TYPIC
AL QUO
TATIO
N
MINIAT
URE S
AMPL
EDear Mr. A Sample,
We are pleased to submit the following quotation as requested for works to be carried out at Foxes Cottage, Bolton Road,Bury St Edmunds, IP32 2DB.
As you may already be aware, we have many years of experience in the building trade and we also keep up to date with thelatest techniques and materials so we are able to provide the best possible job satisfaction for our customers.
We have based the quotation on the site meeting and plans provided.Our emphasis is on consistent quality, whether the job is large or small, and if you decide to change your instructions wecan swiftly provide you with alternative costings.
We use a professional estimating program to ensure our works are accurately priced; we include detailed reports and a fullwritten quotation so you can see exactly what’s been allowed and have clear concise information to further assist with thesmooth running of the work.
When the job is underway we aim to keep you informed throughout and provide careful project management so you willalways be kept up to date on the progress of your contract. We have provided a full work schedule and payment schedulewith this quotation for your perusal.
We hope this quotation is to your satisfaction and look forward to hearing from you soon.
Yours sincerely
Mr Example,Premier Build Ltd
Mr. A SampleFoxes CottageBolton RoadBury St EdmundsIP32 2DB
6th January 2014
Clien
t
Docu
ments
1 Site setup:Not allowed for/not required.
2 Foundations:Set out & excavateSet out foundation area and excavate foundations.
Trench foundationWe have allowed for an excavation of 79 LM of trench foundations 1 LM deep and 450mm wide, leaving the top of theconcrete approximately 300mm below ground level.We've allowed for the removal and disposal of all soils from the site, for the above excavations. Please note: building control o�cers will inspect foundations and may require changes in foundation depths. If changesneed to be made, this would be an additional cost to this quotation.We have assumed that ground conditions are satisfactory, and have therefore not allowed for shoring of the foundations.
3 Ground �oor:Walls up to DPC.
External walls (walls up from foundations to DPC level)Build outer and inner external walls with solid concrete block 100mm and bricks allowance £250.00 per thousandbricks up to DPC level, leaving the outer leaf down 0.3 LM for face work.
Internal load bearing walls (walls up from foundations to DPC level)Construct single internal load bearing walls with solid concrete block 100mm and bricks allowance £250.00 perthousand bricks up to DPC level.Construct double internal walls with solid concrete block 100mm blocks and bricks allowance £250.00 per thousandbricks up to DPC level.We have allowed 300mm of Leicester Red (Ibstock) face work below DPC.
Vegetation soils (top soil)Remove all vegetation soil from oversite area. We have allowed up to 300mm of top soil to be removed from theoversite area.
DPC (Damp Proof Course)We have allowed to install a DPC to the base of all ground �oor walls to the minimum of 150mm above ground level.
Oversite sub-base (ground �oor)We have allowed for 550mm of sub-base below the main �oor to be mechanically compacted down.
DPM (Damp Proof Membrane)Lay radon barrier green 360 mu polythene on 15mm blinding and lapped onto DPC.Insulation (to the ground �oor)Lay �oor insulation Kingspan Kooltherm K3 x 40mm board.
Concrete (ground �oor)For the ground �oor oversite we have allowed to lay a concrete slab 100mm thick.
Block and beamWe have allowed for 150mm beams at 450mm centres for the approximate area of 25.4 m2.We have allowed for a rodent and weed membrane under void area. This barrier will consist of 50mm thick concrete, anda layer of polythene 100 (black).
4 Walls:
External leafFor the main walls we have based our costs on brickwork being, Leicester Red (Ibstock).For section 2 we have based our costs on �rst �oor structure being, Leicester Red (Ibstock).
Internal Leaf (the internal leaf to external walls)For the main walls we have based our costs on blockwork being, lightweight block 100mm.For section 2 we have based our costs on �rst �oor structure being, lightweight block 100mm.
Masonry partition wallsWe have based our material costs on blockwork partitions, building up with lightweight block 100mm.
Cavity insulationWe have allowed for wall insulation Rockwool cavity 75mm to be �tted to all external cavity walls.
LintelsTo be �tted to all new openings with minimum required bearings.
ChimneyWe have allowed for the erection of a 7 LM chimney.
Sca�oldingWe have allowed for the supply and �t of all sca�olding required to carry out necessary works.
5 Above ground �oor: (all �oors above the ground �oor)
Timber JoistsFitted above ground �oors, �tting all necessary restraint straps and �tting intermediate solid noggins to a minimum of2.4 LM centres.
6 Windows and doors:
WindowsSupply and �t new softwood windows.
External doorsWe have allowed for 1 personnel door including frame,1 patio door including frame, 2 French doors including frames.
7 Roof:
Wall plate (timber that roof structure sits on)Fit sawn 47 x 100mm carcassing c16/c24 drygraded softwood timber, held down with restraint straps.
Trusses/Rafters (Roof Structure)We have allowed to �t rafters as per plans �tting all required binders, bracings and gable restraint straps.
Fascia's, So�ts (Fascia's = Boards Guttering is Fixed to)Fascia's to be fascia soft wood 200 x 18mm with so�ts to be plywood structural spruce x 18mm.
Barge boards (boards that are �xed on gables ends)Bargeboards to be PSE timber 18 x 175mm with plywood exterior WBP 6mm to eaves.
Roof coverings We have included breather membrane with tile battens 19 x 38mm (treated) and Redland Concrete Plain Tile Antique Red 03 Granular for the covering of the roof.
Guttering & Down PipesFit standard plastic guttering and downpipes, colour to clients choice.
8 First �x carpentry: (all internal carpentry works required before plastering)
Ground �oorWe've allowed to lay �oor insulation Kingspan Kooltherm K3 x 60mm and polythene 55 (clear) vapour barrier and �t�oor grade chipboard 18mm waterproof treated �ooring.
PlasterboardWe've allowed to �t SE plasterboard 9.5mm to ceiling.
Window boards (board �tted to the internal ledge of window)Window board bullnose MDF 25 x 144mm to be �tted to all windows with the exception of the bathroom, kitchen, utility,and WC.
Stud partition walls (internal timber framed walls)We've allowed to �t new partition walls as shown on plans sawn 47 x 100mm carcassing c16/c24 drygraded softwoodstuds set at 0.6 LM centres clad in SE plasterboard 9.5mm.
StairsWe have based our costs on an allowance for stairs £600.
9 Plastering:
External wallsNot allowed for/not required.
Internal wallsWe have allowed for plaster to all �nished walls; render and set to �nish masonry walls and skim coat plaster to all studpartition walls. To all external corners to walls and opening reveals we have allowed for the �tting of appropriate corner beads. We havealso allowed to �t scrim reinforcement tape to all plasterboard joints and �xings.
CeilingsCeilings to be plastered, again �tting all required scrim reinforcement tape to all joints and �xings.
Coving (plaster moulding to perimeters of rooms)We have allowed for approximately 220 LM plaster cove 100mm to be �tted.
10 Second �x carpentry: (all internal �nished carpentry required after plaster works)
Internal doorsWe have allowed for door interior �ush plywood.For the handles of internal doors we have based the costs on internal door handles brass.
Skirting (timber board with moulding �tted to base of walls to perimeter of rooms)Fit new skirting boards. We have allowed for skirting pine torus 19 x 167mm.
Architraves (timber moulding to the surrounds of internal doors)We have allowed for architrave chamfered 14 x 69mm architrave.
Curtain battens (timbers �tted to above all windows so as to �t curtains to)Fit above all windows, we have allowed for PSE timber 20 x 44mm batten.
Boxing (this is normally a timber casing �tted around pipe work/soil pipes)We have allowed for 3 new boxings to encase pipe work.
Airing cupboard shelvesWe have allowed for 2 airing cupboard shelves approximately 0.6 LM wide and 1 LM long.
Loft hatchesWe have allowed for 2 loft hatches.
11 Alterations:Not allowed for/not required.
12 Electrics:
First �x electricsWe have allowed a P.C Sum of £1600.00 for the 1st �x electrics.
Electric's 2nd �xWe have allowed a P.C Sum of £1600.00 for 2nd �x electrics.
13 Plumbing:Not allowed for/not required.
14 Kitchen:Not allowed for/not required.
15 Decorating
Painting walls / ceilings
PaintingWe have allowed 2.5 coats for painting external plastered walls.We have allowed 2.5 coats for painting internal walls.We have allowed 2 coats for painting internal ceilings and coving.
Painting external framesWe have allowed 1 coat of primer, 1 coat of undercoat, 1 coat of gloss and any knotting required for external decorations.External frames.We have allowed the following items to be painted (external):All windowsExternal door and framePatio door and frameFrench doors and frameRoof items inc. fascia; so�t; bargeboards
16 FinishesWe have allowed for a PC Sum of £900.00 for ceramic wall and �oor tiling.
17 ServicesWe have not allowed for any service connections.
18 Not allowed for/not required.
19 External worksFoul drainage/storm waterWe have allowed for the �tting of 4 new manholes. We have allowed for the �tting of pipe plastic 110mm to runinto 3 new surface water soakaways.
Please note:Upon completion of works, all building materials and debris will be removed from the site and disposed of.
We have allowed the following items to be painted (internal):Architrave and skirtingInternal doorsCarpet stepsLoft hatchWindow boardsStairs inc. ballustrades; handrail, nosing and cappingsCurtain battens
Total quotation price £173,470.57 + VAT Zero Rated
Total price £173,470.57
All building work will be carried out in accordance with building control regulationsThe above quotation costs are based on that stated above and if you have any queries please do not hesitate to contact us.We cannot accept liability for damage caused by suppliers delivery vehicles, or for compaction damage caused by plantmovement on site during the course of the building work.
Client’s responsibilities:We will need access to water and electricity, it would be useful if you could inform us where the stop valve is for the waterand if you know where the electric, phone line, or any other services are located.
1st payment initial payment £10,0002nd payment completion of oversite £30,8003rd payment completion of joists £22,4004th payment completion of wall plate £16,5005th payment completion of roof £39,5006th payment completion of plastering £30,8007th payment completion of contract £23,470.57
So as to help us keep our records up to date, we would appreciate it if you could return the slip below once you havemade your decision.
For quotation dated 1st October 2013 for works to be carried out at Foxes Cottage, Bolton Road, Bury St Edmunds, IP32 7DBwe have decided to:
Accept you quotation Decline your quotation
Signed ...................................... Mr A Sample
If you decide to decline this quotation would you mind informing us of your reason(s):
Price is too high
Work is no longer going ahead
Chosen a cheaper building company
All quotations received were too high
Not proceeding with work until later date
Other.................................................................................................................................................................................................................................................
.............................................................................................................................................................................................................................................................
.............................................................................................................................................................................................................................................................
FoundationsClient Summary
Hours =
Plant =Materials =
Labour =Total =
£1,634.57£2,636.84£2,411.65£6,683.0593
Ground Floor
Hours =
Plant =Materials =
Labour =Total =
£1,780.10£8,308.54£5,406.61
£15,495.25213
Walls
Hours =
Plant =Materials =
Labour =Total =
£835.10£12,274.31£14,472.08£27,581.49575
Sca�olding
Hours =
Plant =Materials =
Labour =Total =
£963.90£0.00
£3,277.26£4,241.16120
Windows & Door Frames
Hours =
Plant =Materials =
Labour =Total =
£67.81£3,469.40£443.36
£3,980.5716
Glazing
Hours =
Plant =Materials =
Labour =Total =
£0.00£2,577.53£354.42
£2931.9411
Lintels
Hours =
Plant =Materials =
Labour =Total =
£0.00£838.00£118.05£956.045
Above Ground Floors
Hours =
Plant =Materials =
Labour =Total =
£0.00£521.19£578.10
£1099.2921
Roof Structure
Hours =
Plant =Materials =
Labour =Total =
£0.00£9,090.10£4,277.45
£13,367.55157
Roof Tiling
Hours =
Plant =Materials =
Labour =Total =
£714.31£17,925.79£5,834.47
£24,474.58234
Guttering
Hours =
Plant =Materials =
Labour =Total =
£0.00£499.55£573.24
£1,072.7921
1st Fix Carpentry
Hours =
Plant =Materials =
Labour =Total =
£91.46£8,891.01£7,433.00
£16,415.47278
Electrics 1st Fix (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£708.87£891.13
£1,600.0033
Plastering
Hours =
Plant =Materials =
Labour =Total =
£471.94£4,024.57£8,796.28
£13,929.79357
Electrics 2nd Fix (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£587.25
£1,012.75£1,60037
2nd Fix Carpentry
Hours =
Plant =Materials =
Labour =Total =
£0.00£5,179.01£4,115.90£9,294.91153
Finishes (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£469.06£430.94£900.0019
Foul/Stormwater Drainage
Hours =
Plant =Materials =
Labour =Total =
£1,353.57£3,573.07£2,005.08£6,931.5377
Driveway
Hours =
Plant =Materials =
Labour =Total =
£887.74£3,967.57£3547.04£8,402.35137
Decorating
Hours =
Plant =Materials =
Labour =Total =
£0.00£893.91
£11,618.91£12,512.81
Total=Total Tax=
Total Price =
£173,470.57£0.00
£173,470.57
450
Total Days =Total Weeks =
154 Days31 Weeks (based on a 5 day week)
Start Date:Completion Date:
25-Feb-1428-Sep-14
No. of Days (per stage)
Please note that bad weather or additional works are not allowed for.
6 Days
3 Days
8 Days
3 Days
1 Days
13 Days
Foundations
Foul/Stormwater Drainage
Ground Floor
25-Feb-14
05-Mar-14
10-Mar-14
Walls
Sca�olding
Windows & Door Frames
29-Mar-14
08-Apr-14
13-Apr-14
Lintels
Walls
Above Ground Floor
14-Apr-14
15-Apr-14
20-Apr-14
Foundations
Foul/Stormwater Drainage
Ground Floor
04-Mar-14
09-Mar-14
26-Mar-14
Start Work Finish Works
PaymentInitial Payment £10,000.00 £10,000.00 Due on: 25-February-2014
Completion of Oversite £30,800.00 £30,800.00 Due on: 26-March-2014
Completion of Joists £22,400.00 £22,400.00 Due on: 20-April-2014
Completion of Wall Plate £16,500.00 £16,500.00 Due on: 12-May-2014
Completion of Roof £39,500.00 £39,500.00 Due on: 24-June-2014
Completion of Plastering £30,800.00 £30,800.00 Due on: 04-August-2014
Completion of Contract £23,470.57 £23,470.57 Due on: 28-September-2014
VAT Total Due Date
1 Days
1 Days
3 Days
Walls
Sca�olding
Windows & Door Frames
07-Apr-14
12-Apr-14
13-Apr-14
Lintels
Walls
Above Ground Floor
14-Apr-14
19-Apr-14
20-Apr-14
5 Days
1 Days
1 Days
Walls
Sca�olding
Windows & Door Frames
21-Apr-14
28-Apr-14
29-Apr-14
Lintels
Sca�olding
Walls
30-Apr-14
03-May-14
06-May-14
1 Days
5 Days
3 Days
Walls
Sca�olding
Roof Structure
13-May-14
21-May-14
24-May-14
Roof tiling
Guttering
Sca�olding
07-Jun-14
21-Jun-14
23-Jun-14
Glazing
1st Fix Carpentry
Plastering
25-Jun-14
28-Jun-14
21-Jul-14
1 Days
11 Days
17 Days
Glazing
1st Fix Carpentry
Plastering
25-Jun-14
20-Jul-14
04-Aug-14
Walls
Sca�olding
Windows & Door Frames
20-May-14
21-May-14
04-Jun-14
Roof tiling
Guttering
Sca�olding
18-Jun-14
22-Jun-14
24-Jun-14
Walls
Sca�olding
Windows & Door Frames
27-Apr-14
28-Apr-14
29-Apr-14
Lintels
Sca�olding
Walls
30-Apr-14
05-May-14
12-May-14
2nd Fix Carpentry
Foul/Stormwater Drainage
Decorating
05-Aug-14
19-Aug-14
20-Aug-14
Driveway 06-Sep-14
2nd Fix Carpentry
Foul/Stormwater Drainage
Decorating
18-Aug-14
19-Aug-14
03-Sep-14
Driveway 28-Sep-14
Work Schedule
10 Days
11 Days
17 Days
1 Days
6 Days
1 Days
10 Days
10 Days
2 Days
2 Days
Work Schedule
Driv
eway
Com
plet
ion
of O
vers
iteCo
mpl
etio
n of
Joist
sCo
mpl
etio
n of
Wal
l Pla
teCo
mpl
etio
n of
Roo
fCo
mpl
etio
n of
Pla
ster
ing
Com
plet
ion
of C
ontr
act
Dec
orat
ing
Foul
/Sto
rmw
ater
Dra
inag
e
2nd
Fix
Carp
entr
y
Plas
terin
g
1st F
ix C
arpe
ntry
Gla
zing
Sca�
oldi
ng
Gut
terin
g
Roof
Tili
ng
Roof
Str
uctu
re
Sca�
oldi
ng
Wal
ls
Wal
ls
Sca�
oldi
ng
Lint
els
Win
dow
s & D
oor
Fram
es
Sca�
oldi
ng
Wal
ls
Abo
ve G
roun
d Fl
oors
Wal
ls
Lint
els
Win
dow
& D
oor
Fram
es
Sca�
oldi
ng
Wal
ls
Gro
und
Floo
r
Foul
/Sto
rmw
ater
Dra
inag
e
Foun
datio
ns
020
4060
8010
012
014
016
018
0
Foundations
Summary
Hours =
Plant =Materials =
Labour =Total =
£1,362.14£2,292.90£1,773.27£5,428.31
Ground Floor
Hours =
Plant =Materials =
Labour =Total =
£1,483.42£7,224.82£3,975.45
£12,683.69
Walls
Hours =
Plant =Materials =
Labour =Total =
£695.92£10,061.09£10,641.23£21,398.24
Sca�olding
Hours =
Plant =Materials =
Labour =Total =
£803.25£0.00
£2,409.75£3,213.00
Windows & Door Frames
Hours =
Plant =Materials =
Labour =Total =
£56.51£3,016.87£326.00
£3,980.57
Glazing
Hours =
Plant =Materials =
Labour =Total =
£0.00£2,241.33£260.60
£2,501.93
Lintels
Hours =
Plant =Materials =
Labour =Total =
£0.00£728.69£86.80
£815.49
Above Ground Floors
Hours =
Plant =Materials =
Labour =Total =
£0.00£453.21£425.07£878.28
Roof Structure
Hours =
Plant =Materials =
Labour =Total =
£0.00£7,904.43£3,145.19
£11.049.62
Roof Tiling
Hours =
Plant =Materials =
Labour =Total =
£595.26£15,587.65£4,290.05
£20,472.96
Guttering
Hours =
Plant =Materials =
Labour =Total =
£0.00£434.39£421.50£855.89
1st Fix Carpentry
Hours =
Plant =Materials =
Labour =Total =
£76.22£7,731.31£5,465.44
£13,272.97
Electrics 1st Fix (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£629.41£791.23
£1,420.64
Plastering
Hours =
Plant =Materials =
Labour =Total =
£393.28£3,499.63£6,467.85
£10,360.76
Electrics 2nd Fix (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£513.52£885.60
£1,399.12
2nd Fix Carpentry
Hours =
Plant =Materials =
Labour =Total =
£0.00£4,503.49£3,026.40£7,529.89
Finishes (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£399.13£366.70£765.83
Foul/Stormwater Drainage
Hours =
Plant =Materials =
Labour =Total =
£1,127.81£3,107.02£1,474.33£5,709.16
Driveway
Hours =
Plant =Materials =
Labour =Total =
£739.78£3,450.07£2,608.12£6,797.96
Decorating
Hours =
Plant =Materials =
Labour =Total =
£0.00£777.31
£8,543.31£9,320.62
93
213
575
120
16
11
5
21
157
234
21
278
33
357
37
153
19
77
137
450
Foundations
Summary
Hours =
Plant =Materials =
Labour =Total =
£1,362.14£2,292.90£1,773.27£5,428.31
Ground Floor
Hours =
Plant =Materials =
Labour =Total =
£1,483.42£7,224.82£3,975.45
£12,683.69
Walls
Hours =
Plant =Materials =
Labour =Total =
£695.92£9,685.14
£10,641.23£21,022.29
Sca�olding
Hours =
Plant =Materials =
Labour =Total =
£803.25£0.00
£2,409.75£3,213.00
Windows & Door Frames
Hours =
Plant =Materials =
Labour =Total =
£56.51£3,016.87£326.00
£3,399.38
Glazing
Hours =
Plant =Materials =
Labour =Total =
£0.00£2,241.33£260.60
£2,501.93
Lintels
Hours =
Plant =Materials =
Labour =Total =
£0.00£728.69£86.80
£815.49
Above Ground Floors
Hours =
Plant =Materials =
Labour =Total =
£0.00£453.21£425.07£878.28
Roof Structure
Hours =
Plant =Materials =
Labour =Total =
£0.00£7,904.43£3,145.19
£11,049.62
Roof Tiling
Hours =
Plant =Materials =
Labour =Total =
£595.26£15,587.65£4,290.05
£20,472.96
Guttering
Hours =
Plant =Materials =
Labour =Total =
£0.00£434.39£421.50£855.89
1st Fix Carpentry
Hours =
Plant =Materials =
Labour =Total =
£76.22£7,731.31£5,465.44
£13,272.97
Electrics 1st Fix (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£629.41£791.23
£1,420.64
Plastering
Hours =
Plant =Materials =
Labour =Total =
£393.28£3,499.63£6,467.85
£10,360.76
Electrics 2nd Fix (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£513.52£885.60
£1,399.12
2nd Fix Carpentry
Hours =
Plant =Materials =
Labour =Total =
£0.00£4,503.49£3,026.40£7,529.89
Finishes (P.C. Sum)
Hours =
Plant =Materials =
Labour =Total =
£0.00£399.13£366.70£765.83
Foul/Stormwater Drainage
Hours =
Plant =Materials =
Labour =Total =
£1,127.81£3,107.02£1,474.33£5,709.16
Driveway
Hours =
Plant =Materials =
Labour =Total =
£739.78£3,450.07£2,608.12£6,797.96
Decorating
Hours =
Plant =Materials =
Labour =Total =
£0.00£777.31
£8,543.31£9,320.62
93
213
575
120
16
11
5
21
157
234
21
278
33
357
37
153
19
77
137
450
Compa
ny
Docu
ments
Total Floor Area M2 =Total Cost Per M2=
Total Quotation Price Per M2=Total Cost Is =
193.8£718.70£888.09
£138,897.79
Total Floor Area Square Foot =Total Cost Per Square Foot=
Total Quatation Price Per Square Foot=
2,086.3£68.58£82.51
Plant Cost £7,333.59
Mark up Margin On PlantQuotation For Plant
£1,466.72£8,800.31
Materials Cost £74,180.32
Mark up Margin On MaterialsQuotation For Materials
Labour Cost£55,340.36
Clear Pro�t£10,571.99
Overheads£22,283.80
Materials Cost£73,014.20
PC Sums£3,585.59
Plant Cost£7,333.59
£11,127.05£85,307.37
20 %
15 %
Labour Cost £55,340.36
Mark up Margin On LabourQuotation For Labour
£19,922.53£75,262.89
36 %
PC Sums £3,585.59
Mark up Margin On PlantQuotation For Plant
£514.41£4,100.00
10 %
Services and professional fees £0.00
Mark Up On ServicesQuotation For Services & Fees
£0.00£0.00
20 %
Gross Percentage On CostsClear Pro�t On Costs
Clear Pro�t On Quotation PriceOver HeadsClear Pro�t
Total Direct CostsTotal mark up on job, covering overheads & pro�t
Total Quotation PriceVAT/Tax
Total Price
23.59 %7.59 %6.14 %
£22,470.38£10,659.39
£140,439.86£33,030.71
£173,470.57£0.00
£173,470.57
16 %
Bill of Quantities
This is a sample. This report continues for every section of the works.
WallsQuantity
1128625072152
1015.5103998279
Unit TypeBricksBlocksBricksRollsTonsBagsNo
PacksNo
DescriptionLeicester Red (IBSTOCK)Lightweight Block 100mmAllowed PC. Of £400.00 per ThousandDPC. 100mm x 30LMBricking Sand 1 TonCement Bag (25kg Bag)Wall Tie Butter�y Steel 200mmWall Insulation Rockwool Cavity 50mmPlasterciser 5 LitreClay Flue Liner 185mm Int DIa 180mm Tall
Plant Material£3,950.10£1,905.32£989.92£44.85
£645.62£354.17£218.06£450.85£41.40
£473.17
Labour£7,248.61£5,597.76£1,077.12£168.40
£48.55
Total Cost£11,198.71£7,503.08£2,067.04£213.25£645.62£354.17£218.06£450.85£41.40
£521.72
FoundationsQuantity
185643233
168842
26.5
Unit TypeDay
StakesLM
RollsCansDaysDaysLMLM
PackM3
DescriptionBuilders Auto Level38 x 38 x 800mm StakesSawn 25 x 100mm (treated)Brickline Marshalltown Hi-Viz 28 x 11 x 49 cm x 76MLine Marker (yellow spray) No-Nonsense 750mlExcavator 3.5 TonDumper 4 TonReinforcement Bar Mildsteel 16mm per meterReinforcement Bar Mildsteel 20mm per meterSpacers Plastic 65/75mm x 125Concrete Foundation (6 m3 Loads)
Plant£39.77
£429.23£325.57
£1634.57
Material
£81.13£77.28£17.28£14.90
£139.10£100.46£91.70
£2,114.97
£2,636.84
Labour£206.72
£620.16£620.16£163.31£81.65
£616.28
£2,411.65
Total Cost£246.49£81.13£77.28£17.28£14.90
£1,049.39£945.73£302.41£182.11£91.70
£2,731.25
£6,683.06
Ground FloorQuantity
22
443269152135
3209386
27271
0.21
1.51.51
1031122
10351
281
62
Unit TypeDaysDaysBricksBlocksBlocksBlocksTonsBagsNoNo
DaysM2
BagsBagsDayNoDayM3M3RollTonDayDayTonsRollsM3
SheetsSheetsSheets
PackNo
DescriptionExcavator 3.5 TonDumper 4 TonAllowed PC of £250.00 Per ThousandTrench Block Thermalite 255mmTrench Block Thermalite 255mmSolid Concrete Block 100mmBricking Sand 1 TonCement (25kg Bag)Wall Tie Butter�y Steel 225mmConcrete Lintel 70 x 100 x 1200mm4/3 Mini Mix Petrol150mm Beams at 450mm CentresCement (25kg Bag)Plastering Sand (25kg Bag)Disc Cutter 350mm PetrolDiamond Disc (12”)4/3 Mini Mix PetrolLean Mix (3 M3 Loads)Additional Cost for Part LoadPolythene 100 (Black) 4 x 25mCrushed Concrete (20 Ton Loads)Excavator 2.8 TonPlate CompactorBricking Sand (5 Ton Loads)Radon Barrier Green 15 x 4 360muConcrete Oversite (6 M3 Loads)Floor Insulation Kingspan Kooltherm K3 40mmFloor Insulation Kingspan TF70 25mmA142M Mesh 3600 x 2000mmSpacers Plastic 40/50mm x 200Spacers Wire Chairs 200mm A Frame 25 x 2m
Plant£302.15£229.04
£128.98
£46.52£18.72£26.50
£131.28£56.92
£1,780.10
Material
£127.36£940.42£531.39£197.79£124.96£68.77£23.53£59.89
£698.94£6.88
£14.49
£127.65£43.13£34.52
£1,972.19
£62.91£242.97
£1,033.85£902.81£13.23
£767.65£45.85
£267.38
£8,308.54
Labour£413.44£413.44£326.40£707.20£408.00£778.41
£54.40
£393.80
£34.88
£13.12£743.25£206.72
£76.23£36.20
£280.02£120.70
£7.36£289.68
£5,406.63
Total Cost£715.59£642.48£453.76
£1,647.62£939.39£976.20£124.96£68.77£23.53
£114.29£128.98
£1,092.74£6.88
£14.49£46.52£18.72£26.50
£162.53£43.13£47.64
£2,715.44£338.00£56.92
£139.14£279.17
£1,313.87£1,023.51
£20.59£1,057.33
£45.85£267.38
£15,495.27
Walls
Breakdown of Direct Costs for the ContractPlant Cost£7,333.59
5%
Payment Chart
Materials Cost£74,180.32
52%
Labour Cost£55,340.36
40%
PC Sums Cost£3,585.59
3%
Completion of Roof£39,500.00
23%
Completion of Plastering£30,800.00
18%
Completion of Contract£22,129.53
23%
Initial Payment£10,000.00
6%
Completion of Oversite£30,800.00
18%
Completion of Joists£22,400.00
13%
Completion of Wall Plate£16,500.00
9%
Foundations
Ground Floor
Walls
Sca�olding
Windows & Door Frames
Glazing
Lintels
Above Ground Floors
Roof Structure
Roof Tiling
Guttering
1st Fix Carpentry
Electrics 1st Fix (P.C. Sum)
Plastering
Electrics 2nd Fix (P.C. Sum)
2nd Fix Carpentry
Finishes (P.C. Sum)
Foul/Stormwater Drainage
Driveway
Decorating
£0.00 £5,000.00 £10,000.00 £15,000.00 £20,000.00 £25,000.00
Works Chart Costs to Each Section of Works
Material Order SheetFoundations Unit CostUnitQuantityDescription Total
38 x 38 x 800mm long stakesSawn 25 x 100mm (treated)
Brick line Marshalltown Hi-Viz 28x11x49cm x 76MLine Marker (yellow spray) No-Nonsense 750ml
Reinforcement Bar Mildsteel 16mm per meterReinforcement Bar Mildsteel 20mm per meter
Spacers Plastic 65/75mm x 125Concrete foundation (6 m3 loads)
856432
168842
26.5
StakesLM
RollsCansLMLM
PackM3
£0.83£1.05£5.01£6.48£0.72£1.04
£39.87£69.40
Total
£70.55£67.20£15.03£12.96
£120.96£87.36£79.74
£1,839.10
£2,292.90
Ground FloorAllowed PC. of £250.00 per Thousand
Trench Block Thermalite 255mmSolid Concrete Block 100mm
Bricking Sand 1 tonCement (25kg Bag)
Wall Tie Butter�y Steel 225mmConcrete Lintel 20 x 100 x 1200mm
150mm Beams at 450mm CentresPlastering Sand (25kg Bag)
Lean Mix (3 m3 Loads)Additional Cost For Part Load
Polythene 100 (Black) 4 x 25mCrushed Concrete (20 ton loads)
Bricking Sand (5 ton loads)Radon Barrier Green 15 x 4m 360mu
Concrete Oversite (6 m3 loads)Floor Insulation Kingspan Kooltherm K3 1200 x 2400 x 40mm
Floor Insulation Kingspan TF70 2400 x 1200 x 25mmA142M Mesh 3600 x 2000 mm
Spacers Plastic 40/50mm x 200Spacers Wire Chairs 200mm A Frame 25 x 2m
443421135
322938
277
1.51.51
10322
10351
281
62
BricksBlocksBlocksTonsBagsNoNoM2
BagsM3M3RollTonsTonsRollsM3
SheetsSheetsSheets
PackNo
£0.25£3.04£1.27
£36.22£2.99£0.22£6.51
£22.51£1.80
£74.00£25.00£30.02£16.65£27.35
£105.64£89.90£22.43£11.50£23.84£39.87£3.75
Total
£110.75£1,279.84£171.99£108.66£65.78£20.46£52.08
£607.77£12.60
£111.00£37.50£30.02
£1,714.95£54.70
£211.28£899.00£785.05£11.50
£667.52£39.87
£232.50
£7,224.82
Leicester Red (IBSTOCK)Lightweight Block 100mm
Allowed PC of £400.00 per ThousandDPC. 100mm x 30LM
Bricking Sand 1 tonCement (25kg Bag)
Wall Tie Butter�y Steel 200mmWall Insulation Cavity 50 x 1200 x 455m (12pp)
Plasterciser 5 litreClay Flue Liner 185mm Int Dia 180mm TallClay Flue Liner 225mm Int Dia 300mm Tall
Milner Scored Fire Back (450mm Height)Roll Top Chimney Pot (900mm Length)
Pipe Plastic 100mm 6m LengthBend 87.5 Deg Single Socket PCVu
Air Brick 220 x 145mmLouvre Vent 229 x 76 x 229
Cavity Closer Rigid 100mm x 2.5m
1128625072152
1015.5103998279
393112221
64
BricksBlocksBricksRollsTonsBagsNo
PacksNoNoNoNoNoNoNoNoNoLM
£0.35£0.76£0.40£3.90
£36.22£2.99£0.19
£14.52£4.00
£10.55£13.50£60.00
£100.70£16.17£5.95£3.26£0.59
£12.17
Total
£3,950.10£1,905.32£860.80£39.00
£561.41£307.97£189.62£392.04£36.00
£411.45£40.50£60.00
£100.70£32.34£11.90£6.52£0.59
£778.88
£9,685.14
Windows and Doors1.2 x 1.2 Softwood Window
1.774 x 1.2 Softwood Window1.832 x 2.076 Hardwood Front Doorframe+2 Side Frame
2.41 x 2.1 Hardwood Sub Frame1.8 x 2.1 Hardwood French Doorframe
Window Anchor 8 x 100mm pack of 10
143112
31
NoNoNoNoNo
Boxes
£113.41£113.41£366.23£92.60
£300.00£0.97
Total
£1,587.74£340.23£366.23£92.60
£600.00£30.07
£3,016.87
This is a sample. This report continues for every section of the works.