Transcript
Page 1: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures Week 16

• Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10

Page 2: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures• Steelwork installed to

tapered wall and foundation for flank wall 4 and starter bars.

Page 3: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures• Gas meter house

demolished, foundation excavated from C1 – C5 and 50% blinded, 3no column bases excavated

Page 4: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures Water tank downstand

beams poured, tanks sanded up and insulation and volclay installed.

Page 5: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures

2no underpins excavated and poured.


Top Related