![Page 1: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/1.jpg)
Cost of Transport Large Scale and Post Demonstration
Dusseldorf 9th November 2011 Per Arne Nilsson
panaware ab
![Page 2: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/2.jpg)
2
![Page 3: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/3.jpg)
Contents
Background – ZEP & CCS Cost Project
Transport Costs Approach, Assumptions & Networks
Cost Predictions
Conclusions
3 panaware ab
![Page 4: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/4.jpg)
Background – ZEP & CCS Cost project
4 panaware ab
![Page 5: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/5.jpg)
Objective: Enable commercial availability of CCS
Three different challenges:
EU CCS Demonstration Programme
Minimize
Cost by Early Planning
€
Technology Down the
Learning Curve
Demonstrate Secure
for Public Perception + +
5 panaware ab
![Page 6: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/6.jpg)
Why is the ZEP Cost Report unique?
Publicly available cost data on CCS are scarce
New, live, in-house data provided exclusively by ZEP member organizations
Over 100 contributors and nearly 2 years of work…
Complete CCS value chains; individual reports analyse costs for: • Capture • Transport • Storage
Establishes reference point for costs of CCS, based on a “snapshot” in time (CAPEX referenced to Q2 2009)
6
![Page 7: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/7.jpg)
Main Messages
CCS will be cost-competitive with other low-carbon power technologies
(Will be covered in the next presentation)
7
![Page 8: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/8.jpg)
Transport Costs Approach, Assumptions & Networks
8
![Page 9: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/9.jpg)
Approaches to transport cost estimation
Bottom-up Detailed component cost built into dimensioning model for specific CCS cases Focusing on material costs, operating expenses Static, detailed view on cost
Top-down
Analyzing ”the market”, potential capture projects coming on stream in a coordinated mode
Based on phased-in volumes, approximating required, optimal transport capacities Focusing on total CAPEX Dynamic volume development view, extrapolations on cost
Integrated Live, transport chain cost components, CAPEX and OPEX Simulated transport volume demands and network developments Integrating network scenarios and component costs Dynamic, generic view on cost and volume
panaware ab 9
![Page 10: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/10.jpg)
ZEP: The costs of CO2 transport – method
panaware ab
?
Network & volume scenarios
Iteration 2 Iteration 1
Sensitivities Uncertainties
First results
Partner review
ZEP membership scrutiny
Final Report
European conditions
Definitions, assumptions &
interfaces
Detailed CAPEX and OPEX data
collection
10
![Page 11: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/11.jpg)
http://www.zeroemissionsplatform.eu/library/publication/167-zep-cost-report-transport.html
Key Assumptions
11
General o exchange rates o project lifetime o cost of energy o interest rates o residual value o inflation o cost time stamp
panaware ab
Common CCS o flow rates (volumes) o annual production profile o CO2 purity o interface conditions
o inlet pressure/temperature o outlet pressure/temperature
o injection properties
Onshore pipeline o custom installations o flat topography, simple soil conditions o unobstructed right of way o pressures
o inlet 100 barg o outlet 80 barg o maximum design 100 barg
o maximum CO2 temperature 50oC o booster pumping >200 km’s
Offshore pipeline o custom installations o 4 slot subsea template o control cable o pressures:
o inlet 100 barg o outlet 60 barg o maximum design 250 barg o start 200 barg
o environmental factors o market factors
Shipping o custom ship design maximum 40’ m3
o buffer storage 0.8–1.0 * ship size o offshore terminal submerged turret o transport mode 7 bara & -55oC o discharge conditions
o pressure 60 barg o temperature 0oC
o direct injection o no offshore buffer storage o subsea template & control cable
![Page 12: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/12.jpg)
Source Capture/
Compression Onshore pipeline
Pump Launcher/
Landfall Offshore Pipeline
Template Storage
Offshore Pipeline
Template Storage
Control Cable
Length 10 km 180 –
1 500 km 10 km 50 km
Pressure 110 barg 110
100 barg 100–>
200 barg 200 barg
200 60 barg
60 barg 60 barg 60 barg
A B C D E F G H I J
Battery limits and cost zones for offshore pipeline
12 panaware ab
Collection of Component Costs - Example
![Page 13: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/13.jpg)
CO2 Transport from Point-to-Point ...
13
Pipeline offshore
180 km 10 km
Storage
Pipeline onshore Source 10 Mtpa
Offshore spine
Pumping
Pipeline onshore
180 km
Storage
Source 10 Mtpa
10 km
Pipeline onshore
Onshore spine
![Page 14: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/14.jpg)
... to Complex Networks
14
Pipeline onshore
Storage
Storage
180 km, 500 km
10 km
10 km
Source 5 Mtpa
Terminal Pumping
10 km
Source 2.5 Mtpa
Source 10 Mtpa
Source 2,5 Mtpa
180 km
750 km
Liquid CO2 -50C 7 barg
Liquefaction and buffer
storage
Complex networks with onshore pipeline spine of 180 km and 500 km
![Page 15: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/15.jpg)
More robust scenarios built in other studies...
15 panaware ab
One North Sea study “Very High scenario 2050” May 2010
CO2Europipe Reference scenario 2030 September 2011
Feasibility Study for Europe-wide CO2 Infrastructures 2050 Mid CO2 Capture Scenario October 2010
![Page 16: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/16.jpg)
....but more detailed and reality based cost element analysis in ZEP
Pipeline data from both existing CO2 pipelines and….
… in comparison with hydrocarbon networks
Data from current (2010) demonstrator projects
Detailed interface definitions with Capture and Storage experts
Shipping data from live projects and LPG tonnage
Process (compression, regas and liquefaction) from vendors and
projects
16
panaware ab
![Page 17: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/17.jpg)
Cost Predictions
17
![Page 18: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/18.jpg)
Scale effects are real (total cost €/t)
18
0
5
10
15
2.5 10 20
€/t
Mtpa
onshore pipeline offshore pipeline ship
Point-to-Point 180 km
0
5
10
15
20
25
2.5 10 20
€/t
Mtpa
onshore pipeline offshore pipeline ship
Point-to-Point 500 km
panaware ab
![Page 19: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/19.jpg)
Selected Networks: 20 Mtpa, 2 sources, 2 offshore storages
19
Pipeline offshore
180, 500, 750, 1 500 km
10 km Storage
Source 10 Mtpa
Offshore spine
Pumping
Source 10 Mtpa
10 km
180, 500, 750, 1 500 km
10 km Storage
Source 10 Mtpa
Onshore spine
Pumping
Source 10 Mtpa
10 km Pipeline onshore
180, 500, 750, 1 500 km
10 km Storage
Source 10 Mtpa
Ship spine
Liquefaction Buffer storage
Source 10 Mtpa
10 km
panaware ab
![Page 20: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/20.jpg)
Network costs: 20 Mtpa, 2 sources, 2 offshore storages
20 panaware ab
0 1000 2000 3000 4000
Onshore 180
Onshore 500
Onshore 750
Onshore 1 500
Offshore 180
Offshore 500
Offshore 750
Offshore 1 500
Ship 180
Ship 500
Ship 750
Ship 1 500
CAPEX (M€) Spine (km)
0 100 200
OPEX (M€ p a)
2.5
4.6
6.3
11.3
3.4
6
8.2
16.3
11.1
12.2
13.2
16.1
0 10
Unit cost (€/t)
![Page 21: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/21.jpg)
Pipeline sensitivities
Sensitivities for offshore pipeline 10 Mtpa and 500 km
panaware ab 21
Pipeline % changes in cost per ton
![Page 22: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/22.jpg)
Volume Ramp-up Sensitivity
22
Tran
spo
rt c
ost
€/t
panaware ab
Ramp up transport cost 500 km, increasing by 2 Mtpa to maximum 20 Mtpa
Year
![Page 23: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/23.jpg)
Conclusions
23
![Page 24: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/24.jpg)
Adding up, for Europe, we speak BIG numbers...
24 Illustration: Arup, EUC, DG ENER, Infrastructure study Oct 2010; High Scenario 2050
report year CAPEX (b€)
Arup/EUC 2010 7 – 20
ZEP 2011 40 - 50
CO2 Europipe 2011 50 - 80
Infrastructure investment required is massive, yet overall numbers remain the results of highly approximate extrapolations, only, so no guarantees issued on this
![Page 25: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/25.jpg)
Key Conclusions
Capital expenditure appears prohibitive and provides high risk – combining pipelines and ships can reduce risk
Clustering plants to a transport network can achieve significant economies of scale – in both transport and storage
Large-scale CCS requires the development of a transport system equivalent to the current hydrocarbon transport infrastructure
Greatly reduced long-term costs can be ensured with early strategic planning 25 panaware ab
Early strategic planning of large-scale CO2 transport infrastructure is vital to reduce costs
![Page 26: Cost of Transport Large Scale and Post Demonstration](https://reader030.vdocuments.net/reader030/viewer/2022032414/62332ebf408664399c6c14c3/html5/thumbnails/26.jpg)
Acknowledgements – Working Group Participants
panaware ab
Name Country Organisation
Authors
Nilsson, Per Arne Sweden panaware ab
Apeland, Sigve Norway Gassco
Dale, Henning M Norway Gassco
Decarre, Sandrine France IFP Energies nouvelles
Eldrup, Nils H Norway Tel-Tek
Hansen, Hans-Richard Norway Teekay Shipping / Low Carbon Shipping
Nilsson, Jenny-Ann Sweden Vattenfall Power Consultants
Rennie, Alastair UK AMEC
Skagestad, Ragnhild Norway Tel-Tek
Wendt, Tobias Germany Open Grid Europe GmbH
Commentators
Demofonti, Giuseppe Italy Centro Sviluppo Materiali
Piessens, Kris Belgium European Federation of Geologists (EFG)
26