Memorandum

DATE January5, 2012

TO Trinity River Corridor Project Committee Members: Vonciel Jones Hill (Chair)Linda Koop (Vice Chair), Monica Alonzo, Scott Griggs, Angela Hunt, and Delia Jasso

SUBJECT Continental Bridge & West Dallas Gateway

At the next Trinity River Corridor Project Council Committee Meeting on Monday,January 9, 2012, the attached briefing will be presented by David Whitley. This briefingwill provide an overview and update on the West Dallas Gateway and ContinentalBridge Conversion projects.

Please contact me if you have questions.

Jill A. Jordan, P.E.Assistant City Manager

TRE TRINITYDALLAS

Attachment

cc: Honorable Mayor and Members of the City CouncilMary K. Suhm, City ManagerA. C. Gonzalez, First Assistant City ManagerRyan S. Evans, Assistant City ManagerForest E. Turner, Assistant City ManagerJoey Zapata, Assistant City Manager

Kelly High, Director, Trinity Watershed ManagementRebecca Rasor, P.E., Managing Director, Trinity River Corridor ProjectPaul D. Dyer, Director, Park and RecreationTheresa O’Donnell, Director, Sustainable Development & ConstructionStephanie Cooper, Assistant to the City Manager — Council

CITY OF DALLAS

“Dallas. the City that works: diverse, vibrant, and progressive”

CONTINENTAL BRIDGE & WEST DALLAS GATEWAY trinity river corridor project committee 01.09.12dallas citydesign studio

1

purpose

Provide an overview of all of the projects affiliated with the Continental Bridge conversion

Review anticipated schedule and budget

Outline additional next steps

dallas citydesign studio

2

2006 Bond Program included $1.9 million for Continental Bridge and $1.8 million for the West Dallas Gateway

$8 million in additional funds donated for the Continental Bridge Project

Planning efforts with the community by the dallas citydesign studio defined the program for the West Dallas Gateway project to connect West Dallas to the Continental Bridge

backgrounddallas citydesign studio

3

Continental Bridge

dallas citydesign studio

4

WRT

dallas citydesign studio

5

WRT

dallas citydesign studio

6

WRT

“FLOWER” GATEWAY•“Trefoil” shade structures with vines & seating•Vending areas

150’.

dallas citydesign studio

7

WRT

dallas citydesign studio

8

WRT

dallas citydesign studio

9

WRT

PLAY AREA•Shade Trees•Seating•Bocce Court•Chess Panel•Climbing Blocks•“Sidewalk” Games

150’ 300’

dallas citydesign studio

10

WRT

(POTENTIAL 

INTERIM, USE)

dallas citydesign studio

11

WRT

dallas citydesign studio

12

WRT

dallas citydesign studio

13

WRT

FOUNTAIN/ MIST PLAZA•Programmable Mist and Water Jets•Seating Area•Cooling Fog Poles

150’150’ 300’

dallas citydesign studio

14

WRT

“ISLAND” GARDENS•Shade trees•Planters•Hanging vines•Seating

150’ 300’ 180’150’

dallas citydesign studio

15

WRT

dallas citydesign studio

16

WRT

dallas citydesign studio

17

WRT

MEDITATION PLAZA•Labyrinth

150’ 300’ 180’ 230’150’

dallas citydesign studio

18

WRT

dallas citydesign studio

19

WRT

EVENT PLAZA•Shade trees•Planters•Seating•Electrical supply

150’ 300’ 180’ 230’ 640’150’

dallas citydesign studio

20

WRT

dallas citydesign studio

21

WRT

dallas citydesign studio

22

WRT

example style of light fixture

dallas citydesign studio

23

WRT

PEDESTRIAN PEDESTRIAN ZONEZONE

SPECIAL SPECIAL EVENT EVENT

CONTROL CONTROL POINTPOINT

NORMAL NORMAL CONTROL CONTROL POINTPOINT

removable bollards

dallas citydesign studio

24

WRT

limits of construction on eastern end of project

landscaping to include 9 trees and shrubs

no change proposed to street configuration

area for parallel parking

RIV

ERFR

ON

T BL

VD

RIV

ERFR

ON

T BL

VD

CONTINENTAL ST

CONTINENTAL ST

staircase

dallas citydesign studio

25

WRT

landscaping to include 9 trees and shrubs

area available for special event parking

staircase

removable bollards

Section through the eastern end of Continental looking toward Riverfront Blvd

Western Gateway

dallas citydesign studio

26

TxDOT reconfigured intersection

levee top canada drivecontinental

pedestrian bridge singleton avenue margaret hunt hill bridge

dallas citydesign studio

27

early community planning to define the project’s program

provide neighborhood access to the park and

Continental Bridgeprovide much-needed

vehicular parkingcreate a

plaza/gathering space

provide a strong bicycle &pedestrian connection from the bridge/plaza to adjacent development opportunities

provide for occasional vehicular access to the Continental Bridge for emergency and service vehicles

utility station/additional median enhancements as a future design opportunity for the gateway

utility station/additional median enhancements as a future design opportunity for the gateway

dallas citydesign studio

28

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

29

WRT

FUTURE IMPROVEMENTS

current proposed design

dallas citydesign studio

30

WRT

dallas citydesign studio

31

WRT

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

32

pedestrian connectivity

WRT

SEAT WALL (SPECIAL FEATURE)

dallas citydesign studio

33

WRT

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

34

bike connectivity

WRT

Potential future DART bus stop

Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

35

WRT

vehicular connectivity

Gulden St.

EMERGENCY ACCESS

FUTURE CONCESSIONS & RESTROOM

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

36

WRT

PICNIC AREA

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

37

WRT

POTENTAIL AREA FOR FUTURE STREET FAIR/ MARKET TENTS

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

38

WRT

Gulden St. Sing

leto

n Bl

vd.

N. Beckley

POTENTIAL AREA FOR FUTURE STAGE / FESTIVAL TENT

dallas citydesign studio

39

WRT

Project Budget: Continental Bridge: $9.9 million – Inclusive of design/ engineering and construction West Dallas Gateway: $1.8 million – Inclusive of design/ engineering and construction Total Budget: $11.7 millionAvailable Funding: $11.7 million

Project Schedule:Bid Documents – Design underwayBid Advertisement – March 2012Thoroughfare Plan Amendments – March 2012Bid Award – April 2012Construction Duration – 16 monthsProject Opening – August 2013

Project Awards for Continental Bridge:2011 ‘Dream Award’ from the Greater Dallas Planning Council

dallas citydesign studio

40

anticipated schedule and budget

Sing

leto

n Bl

vd.

N. Beckley

dallas citydesign studio

41

WRT

thoroughfare plan amendments

Delete Continental Avenue from Singleton

to Riverfront from the Thoroughfare Plan

Gulden St.

Delete Canada Drive from Singleton to

Gulden from the Thoroughfare Plan, if

necessary

Change Beckley-

Canada Connection to North Beckley Avenue

next steps: thoroughfare plan amendment process

1 | 

CPC Transportation Committee – February 2, 2012

2 | 

City Plan Commission – February 16, 2012

3 | 

City Council – March 28, 2012

dallas citydesign studio

42

dallas citydesign studio

43