Facilities Modernization ProgramFunded by Measure B
Project Report
March 19, 2012
![Page 2: Facilities Modernization Program Funded by Measure B Project Report March 19, 2012](https://reader031.vdocuments.net/reader031/viewer/2022032606/56649eaa5503460f94bb001e/html5/thumbnails/2.jpg)
PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)
Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction
Project Update:• Project is complete.• DSA Closeout is in progress.
Occupancy: 04/2011
LAS POSITAS COLLEGEMarch 19, 2012
![Page 3: Facilities Modernization Program Funded by Measure B Project Report March 19, 2012](https://reader031.vdocuments.net/reader031/viewer/2022032606/56649eaa5503460f94bb001e/html5/thumbnails/3.jpg)
PROJECT PROGRESS REPORTScience Building, Phase II
Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc
Project Update:• Interior Casework, Lighting and Fume hoods being installed.• Exterior Painting is in progress. Interior Painting is Completed. • Electrical and Data installation and termination is continuing at first and second floors.• Flooring at 2nd floor classrooms completed.• Storefront installation and Glazing Completed.• Stair Treads installed.
Occupancy: 09/2012
LAS POSITAS COLLEGEMarch 19, 2012
![Page 4: Facilities Modernization Program Funded by Measure B Project Report March 19, 2012](https://reader031.vdocuments.net/reader031/viewer/2022032606/56649eaa5503460f94bb001e/html5/thumbnails/4.jpg)
PROJECT PROGRESS REPORTStudent Services & Central Administration
Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction
Project Update:• GFRC installation complete.• Storefront installation has started along with glazing.• Site fine grading is complete.• Building metal panels have to start within 2 weeks.• Sheetrock has started on one side of the walls.• Elevator installation to begin next week.• Roofing is complete.
Occupancy: Spring 2013
LAS POSITAS COLLEGEMarch 19, 2012
![Page 5: Facilities Modernization Program Funded by Measure B Project Report March 19, 2012](https://reader031.vdocuments.net/reader031/viewer/2022032606/56649eaa5503460f94bb001e/html5/thumbnails/5.jpg)
PROJECT PROGRESS REPORTCampus Boulevard Phase I-III
Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: TBD
Project Update:• 100% Design review completed, final design was Approved by DSA February 2012. • Project was Bid on March 13, 2012 and Low Bid Contractor will be Board Approved April 17, 2012
Design Re-Start: 04/2011DSA Permit Approval: 02/2012Construction Start: 05/2012Occupancy: TBD
LAS POSITAS COLLEGEMarch 19, 2012
![Page 6: Facilities Modernization Program Funded by Measure B Project Report March 19, 2012](https://reader031.vdocuments.net/reader031/viewer/2022032606/56649eaa5503460f94bb001e/html5/thumbnails/6.jpg)
PROJECT PROGRESS REPORTPhotovoltaic System Phase II
Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff
Project Update:• Fencing Completed.• Racking System and Array installation is completed.• Inverters and Transformer installed and completed. • New Switchgear tie in during Spring Break.
Operational: February 2012
LAS POSITAS COLLEGEMarch 19, 2012