![Page 1: HOW TO AVOID OR REDUCE LIQUIDATED DAMAGES · PDF file · 2015-12-15clause fixes a sum recoverable by the owner as damages for each day work extends beyond the ... the per-day sum](https://reader031.vdocuments.net/reader031/viewer/2022030407/5a85783a7f8b9a87368cce61/html5/thumbnails/1.jpg)
-1-
HOW TO AVOID OR REDUCE LIQUIDATED DAMAGES WHEN A JOB TAKES LONGER THAN ORIGINALLY ANTICIPATED
Roofing contractors are frequently delayed by adverse weather conditions, delays caused
by their suppliers or subcontractors, changes to the scope of work and a host of other causes.
Besides merely putting a project behind schedule, such delays may have a serious financial effect
on a roofing contractor particularly if the contract provides for “liquidated damages.”
Because the financial effects suffered by an owner as a result of delays are often difficult
to quantify, many owners employ liquidated damages clauses instead. A liquidated damages
clause fixes a sum recoverable by the owner as damages for each day work extends beyond the
scheduled substantial completion date because of an unexcused contractor delay. Liquidated
damages serve as a substitute for any actual damages the owner might incur as a result of such a
delay. These clauses are typically enforced by courts on freedom of contract principles unless
the per-day sum is so exorbitant that, viewed from the time the contract was executed, it could
not bear any reasonable relation to the likely actual damages that would be suffered by the owner
in the event of a delay. This is a difficult standard to meet, and a roofing contractor should
generally assume damages will be assessed at the agreed-upon rate without regard to the actual
losses incurred by the owner.
ADDRESS SCHEDULE AND LIQUIDATED DAMAGES IN CONTRACTS
Although a roofing contractor may be unable to perform work because of conditions
beyond his or her control, roofing contractors sometimes unwittingly assume the risk of such
– more –
![Page 2: HOW TO AVOID OR REDUCE LIQUIDATED DAMAGES · PDF file · 2015-12-15clause fixes a sum recoverable by the owner as damages for each day work extends beyond the ... the per-day sum](https://reader031.vdocuments.net/reader031/viewer/2022030407/5a85783a7f8b9a87368cce61/html5/thumbnails/2.jpg)
LIQUIDATED DAMAGES/2
- 2 -
conditions in contracts and may be held liable for liquidated damages. Most contracts drafted by
owners or prime contractors require a roofing contractor to complete the work by a certain date
without regard for the effects adverse weather may have on that date. Some contracts expressly
allow extensions only for “abnormal” weather conditions, which are conditions that are unusual
when compared with historical averages. These contracts may also include an agreement by the
roofing contractor to work Saturday and/or Sunday at no extra charge to make up for days lost to
weather during the week.
Examination of the contract for schedule and delay-related clauses before execution and
changing these clauses if necessary can save a roofing contractor from substantial liquidated
damages. Ideally, a roofing contractor should seek to define the contract time by the number of
work days (the number of days with conditions suitable to perform roofing work) or should
alternatively seek to modify the section addressing delays to provide that the roofing contractor
will be given an extension of time in the event it is delayed by adverse weather without any
requirement that such adverse weather be “abnormal.” Similarly, it is imperative that any
subcontractors and suppliers be contractually bound by the same liquidated damages clauses as
are applicable to the roofing contractor, so the roofing contractor can charge the appropriate
supplier or subcontractor for any liquidated damages assessed as a result of that party’s fault.
Many contracts drafted by prime contractors only contain a general statement to the
effect that if a prime contract contains a liquidated damages clause and such damages are
assessed against the prime contractor, the roofing contractor will be required to pay his or her
proportionate share of any such liquidated damages. For risk evaluation and management
purposes, a copy of the prime contract should be obtained and reviewed so any liquidated
– more –
![Page 3: HOW TO AVOID OR REDUCE LIQUIDATED DAMAGES · PDF file · 2015-12-15clause fixes a sum recoverable by the owner as damages for each day work extends beyond the ... the per-day sum](https://reader031.vdocuments.net/reader031/viewer/2022030407/5a85783a7f8b9a87368cce61/html5/thumbnails/3.jpg)
LIQUIDATED DAMAGES/3
- 3 -
damages provisions are known at a project’s outset.
PROMPTLY PURSUE ALL CHANGE ORDERS AND COMPLY WITH NOTICE REQUIREMENTS
If it becomes necessary to perform additional work that requires an extension of time,
roofing contractors should read contracts before performing any change order work. Most
contracts provide specific instructions for what must be done in the event change order work
becomes necessary and identify specific steps that must be taken by a roofing contractor to
preserve his or her rights. The steps and notices a contract requires should be closely and strictly
followed. Typically, a roofing contractor must provide written notice within two to three days of
his or her knowledge of the events giving rise to the change order work. Any such provision
should be measured from the time the roofing contractor became aware of the event and not from
the event itself to reduce the possibility of losing a claim before the contractor even knew it
existed.
The contract may require this notice to include a description and estimation of the effect
on the schedule and the cost to the roofing contractor. In addition, most contracts provide that if
a roofing contractor performs additional work without a written change order and providing the
required written notice, the roofing contractor has waived his or her right to dispute the other
party’s decision or has conclusively agreed he or she is entitled to no additional time or
compensation. Similarly, most contracts identify other situations, such as delays caused by the
owner or other trades, discovery of hidden or unanticipated conditions, and discovery of
noncompliance of the drawings with local building codes, which require written notice from a
roofing contractor. Absent such a notice, a contract may provide that a roofing contractor
– more –
![Page 4: HOW TO AVOID OR REDUCE LIQUIDATED DAMAGES · PDF file · 2015-12-15clause fixes a sum recoverable by the owner as damages for each day work extends beyond the ... the per-day sum](https://reader031.vdocuments.net/reader031/viewer/2022030407/5a85783a7f8b9a87368cce61/html5/thumbnails/4.jpg)
LIQUIDATED DAMAGES/4
- 4 -
forfeits any extension to which he or she may otherwise be entitled.
COMMUNICATE WITH THE OTHER PARTY
Regardless of the particular contract requirements , the best practice is for a roofing
contractor to provide written notice to the other party of the interpretation of the facts at the
earliest possible time, particularly when change orders are disputed or work is being delayed by
causes beyond the roofing contractor’s control. The actions a contractor takes at this time may
be scrutinized in the future, and it is important to have a written record of his or her position and
understanding. Moreover, sending written notice puts the onus on the other party to respond, and
their failure to do so in a timely manner may be construed as an implied acceptance or
acknowledgment of the contractor’s position. Any pertinent telephone conversations should be
summarized in an e-mail or letter to the other party confirming any oral agreement or
understanding.
If the other party disputes the contractor’s position, the contractor should continue to treat
the extra work as entitling him or her to a change order by sending a proposed change order in
the proper format to the other party and by referring to his or her entitlement to additional time in
any schedules or correspondence relating to schedule. A contractor should seek to negotiate
extensions at the earliest possible time. As the end of the job approaches and the other party is
holding retainage which is soon to become due, the other party’s negotiating leverage improves.
CONCLUSION
Delays are sometimes unavoidable in construction, and there will be times where a
– more –
![Page 5: HOW TO AVOID OR REDUCE LIQUIDATED DAMAGES · PDF file · 2015-12-15clause fixes a sum recoverable by the owner as damages for each day work extends beyond the ... the per-day sum](https://reader031.vdocuments.net/reader031/viewer/2022030407/5a85783a7f8b9a87368cce61/html5/thumbnails/5.jpg)
LIQUIDATED DAMAGES/5
- 5 -
roofing contractor is appropriately charged liquidated damages. However, liquidated damages
may also be assessed if a roofing contractor is not wary of contract provisions or takes an overly
casual approach to compliance with notice requirements. The best way to protect against
excessive liquidated damages—aside from completing work within the contemplated schedule—
is to review and edit contract as necessary before signing and to carefully comply with the
contract. Contractors should review contracts to determine their rights and obligations and
strictly comply with any notice and timing requirements and the likelihood of exorbitant
liquidated damages will be substantially reduced.
# # #