Page 1: GENERAL LAYOUT PLAN FOR THE STUDY AREA VENDARASAN KULAM … and Kaluganga/UEC_Map_si.pdf · 6 5 + 5 0 0 6 5 + 0 0 0 6 2 + 5 0 6 0 + 0 0 5 7 + 5 0 5 + 0 0 5 2 + 5 0 5 0 + 0 0 4 7 +

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/"/

"/

"/"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

"/

65+50

065+

000

62+500

60+000

57+500

55+000

52+500

50+000

47+500

45+000

42+500

40+000

37+500

35+000

32+500

30+000

27+509

25+000

22+500

20+000

17+500

15+00012+500

10+000

7+500

5+000

2+500

0+000

6+226

54+249

TUNNEL NO 2

TUNNEL NO 3

PROPOSED CUT & COVER SECTION

PROPOSED KALU GANGA MORAGAHAKANDATRANSFER ROUTE (KMTC)

PROPOSED ERUWEWA MANANKATTIYA DIVERSION CANAL

PROPOSED UPPER ELAHERA CANAL 65.5 KM (UEC)

PROPOSED NCP CANAL

Kala Oya

Y anOy

a

K ir i O

ya

Kanadara Oya

MoragollaOya

Talkot eoy a

Kalu

G anga

Amban Ganga

Ruppe Ela

Erig e oya

Malwat uO ya

Aban Ganga

Dambulu Oya

Maha

w eli G

anga

Halmilla Oya

Kongetiya Oya

Habarana Oya

Heerati Oya

Siyab

alang

amuw

a oya

HURULU WEWA FEEDER CANAL (HFC)

ELEHERA MINNERIYA YODA ELA(EMYE)

EXISTING BOWATENNA TUNNEL

SIGIRIYA WEWA

PAHALA TALKOTE WEWA

MUSEUM ARCHAEOLOGICAL RESERVE

NORTH WESTERN PROVINCE DIVERSION CANAL (NWPC)

PROPOSED MAHAKANADARAWA DIVESION

PROPOSED KALINGANUWARAPUMPING COMPLEX

WASGAMUWA EXTENSION

PROPOSED ELEPHANT CORRIDOR

WASGAMAWA NATIONAL PARK

MINNERIAYA NATIONAL PARK

SOMAWATHIYA NATIONAL PARK

KAUDULLA MINNERIYA NATIONAL PARK

SIGIRIYA SANCTUARY

ANGAMMADILLA NATIONAL PARK

GIRITALE NR

KAHALA - PALLEKALE SANCTUARY

MINNERIYA-GIRITALE NATURE RESERVEELAHARA GIRITALE SANCTUARY

KAUDULLA NATIONAL PARK

POLONNARUWA SANCTUARY

RITIGALA SANCTUARY

FLOOD PLAINS NATIONAL PARK

MADURU OYA NATIONAL PARK

HURULU FOREST RESERVE

KAHALLA FOREST RESERVE

CHUNDANKADU FOREST RESERVE

PALLEKELE FOREST RESERVE

KANTALAI FOREST RESERVE

PALWEHERA FOREST RESERVE

INAMALUWA FOREST RESERVE

MIHINTALE F.R.

PALLEKELE FOREST RESERVE

YODAELA F.R.

GORAKADOLA FOREST RESERVE

CHUNDANKADU FOREST RESERVE

PALLEKELE FOREST RESERVE

KIRINDIGALLA F.R.

KALA WEWA

KAUDULLA WEWA

MINNERIYA WEWA

PARAKRAMA SAMUDRA

HURULU WEWA

KANTALE WEWA

BALALU WEWA

NACHCHADUWA WEWA

KANDALAMA TANK

ERU WEWA

GIRITALE WEWA

DEWAHUWA WEWA

NALANDA RESERVOIR

DAMBULU OYA RESERVOIR

MANANKATTIYA WEWA

BOWATHENNA RESERVOIR

MAHAKANDARA WEWA

WEMEDILLA RES

HABARANA WEWA

HIRIWADUNNA WEWA

PAHALA TALKOTE WEWA

MAHA ILUPPALLAMA TANK

SIGIRIYA WEWA

HINGURU WEWA

ANDIYAGALA TANK

VENDARASAN KULAM

KALU GANGA RESERVOIR

KONGETIYA RESERVOIR

MADETHTHA WEWA

RIDIELLA RESERVOIRHEERATI OYA RESERVOIR

BOGAHA WEWA

NAULA

YAKALLA

GAL OYA

YAKKURE

KIBISSA

ELAHERA

NEW TOWN

BAKAMUNA

GIRITALE

SIRIPURA

HABARANA

ALUT OYA

DAMBULLA

GALKULAMA

DIYABEDUMA

GANEWALPOLA

PALUGASWEWA

POLONNARUWA

PARAWAHAGAMA

KALINGANUWARA

KAWUDUPELELLA

PADIKARAMADUWA

GALOYA JUNCTION

ATTHANAKADAWALA

£¤A6

£¤A11

£¤ A9

£¤B34

£¤B64

£¤B38

£¤A12

£¤B63

£¤A13

£¤A9

¬«C

¬«H

¬«E

¬«D1

¬«M/H

MORAGAHAKANDA RESERVOIR

170000 180000 190000 200000 210000 220000 230000

26000

0270

000

28000

0290

000

30000

0310

000

32000

0330

000

34000

0350

000

GENERAL LAYOUT PLAN FOR THE STUDY AREA

±

DATA SOURCE: - 1:50,000 LAND USE PLAN DEPARTMENT OF SURVEY SRI LANKA Environment Impact Assessment (EIA)- Upper Elahera Canal 2013/2014

NOTE :1.REFER FIG NO - 3.8 Sheet 1 to 9 FOR 1:10,000 LAND USE PLAN

0 105 Kilometers

Legend"/ Twon / Village

Existing Power StationProposed Power StationExisting Irrigation CanalMK - Kaluganga Link TunnelOpen CanalDouble ConduitLevel CrossingAqueductCut & Cover TunnelProposed Other Irrigation CanalExisting Irrigation TunnelRoad - Class ARoad - Class BRailwayRiver / StreamExisting Tank / Reservoir

Reservoir Under Construction Home GardenForest ReserveNational ParkNature PeserveSanctuaryStrict Nature ReserveProposed Forest CorridorMahaweli_Systems