Transcript
Page 1: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Rolling Road Wideningfrom Fullerton Road to Delong DriveFairfax County Project # 1400023-2009

April 19, 2012

Page 2: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Project Description

■ Widen a 2-lane roadway to 4-lanes

■ Add new sidewalk, bike lanes and shared use path

■ Upgrade traffic signals, drainage and utilities

■ Estimated total project cost is $17,800,000

■ Project distance is 1.1 miles

Page 3: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Project Objectives

■ Accommodate future traffic demand

■ Reduce congestion and improve vehicular circulation

■ Improve accommodations for pedestrians (ADA) and bicyclists

■ Improve access to Route 1 and Fairfax County Parkway

Page 4: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Project Objectives (continued)

■ Minimize stormwater impacts to Accotink and Pohick creeks

■ Improve safety by increasing sight distance

■ Provide access management, including a raised median, to improve safety

Page 5: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Project Area Map

Page 6: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Proposed Typical Section4-lane divided roadway with shared lanes, sidewalk and shared use path

Page 7: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Implemented Changes to Reduce Impacts to Properties

Reduce width of thru lanes from 12 feet to 11 feet.

Right-of-way width reduced by 4 feet. 

Provide 14 foot outside shared lanes in lieu of the 4 foot bike lanes.

Right-of-way width reduced by 4 feet. 

Reduce Shared Use Path width from 10 feet to 8 feet in constrained locations.

Right-of-way width reduced by 2 feet. 

Shift horizontal alignment between stations 156+00 to 163+00 to avoid impact on Saratoga Square Apartments and the community center.

Community center will remain in its current location and parking lot will lose fewer parking spaces. 

Using all proposed recommendations. Total right-of-way width reduced by 8 to10 feet.

 

Value Engineering Recommendation Result

Page 8: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Design Changes from Previous

Citizens Information MeetingTraffic SignalsSignal warrants performed at four intersections. Based on volume three intersections did not meet the warrant – Delong Drive, Northumberland Road, and Edinburgh Drive (South intersection). Warrant met at Saratoga Shopping Center main entrance

CrosswalksCrosswalks location added to the plan including one mid-block crossing near Terra Grande Avenue. Crosswalk warrants to be performed, final approval by VDOT.

Reduced Community ImpactsAvoided Community Center at Saratoga Square Apartments.

Roadway moved further from Newington Community Pool.

Page 9: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Funding and Schedule

Funding$1.3 million OEA grant for design (Office of Economic Adjustment, Department of Defense)

No funding identified for right-of-way or construction 

ScheduleRight-of-way authorization – Fall /Winter 2013 (pending funding availability)

Complete design – Winter/Spring 2014 (pending funding availability) Utility relocation – Winter 2013 to Spring 2014 (pending funding availability) Construction advertised – Spring 2014 (pending funding availability) Construction complete – Fall 2015 (pending funding availability)

Page 10: FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012

Questions?


Top Related