Community College District

Bi-Weekly Progress Update

Through November 15, 2016

PROJECT STATUS:

• The irrigation controller was installed.

• The mow curb along both sides of the access road was placed.

• The asphalt patching was competed on Barranca.

• Potholing was complete at the Shadow Oaks entry to locate the existing utilities.

• Scheduled completion date: January 19, 2017. Project currently on schedule.

• Project is 70% complete overall.

Barranca Median Asphalt Patch Back

Page 2: Barranca Median Asphalt Patch Back - SOCCCD...Barranca Parkway Access Road IRVINE VALLEY COLLEGE South Orange County Community College District Bi-Weekly Progress Update Through November

Mow Curb Placed Along Access Road

Page 3: Barranca Median Asphalt Patch Back - SOCCCD...Barranca Parkway Access Road IRVINE VALLEY COLLEGE South Orange County Community College District Bi-Weekly Progress Update Through November

Irrigation Controller was installed

.

Upcoming Activities:

• Install planting material

• Install traffic signal foundations

• Place ramps at the access road entrance along Barranca


Top Related