BEST MANAGEMENT PRACTICES PLAN FOR FUGITIVE DUST
Greenwood Aggregates Company Limited Violet Hill Pit > Town of Mono, ON
PreparedFor:GreenwoodAggregatesCompanyLimited
205467CountyRoad109Amaranth,OntarioL9W0V1
PreparedBy:TRINITYCONSULTANTSONTARIOINC.
885DonMillsRoad,Suite106Toronto,ONM3C1V9
416‐391‐2527
January2018
TrinityProject177201.0051
PreparedBy: ReviewedBy:
ChrisScullion,B.E.Sc.ManagingConsultant
KarinaEKenigsberg,M.Sc.,P.Eng.SeniorConsultant
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. i
REVISIONRECORD
Date Revisions/Comments ReviewedBy: ApprovedBy:
June2016 DRAFTBMPPforFugitiveDust C.S./R.S. S.G
January2018 FINALBMPPforFugitiveDust C.S./K.K. S.G.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. ii
TABLE OF CONTENTS
TABLE OF CONTENTS
1. INTRODUCTION 1
2. SOURCES OF FUGITIVE DUST 2 2.1.OverviewofPitOperations....................................................................................................................................2 2.2.InventoryofFugitiveDustSources......................................................................................................................2
3. MEASURES TO CONTROL OR MINIMIZE FUGITIVE DUST 3 3.1.PavedRoadsandEntranceWays..........................................................................................................................3 3.2.UnpavedRoads...........................................................................................................................................................3 3.3.WinderosionofExposedStockpiles...................................................................................................................4 3.4.AggregateCrushing,Screening&WashingPlants..........................................................................................4 3.5.TruckLoadingandTransportation.....................................................................................................................4 3.6.WindErosionofExposedFaces.............................................................................................................................4
4. IMPLEMENTATION 5 4.1.Schedule.......................................................................................................................................................................5 4.2.ImplementationPlan................................................................................................................................................5
5. INSPECTION AND MAINTENANCE 6 5.1.Maintenance................................................................................................................................................................6 5.2.IdentificationofProblems......................................................................................................................................6
6. MONITORING AND RECORD KEEPING 7
7. RESPONSE TO COMPLAINTS 8
8. CONCLUSION 9
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 1
1. INTRODUCTION
ThisBestManagementPracticesPlanforFugitiveDust(BMPP)hasbeenpreparedfortheGreenwoodAggregatesCompany Limited (Greenwood) proposed Violet Hill Pit (the Pit) to be located on Part Lots 30, 31 and 32,Concession 4 in the Township ofMono, County of Dufferin, Ontario. The BMPP is a detailed document thatidentifiesfugitivedustsourcesanddescribesmeasurestobeusedtocontroldustemissionstotheatmosphere.Theprimaryairemissionassociatedwithpitoperationsisanticipatedtobeparticulatematterreleasedintheformoffugitivedust.Sourcesoffugitivedustcanincludetrafficfromon‐sitehaulroutes,aggregateprocessing,recycling,andhandling,andnaturalreleasesoccurringfromexposedstockpilesandgravelfaces.Tolimitthetransferofdusttosurroundingproperties,theoperatormusttakeallreasonableactionstoensurethatfugitivedustemissionsareminimizedusingbestmanagementpracticesassociatedwiththeindustry.TheobjectivesofthisBMPParethereforeto:
ProvideanoverviewoftheoperationsatthePit; Identifypotentialsourcesoffugitiveemissions; Outlinemaintenanceandinspectionprocedures; Provideasummaryofcontrolmeasuresthatareorshallbeimplemented; Provideanimplementationscheduleforthecontrolmeasures Illustrate how on‐going compliance is ensured through the use of a monitoring and record keepingprogram;and
Detailtheemployeetrainingprogramforfugitivedustcontrolprocedures.Once implemented, the BMPP will serve to minimize dust emissions from the Pit, thereby minimizing oreliminatingimpacttonearbypropertiesandtolocalecology.The Site Foreman shall be responsible for ensuring that the control measures identified in this plan areimplemented.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 2
2. SOURCES OF FUGITIVE DUST
2.1. OVERVIEW OF PIT OPERATIONS
TheprimaryoperationsatthePitwillconsistofaggregateextraction,aggregatecrushing,aggregatescreeningand/orwashing,aggregatestockpilingandaggregateoff‐siteshipping.
2.1.1. Aggregate Extraction
Extraction can take place in the north and south Pits. Excavationwill occur by stripping the deposit with abulldozerandscrapersorhighhoe.Therewillbenoblastingordrillingonthesite.
2.1.2. Aggregate Processing and Recycling
Aggregateprocessingandrecyclingcanincludecrushing,screeningand/orwashingplants.Crushingplantscanconsistofprimaryandsecondarycrushersandscreeningplantscanconsistofprimaryandsecondaryscreeners.
2.1.3. Shipping
Afront‐endloaderloadshighwaytrucksforshipmentofaggregateoff‐site.TrucksareweighedatthescalehousebeforeleavingthePit.Thereisone(1)entrancetothePit,whichwillbelocatedoff3rdLineE.The500‐metre(m)section of the haul road from the entrance to the Pit will be paved and recycled asphalt will be laid on theremainderoftheinternalroute.
2.2. INVENTORY OF FUGITIVE DUST SOURCES
TheoperationswithinthePit,andtheassociatedpotentialsourcesoffugitiveemissions,consistofthefollowing:
Sitepreparation(i.e.topsoilstrippingandbermconstruction):o Loading/unloadingofaggregateso Trafficonunpavedroads
Aggregateextraction:o Loading/unloadingofaggregateso Trafficonunpavedroads
Crushing,ScreeningandWashingPlantso Loading/unloadingofaggregateso Trafficonunpavedroadso Conveyortransfers
Othergeneralsite‐widesourcesoffugitiveemissions:o Trafficonpavedandunpavedhaulroadsfromshippingandgeneralsiteactivitieso Winderosionofactiveandinactivestockpileso Loading/unloadingofaggregatesfromgeneralsiteactivities
Characterizationofdust:Chapter11oftheUSEPAAP‐42documentcharacterizesfugitivedustfromstonecrushingandaggregatehandlingasthree(3)formsofparticulatematter:PM,PM10andPM2.5.PMisrepresentativeoftotalsuspendedparticulatematter.PM10andPM2.5istherespirablefractionofparticulateandcanhaveanimpactonhumanhealth.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 3
3. MEASURES TO CONTROL OR MINIMIZE FUGITIVE DUST
3.1. PAVED ROADS AND ENTRANCE WAYS
Theinternalhaulrouteextendingfromthepublicroadtothescalesonthesitehavebeenpavedandrecycledasphaltwillbelaidontheremainderoftheinternalroute.RefertoAppendixAforlocationofhaulroutes.Thefollowingmeasuresshallbeusedtocontrolandminimizefugitivedustfromtheinternalpavedroads.
ThePitwillhaveone(1)pointofentry/exit,whichwillbepavedandwellmaintainedduringoperations.Theentry/exitpointisextending500meastof3rdLineE.
ThePitshallhavethecapabilitytospraywaterorotherapproveddustsuppressantsasdeemednecessarybytheSiteForemanonpavedsurfaceson‐site,aswellasroadsnearthesiteentranceasneeded.
Theactualapplicationrateshallvary,dependingonsurfacemoistureconditionsandtrafficlevels,andshallbe triggeredwhenever thescaleoperatoror SiteForemanobserves trailersproducinga trailingcloudofdustgreaterthan1/3ofatrailerlength.
HaulroutesshallbemaintainedduringPitoperations,toensurethatloosefinematerialonthehaulroutesurfaceisminimized.
To prevent spillage and air entrainment during transport of aggregates, the aggregate loads shall becoveredduringtransportontheinternalunpavedroads.
Anyspillageormaterialdepositedonthepavedroadsshallberemovedpromptly. Regularsweepingofthepavedroadswillbeconductedasrequired,atthediscretionoftheSiteForeman,toensurethatvisibleloosefinematerialofthehaulroadsurfaceisminimized.
Trucksandothermobileequipmentshallreducespeedasnecessarilytoreducetrailingdustclouds.Themaximumspeedwillbe35km/hr.
3.2. UNPAVED ROADS
TheinternalhaulroutesattheSitebeyondthepavedrouteareunpaved.Thefollowingmeasuresshallbeusedtocontrolandminimizefugitivedustfromtheinternalunpavedroads:
Atruckortrailer‐mountedtankwillbelocatedonsiteatalltimesandshallbeequippedwithaspraybartodeliverwaterevenlyoverthehaulroutesurface.
AsthediscretionoftheSiteForeman,analternativeMOECC/US‐EPAapproveddustsuppressantmaybeusedshouldwaterproveinsufficienttocontroldustemissions.Environmentallyhazardouscompoundssuchaswasteoilshallnotbeusedasadustsuppressant.
Dustsuppressantsupply(wateroralternative)shallbeavailabletoallowthetankertrucktofillandapplythefullpayloadeachhour,ifnecessary,duringdryconditions.
Theactualapplicationrateshallvary,dependingonsurfacemoistureconditionsandtrafficconditions,andshallbetriggeredwhenevertheSiteForemanorscaleoperatorobservestrucksproducingatrailingcloudofdustgreaterthan1/3ofatrailerlength.
Haulroutesshallbemaintained(i.e.re‐graded)approximatelymonthlyduringMaytoOctober,toensurethatloosefinematerialonthehaulroutesurfaceisminimized.
Trucksandothermobileequipmentshallreducespeedasnecessarilytoreducetrailingdustclouds.Themaximumspeedwillbe35km/hr.
Theinternalroadsshallbeclearlydelineatedtolimittraffictotheestablishedhaulroadsthathavebeenmaintained. Limiting the trucks away from unmaintained areas of the site is intended to minimizedisturbanceofunmaintainedareas.
Topreventspillageandairentrainmentduring transportofaggregates, the truckscarryingaggregateloadsshallbecoveredduringtransportonthepavedandunpavedroads.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 4
Disturbedareasofunpavedroadsshallbestabilizedtotheextentpossiblewithrollersorothersimilarequipment.
3.3. WIND EROSION OF EXPOSED STOCKPILES
Extractionshallbereducedorsuspendediftheconditionoftheactiveextractionfaceisdryanddustyandthewindisdirectedtowardaresidenceataspeedsufficienttocausewidespreadvisibleerosionoftheopenface.
Watershallbeappliedtostockpilematerialthataredryanddustywhenthewindisdirectedtowardaresidenceataspeedsufficienttocausewidespreadvisibleemissions.
Stockpilesshallbemaintainedtoavoidsteepsidesorfaces. Disturbanceofstoragepilesshallbeminimizedwherefeasible.Foractivestockpiles,thedisturbedareashallbeminimizedtotheextentpossible.
3.4. AGGREGATE CRUSHING, SCREENING & WASHING PLANTS
WheretheSiteForemandeemsnecessary,theprocessingplantsshallbeequippedwithawaterspraysystem. The actualwater application rate shall vary, being adjusted as needed to reduce visible dustemission.
Waterforthespraysystemwillbeprovidedfromthesumporsettlingpond. The spray‐barswill be triggeredwhenever the Site Foreman or scale operator observes visible dustemissions.
Wherepossible, theheightof liftsanddischargedistancesto thetopof thestockpilewillbekept toaminimum.
Conveyor drop heights shall be minimized to the extent possible to reduce spillage and providewindbreak.
Conveyorbeltsshallbecleanedperiodicallytoremoveentrainedmaterial.
3.5. TRUCK LOADING AND TRANSPORTATION
TruckloadingwillbesuspendediftheSiteForemanorscaleoperatorobservesthematerialtobedryanddustyandthewindissufficienttocausewide‐spreadvisibleemissionswithplumesdirectedtowerstheresidences.Thehighestpointofthematerialloadedintoatruckshallnotexceedthevehiclestraywallsunlessitiscovered.
3.6. WIND EROSION OF EXPOSED FACES
Extractionshallbesuspendediftheconditionoftheextractionfaceisdryanddustyandthewindissufficienttocausewide‐spreadvisibleerosionoftheopenfacewithplumesdirectedoff‐site.AggregatestockpileswillbelocatedonthePitfloorincloseproximitytotheextractionfaceorinthestockpilearea.Windforecastsshallbemonitoredregularlyforheavywindsduringthisphaseoftheoperationtoanticipatetheneedforthesemeasuresandallowfornextdayplanning.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 5
4. IMPLEMENTATION
4.1. SCHEDULE
AllcontrolmeasuresaretobeinplacepriortoextractioncommencinginthePit.ControlmeasuresshallremaininplacesolongasthePitremainsinoperation.
4.2. IMPLEMENTATION PLAN
ThefollowingoutlineshowtheBMPPshallbeimplemented,includingtrainingoffacilitypersonnel:
TheBMPPshallbekeptonfileatthescalehouse; Trainingonnewandexistingoperatingproceduresshallbeprovidedtorelevantstaff; Refreshertrainingshallbeprovidedataminimumofonceevery2years; ThePitmanagementshallcommunicatetheBMPPtoresponsiblesupervisors,whoshallensurestaffarefollowingoperatingproceduresdefinedintheBMPP;
TheSiteForemanshallberesponsibleforensuringtheBMPPisfollowed; ManagementshallensureBMPPisreviewedannually;and ThestaffshallfollowtheBMPPprocedures.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 6
5. INSPECTION AND MAINTENANCE
5.1. MAINTENANCE
Thefollowingoutlinesthedetailsregardingtheinspectionandmaintenanceproceduresthatshallbeemployedatthesite:
Thewaterspraysystemfortheprocessingplantwillbeinspectedwheninuse; HaulroutesshallbemaintainedonaregularbasisaspreviouslyindicatedinSection3.1and3.2;and, Haulroutesshallbeinspecteddaily,ormoreregularlyasdictatedbywindconditionsandtrucktraffic.Thehaulroutesshallbemaintainedonaregularbasis,aspreviouslyindicated,basedontheinspection,thewindconditionsandthetrucktraffic.
Priortotheoperationoftheprocessingplants,thewaterspraysystemsshouldbeinspected,andpondwaterlevelsshallinspectedtoensureadequatewatersupply;
5.2. IDENTIFICATION OF PROBLEMS
TheSiteOperator shallbe informedofany issues thatarise from inspectionsperformed. Operationsmaybecurtailedifdustcontrolequipmentisnotadequatelyperforming.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 7
6. MONITORING AND RECORD KEEPING
Visual inspection for dusty conditions in areas of emission sources identified in the BMPP shall occur at aminimumoftwicedailyduringdryweatherandonceperdayotherwise.Recordsshallbemadeeachtimethefollowingeventsoccur:
Dustsuppressantisappliedtopavedandunpavedhaulroutes; Unpavedhaulroutesaremaintained; Waterspraysareusedattheprocessingplant; Wetorvacuum‐sweeperarrivesandcleanspavedsurfaces; Heavydustplumesareobserved;and, Acomplaintisreceived.
Allrecordswillbekeptonsiteinalogbook.AsampleComplaintRecordReportlogformcanbefoundinAppendixB.
Intheeventofadustcomplain,thecomplaintwillbedirectedtotheSiteSupervisor,whowillfollowtheprotocolsoutlinedintheGreenwoodComplaintsProceduresdocument,whichiskepton‐site.
ThePitwillenactanactionplanconcerningitsoperationsinresponsetoacomplaint,asdetailedinthefollowingsection.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 8
7. RESPONSE TO COMPLAINTS
Complainantsarerequestedtoidentifythelocationoftheincidentaswellasthetimeofdaythatitwasdetectedandanyotherrelevantinformation.AlldustcomplaintsshallbeforwardedtotheSiteForemanandrecordedinthelogbookasidentifiedintheprevioussection.
TheSiteForemanshallensurethefollowingactions:
Conductasitesurveytoidentifysourcesofvisibledustcontributingtothecomplaint; Createarecordofthissurvey; Determineweatherconditions(bothcurrentandatthetimethatthecomplaintwasmade);and Reportonallon‐siteactivitiesatthetimethecomplaintwasmade.
IftheinformationcollectedfromthesurveyproceduresindicatesthatPitisnotthesourceofthedustcomplaint,thecomplainantshallbenotifiedofthisfinding.Documentationsupportingthisresponsemechanism(sitesurveyrecordandwindstationreadingsatthetimeofthecomplaint)shallbeprovidedtothecomplainantuponrequest.The Site Foreman or other Pit staff shall respond to all complaintswithin 24 hourswith a phone call to thecomplainant.
If it is determined that the complaint is related to Pit activities, the following response procedures shall befollowed,intheorderprovidedbelow:
Level1–InspectionandCorrectionofOperations
The Site Foreman shall ensure that all elements of the BMPP are being followed. Control measures such assprayingorwateringshallbeincreasedoroperationsmaybecurtailed,asrequired.
Level2–ReviewoftheBMPP
IftheLevel1responsedoesnotadequatelyresolvethesourceofthedustcomplaint,theBMPPshallbereviewedforadditionalcontrolmeasures.
Level3–Operationalmodifications
If theLevel2 responsedoesnot adequately resolve the sourceof thedust complaint, thePit shall commit tomakingphysicalchangestothefacilitytoaddressthesourceofthedustemissions.Suchchangesmayinclude,butarenotlimitedtoadditionalenclosures,relocationofequipment,oradditionalpaving.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. 9
8. CONCLUSION
This document presents a Best Management Practices Plan (BMPP) to control and minimize fugitive dustemissionsfromthePitoperations. ThePitwillimplementandabidebythesemeasurescontainedintheplan.Record keeping, inspections and oversight will ensure an effective dust mitigation program throughout thelifespanofoperationsatthePit.
TheBMPPwillservetominimizealldustemissionsfromthePit,sothattherisktohumanhealthandthepotentialforoffsitenuisanceisalsominimized.
ThisBMPPwillbekepton‐siteatalltimesinthescalehouseforreference.
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. A
APPENDIX A: SITE PLAN
Greenwood Aggregates Company Limited – Violet Hill Pit | Best Management Practices Plan for Fugitive Dust Trinity Consultants Ontario Inc. B
APPENDIX B: COMPLAINT RECORD REPORT LOG
GENERAL INFORMATION - COMPLAINTANT
Source of Complaint: Residential or Other:
Name: Mr. Mrs. Ms.
Telephone No.: ( ) (home/cell) ( ) (work)
Email Address:
Home/Business Address:
City: Postal Code:
Other Comments:
COMPLAINT INFORMAION
Date (Month/Day/Year) : / / Time: From: AM / PM
To: AM / PM
Complaint Type: Dust Noise Other :
Address or Nearest Cross Street of Observed Incident:
Description:
WEATHER CONDITIONS DURING TIME OF COMPLAINT
Wind Direction: (Blowing From)
Wind Speed: Calm Moderate Strong
Cloud Cover: Clear Partly Cloudy Overcast
Condition: Clear Fog Precipitation
Temperature: °C or Humid Dry
OPERATIONS DURING TIME OF COMPLAINT
Description of Operations (production activity & recorded events during/before complaint period) :
MITIGATION EFFORTS & COMPLAINT RESPONSE
Date of Response (Month/Day/Year) : / /
Response Summary : Attached Copy of Written Response
Corrective Action Taken :
REPORT PREPARATION
Report Prepared by:
Contact: Phone ( ) Email
Date (Month/Day/Year): / /
COMPLAINT RECORD REPORT
Violet Hill Pit, Town of Mono
Version 1.0