A FIRST OF ITS KIND
MULTIMODAL LOGISITCS HUB
IN INDIA
TAKEN UP
BY MP MANDI BOARD
RAIL TERMINAL,ICD,CFS,WAREHOUSING ZONE,COLD STORAGE, AGRI PROCESSING ZONE
![Page 3: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/3.jpg)
Overview and Pre-Award
![Page 4: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/4.jpg)
Overview (1)
Short Description
Setting up Composite Logistics Hub at Powarkheda, Distt. Hoshangabad
Implementing Agency
MP State Agricultural Marketing Board (Mandi Board)
Line Department
Agriculture Department
Location •Powarkheda, Distt. Hoshangabad (between NH 69 & Delhi-Mumbai rly line next to Powarkheda rly stn, 6.5 km from Itarsi rly stn)
•Well-connected:– NH 69 for North-
South– NH 12 for East
Area 115 acres land
Concession Period
33 years, extendable by 15 years
Beneficiary of the project:
Project Influence Area (PIA) : Hoshangabad, Betul, Harda, Sehore, Bhopal, Raisen
Cargoes: Wheat, Rice, Soya Bean, DOC, Horticulture produce, Industrial Products
![Page 5: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/5.jpg)
• All services under one roof to entire logistics chain • Mandi for sale of produce• Warehouses for storage - WDRA
approved • Modern logistics support
services• Export / Import facility • Storage for perishable / high
value produces• Value addition for the produces• Reduction in losses
Farmers Point of view
Benefits from the Project
• Facility will catalyze the development of the area• Employment Generation• Attract investments by way of
ancillary facilities• Value enhancement to the
farmers• Encourage farmers to grow
horticulture crops due to cold storage
• De-congestion of city of Itarsi from truck movement
Social point of view
![Page 6: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/6.jpg)
Dedicated marketing Facilities for Farmers
Negotiable Warehouse Receipts
Wholesale Market / Mandi to be operated by Mandi Board
Inland Container Terminal Bulk Terminal Railway Siding & Trucking Hub
State of the Art Warehousing FCI Facility with Modern Double Deep/Multiple Layer Stacking Cold Storage
State of the Art Processing Facilities
Procurement
Logistics & Transport
Marketing
Storage
Processing & Value Addition
Farm
to F
ork
Inte
grat
ion
Empowering the Farmer, right to sell when and where he wants to
State of the art warehousing for PIA to reduce menace of wastage
Better & Higher Prices to farmers, access to processing, Logistics industry
Value Addition & Processing integration with procurement
End to End Integration with Dedicated Logistics & Transport Infrastructure
Dedicated marketing Facilities for Farmers
Negotiable Warehouse Receipts
Wholesale Market / Mandi to be operated by Mandi Board
Inland Container Terminal Bulk Terminal Railway Siding & Trucking Hub
State of the Art Warehousing FCI Facility with Modern Double Deep/Multiple Layer Stacking Cold Storage
State of the Art Processing Facilities
Procurement
Logistics & Transport
Marketing
Storage
Processing & Value Addition
Farm
to F
ork
Inte
grat
ion
Empowering the Farmer, right to sell when and where he wants to
State of the art warehousing for PIA to reduce menace of wastage
Better & Higher Prices to farmers, access to processing, Logistics industry
Value Addition & Processing integration with procurement
End to End Integration with Dedicated Logistics & Transport Infrastructure
Benefits
![Page 7: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/7.jpg)
PPP Mode DBFOT
Estimated Cost Rs. 138.50 crs.
Construction period
•3 years for minimum facilities (COD)•7 years for completion
IRR •20.70% (post-adjustment of cash flow to rly for revenue sharing)
Overview (2)
Bid Process • 2-Stage
1st RfQ • Issued 01.12.2009• No response• Stringent criteria, no
qualifiers
2nd RfQ • Issued 04.03.2011• Opened 30.03.2011• 13 RfQs recd / 12
short-listed
RfP • Issued 16.05.2011• Opened 14.07.2011
Concession signed 24.10.2011
Substitution Agreement signed 11.10.2012 with lead bank
Bidding Parameter Highest Premium
![Page 8: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/8.jpg)
Winning Bidder
Kesar MultiModal Logistics Ltd., Mumbai (Consortium of Kesar Terminal & Infrastructure Ltd with Kesar Enterprises Ltd)
Winning Bid
• Rs. 12.78 crs. • To be paid in 10 equal yearly
instalments w.e.f. Fin Close so that PV of instalment @12% discounting is same as 1/10th of quoted premium based on formula
Cfn = Cq x (1+r)n-1
- Cfn : Premium to be paid in nth year
- Cq : Original quoted premium instalment
- n : Year of cash flow- r : Discount Rate (12%)
Procurement (2)
S. No.
Amount (Rs. Crs)
Status
1 1,27,80,000
Paid2 1,43,13,600
3 1,60,31,232
4 1,79,54,980
5 2,01,09,577
Future Payments
6 2,25,22,727
7 2,52,25,454
8 2,82,52,508
9 3,16,42,809
10 3,54,39,947
22,42,72,834 Grand Total
Bid Highlights Annual Concession Premium
![Page 9: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/9.jpg)
• Railway siding/private freight terminal
• CFS/ICD • Warehouse for agro and industrial
cargo (Bulk, Bonded, transit etc.) • Cold Storage • Processing Facility• Value add services area
Conceptual Scope of Work (1)
Development by Concessionaire (88.3 acres)
Development by Govt Agencies (26.7 acres)
• Wholesale market for agriculture and horticulture (developed by Mandi Board)
• Warehousing Facilities (developed by MP Warehousing & Logistics Corp as National Storage Reserve)
![Page 10: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/10.jpg)
![Page 11: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/11.jpg)
Post-Award
![Page 12: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/12.jpg)
Approvals AccordedS. No. Purpose Agency Date
1 Master Plan Mandi Board 24-12-12
2 Railway Siding GM-Western Railway 18-12-12
3 Pollution MP Pollution Control Board 18-09-12
4 ICD Inter-Ministerial Committee, GoI 19-12-12
Particulars Agency Amount
Financial Closure Consortium of Banks 148.67
Debt : Equity ratio 2 : 1
Financing Scheme
Project Progress
![Page 13: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/13.jpg)
Construction Progress
Details Total (7 years) Minimum as per CA (3 yrs)
Actual
COD 21-04-15 20-04-15
Warehouse & Bulk Terminal
47,500 sq. mt.
15,000 sq. mt.
15,127 sq. mt. complete + 8,125 sq. mt. up to plinth
Transit & Bonded Warehouse
1,946 sq. mt. 1,076 sq. mt. 1,375 sq. mt.
Railway Lines 3 nos. 2 nos. 3 nos.
Cold Storage 3,000 sq. mt. 600 sq. mt. 3,600 sq. mt.
Paved Area 72,817 sq. mt. 28,200 sq. mt. 28,449 sq. mt.
Weigh Bridges 2 Nil 2 nos.
Common Facilities 87,703 sq. mt. 51,142 sq. mt. 55,638 sq. mt.
![Page 14: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/14.jpg)
Highlights
COD expectedDue to time taking Railway /CRS approvals and Delays from Railway side due to accidents at Itarsi and Harda. Planned COD could not be achieved as railway siding could not be commissioned. However all other facilities were ready and commissioned on 20th April 2015.
30th Sept 2015
![Page 15: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/15.jpg)
Inauguration on 30/05/2015
![Page 16: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/16.jpg)
Inauguration on 30/05/2015
![Page 17: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/17.jpg)
Inauguration on 30/05/2015
![Page 18: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/18.jpg)
Project Photographs as on 30/08/2015
![Page 19: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/19.jpg)
Site Office
![Page 20: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/20.jpg)
Admin Building
![Page 21: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/21.jpg)
ICD Warehouse
![Page 22: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/22.jpg)
Container Yard at ICD
![Page 23: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/23.jpg)
Warehouse-3 (3000 Sq.Mtr Agri Warehouse) Front View
![Page 24: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/24.jpg)
Warehouse-3 (3000 Sqm) view of Tremix Flooring
![Page 25: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/25.jpg)
Warehouse-4 (3600 Sq.Mtr Agri Warehouse) Front View
![Page 26: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/26.jpg)
Warehouse-4 (3600 Sqm Agri Warehouse) Inside View
![Page 27: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/27.jpg)
Rail Warehouse no. 1 – 8125 Sqm
![Page 28: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/28.jpg)
Rail Yard for Line 1 and Line 2
![Page 29: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/29.jpg)
Rail Connectivity on Bhopal end
![Page 30: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/30.jpg)
Track Linking for 3rd Railway Line
![Page 31: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/31.jpg)
Track Linking works in Railway Premises
![Page 32: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/32.jpg)
Cold Storage (3600 Sqm)
![Page 33: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/33.jpg)
Trunk Road from NH to Rail Yard
![Page 34: Development of a Composite Logistics Hub A Public Private Participation initiative by Govt. Of Madhya Pradesh](https://reader036.vdocuments.net/reader036/viewer/2022062409/5697bf901a28abf838c8de65/html5/thumbnails/34.jpg)
Thank You
Logistics Park :
Park (ing) PPPs firmly in MP