Transcript
Page 1: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Steve Boshier

Chairman ARISEG

Rail Suppliers Forum 2013

Page 2: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Agenda New Zealand

Project Overview

Re-Signalling Project Scope

Fact Finding Missions

Key Challenges for the Industry

Project Delivery

Lessons Learnt

Conclusions

Page 3: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

New Zealand Location

2,000km East of Australia

The Land of the Long

White Cloud

All Blacks Middle Earth

NZ Population

4.4m

Auckland 1.5m

Page 4: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

New Zealand 3,898km • Railway Corridor

149 • Tunnels

1,700 • Bridges

506km

• Electrified Network

• 95km DC Wellington

• 411km AC NIMT

Page 5: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Project Overview Auckland Rail Network – 175km

•Newmarket- Britomart

•Newmarket- Morningside

•Newmarket-Westfield

•Penrose- Onehunga

•Morningside- Swanson

•Westfield

•Otahuhu

•Britomart- Westfield

•Otahuhu- Manukau

•Wiri- Otahuhu

10 Sections

of Line

Page 6: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Project Overview

It started with

DART

$500m Duplication

6 car trains and 10 minute

frequency

Newmarket junction station

Page 7: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Project Overview

• Approximately 175 track km Papakura to Swanson

• 25 kV AC System

• Blocks of work

• Civil works (access roads, bridges, track, poles & bases)

• Traction

• Grid power supply from Transpower

Electrification

Page 8: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Project Overview

• A system serving yesterdays needs (An old system)

• 80 Year old points machines

• Much of it life expired

• Mixed technologies old & new

• Failures & delays

Signalling

Page 9: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Re-Signalling Project Scope

• A Train Control System

• An immunised 25kV system

• Additional signalling to improve capacity

• 6 Trains per hour on each route (peak)

• 20 Trains in/out per hour at Britomart

• To increase safety - Automatic Train Protection (ATP)

Re-Signalling

Page 10: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Re-Signalling Project Scope A Signed Signalling Contract in Place

Leading the Charge

Page 11: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Fact Finding Missions April 2007

May 2007

June 2007

Nov 2007

April 2008

April 2009

ARIC/Austrade Mission

ARIC/Austrade Mission

Government Budget Released

ARIC/Austrade Mission

ARIC/Austrade /ICN/Kiwi Rail Presentations

ARIC/Austrade Mission

(EOI Issued)

Page 12: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Fact Finding Missions

Competition Customer

Contractors Suppliers

Manufactures Trading

Conditions

To Understand the Local Market

Page 13: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Fact Finding Missions

Will you make $

Is it the right

market

What's Involved

Is it

doable?

Page 14: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Key Challenges for the Industry

Lack of local NZ rail experience

• Design Resources

• Construction

• Supply

Program

Rugby World Cup

September 2011

Page 15: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Key Challenges for the Industry Equipment to be imported & Freight Logistics

Page 16: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Key Challenges for the Industry Local Presence to Perform the Work

Page 17: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Project Delivery

• EOI Issued 22nd April 2008

• EOI Closed 2nd June 2008

• EOI Evaluation Period June/July 2008

• Short List invited to tender 7th August 2008

• Tender Briefing 12th August 2008

• Tender Closed 6th October 2008

• Preferred Organisation Negotiation 18th November 08

• Contract Signed 20th February 2009

Tender Timetable

10 Months

Page 18: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Project Delivery • Agreed with the Customer Program

• Agreed (Modular/ATP) Solution

• Australia & New Zealand Design

• Australia & New Zealand Construction

• Australia & New Zealand Testing

• New Zealand Commissioning

Page 19: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Lessons Learnt

Time Investment

From 2007 to

contract award 2009

Regular Visits to Auckland

• To understand customer needs & objectives

• To get to know the project site – large rail network

• To develop key relationships – Client, Contractors, Suppliers & Support

• To identify whom to team with & why

Page 20: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Lessons Learnt The value of Industry & Government Organisations

Page 21: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Lessons Learnt • Do you establish a Local Office?

Taking a long term view

• Providing local support Customer Training

• Warranty/Maintenance Support Maintenance

Support

• Having the right level of spare parts available Spare Parts Supply

Knock on Opportunities

Page 22: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Conclusions

• Is achievable

• Takes a level of effort up front

• You need to leverage off local services available

• Requires a time & financial commitment

• Use of local resources, suppliers & manufacturers

• Transport Logistics – Time to get it there & cleared

Export Work

Page 23: CASE STUDY: The Auckland re-signalling project – Lessons for the rail contracting sector

Questions


Top Related