Chattanooga-Hamilton County/N. GA Transportation Planning Organization
2040 Regional Transportation Plan
Leadership SymposiumMarch 13, 2013
![Page 2: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/2.jpg)
TPO Structure & Plan Requirement
Chattanooga-Hamilton County/North Georgia Transportation Planning Organization (TPO)
-29 member regional policy board (19 governments)
- staffed by the Regional Planning Agency
- new plan every four years with 20+ year horizon
- federally funded planning and implementation
- legislative requirements including air quality standards
TPO Planning Area
![Page 3: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/3.jpg)
Public Outreach
26 events/activities:
89 @ 1st Leadership Symposium
113 @ committee meetings
25 @ stakeholder discussion groups
76 @ topic-based workshops (climate change, transit, and call for projects)
58 @ public workshops
+ 451 @ questionnaire
812 interactions
In just six months…
![Page 4: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/4.jpg)
Information Gathering/Synthesis
neighborhood traffic safety
traffic flow
road conditionbuildroads
bikeways
sidewalks
25% Over CapacitySlightly Over Capacity
2010
Transit Gaps
![Page 5: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/5.jpg)
Plan Goals
Adopted 2040 Goals: A Scaled & Balanced Approach
Within Community Community to Region
Region to Region
Investment NeedsThat Support
•Local, multimodal connections and access to community resources
•Advance livability and quality of life principles
Investment NeedsThat Support
•Strategic, multimodal connections between communities and Regional activity/ economic centers to support economic development
Investment NeedsThat Support
•Mobility and intermodal improvements to ensure region is well connected within the state and the nation
• Support economic competitiveness and advance overall economic development potential
![Page 6: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/6.jpg)
GoalBUILD AND MAINTAIN SAFE AND HEALTHY COMMUNITIES
Objectives•Support walkable and bicycle-friendly communities that promote safe connections to community resources•Provide incentives for complete streets project design•Encourage investments anchored in integrated transportation and land use planning that support desired community character•Improve safety through improved system operations, preventative maintenance, and ADA compliance•Prioritize investments in areas where local land use and development regulations support healthy, safe communities•Prioritize investment that improves multimodal access to existing or planned transit hubs or that fills gaps in existing multimodal system•Encourage connected street network
Within CommunityWithin Community
6
![Page 7: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/7.jpg)
GoalCONNECT COMMUNITIES IN THE REGION BY PROVIDING MULTIMODAL TRAVEL OPTIONS TO ACTIVITY AND ECONOMIC CENTERS
Objectives•Preserve, maintain, and improve existing infrastructure before adding new capacity•Provide incentives for complete streets project design•Encourage corridor improvements anchored in integrated transportation and land use planning that support desired community character•Improve mobility and support economic development by providing expanded set of travel options, with emphasis on public transit•Improve travel time reliability through improved system operations•Incentive corridor protection plans
Community to RegionCommunity to Region
7
![Page 8: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/8.jpg)
Region to Region
GoalGROW ECONOMIC OPPORTUNITY THROUGH STRATEGIC INVESTMENT IN CRITICAL REGIONAL INFRASTRUCTURE
Objectives•Preserve, maintain, and improve existing infrastructure before adding new capacity•Support continued economic growth of the region by improving intermodal connections that reduce delay for both people and goods•Reduce delay on critical regional thoroughfares with minimal impact to community, historic and environmental resources•Improve the efficiency and reliability of freight, cargo, and goods movement by reducing delay on corridors critical to freight movement•Improve travel time reliability through improved system operations
Region to Region
8
![Page 9: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/9.jpg)
Performance Evaluation
9
![Page 10: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/10.jpg)
How pleased are you to be here today?
A. Extremely happy, can’t think of anything you’d rather be doing
B. Pleased to be here but concerned about how long it will last
C. Are here because you were told you had to be but don’t mind participating
D. Are only attending to ensure that the planners don’t screw anything up
E. Would rather be at the dentist getting a root canal…
![Page 11: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/11.jpg)
OVERVIEW OF FINDINGS2040 RTP Leadership Symposium
![Page 12: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/12.jpg)
Steps of Plan Development Process
12
![Page 13: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/13.jpg)
Maintaining the System
• Bridge, current conditions assessment– 2012 National Bridge
Inventory (NBI) Database
– Structural deficiency status based on bridge condition
– Functional obsolete status based on geometrics, e.g., number and width of lanes
– All bridges in region greater than 20-foot length
13
Summary Bridge Conditions in Chattanooga Region
![Page 14: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/14.jpg)
Maintaining the System (continued)
14
![Page 15: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/15.jpg)
Maintaining the System (continued)
15
• Pavement, current conditions assessment– 2008 Highway
Performance Monitoring System (HPMS) database
– Percent of lanes miles in good/fair/poor condition based on roughness
– Thresholds defined by Federal Highway Administration
– Sample data
Summary Pavement Conditions in Chattanooga Region
![Page 16: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/16.jpg)
Reducing Congestion
• Base-year congestion analysis– Worst congestion along
I-24 and I-75– Severe congestion at
junction of I-24/I-75– U.S. 27 north of river– Hamilton Place Mall – Northgate Mall
• Downtown relatively uncongested
16
![Page 17: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/17.jpg)
Reducing Congestion (continued)
• Future-year congestion analysis– U.S. 27 congestion relieved
(widening project underway)
• Outward expansion and general increase in severity of general congestion due to population and employment growthover time
17
![Page 18: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/18.jpg)
Reducing Congestion (continued)
• Mobility corridor analysis– More detailed assessment
of 13 mobility corridors– Geographic sample of
corridors with high volume auto and truck traffic (“scale 3”)
– Corridors evaluatedand scored• Congestion Management
Process (CMP) route• 2040 congestion levels• Key freight route• Supports high-volume
external to external (through) trip movement
18
![Page 19: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/19.jpg)
Improving Safety
• Systemwide safety analysis– Traffic crashes leading cause
of death 5-34 years old– 55 deaths; 330 injuries
annually in region– $1,700 per person
• RTP Emphasis areas– Roadway departure– Aggressive driving– Intersection crashes
19
![Page 20: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/20.jpg)
Improving Security
• Climate adaptation analysis– Critical transportation
assets defined• Chickamauga Lock and Dam• Chattanooga Airport
and SR 153 access• Interchange of I-75/I-24• Enterprise South road
and rail access• Downtown bridges• Sequoyah nuclear plant
– Redundant facilities and evacuation routes identified
20
![Page 21: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/21.jpg)
Providing Access
• Accessibility analysis to measure proximity of people and homes to– Active transportation
facilities• Bicycle facilities (B-LOS of B or
better)• Parks and Open Space • Trails• CARTA Transit Stops
– Health-related destinations• Healthcare Facilities• Grocery Stores and
Supermarkets• Farmers Markets /Community
Gardens/ Mobile Markets• Public and Private Schools
21
![Page 22: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/22.jpg)
Environmental Sustainability Needs
1/4 Mile Walk Access 1 Mile Bicycle Access
Providing Access (continued)
22
![Page 23: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/23.jpg)
Connecting the System
• Transit Gap Analysis– Locations of highest transit
demand• Population and household density• Land use mix• Intersection density• Distance to nearest transit stop• Jobs within one mile
– Mapped against existing and planned infrastructure
– Low income, minority and elderly population as overlay
23
![Page 24: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/24.jpg)
Connecting the System (continued)
• Bicycle Gap Analysis– Locations of highest bike
demand• Population and household density• Intersection density• Jobs within one mile• Distance to nearest transit stop• Distance to commercial store• Public/private schools within one
mile• Parks and recreation facilities
within one mile
– Mapped against existing and planned infrastructure
– Low income, minority and elderly population as overlay
24
![Page 25: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/25.jpg)
Connecting the System (continued)
• Pedestrian Gap Analysis– Locations of highest pedestrian
demand• Population and household density• Intersection density• Jobs within one mile• Distance to nearest transit stop• Distance to commercial store• Public/private schools within one
mile• Parks and recreation facilities
within one mile
– Mapped against existing and planned infrastructure
– Low income, minority and elderly population as overlay
25
![Page 26: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/26.jpg)
Improving Livability and the Environment
• Livability corridor analysis– More detailed assessment
of 24 livability corridors– Geographic sample of
corridors with potential for broad multimodal enhancements and VMT reduction (“scale 2”)
– Corridors evaluated and scored in terms of:• Potential complete streets
corridor, 2035 Plan• Lack of bike/pedestrian/
transit infrastructure• Population and employment
density• Congestion levels
![Page 27: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/27.jpg)
Operating the System
• Operations assessment– Extensive ITS coverage on
freeways; opportunity to extend into north Georgia
– Downtown Chattanooga has extensive communication network for managing key arterials in real time; opportunity to extend to more corridors with centralized management center
– Opportunity for transit signal priority for key corridors
27
![Page 28: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/28.jpg)
Which of the following types of roadways should be the highest priority for improvements:A. Freeways (e.g. I-24, I-75,
US-27)B. Major Arterials (e.g.
Amnicola Highway, Lee Highway)
C. Minor Arterials (e.g. Bonny Oaks, E. Brainerd Road)
D. Collectors & Locals (e.g. Snow Hill Rd, Mack Smith Rd.)
![Page 29: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/29.jpg)
What’s the most important transit trip for the region?
A. Trips around town for shopping or recreation
B. Trips to and from workC. Trips that enhance
access to social services
D. There are no important trips
![Page 30: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/30.jpg)
What’s more important to bicycle and pedestrian travel?
A. Connecting to places within your town (parks, schools, libraries, etc.)
B. Connecting to regional destinations (other towns and regional parks, etc.)
C. Both
![Page 31: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/31.jpg)
How important is walkability to the future of the study area?
A. Extremely important, we must have it no matter what
B. Important, but only in the city limits
C. Somewhat important, but primarily in transit corridors and downtowns
D. Nice to have, but not necessarily needed for the area to be a future success
E. Unimportant
![Page 32: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/32.jpg)
FUNDING OUR NEEDS2040 RTP Leadership Symposium
![Page 33: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/33.jpg)
Funding Needs
• Level of investment needed to:– Maintain existing infrastructure– Strategically expand and operate
• Define needs in context of projected revenue over life of 2040 transportation plan
• Define gap/unmet needs• Scenario discussion to support best use of available
funds given needs identified
33
![Page 34: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/34.jpg)
Current Bridge Maintenance Funding Needs
34
Total current needs = $105M
![Page 35: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/35.jpg)
Long Term Bridge Maintenance Funding Needs
Projected Bridge Conditions in 2040 Given Funding Level
35
Total needs over life of plan = $322M
![Page 36: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/36.jpg)
Current Pavement Maintenance Funding Needs
36
![Page 37: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/37.jpg)
Long Term Pavement Maintenance Funding Needs
Projected Conditions in 2040 Given Funding Level
Baseline condition = 83%
37
Total needs over life of plan = $1.38B
![Page 38: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/38.jpg)
Total System Maintenance Needs
How much will it cost to maintain existing How much will it cost to maintain existing transportation system, in current conditions, over transportation system, in current conditions, over life of long-range plan?life of long-range plan?
$1.7 billionMore than doubling current spending levels from 2035 Plan
38
![Page 39: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/39.jpg)
New Investment Needs
How much will it cost to build, operate, and maintain How much will it cost to build, operate, and maintain all additional identified needs in the region?all additional identified needs in the region?
39
$7.0 billion
![Page 40: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/40.jpg)
Total Investment Needs
Existing System Maintenance$1.7 billion$1.7 billion
Total Needs$8.7 billion$8.7 billion
Additional Identified Needs$7.0 billion$7.0 billion
40
![Page 41: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/41.jpg)
Revenue Availability
And how much funding is actually available between And how much funding is actually available between now and 2040?now and 2040?
$5.7 billion
41
![Page 42: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/42.jpg)
Spending the Money
$1.7B$1.7B(MAINTAIN)(MAINTAIN)
$7.0B$7.0B(EXPAND)(EXPAND)
42
![Page 43: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/43.jpg)
Spending the Money (continued)
$5.7B$5.7B(AVAILABLE)(AVAILABLE)
43
![Page 44: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/44.jpg)
Spending the Money (continued)
$5.7B$5.7B(AVAILABLE)(AVAILABLE)
$1.7B $4.0B $3.0B
UNFUNDEDUNFUNDEDFUNDEDFUNDED
44
![Page 45: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/45.jpg)
Spending the Money (continued)
$5.7B$5.7B(AVAILABLE)(AVAILABLE)
$1.3B$1.7B $5.7B
FUNDEDFUNDEDUNFUNDEDUNFUNDED
45
![Page 46: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/46.jpg)
Spending the Money (continued)
$5.7B$5.7B(AVAILABLE)(AVAILABLE)
$0.5B $2.5B$1.2B $4.5B
UN
FUN
DED
UN
FUN
DED
FUNDEDFUNDEDUN
FUN
DED
UN
FUN
DED
46
![Page 47: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/47.jpg)
Spending the Money (continued)
$4.5B$4.5B(AVAILABLE)(AVAILABLE)
$0.5B $2.5B$1.2B $4.5B
Road Capacity
Tran
sit
Capa
city
47
$5.3B$5.3B(AVAILABLE)(AVAILABLE)
![Page 48: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/48.jpg)
Which approach do you believe is most important when considering the management of our transportation system? A. “Fix it first,” fully
maintain what we have before adding to the transportation system
B. Forego some maintenance to allow for more capacity projects
![Page 49: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/49.jpg)
With the understanding that there won’t likely be sufficient funds for all identified needs, I’d be willing to defer some transportation maintenance needs for other transportation improvements.
A. Strongly agreeB. AgreeC. NeitherD. DisagreeE. Strongly disagree
![Page 50: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/50.jpg)
INTERMISSION2040 RTP Leadership Symposium
![Page 51: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/51.jpg)
ALTERNATIVES ANALYSIS2040 RTP Leadership Symposium
![Page 52: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/52.jpg)
Alternatives Analysis
• Two “bookend” scenarios to illustrate benefits of road investments and transit investments
• Includes road and transit capacity investments – Includes “call for projects”– Public involvement– Technical analysis
• Approximately equal cost• Want to use these to produce the “Blend of the Best”
![Page 53: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/53.jpg)
Remember This?
![Page 54: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/54.jpg)
BYPASSES & CONNECTORS SCENARIOPrimary investments in expanding highway accessibility and improving existing road corridors.
![Page 55: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/55.jpg)
Bypasses and Connectors Scenario27 miles of New Roadways
• Includes 16 mile Northern Hamilton County connection between US 27 and I-75 with new TN River Bridge
•230 miles of Roadway Widening
• Includes almost all of I-24 and I-75
• Includes portions of US-27 and SR-153
• Includes SR 321/SR 151 as Eastern Bypass (4 lane arterial) between Collegedale, TN and Ringgold, GA
23 miles of Safety/Preventative Maintenance
15 miles of complimentary local bus routes
![Page 56: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/56.jpg)
Bypasses & Connectors
Key Growth Drivers:
• Existing zoning & ordinances
• Proximity to major roads
• Interchanges & major Intersections
• Large water & sewer service area
• General preference for greenfield development patterns
![Page 57: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/57.jpg)
Growth Characteristics• Low-density, decentralized growth
• Greater maintenance cost
• Expanding road network allows for increased distance between new neighborhoods and existing centers
• New commercial development follows along widened corridors (linear development pattern)
• Greater amount of land lost to new development.
![Page 58: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/58.jpg)
BIG TRANSIT SCENARIOPlacing a greater emphasis on alternate travel modes
![Page 59: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/59.jpg)
Big Transit Scenario•“Chattanooga Way”
o 15 mile long new light rail line
o Connects Downtown, Airport, Enterprise South
•SR 153/US 27 “Bus Plus”
o 19 mile long new Bus Rapid Transit (BRT) line
o Connects Hamilton Place, Airport, Northgate, Soddy Daisy
•“Premium Bus” Express Service on Interstates
o 24 miles of new routes/extension of Route 4
o Connects Ringgold/Lookout Valley/Collegedale to Downtown
![Page 60: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/60.jpg)
Big Transit Scenario• Expanded Local Bus Routes
o 76 miles of new/extended routeso Expands service area to include:
Red Bank, East Ridge, Collegedale in Tennessee
Rossville, Fort Oglethorpe, Ringgold in North Georgia
• Improved Frequency of Existing CARTA Routes
• Free Circulator Shuttleso Builds on success of downtown electric
shuttleo East-west downtown shuttle (Aquarium,
Erlanger Hospital)o New Hamilton Place Mall area shuttleo Complimentary Roadway Projects (85
miles)
![Page 61: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/61.jpg)
Big Transit Scenario
Key Growth Drivers:• Premium transit service
(bus rapid transit & light rail)
• Station areas & existing centers
• Existing water & sewer service area
• General preference for infill development & redevelopment
• Protect environmentally-sensitive areas & agriculture
![Page 62: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/62.jpg)
Growth Characteristics• New: compact, higher-density growth attracted
premium transit station areas (1-mile radius)• Significant number of local farms protected from
new development• Maintain small town feel to outlying areas• Average household transportation costs reduced• More efficient development pattern reduces
overall infrastructure cost
![Page 63: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/63.jpg)
Comparison of Alternatives
Bypasses and Connectors Measure of Effectiveness Big Transit
16,035,000 Vehicle Miles Traveled (VMT) 14,943,000
521,000 Vehicle Hours Traveled (VHT) 533,500
2,670 Delay (Hours) 3,060
3,573,00 Total Number of Trips 3,573,00
6,400 Transit Trips 12,000
28.7 Vehicle Miles Traveled / Capita 26.8
0.1%-0.3% Percent of trips by transit 0.5%-1.5%
![Page 64: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/64.jpg)
Overall, how attractive is the “Bypasses and Connectors” Investment Scenario?
A. Very attractive
B. Attractive
C. Somewhat attractive
D. Neutral
E. Not very attractive at all
![Page 65: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/65.jpg)
Overall, how attractive is the “Big Transit” Investment Scenario?
A. Very attractive
B. Attractive
C. Somewhat attractive
D. Neutral
E. Not very attractive at all
![Page 66: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/66.jpg)
Which scenario best supports quality of life?
A. Highways and Corridors
B. Big Transit
C. Combined approach
D. Neither
![Page 67: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/67.jpg)
Where should transportation investments seek to encourage future growth?
A. Existing corridorsB. New corridorsC. Existing centersD. New centersE. Outlying areasF. Grow anywhere we can
![Page 68: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/68.jpg)
CONSIDERING THE TRADEOFFSLightening Round
![Page 69: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/69.jpg)
What will provide the biggest bang for the region’s bucks?
A. Widen existing roads
B. Build new roads
C. Expand transit service
D. Create more quality walking and biking choices
![Page 70: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/70.jpg)
What’s the most important regional transit corridor?
A. Light Rail (Chattanooga Way) between downtown, airport, and Enterprise South
B. SR-153/US-27 BRT route between Hamilton Place, Airport, Northgate, and Soddy-Daisy
C. Express bus on I-75/I-24 to the suburbs (Collegedale, Ringgold, Lookout Valley)
D. Free Circulator Shuttles (Downtown East/West, Hamilton Place)
![Page 71: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/71.jpg)
Regarding transit…Rank the following from most important to least important.
A. Expand local bus service to areas not currently served (Red Bank, East Ridge, Collegedale, North Georgia)
B. Frequency of serviceC. Length of weekday serviceD. Weekend serviceE. Low fareF. Type of transit vehicle
![Page 72: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/72.jpg)
Which intermodal facility should be the top priority area for coordination and collaboration? A. Chattanooga Metropolitan
Airport passenger and/or freight improvements and expansion
B. Chickamauga Dam and Locks Reconstruction
C. Development of a freight intermodal (rail/truck/waterway) center/facility within Chattanooga
D. Atlanta-Chattanooga High Speed Rail
![Page 73: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/73.jpg)
What do you believe best supports business recruitment and retention?
A. Less congestion
B. Increased choice (travel modes)
C. Increased accessibility
D. Attractive streets
E. Complete streets
![Page 74: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/74.jpg)
It’s important to begin building a rapid transit network in our region in the near future.
A. Strongly agree
B. Agree
C. Neither
D. Disagree
E. Strongly disagree
![Page 75: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/75.jpg)
Priority transit investments in the region should include:
A. Within community (Service within the cities and towns
B. Community to region (Express bus from the small towns to the large employment centers)
C. Region to region (Service connecting between the cities and towns)
![Page 76: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/76.jpg)
What would it take to make your community bicycle friendly?
A. Safe streets
B. Greenways
C. More signed routes
D. Better intersection design
E. All of the above
![Page 77: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/77.jpg)
What would help my daily commute most?
A. Widen existing roads
B. Build new bypasses
C. Add rapid transit
D. Quality housing choices within close proximity to employment centers
![Page 78: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/78.jpg)
Considering that our financial resources are fixed; how would you prioritize the following funding scenarios?A. Large/expensive transportation
improvements
B. Smaller/less expensive local transportation improvements
C. System maintenance and operation enhancements (traffic control enhancements & use of technology) with remaining funds used for system expansion
![Page 79: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/79.jpg)
Considering that our financial resources are fixed; how would you prioritize the following funding scenarios?A. Regional congestions
solutionsB. Project specifically
intended to spur economic development
C. Projects that improve the quality of life for local residents
D. Other
![Page 80: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/80.jpg)
If you had control over the transportation budget, how would you rank the following in importance?A. Neighborhood traffic safety
& calmingB. Sidewalk construction and
repairsC. Bikeway construction on
roads and greenwaysD. Widening and building roadsE. Improving condition of
roadwaysF. Improving traffic flowG. Public transportationH. Other
![Page 81: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/81.jpg)
If additional funding for transportation improvements is needed, would you support any of the following sources?A. Higher gas taxB. Higher sales taxC. Higher property taxD. Toll roadsE. Development impact feesF. Transportation bonds
(borrowing)G. OtherH. Do not support additional
funding
![Page 82: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/82.jpg)
Which of the following is most important when considering which projects to fund?
A. Does the project open up new land for development
B. Does the project reduce congestion
C. Does the project result in travel time savings
![Page 83: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/83.jpg)
CLOSING THOUGHTS AND REMARKSQuestions & Comments
![Page 84: Chattanooga-Hamilton County/N. GA Transportation Planning Organization](https://reader036.vdocuments.net/reader036/viewer/2022062519/56814ed6550346895dbc7085/html5/thumbnails/84.jpg)
Next Steps
• Draft Needs Plan• Project Evaluation / Costing• Policy Board Review and Endorsement of
Financial Constrained Project List• Public Review and Comments• Draft Final Plan