Summary
Contents
Key Activities
Scope Development
Schedule
Progress Photos
1
2
3
4
5
EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANOR ARCHITECTS I ADG
JULY 2016
OKLAHOMA STATE CAPITOL RESTORATION
Exterior Rehabilitation
EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANORHL ARCHITECTS I ADG
OKLAHOMA STATE CAPITOL RESTORATION
Exterior Rehabilitation
ContentsSummary
Safety
Progress Photos
Attachments
1
2
3 Roofi ng Update
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4
5
September 2019
STATE CAPITOL REST
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P
CLICK HERE
Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
September2019
Summary:
During the month of September on the Oklahoma Capitol Exterior Restoration Proj-
ect, the northwest quadrant fi ne grading and the sod installation was completed.
The only remaining site work is in the northeast quadrant, which will be done once
the tower crane is dismantled and demobilized in March 2020. The installation of
glass where mapes panels were previously installed was completed in the Governor’s
suite in mid-September. The remaining mapes panels around the building will be
swapped out with glass in the coming months before the next legislative session.
The interior fi nal fi nishes inside the tunnel will start in late October 2019. However,
the tunnel will remain closed until the new Visitor’s Center is complete.
The roofi ng replacement has progressed with both the South and North Wing’s,
fl at lock copper panels in the gutterways being soldered to completion. The South
Wing standing seam copper panels started in September and were installed from
the cornice to the skylights. The copper for the skylights and the remaining standing
seam panels will be installed over the next several weeks. The copper on and around
the skylights is very detailed and meticulous work. The standing seam panels on the
North Wing have started and will wrap up in early October. The East Wing monitor
roofi ng demo, steel modifi cations, and new crete plank substrate installation began
in August and will be completed in October with the copper roofi ng installation to
follow. The West Wing’s monitor roof scope will start in October and fi nish in Decem-
ber, with the new copper roofi ng completing in March of 2020.
RETURN TO TABLE OF CONTENTS
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E. SHERIDAN AVE SUITE 200 OKLAHOMA CITY, OK 73104 I
CLICK HERE
KeyActivities:
- The fi ne grading and sod installation is complete except for the area at the
tower crane
- North wing gutterway copper installation is icomplete
- East wing monitor demo is in progress
- East wing monitor steel installation is in progress
- East wing monitor Crete Plank installation is in progress
- West wing low roof repairs are in progress
- South wing gutterway copper installation is complete
- South wing standing seam panel installation is in progress
- North wing standing seam panel installation is in progress
JE DUNN I TREANORHL ARCHITECTS I ADG
Exterior RehabilitationAugust 2019September2019
RETURN TO TABLE OF CONTENTS
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P
CLICK HERE
Safety:The safety of our workforce and the general public during the course of
construction is the most important task that we must deliver. To that end, every
craftsmen involved with the project receives a detailed project orientation, and prior
to performing any task, the teams develop detailed task specifi c work plans. These
work plans are often called Job Site Analysis (JSA) and assist project teams with ana-
lyzing diff erent hazards associated with each work activity prior to
beginning work.
JE DUNN I TREANORHL ARCHITECTS I ADG
Safety Data and Metrics
Orientations Performed through
09.30.19732
First Aid Incidents for the month of
September0
Recordable Incidents for the month
of September1*
Trade Partner Incidents for the
month of September1**
Total Man-Hours for the month of
September (hrs)2,785
Total Project Man-Hours (hrs.) 210,054
Exterior Rehabilitation
*While operating a skytrack to move bundles of crete plank material from the delivery truck to the laydown area, the end of the load clipped the tower crane test weights near the crane base and the load fell to the ground. There were no injuries.**After soldering a copper fl at lock panel, the soldering iron made contact with the hose while not in use. The heat from the soldering iron caused the hose to melt and started a small fi re on the hose. The fi re was immediately put out, there were no injuries and no property damage.
September2019
RETURN TO TABLE OF CONTENTS
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P
CLICK HERE
JE DUNN I TREANORHL ARCHITECTS I ADG
Safety Spotlight
In September on the Oklahoma Capitol Exterior Restoration project, the safe-
ty focus was on Electrocution, which is one of the Focus Four that JE Dunn is
focusing on this summer and fall. Electrocution can occur after contact with
overhead powerlines, contact with live circuits in panels, working with poorly
maintained cords and tools and lightning strikes. Electrocution accounts for
around 8.3% (or 82) deaths of the yearly average of 991 deaths related to the
Fatal Four.
Exterior RehabilitationSeptember2019
RETURN TO TABLE OF CONTENTS
klahoma Capitol Exterior Restoration project
k By, which is one of the Fatal Four that JE Du
d fall. Struck by relates to falling objects, veh
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P
CLICK HERE
Roofi ng Update
JE DUNN I TREANORHL ARCHITECTS I ADG
Exterior RehabilitationSeptember2019
RETURN TO TABLE OF CONTENTS
Long Pan Installation South Wing Long Pan Installation South Wing
Skylight Mock-Up South Wing
Crete Plank Over Monitor Bay East Wing
Monitor Steel East Wing
Standing Seam Installation South Wing Standing Seam Installation South Wing
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P
CLICK HERE
JE DUNN I TREANORHL ARCHITECTS I ADG
Progress Photos & Field Reports
The photos and fi eld reports attached in the subsequent pages represent progress photos
taken during the month of September for the Oklahoma State Capitol Exterior Restoration
project.
Exterior RehabilitationSeptember2019
RETURN TO TABLE OF CONTENTS
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 144 - 2019_08-20.docx
Page 1 of 5
FIELD OBSERVATION REPORT REPORT NO: 144 DATE: 8/20/2019
TIME: 9:30 - 10:00 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Upper 80s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Brandon Marriott, Lindsey Ross, Mark Maska - JE Dunn
WORK OBSERVED:
Roof work progressing on west slope of north wing (Alpha).
Roof work progressing on north slope of east wing (Delta).
Roof work progressing on south slope of east wing (Foxtrot).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
Grading progressing on northwest portion of site.
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
REMARKS:
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 144 - 2019_08-20.docx
Page 2 of 5
OAC Meeting occurred prior to the site visit in the jobsite trailers.
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Amelia
Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance Kelley (TreanorHL), Mike
Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve
Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Flat lock copper panel installation in progress on west slope of north wing (Alpha)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 144 - 2019_08-20.docx
Page 3 of 5
Frosted glass at light well access window on north elevation of east wing (Delta)
Crete Plank installation in progress at monitor roof on north slope of east wing (Delta)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 144 - 2019_08-20.docx
Page 4 of 5
Crete Plank installation in progress at monitor roof on south slope of east wing (Foxtrot)
Continuous cleat installation in progress at Mock-up I on east slope of south wing (Golf)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 144 - 2019_08-20.docx
Page 5 of 5
Flat lock copper panel installation in progress on west slope of south wing (India)
Grading in progress at northwest portion of site
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 145 - 2019_09-03.docx
Page 1 of 5
FIELD OBSERVATION REPORT REPORT NO: 145 DATE: 9/3/2019
TIME: 9:30 - 10:00 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Low 80s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Lindsey Ross, Mark Maska, Rick Fleming - JE Dunn
WORK OBSERVED:
Roof work progressing on east slope of north wing (Charlie).
Roof work progressing on north slope of east wing (Delta).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
Grading progressing on northwest portion of site.
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
REMARKS:
OAC Meeting occurred prior to the site visit in the jobsite trailers.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 145 - 2019_09-03.docx
Page 2 of 5
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Amelia
Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance Kelley (TreanorHL), Mike
Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve
Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Flat lock copper panel installation in progress on east slope of north wing (Charlie)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 145 - 2019_09-03.docx
Page 3 of 5
Flat lock copper panel installation in progress on east slope of north wing (Charlie)
Crete Plank installation in progress at monitor roof on north slope of east wing (Delta)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 145 - 2019_09-03.docx
Page 4 of 5
Flood test in progress at middle roof drain on east slope of south wing (Golf)
Copper panel installation progress at Mock-up I on east slope of south wing (Golf)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 145 - 2019_09-03.docx
Page 5 of 5
Flood test in progress at middle roof drain on west slope of south wing (India)
Grading progress at northwest portion of site
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 146 - 2019_09-10.docx
Page 1 of 6
FIELD OBSERVATION REPORT REPORT NO: 146 DATE: 9/10/2019
TIME: 10:30 - 11:00 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Low 80s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Brandon Marriott, Mark Maska - JE Dunn
WORK OBSERVED:
Roof work progressing on west slope of north wing (Alpha).
Roof work progressing on east slope of north wing (Charlie).
Grading progressing on northeast portion of site.
Roof work progressing on north slope of east wing (Delta).
Roof work progressing on south slope of east wing (Foxtrot).
Roof work progressing on east slope of south wing (Golf).
Grading progressing on northwest portion of site.
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 146 - 2019_09-10.docx
Page 2 of 6
REMARKS:
None
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Amelia
Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance Kelley (TreanorHL), Mike
Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve
Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Flashing material removal in progress on west slope of north wing (Alpha)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 146 - 2019_09-10.docx
Page 3 of 6
Copper installation in progress at expansion joint on west slope of north wing (Alpha)
Flat lock copper installation in progress at gutterway on east slope of north wing (Charlie)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 146 - 2019_09-10.docx
Page 4 of 6
Grading progress at northeast portion of site
Rosin paper installation in progress near monitor roof on north slope of east wing (Delta)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 146 - 2019_09-10.docx
Page 5 of 6
Steel installation in progress at monitor roof on south slope of east wing (Foxtrot)
Flat lock copper panel installation in progress on east slope of south wing (Golf)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 146 - 2019_09-10.docx
Page 6 of 6
Copper panel installation progress at Mock-up I on east slope of south wing (Golf)
Grading progress at northwest portion of site
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 147 - 2019_09-17.docx
Page 1 of 6
FIELD OBSERVATION REPORT REPORT NO: 147 DATE: 9/17/2019
TIME: 10:00 - 10:30 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Low 80s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Lindsey Ross, Mark Maska - JE Dunn
WORK OBSERVED:
Railing installation progressing at light well on west elevation of north wing (Alpha).
Roof work progressing on west slope of north wing (Alpha).
Roof work progressing on east slope of north wing (Charlie).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
Sod progressing on northwest portion of site.
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
REMARKS:
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 147 - 2019_09-17.docx
Page 2 of 6
None
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Amelia
Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance Kelley (TreanorHL), Mike
Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve
Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Railing installation progress at light well on west elevation of north wing (Alpha)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 147 - 2019_09-17.docx
Page 3 of 6
Copper installation in progress at gutterway on west slope of north wing (Alpha)
Flood test in progress at roof drain at gutterway on west slope of north wing (Alpha)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 147 - 2019_09-17.docx
Page 4 of 6
Roof drain installation progress at gutterway on west slope of north wing (Alpha)
Roof drain installation progress at gutterway on east slope of north wing (Charlie)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 147 - 2019_09-17.docx
Page 5 of 6
Flood test in progress at roof drain at gutterway on east slope of north wing (Charlie)
Copper expansion joint installation at gutterway in progress on east slope of south wing (Golf)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 147 - 2019_09-17.docx
Page 6 of 6
Roof drain installation progress at gutterway on west slope of south wing (India)
Sod progress at northwest portion of site
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.157 - 2019_08_22.docx Page 1 of 5
FIELD OBSERVATION REPORT REPORT NO: 157 DATE: 08/22/2019 TIME: 7:30 am – 2:00 pm DAY OF WEEK: Thursday OWNER: OMES TEMP. RANGE: Mid 60s – Mid 70s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other - Lightning SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Rick Fleming, Lindsey Ross, Mark Maska, (JE Dunn) Vince Latona, Michael Conway, Shannon Cheek (Baker Roofing)
WORK OBSERVED:
South wing – mockup J: Mockup was constructed and in place. Review and comments uploaded on working mockup documents to Box site.
South wing – mockup K: Pediment reglet termination at the flat lock was focus of review. Tapered fill is not as flat as it should be. Masons did not cut the recess square and instead followed the angle leg. This taper needs to be softened on the north wing. Larger lead T-cap needs to be placed at this portion of the reglet to properly seal the copper to stone. Bottom of standing seam is not set per the mockup documents which complicates the standing seam termination unnecessarily. Work to move the cleat up slope started.
South wing – mockup I: Intent to install this mockup was not fulfilled due to the weather.
ITEMS DISCUSSED:
ACTION REQUIRED:
Adjust tapered fill at north wing mockup K areas. (JE Dunn)
Replace t-cap with larger size at tapered fill transition on mockup K. (Baker)
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.157 - 2019_08_22.docx Page 2 of 5
ITEMS TO VERIFY:
REMARKS:
Lightning and thunderstorms moved in around 11 am and work ceased for the day.
Meeting from approximately 1:00 to 2:00 pm to recap and plan the next day.
Pop-up thunderstorms occurred on 8-23-2019. Rescheduled mockup I for 8-27-2019.
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Richard Fleming (JE Dunn), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
View of the east wing from the south wing.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.157 - 2019_08_22.docx Page 3 of 5
View of west wing from the south wing
South wing – mockup J – intended to be removed.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.157 - 2019_08_22.docx Page 4 of 5
Mockup J – view looking back at termination from the southeast. See mockup comments on working set
in Box file.
Mockup K intersection with Mockup I – Tapered fill at triangular transition is too abrupt and needs to be corrected on the north wing. Larger size t-cap needed to improve water resistance of transition. Cleat to
secure bottom of standing seam is too low and should align with the upslope tip of the triangular transition.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.157 - 2019_08_22.docx Page 5 of 5
Area for mockup I installation.
Holes and other defects in underlayment shall be repaired prior to installation of copper.
.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.158 - 2019_08_27.docx Page 1 of 5
FIELD OBSERVATION REPORT REPORT NO: 158 DATE: 08/27/2019 TIME: 9:00 am – 2:00 pm DAY OF WEEK: Tuesday OWNER: OMES TEMP. RANGE: Hi 60s – Lo 70s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Rick Fleming, Lindsey Ross, Mark Maska, (JE Dunn) Vince Latona, Levi Krcmar, Shannon Cheek (Baker Roofing)
WORK OBSERVED:
South wing – mockup I: Cleat to secure the bottom of the standing seam (part of mockup K) has been moved upslope. Panels were laid and termination of reglet receiver/closure were discussed. See mockup comments uploaded on mockup documentation to shared Box file. Ridge and reglet will be finished after panels are laid on the west slope. Panel clip installation shall not be done before seamer has been run. Panel clips shall be installed starting at the fixed zone; sliding clips installed from there up to the ridge and from there down to the gutterway.
ITEMS DISCUSSED:
Edges of the standing seam installation will be protected and dried in with TPO on a temporary basis.
Next mockups to be N and O, date to be confirmed.
ACTION REQUIRED:
Larger t-cap for flat lock termination and transition at pediment reglet required. (Baker)
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.158 - 2019_08_27.docx Page 2 of 5
ITEMS TO VERIFY:
REMARKS:
Lightning and thunderstorms the night before – intermittent power outages in OKC. Start time delayed due to lightning in the area.
Masons are planned to be back September 16 to work on reglets for east and west wing.
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Richard Fleming (JE Dunn), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Section of south wing east slope opened for installation of mockup I.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.158 - 2019_08_27.docx Page 3 of 5
Starter panel installation.
Long pan being moved into position.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.158 - 2019_08_27.docx Page 4 of 5
Seaming operation will use a combination of hand and machine techniques.
Creating envelope folds at upslope panel termination.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.158 - 2019_08_27.docx Page 5 of 5
Termination of reglet closure at gutterway; t-cap will be installed later. Larger t-cap for termination of flat
lock has not arrived yet.
Mockup I – south wing east slope.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.159 - 2019_09_05.docx Page 1 of 6
FIELD OBSERVATION REPORT REPORT NO: 159 DATE: 09/05/2019 TIME: 7:30 am – 2:00 pm DAY OF WEEK: Thursday OWNER: OMES TEMP. RANGE: Mid 60s – Lo 90s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Rick Fleming, Mark Maska (JE Dunn) Vince Latona, Michael Conway, Shannon Cheek (Baker Roofing) Jason Cady (Mass Architects) Mike Thompson (ZFI) Jeff (5-Star)
WORK OBSERVED:
South wing – mockup O: East slope, southern most skylight. Down slope corner and up slope corner installed for review. Edge detail and up slope, down slope and side (rake) are all essentially the same. This is a proposed change from prior iterations but improves the overall performance of the corners. Butyl tape should only be used on the upslope and downslope details. Side edge should not include butyl, the top of the skylights needs to be able to move independently of the main slope panels. See mockup comments uploaded to the Box site dated 09-05-2019.
South wing – mockup N: No mockup ready. Discussed altering the side wall edge detail to match the lower skylight change and ultimately decided against it owing to the ridge detail. See mockup comments and notes uploaded to the Box site dated 09-05-2019.
East wing – monitor: Roof decking replacement is underway. About half of the length of the monitor has been replaced. Shims are necessary at locations on trusses to create a level deck. Over decking of the crete-plank panels has not started. Sidewall framing and decking work has also not started.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.159 - 2019_09_05.docx Page 2 of 6
ITEMS DISCUSSED:
For next visit, mockup N, R, P and Q should be ready. Date to be confirmed, tentatively set for end of the month.
Modifications to steel framing at monitor corners:
ACTION REQUIRED:
Provide section of monitor cornice (two pieces) for use in preliminary discussion of setting remainder of blocking and framing. (Baker)
Correction of TPO lapping at monitor wall corners. (JE Dunn)
Monitor decking installation for vented and non-vented ridge areas need to be corrected. (JE Dunn) ITEMS TO VERIFY:
REMARKS:
Reviewed paint color (proposed change) from Tnemec to powder coat. Tnemec color selected was intended to match color of the limestone. No sample of the color was provided. Powder coat color sample labeled “Chevy white” is very white and does not meet the intent.
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Richard Fleming (JE Dunn), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.159 - 2019_09_05.docx Page 3 of 6
Mockup O: discussion of up slope and edge detail.
Mockup O: review of half cricket.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.159 - 2019_09_05.docx Page 4 of 6
Mockup N & O: down slope corner. Edge side of this detail will vary between upper and lower skylights
to better integrate with the ridge.
Mockup N: Details discussed, but no copper was installed.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.159 - 2019_09_05.docx Page 5 of 6
Monitor re-decking on east wing. Working from the platform out to the pediment.
Portion of vertical leg of eave steel framing to be cut away to allow for cornice return. Temporary
protection at this corner is improperly lapped to drain water. JE Dunn indicated corrected by the end of the day.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.159 - 2019_09_05.docx Page 6 of 6
Rake peak detail discussed and reviewed. Vented versus unvented sections of monitor ridge discussed.
Existing concrete end walls set limits for separating combustibles used in roofing from attic spaces discussed. JE Dunn will make corrections.
.
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P
CLICK HERE
JE DUNN I TREANORHL ARCHITECTS I ADG
Phasing & Schedule Attachments: The following documents are included in the subsequent pages:
- Site Phasing Plan
- Site Utilization Plan
- Schedules
Exterior RehabilitationSeptember2019
RETURN TO TABLE OF CONTENTS
JED
JED
Activity ID Activity Name RemDur
Start Finish
SiteSite 132 09-May-19 A 27-Mar-20
TunnelTunnel 102 18-Sep-19 A 14-Feb-20
Tunnel FinishesTunnel Finishes 102 18-Sep-19 A 14-Feb-20
CON-33860 Inject Control Joints with Waterproofing 9 18-Sep-19 A 03-Oct-19
CON-32750 Frame Walls 15 04-Oct-19* 24-Oct-19
CON-32770 OH Rough-In 10 04-Oct-19 17-Oct-19
CON-32760 In-Wall Rough-In/Wood Bloc king 10 18-Oct-19* 31-Oct-19
CON-32790 Frame Ceilings 15 25-Oct-19 14-Nov-19
CON-32820 Hang Walls 10 01-Nov-19 14-Nov-19
CON-32800 Light Fixtures 10 15-Nov-19 29-Nov-19
CON-32810 Hang Ceilings 5 02-Dec-19 06-Dec-19
CON-32830 Tape/Mud/Paint 15 02-Dec-19 20-Dec-19
CON-32840 Ceiling Grid 5 23-Dec-19 30-Dec-19
CON-32850 Handrails 5 23-Dec-19 30-Dec-19
CON-32860 Acoustical Panels 10 23-Dec-19 07-Jan-20
CON-32870 Millwork 20 23-Dec-19 21-Jan-20
CON-32920 Ceiling Grid Rough-In 5 31-Dec-19 07-Jan-20
CON-32930 Drop Tile 5 08-Jan-20 14-Jan-20
CON-32880 Rubber Stair Treads & Ris ers 3 15-Jan-20 17-Jan-20
CON-32890 Flooring Tile 15 15-Jan-20 04-Feb-20
CON-32900 Carpet 5 05-Feb-20 11-Feb-20
CON-32910 Final Clean 3 12-Feb-20 14-Feb-20
CON-32940 Tunnel Finishes Complete 0 14-Feb-20
Site-Northeast Ret Wall/LandscapeSite-Northeast Ret Wall/Landscape 5 23-Mar-20 27-Mar-20
LandscapeLandscape 5 23-Mar-20 27-Mar-20
CON-33820 NE Wall-Grading & Landscaping (after crane demob) 5 23-Mar-20* 27-Mar-20
Site-Southwest Ret Wall/LandscapeSite-Southwest Ret Wall/Landscape 0 09-May-19 A 23-Sep-19
LandscapeLandscape 0 09-May-19 A 23-Sep-19
CON-33210 SW Wall-Sump Pump Piping Daylighting (MCC Gravel Ramp Removal) 0 09-May-19 A 23-Sep-19
Closeout & WarrantyCloseout & Warranty 307 05-Dec-19 17-Feb-21
.. 50 05-Dec-19 14-Feb-20
.. 50 05-Dec-19 14-Feb-20
CON-10760 Base Job Demobillization 50 05-Dec-19 14-Feb-20
JED-0600 Substantial Completion 0 14-Feb-20
Warranty Review sWarranty Review s 197 11-May-20 17-Feb-21
S S S O O O O N N N N D D D D D J J J J F F F F M M M M M A A A A M M M M M J J J J J J J J A A
Inject Control Joints with Waterproofing
Frame Walls
OH Rough-In
In-Wall Rough-In/Wood Bloc king
Frame Ceilings
Hang Walls
Light Fixtures
Hang Ceilings
Tape/Mud/Paint
Ceiling Grid
Handrails
Acoustical Panels
Millwork
Ceiling Grid Rough-In
Drop Tile
Rubber Stair Treads & Ris ers
Flooring Tile
Carpet
Final Clean
Tunnel Finishes Complete
NE Wall-Grading & Landscaping (after crane demob)
SW Wall-Sump Pump Piping Daylighting (MCC Gravel Ramp Removal)
Base Job Demobillization
Substantial Completion
Remaining Construction
Data Date: 23-Sep-19
Run Date: 23-Sep-19; 12:28
Oklahoma State Capitol Exterior Renovation
Page 1 of 1
Activity ID Activity Name Rem
Dur
Start Finish
OSCR-Roof ReplacementOSCR-Roof Replacement 185 06-Feb-19 A 10-Apr-20
SummarySummary 176 06-Feb-19 A 30-Mar-20
CON-2110 South Wing Duration 64 06-Feb-19 A 18-Oct-19
CON-2120 North Wing Duration 42 18-Feb-19 A 18-Sep-19
CON-2130 East Wing Duration 108 10-Apr-19 A 23-Dec-19
CON-2140 West Wing Duration 155 15-Jul-19 A 28-Feb-20
CON-2100 Demob Scaffolding/Mtl 5 02-Mar-20 06-Mar-20
CON-2090 Demob Crane 5 09-Mar-20 13-Mar-20
CON-2070 Planned Weather Contingency 11 16-Mar-20 30-Mar-20
CON-2080 Substantial Completion 0 30-Mar-20*
ProcurementProcurement 7 24-Jun-19 A 30-Jul-19
CON-3760 Fab/Deliver-Steel 7 24-Jun-19 A 30-Jul-19
ConstructionConstruction 185 22-Jul-19 10-Apr-20
South Wing-IndiaSouth Wing-India 67 22-Jul-19 12-Oct-19
CON-1010 Install Flatlock Copper-South Wing India 12 22-Jul-19 03-Aug-19
CON-3730 Install Initial Copper Panels-South Wing India 2 16-Aug-19 17-Aug-19
CON-4060 Install Copper on Small Skylight A/Panels-South Wing India 7 21-Aug-19 28-Aug-19
CON-4070 Install Copper on Small Skylight B/Panels-South Wing India 7 04-Sep-19 11-Sep-19
CON-4080 Install Copper on Small Skylight C/Panels-South Wing India 5 12-Sep-19 17-Sep-19
CON-1020 Install Copper on Small Skylight D/Panels-South Wing India 5 18-Sep-19 23-Sep-19
CON-1050 Parapet Flashing-South Wing India 1 11-Oct-19 11-Oct-19
CON-1200 Install 4" Gutter-South Wing India 1 12-Oct-19 12-Oct-19
South Wing-GolfSouth Wing-Golf 64 22-Jul-19 18-Oct-19
CON-1060 Install Flatlock Copper-South Wing Golf 12 22-Jul-19 03-Aug-19
CON-4340 Install Initial Copper Panels-South Wing Golf 2 19-Aug-19 20-Aug-19
CON-4090 Install Copper on Small Skylight A-South Wing Golf 7 21-Aug-19 28-Aug-19
CON-4100 Install Copper on Small Skylight B-South Wing Golf 7 04-Sep-19 11-Sep-19
CON-4110 Install Copper on Small Skylight C-South Wing Golf 5 12-Sep-19 17-Sep-19
CON-1130 Install Copper on Small Skylight D-South Wing Golf 5 18-Sep-19 23-Sep-19
CON-1100 Parapet Flashing-South Wing Golf 1 11-Oct-19 11-Oct-19
CON-1250 Install 4" Gutter-South Wing Golf 1 12-Oct-19 12-Oct-19
CON-3880 Clean-Up-Demob-Punchlist-South Wing 5 14-Oct-19 18-Oct-19
South Wing-Large SkylightsSouth Wing-Large Skylights 15 24-Sep-19 10-Oct-19
CON-4350 Install Copper on Skylight A-South Wing 5 24-Sep-19 28-Sep-19
CON-4360 Install Copper on Skylight B-South Wing 5 30-Sep-19 04-Oct-19
CON-4370 Install Copper on Skylight C-South Wing 5 05-Oct-19 10-Oct-19
North Wing-CharlieNorth Wing-Charlie 27 05-Aug-19 11-Sep-19
CON-1180 Install Flatlock Copper-North Wing Charlie 10 05-Aug-19 15-Aug-19
CON-1195 Install Copper Panels-North Wing Charlie 7 16-Aug-19 23-Aug-19
CON-1220 Parapet Flashing-North Wing Charlie 1 06-Sep-19 06-Sep-19
CON-1040 Install 4" Gutter-North Wing Charlie 1 07-Sep-19 07-Sep-19
CON-3990 Install Roof Ladders-North Wing 3 09-Sep-19 11-Sep-19
North Wing AlphaNorth Wing Alpha 32 05-Aug-19 18-Sep-19
CON-1230 Install Flatlock Copper-North Wing Alpha 10 05-Aug-19 15-Aug-19
CON-1240 Install Copper Panels-North Wing Alpha 6 24-Aug-19 05-Sep-19
CON-1090 Install 4" Gutter-North Wing Alpha 1 09-Sep-19 09-Sep-19
CON-3870 Clean-Up-Demob-Punchlist-North Wing 5 12-Sep-19 18-Sep-19
East Wing-MonitorEast Wing-Monitor 72 31-Jul-19 08-Nov-19
Remove Sheathing/Install Crete-PlankRemove Sheathing/Install Crete-Plank 58 31-Jul-19 21-Oct-19
CON-2360 Remove Sheathing/Install Crete-Plank-Sec.1-East Monitor 5 31-Jul-19 06-Aug-19
CON-2370 Remove Sheathing/Install Crete-Plank-Sec.2-East Monitor 5 07-Aug-19 13-Aug-19
CON-2380 Remove Sheathing/Install Crete-Plank-Sec.3-East Monitor 5 14-Aug-19 20-Aug-19
CON-2390 Remove Sheathing/Install Crete-Plank-Sec.4-East Monitor 5 21-Aug-19 27-Aug-19
CON-2400 Remove Sheathing/Install Crete-Plank-Sec.5-East Monitor 5 28-Aug-19 04-Sep-19
CON-3350 Rebuild Monitor Sidewall Framing-East Monitor West Cornice/Sec 1 3 05-Sep-19 09-Sep-19
CON-2410 Remove Sheathing/Install Crete-Plank-Sec.6-East Monitor 5 05-Sep-19 11-Sep-19
CON-2420 Remove Sheathing/Install Crete-Plank-Sec.7-East Monitor 4 12-Sep-19 17-Sep-19
CON-4280 Rebuild Monitor Sidewall Framing-East Monitor-Sec 2-5 3 18-Sep-19 20-Sep-19
CON-2430 Remove Sheathing/Install Crete-Plank-Sec.8-East Monitor 4 18-Sep-19 23-Sep-19
CON-2440 Remove Sheathing/Install Crete-Plank-Sec.9-East Monitor 4 24-Sep-19 27-Sep-19
CON-4290 Rebuild Monitor Sidewall Framing-East Monitor-Sec 6-9 3 30-Sep-19 02-Oct-19
CON-2450 Remove Sheathing/Install Crete-Plank-Sec.10-East Monitor 4 30-Sep-19 03-Oct-19
CON-4300 Rebuild Monitor Sidewall Framing-East Monitor East Cornice/Sec 10 3 17-Oct-19 21-Oct-19
Copper Panels/Wall CladdingCopper Panels/Wall Cladding 44 10-Sep-19 08-Nov-19
CON-4120 Install Copper Panels/Cladding-East Monitor West Cornice/Sec 1 10 10-Sep-19 20-Sep-19
CON-4130 Install Copper Panels/Cladding -East Monitor-Sec 2-5 10 21-Sep-19 02-Oct-19
CON-4140 Install Copper Panels/Cladding-East Monitor-Sec 6-9 10 03-Oct-19 21-Oct-19
CON-1300 Install Copper Panels/Cladding-East Monitor East Cornice/Sec 10 10 22-Oct-19 01-Nov-19
Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2019 2020
South Wing Duration
North Wing Duration
East Wing Duration
West Wing Duration
Demob Scaffolding/Mtl
Demob Crane
Planned Weather Contingency
Substantial Completion
Fab/Deliver-Steel
Install Flatlock Copper-South Wing India
Install Initial Copper Panels-South Wing India
Install Copper on Small Skylight A/Panels-South Wing India
Install Copper on Small Skylight B/Panels-South Wing India
Install Copper on Small Skylight C/Panels-South Wing India
Install Copper on Small Skylight D/Panels-South Wing India
Parapet Flashing-South Wing India
Install 4" Gutter-South Wing India
Install Flatlock Copper-South Wing Golf
Install Initial Copper Panels-South Wing Golf
Install Copper on Small Skylight A-South Wing Golf
Install Copper on Small Skylight B-South Wing Golf
Install Copper on Small Skylight C-South Wing Golf
Install Copper on Small Skylight D-South Wing Golf
Parapet Flashing-South Wing Golf
Install 4" Gutter-South Wing Golf
Clean-Up-Demob-Punchlist-South Wing
Install Copper on Skylight A-South Wing
Install Copper on Skylight B-South Wing
Install Copper on Skylight C-South Wing
Install Flatlock Copper-North Wing Charlie
Install Copper Panels-North Wing Charlie
Parapet Flashing-North Wing Charlie
Install 4" Gutter-North Wing Charlie
Install Roof Ladders-North Wing
Install Flatlock Copper-North Wing Alpha
Install Copper Panels-North Wing Alpha
Install 4" Gutter-North Wing Alpha
Clean-Up-Demob-Punchlist-North Wing
Remove Sheathing/Install Crete-Plank-Sec.1-East Monitor
Remove Sheathing/Install Crete-Plank-Sec.2-East Monitor
Remove Sheathing/Install Crete-Plank-Sec.3-East Monitor
Remove Sheathing/Install Crete-Plank-Sec.4-East Monitor
Remove Sheathing/Install Crete-Plank-Sec.5-East Monitor
Rebuild Monitor Sidewall Framing-East Monitor West Cornice/Sec 1
Remove Sheathing/Install Crete-Plank-Sec.6-East Monitor
Remove Sheathing/Install Crete-Plank-Sec.7-East Monitor
Rebuild Monitor Sidewall Framing-East Monitor-Sec 2-5
Remove Sheathing/Install Crete-Plank-Sec.8-East Monitor
Remove Sheathing/Install Crete-Plank-Sec.9-East Monitor
Rebuild Monitor Sidewall Framing-East Monitor-Sec 6-9
Remove Sheathing/Install Crete-Plank-Sec.10-East Monitor
Rebuild Monitor Sidewall Framing-East Monitor East Cornice/Sec 10
Install Copper Panels/Cladding-East Monitor West Cornice/Sec 1
Install Copper Panels/Cladding -East Monitor-Sec 2-5
Install Copper Panels/Cladding-East Monitor-Sec 6-9
Install Copper Panels/Cladding-East Monitor East Cornice/Sec 10
Construction Schedule
Data Date: 22-Jul-19
Run Date: 24-Jul-19; 12:53
OSCR-Roof Replacement
Page 1 of 2
Activity ID Activity Name Rem
Dur
Start Finish
CON-3860 Clean-Up-Demob-Punchlist-EW Monitor 5 04-Nov-19 08-Nov-19
Small Skylight-EastSmall Skylight-East 54 04-Oct-19 21-Dec-19
CON-2700 Demo Small Skylights-East 1 04-Oct-19 04-Oct-19
CON-2710 Rebuild Small Skylights-East 6 07-Oct-19 14-Oct-19
CON-1370 Install Copper Small Skylight-East 10 11-Dec-19 21-Dec-19
East Low Roof-South SideEast Low Roof-South Side 60 21-Oct-19 16-Jan-20
CON-4180 Install Flatlock Copper-East Low South Side 5 21-Oct-19 25-Oct-19
CON-1400 Install Copper Panels/Gutter-East Low South Side-Area A 8 26-Oct-19 04-Nov-19
CON-3770 Install Copper Panels/Gutter-East Low South Side-Area B 8 05-Nov-19 13-Nov-19
CON-3980 Install Roof Ladders-East Wing 3 14-Nov-19 18-Nov-19
CON-3890 Paint Clerestory Masonry-East Low South Side 5 19-Nov-19 25-Nov-19
CON-3810 Clean-Up-Demob-Punchlist 4 26-Nov-19 03-Dec-19
CON-3930 MCC Flat Roof Scope-East Low South Side 30 04-Dec-19 16-Jan-20
East Low Roof-North SideEast Low Roof-North Side 74 21-Oct-19 05-Feb-20
CON-4190 Install Flatlock Copper-East Low North Side 5 21-Oct-19 25-Oct-19
CON-1440 Install Copper Panels/Gutter-East Low North Side-Area A 8 14-Nov-19 22-Nov-19
CON-3780 Install Copper Panels/Gutter-East Low North Side-Area B 8 23-Nov-19 10-Dec-19
CON-1260 Parapet Flashing-East Low South Side 4 06-Dec-19 10-Dec-19
CON-3900 Paint Clerestory Masonry-East Low North Side 5 11-Dec-19 17-Dec-19
CON-3820 Clean-Up-Demob-Punchlist 4 18-Dec-19 23-Dec-19
CON-3940 MCC Flat Roof Scope-East Low North Side 30 24-Dec-19 05-Feb-20
West Wing Monitor-South SideWest Wing Monitor-South Side 82 17-Sep-19 14-Jan-20
Remove Sheathing/Install Crete-PlankRemove Sheathing/Install Crete-Plank 62 17-Sep-19 13-Dec-19
CON-2970 Remove Sheathing/Install Crete-Plank-Sec.1-West Monitor 4 17-Sep-19 20-Sep-19
CON-2980 Remove Sheathing/Install Crete-Plank-Sec.2-West Monitor 4 23-Sep-19 26-Sep-19
CON-2990 Remove Sheathing/Install Crete-Plank-Sec.3-West Monitor 4 27-Sep-19 02-Oct-19
CON-3000 Remove Sheathing/Install Crete-Plank-Sec.4-West Monitor 4 03-Oct-19 08-Oct-19
CON-3010 Remove Sheathing/Install Crete-Plank-Sec.5-West Monitor 4 09-Oct-19 14-Oct-19
CON-3030 Remove Sheathing/Install Crete-Plank-Sec.6-West Monitor 5 15-Oct-19 21-Oct-19
CON-3020 Remove Sheathing/Install Crete-Plank-Sec.7-West Monitor 5 22-Oct-19 28-Oct-19
CON-3090 Remove Sheathing/Install Crete-Plank-Sec.8-West Monitor 5 29-Oct-19 04-Nov-19
CON-3370 Rebuild Monitor Sidewall Framing-West Monitor-East Cornice/Sec 1 3 30-Oct-19 01-Nov-19
CON-3040 Remove Sheathing/Install Crete-Plank-Sec.9-West Monitor 5 05-Nov-19 11-Nov-19
CON-4310 Rebuild Monitor Sidewall Framing-West Monitor-Sec 2-5 3 11-Nov-19 13-Nov-19
CON-3050 Remove Sheathing/Install Crete-Plank-Sec.10-West Monitor 5 12-Nov-19 18-Nov-19
CON-4320 Rebuild Monitor Sidewall Framing-West Monitor-Sec 6-9 3 27-Nov-19 03-Dec-19
CON-4330 Rebuild Monitor Sidewall Framing-West Monitor-West Cornice/Sec 10 3 11-Dec-19 13-Dec-19
Copper Panels/Wall CladdingCopper Panels/Wall Cladding 48 02-Nov-19 14-Jan-20
CON-4200 Install Copper Panels-West Monitor-East Cornice/Sec 1 10 02-Nov-19 13-Nov-19
CON-4210 Install Copper Panels-West Monitor-Sec 2-5 10 14-Nov-19 25-Nov-19
CON-4220 Install Copper Panels-West Monitor-Sec 6-9 10 04-Dec-19 14-Dec-19
CON-1485 Install Copper Panels-West Monitor-West Cornice/Sec 10 10 16-Dec-19 07-Jan-20
CON-3830 Clean-Up-Demob-Punchlist-WW Monitor 5 08-Jan-20 14-Jan-20
Small Skylight-WestSmall Skylight-West 68 19-Nov-19 26-Feb-20
CON-3310 Demo Small Skylights-West 1 19-Nov-19 19-Nov-19
CON-3320 Rebuild Small Skylights-West 5 20-Nov-19 26-Nov-19
CON-1550 Install Copper Small Skylight-West 10 15-Feb-20 26-Feb-20
West Low Roof-South SideWest Low Roof-South Side 164 05-Aug-19 26-Mar-20
CON-3240 Demo Sheathing/Repair Sleepers (if needed)-West Low South Side 10 05-Aug-19* 16-Aug-19
CON-3250 Install New Sheathing-West Low South Side 10 12-Aug-19 23-Aug-19
CON-4260 Install Flatlock Copper-West Low South Side 5 03-Jan-20 08-Jan-20
CON-4380 Install Copper Panels/Gutter-West Low South Side-Area A 8 09-Jan-20 17-Jan-20
CON-1580 Install Copper Panels/Gutter-West Low South Side-Area B 8 18-Jan-20 27-Jan-20
CON-3970 Install Roof Ladders-West Wing 3 28-Jan-20 30-Jan-20
CON-3910 Paint Clerestory Masonry-West Low South Side 5 31-Jan-20 06-Feb-20
CON-3840 Clean-Up-Demob-Punchlist-West Low South Side 5 07-Feb-20 13-Feb-20
CON-3950 MCC Flat Roof Scope-West Low South Side 30 14-Feb-20 26-Mar-20
West Low Roof-North SideWest Low Roof-North Side 160 26-Aug-19 10-Apr-20
CON-3280 Demo Sheathing/Repair Sleepers (if needed)-West Low North Side 10 26-Aug-19 09-Sep-19
CON-3290 Install New Sheathing-West Low North Side 10 03-Sep-19 16-Sep-19
CON-4270 Install Flatlock Copper-West Low North Side 5 03-Jan-20 08-Jan-20
CON-4390 Install Copper Panels/Gutter-West Low North Side-Area A 8 28-Jan-20 05-Feb-20
CON-1680 Install Copper Panels/Gutter-West Low North Side-Area B 8 06-Feb-20 14-Feb-20
CON-3920 Paint Clerestory Masonry-West Low North Side 5 17-Feb-20 21-Feb-20
CON-3850 Clean-Up-Demob-Punchlist-West Low North Side 5 24-Feb-20 28-Feb-20
CON-3960 MCC Flat Roof Scope-West Low North Side 30 02-Mar-20 10-Apr-20
Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2019 2020
Clean-Up-Demob-Punchlist-EW Monitor
Demo Small Skylights-East
Rebuild Small Skylights-East
Install Copper Small Skylight-East
Install Flatlock Copper-East Low South Side
Install Copper Panels/Gutter-East Low South Side-Area A
Install Copper Panels/Gutter-East Low South Side-Area B
Install Roof Ladders-East Wing
Paint Clerestory Masonry-East Low South Side
Clean-Up-Demob-Punchlist
MCC Flat Roof Scope-East Low South Side
Install Flatlock Copper-East Low North Side
Install Copper Panels/Gutter-East Low North Side-Area A
Install Copper Panels/Gutter-East Low North Side-Area B
Parapet Flashing-East Low South Side
Paint Clerestory Masonry-East Low North Side
Clean-Up-Demob-Punchlist
MCC Flat Roof Scope-East Low North Side
Remove Sheathing/Install Crete-Plank-Sec.1-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.2-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.3-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.4-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.5-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.6-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.7-West Monitor
Remove Sheathing/Install Crete-Plank-Sec.8-West Monitor
Rebuild Monitor Sidewall Framing-West Monitor-East Cornice/Sec 1
Remove Sheathing/Install Crete-Plank-Sec.9-West Monitor
Rebuild Monitor Sidewall Framing-West Monitor-Sec 2-5
Remove Sheathing/Install Crete-Plank-Sec.10-West Monitor
Rebuild Monitor Sidewall Framing-West Monitor-Sec 6-9
Rebuild Monitor Sidewall Framing-West Monitor-West Cornice/Sec 10
Install Copper Panels-West Monitor-East Cornice/Sec 1
Install Copper Panels-West Monitor-Sec 2-5
Install Copper Panels-West Monitor-Sec 6-9
Install Copper Panels-West Monitor-West Cornice/Sec 10
Clean-Up-Demob-Punchlist-WW Monitor
Demo Small Skylights-West
Rebuild Small Skylights-West
Install Copper Small Skylight-West
Demo Sheathing/Repair Sleepers (if needed)-West Low South Side
Install New Sheathing-West Low South Side
Install Flatlock Copper-West Low South Side
Install Copper Panels/Gutter-West Low South Side-Area A
Install Copper Panels/Gutter-West Low South Side-Area B
Install Roof Ladders-West Wing
Paint Clerestory Masonry-West Low South Side
Clean-Up-Demob-Punchlist-West Low South Side
MCC Flat Roof Scope-West Low South Side
Demo Sheathing/Repair Sleepers (if needed)-West Low North Side
Install New Sheathing-West Low North Side
Install Flatlock Copper-West Low North Side
Install Copper Panels/Gutter-West Low North Side-Area A
Install Copper Panels/Gutter-West Low North Side-Area B
Paint Clerestory Masonry-West Low North Side
Clean-Up-Demob-Punchlist-West Low North Side
MCC Flat Roof Scope-West Low N
Construction Schedule
Data Date: 22-Jul-19
Run Date: 24-Jul-19; 12:53
OSCR-Roof Replacement
Page 2 of 2