User Manual
Project System
TCS Limited TCS Client Confidential
Page 1 of 26
USER MANUAL
New Service Connection Project
Submitted to
WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD
By
TATA CONSULTANCY SERVICES LIMITED
VVEERRSSIIOONN:: 44..00
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 2 of 26
DOCUMENT HISTORY
Version Document Name Date Author Reviewed BY
1.0 User Manual – New Connection Project
12.11.2015 Subhabrata Bhandari
Sourav Mukherjee
2.0 User Manual – New Connection Project
26.11.2015 Abhishek Sarkar
Sourav Mukherjee
3.0 User Manual – New Connection Project
07.12.2015 Abhishek Sarkar
Sourav Mukherjee
4.0 User Manual – New Connection Project after the incorporation of Modified Cable Rate Matrix
28.12.2018 Sajal Mukherjee
Project Name Document Name Document Location WBSEDCL ERP User Manual – New Connection Project
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 3 of 26
TABLE OF CONTENTS
1. FUNCTIONALITY ............................................................................................................................................. 5 2. LOG ON TO SAP EASY ACCESS ....................................................................................................................... 5 3. PROCESS FLOW DIAGRAM (NEW CONNECTION) ............................................................................................ 10 4. NEW SERVICE CONNECTION DATA MAINTENANCE ...................................................................................... 14 5. IMPORTANT POINTS TO REMEMBER ............................................................................................................... 25
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 4 of 26
LIST OF FIGURES
Figure 1 : Log on to SAP ................................................................................................................ 5 Figure 2 : SAP Easy Access ........................................................................................................... 6
Figure 3 : Command Box in SAP Easy Access .............................................................................. 6
Figure 4 : T-Code in Command Box .............................................................................................. 7
Figure 5 : Add T-Codes to Favorites .............................................................................................. 8 Figure 6 : Manual entry of a transaction ......................................................................................... 8 Figure 7 : Favorites List .................................................................................................................. 9 Figure 8 : Initial Screen ................................................................................................................ 14
Figure 9 : Supply Code Search Help ............................................................................................ 15 Figure 10 : Order Issue Date Search Help .................................................................................... 15
Figure 11 : Selection Screen ......................................................................................................... 16 Figure 12 : View New connection Data Maintenance ................................................................. 16 Figure 13 : Enter Necessary Fields .............................................................................................. 17
Figure 14 : View of Execution cost and WBSEDCL Contribution ............................................. 17 Figure 15 : Overview of New Connection cable rate .................................................................. 20
Figure 16 : View of project structure ........................................................................................... 21
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 5 of 26
1. Functionality
User can create New Connection Project for both Pole and Non Pole cases.
2. Log on to SAP Easy Access
a) User logs in to SAP using logon credentials.
Figure 1 : Log on to SAP
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 6 of 26
b) After successful login, the following screen is displayed.
Figure 2 : SAP Easy Access
c) In SAP, any screen is associated with a Transaction Code (T-Code) using which the
user can open the screen from SAP Easy Access screen.
Figure 3 : Command Box in SAP Easy Access
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 7 of 26
d) The highlighted box in the following screen, is called 'Command Box', where user
types the T-Code and presses 'Enter'.
Figure 4 : T-Code in Command Box
e) Favorites Menu and its use User can also mark a Transaction Code (T-Code) as 'favourite'. By this, user will not be required to remember and type the T-Code each time, he/she logs in. To add a T-Code as favourite, user needs to right click on 'Favorites' button and choose 'Insert Transaction' option.
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 8 of 26
Figure 5 : Add T-Codes to Favorites
A pop-up window appears, with label "Manual entry of a transaction", where user will type the T-Code and presses 'Enter'.
Figure 6 : Manual entry of a transaction
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 9 of 26
User will find the T-Code in his/her Favorites list, where he/she can 'double click' to execute the T-Code directly. User does not require to type the T-Code in Command box.
Figure 7 : Favorites List
User can mark all the frequently used T-Codes as Favorite like this.
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 10 of 26
3. Process flow Diagram (New connection)
Mark Connection Type (ZNCD)
Pole Connection Non Pole
Connection
Cost Estimation (ZBOM)
Create Document
(CV01N / CV02N)
Inspection and
Installation Confirmed
CRM sends Work
Orders to ERP (ZNCD)
A B
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 11 of 26
Appropriation
Request (IMA11)
Create Project
Structure (CJ20N) (NPC/3433102/11/15/01)
Auto-Create Project
Structure (CJ20N) (NCN/3433102/11/15)
A B
Enter Service
Specifications for
Activities (CJ20N)
Enter Purchasing
Group / Org for
Activities (CJ20N)
Project Structure
Completed
(CJ20N)
Create CWIP (AS01) and
Define Settlement Rule
(CJ20N / CJ02)
Release WBS
(CJ20N)
Auto-create
Purchase
Requisition (PR)
(CJ20N)
Create Purchase
Order (ME21N)
including relevant Tax
C
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 12 of 26
Release Purchase
Order (ME29N)
C
Pole Connection
Project
Non Pole
Connection Project
Distribute / Issue /
Consumption
of
Materials
(ZMDC,
ZMREQ,
ZMREQA,
ZRMDC,
ZMIGO,
ZMCON)
Acceptance of
Service (ML81N)
Confirmation of
Activity (CN25)
Crate Invoice
against PO
(MIRO)
D
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 13 of 26
D
Project Monitoring
i. Physical: CN41
ii. Financial: CJI3
Actual Cost
Settlement to
CWIP (CJ88)
Change WBS
status as TECO
(CJ20N)
WBS Report for Assets
(ZNCR) i. Consumer Contribution Asset
ii. WBSEDCL Contribution Asset
Fixed Asset
(AIAB)
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 14 of 26
4. New Service Connection Data Maintenance
a) The New Connection details (Work Orders) are automatically entered into ERP
system.
b) User can view the same using T-Code ZNCD.
Transaction Code
ZNCD
Figure 8 : Initial Screen
c) User can open New Connection data using 2 optional selection input i. Supply Code, ii. Order Issue Date Range
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 15 of 26
d) Screenshot of Search help for Supply Code and Date Range given below.
i) Supply Code
Figure 9 : Supply Code Search Help
ii) Order Issue date
Figure 10 : Order Issue Date Search Help
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 16 of 26
e) User will select relevant Supply Code / Order Issue Date, and the following screen appears.
Figure 11 : Selection Screen
f) Now user will mark the Cable Type, Connection type and other relevant details.
For the Applications with Work Order Date before 01.01.2019-
1) After entering the details in the Selection screen, click on Execute Button
(F8), and the following screens appears.
Figure 12 : View New connection Data Maintenance
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 17 of 26
2) User will enter Inspection date, Pole/Non Pole Indicator and Cable Type from
Search Help Box.
Figure 13 : Enter Necessary Fields
3) Click on Save button.
4) The Execution Cost field is auto-populated for Non-Pole and Pole Underground cases, based on predefined Cable Rate Matrix.
Figure 14 : View of Execution cost and WBSEDCL Contribution
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 18 of 26
For the Applications with Work Order Date beyond 01.01.2019-
1. After entering the details in the Selection screen, click on Execute Button
(F8), and the following screens appears.
2. User will enter Inspection date. User will choose the Connection Type and Cable Type from Search Help.
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 19 of 26
3. User must choose valid combination of Connection Type (Marked as New) and Cable Type.
4. User needs to specify the Cable Length (Note: Cable length can be entered maximum up to 10 meter for Drop16(D16) and Drop 25(D25) Services and maximum up to 27 meter for the other connection types.)
5. User need to specify the additional charges if there is any. (INR 53 as
inspection charge for 3Phase Connections and INR 50 as mobilization charges for 1Phase Connections)
6. Click on Save button.
7. The Execution Cost field is auto-populated for Non-Pole cases, based on predefined Modified Cable Rate Matrix.
Execution Cost = Cable Length * Rate per meter of Cable + Service Connection Cost + Additional Cost (If any).
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 20 of 26
g) The Cable Rates are maintained via T-code – ZCBLRATE.
Figure 15 : Overview of New Connection cable rate
The modified Cable Rates are maintained via T-Code – ZNEWCBLRATE
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 21 of 26
h) There will be a batch program run periodically to create the project for non pole with project code as follows:
1. Non Pole Connection
i) User can view the project structure via T-code CJ20N. (For Non Pole)
Figure 16 : View of project structure
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 22 of 26
j) Each WBS(s) element will be tagged to individual work order (CRM).
k) User can find all user fields of Activity fetched automatically from CRM provided data.
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 23 of 26
l) User will specify Service Specification for each Activity manually. Execution cost per Activity must be equal to respective Service Gross Price
m) Pole Case: User need to select “POLE” indicator in “ZNCD” n) Execution cost will not updated in ZNCD automatically only for “Pole
Underground” cases based on available Rate maintained at ZCBLRATE. Note: Procurement and posting process same as NON TURNKEY project.
2. Pole Connection
a) User will manually create Appropriation Requests manually /supply code/month/year.
b) The Project Profile will be New Connection Profile.
c) The Coding mask will be as follows:
d) User can create multiple appropriation requests too based on number of new connection requests.
e) User will choose Appropriation Request Type from ‘9’, ‘10’, ‘11’ based on DOP.
NPC/XXXXXXX/00/00/00 (NPC/SUPPLYCODE/MONTH/YEAR/SERIAL
)
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 24 of 26
f) Once the appropriation request is approved, user will initiate the Project from IMA11.
g) The WBS Description should follow the structure as follows:
WBS ID WBS Description
NPC/31221200/04/15/01-01 NPC/31221200/04/15/01/90017 (where 90017 is the CRM Work Order Number)
For Pole Connection Projects, user must provide the WBS Description carefully. Only ‘/’ must be given as delimiter and it must replace WBS Element serial no. with Work Order Number.
h) There will be a single WBS per Work Order.
i) Each WBS will have 2 Networks (for Material and Service respectively)
a) New Connection Material (Non Procurement Profile), b) New Connection Service (Procurement Profile)
j) Rest of the process will be same as Non Turnkey project.
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 25 of 26
5. Important points to remember
1. User will mark only Installed Connections.
2. User need to generate Purchase Requisition (PR) and thereby PO (Tax will be included during PO creation) for New Connection activities; Issuance of PO using ME21N for New Service Connections is to be discontinued from 26-Nov-2015 (PS-PM Go Live).
3. While marking ZNCD, user must observe if Execution Cost field is populated (after SAVE) for Non Pole and Pole Underground (PUG) cases.
4. User must notify and raise a ticket if Execution Cost is not populated (except Pole Connections)
5. Non Pole Connections marked on day 1 in ZNCD will be reflected in Project Structure
(CJ20N) on day 2.
6. Only Non Pole connections with valid Execution Cost will be picked up by system and included in project structure automatically.
7. User must maintain a list of applications, while preparing Cost Estimation for a number of Pole Connections, to prevent duplicate entry of consumer details during forthcoming Estimations / Projects.
8. Cancelled Applications will be flown to ERP with Work Order Status 'C' and Issued Applications will have marking as 'I'.
9. User, if fills up details of a Non Pole Cancelled Application, it will be picked up by system and will Lock (AALK: Account Assignment Locked) the corresponding Activity.
10. If a cancelled application, picked up by system and the Corresponding activity is not found in project structure, it will be identified as an erroneous entry and ERP_STATUS field will become 'E' for such entry.
11. If a WBS (Non Pole) has already been released by user for payment processing and a pending application of the same Work Order arrives to ERP; system will pick it up and create a New Network under the same WBS automatically.
12. User needs to release the Network to create a New PR for pending applications of the same Work Order (WBS).
-
User Manual
Project System
TCS Limited TCS Client Confidential
Page 26 of 26
13. User can always take advantage of PR Collection Indicator to group / segregate number of activities and collect PR as per convenience.
14. There will be a single WBS per (CRM) Work Order. It is recommended NOT to Release the WBS until all applications are captured under it.
15. There will be a parent WBS for any New Connection Project.
16. Parent WBS ID / Description will be same as Project ID.
17. Each Child WBS description will contain the Work Order Number at the end, prefixed by forward slash (/). For Pole cases, users have to ensure the same manually. Example: NPC/3314200/11/15/01/90060
18. For Pole Projects, user will create 2 Networks under same WBS (Work Order):
Material Network (Non Procurement Profile): User will create an Internal Activity and tag all required materials into it.
Service Network (Procurement Profile): User will create individual Service Activity for each consumer and fill up Service Specification Gross Price as per Erection Work Costing.
19. For Non Pole projects, Meters and other materials (if applicable) to be issued from store creating manual reservation; those will not be tagged to Project Structure.
20. For New Connection projects, there will only 2 Fixed Assets: a. Consumer Contribution Asset b. WBSEDCL Contribution Asset
21. For the Applications with Work Order Date Before 01.01.2019 user needs to select the Old Connection Type and Cable Type. Execution cost will be populated based on the old cable rate matrix (T-Code - ZCBLRATE).
22. For the Applications with Work Order Date Beyond 01.01.2019 user needs to select the NEW Connection Type (Marked as New) and Cable Type. Additionally user needs to specify the length of the cable and Additional Cost (If there is any). Execution cost will be populated based on the new cable rate matrix (T-Code- ZNEWCABLERATE). The logic for the calculation of the execution cost will be – Execution Cost = Cable Length * Rate per meter of Cable + Service Connection Cost + Additional Cost (If any).