![Page 1: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/1.jpg)
Great Streets BTVSt. Paul Street Presentation August 9, 2018
Construction
![Page 2: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/2.jpg)
Agenda
•Team
•Schedule
•Plans & Property Lines/Parklets
•Construction Traffic Control
•Outreach/Resources
•QuestionsGreat Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 3: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/3.jpg)
Team
• DPW• Laura Wheelock
Project Manager• Ashley Toof
Project Manager• Rob Goulding
Outreach
• CEDO• Kirsten Merriman-Shapiro
Project Manager
Great Streets BTVSt. Paul Street Presentation August 9, 2018
• SD Ireland General Contractor
• EIV Technical Services Resident Engineer &
City’s On-Site Representative
• Dubois & King Design Engineer
![Page 4: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/4.jpg)
Schedule - Tentative
• City Council Approval 8/13/18
• Earliest Start for Construction 8/20/18
• Road Closed to All Through Traffic until 11/16/18
• Winter Construction (Select/Specialized) 11/2018-3/2019
• Resume Construction 4/2019
• Complete All Work 5/24/19
Great Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 5: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/5.jpg)
St. Paul –Main to King Plan
Great Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 6: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/6.jpg)
St. Paul –King to Maple Plan
Great Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 7: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/7.jpg)
St. Paul – Property Line/Parklet
Great Streets BTVSt. Paul Street Presentation August 9, 2018
• Right of Way for St Paul = 99 feet
• Building Encroachments – License Agreement
• Stairs/Ramp Encroachments – License Agreement
• Parklet (Tree Belt or Parking Lane)• Tables/Chairs
• Public/Private Spaces
• License Agreement
![Page 8: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/8.jpg)
Traffic Control - Tentative
• Pedestrian Access to Businesses – maintained while business open/occupied
• Pedestrian Access to Residences – at all times
• Road will be closed to all through traffic; local traffic to Stratosand exit to Hilton Garden maintained except for proximate adjacent work
• Bicycles will need to follow detour signage or walk bicycles through designated pedestrian paths
• GMT – adjusting bus routes during construction
Great Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 9: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/9.jpg)
Traffic Control - Tentative
• Parking• No on-street parking during full road closure• Most parking available through Winter Construction• Some parking available during Spring 2019 Construction• New proximate parking at 194 St. Paul Street
• Deliveries• On adjacent side streets – hand cart to door• Temporary loading zone 7am-4pm added on Main Street during
full closure (3 spaces in front of Gryphon)
Great Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 10: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/10.jpg)
Order of Work - Tentative
• Ductbank under west sidewalk
• Utility Vaults and Stormwater piping
• Silva Cells and Road Subbase/Curbing
• Paving 1st layer
• Concrete Sidewalks – Pervious Pavers
• Utility Relocations
Great Streets BTVSt. Paul Street Presentation August 9, 2018
Fall/Winter 2018
![Page 11: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/11.jpg)
Order of Work - Tentative
• Stormwater Gardens
• Sidewalks & Pavers
• Tree Wells & Plantings
• Remove Utility Poles and Finish Tree Belt
• Paving 2nd & 3rd Layers
• Pavement Markings
Great Streets BTVSt. Paul Street Presentation August 9, 2018
Spring 2019
![Page 12: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/12.jpg)
Outreach/Resources
•Neighborhood Meetings
•Project Website & Social Media (FB/Twitter/FPF)
•City Staff (DPW/CEDO)
•On-Site Representative (EIV Technical Services)
Great Streets BTVSt. Paul Street Presentation August 9, 2018
![Page 13: Construction - Burlington, Vermont St...Schedule - Tentative •City Council Approval 8/13/18 •Earliest Start for Construction 8/20/18 •Road Closed to All Through Traffic until](https://reader035.vdocuments.net/reader035/viewer/2022070719/5edf8d50ad6a402d666ae3cb/html5/thumbnails/13.jpg)
Questions
Great Streets BTVSt. Paul Street Presentation August 9, 2018