Implementing Post-Construction
Stormwater Controls
Greg Davis, EPA Region 8
![Page 2: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/2.jpg)
Source: National Water Quality Inventory – 2000 Report (EPA)
![Page 3: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/3.jpg)
Source: National Water Quality Inventory – 2000 Report (EPA)
![Page 4: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/4.jpg)
Source: National Water Quality Inventory – 2000 Report (EPA)
![Page 5: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/5.jpg)
Rain/snow is a source of pollution?Rain/snow is a source of pollution?
Storm water is a vector for pollutants
Storm water is a pollutant itself
![Page 6: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/6.jpg)
Stormwater is a vectorStormwater is a vector
Common pollutants in storm water runoff include heavy metals, oil, grease, nutrients, toxic substances, sediment, bacteria, and temperature
![Page 7: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/7.jpg)
Stormwater is a pollutant
Increased flow from impervious surfaces causes impacts to rivers and lakes
Increased imperviousness =
Increased runoff from storm events Increased exposure to pollutants Impacts to stream banks
![Page 8: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/8.jpg)
Natural runoff Natural runoff conditionsconditions
![Page 9: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/9.jpg)
Impervious conditionImpervious condition
![Page 10: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/10.jpg)
![Page 11: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/11.jpg)
Stream degradation with imperviousnessimperviousness
Watershed with lessthan 5% impervioussurface
![Page 12: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/12.jpg)
Stream degradation with Stream degradation with imperviousnessimperviousness
10% impervious
- Stream width doubled - Bank erosion - Pool and riffle structure lost
![Page 13: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/13.jpg)
Stream degradation with imperviousnessimperviousness
20% impervious
- Eroded stream banks - Intermittent flow - Noticeable debris
![Page 14: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/14.jpg)
RUNOFF
TIME
![Page 15: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/15.jpg)
![Page 16: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/16.jpg)
Post-construction BMPs: landscape detention
![Page 17: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/17.jpg)
Post-construction BMPs: Post-construction BMPs: retention pondretention pond
![Page 18: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/18.jpg)
Post-construction BMPs: Post-construction BMPs: sand filter detention basinsand filter detention basin
![Page 19: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/19.jpg)
Post-construction BMPs: Post-construction BMPs: grassy area with curb cutsgrassy area with curb cuts
![Page 20: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/20.jpg)
Post-construction BMPs: Post-construction BMPs: level spreaderlevel spreader
![Page 21: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/21.jpg)
Post-construction BMPs: Post-construction BMPs: porous concreteporous concrete
![Page 22: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/22.jpg)
Post-construction BMPs: Post-construction BMPs: green roofgreen roof
![Page 23: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/23.jpg)
Create an ordinance
Use/ borrow what other people have done
Demonstrate cost-effectiveness to legislators
Demonstrate environmental effects
![Page 24: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/24.jpg)
http://www.epa.gov/owow/nps/ordinance/postcons.htm
![Page 25: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/25.jpg)
Components of a stormwater ordinance
![Page 26: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/26.jpg)
Provide training
Use/modify this presentation or any other non-copyrighted material
http://cfpub.epa.gov/npdes/outreach.cfm?program_id=0&otype=1
Provide training to legislators, contractors, contracting office technical representatives, developers, and facility maintenance staff
![Page 27: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/27.jpg)
Utilize a stormwater fee
Stormwater fees should be based on effective impervious surface
Credits should be provided for retrofits and water quality features
![Page 28: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/28.jpg)
Demonstrate financial impacts
The 9.8 million visitors to Montana represent 10 times Montana’s resident population and result in 43,300 jobs for an economic impact of $2.75 billion.
Source: Montana Fish, Wildlife, and Parks - Fish & Wildlife Recreation and Tourism
by: Cindy S. Swanson, Director, Watershed, Wildlife, Fisheries & Rare Plants, USDA Forest Service, Northern Region, Missoula (2004)
![Page 29: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/29.jpg)
Use existing resources and speakers
Montana Fish, Wildlife, and Parks Research Reports - http://fwp.mt.gov/tmc/reports/default.html
Universe of Montana Institute for Tourism, Recreation, and Research - http://www.itrr.umt.edu/wilton.htm
Montana Trout Unlimited - http://www.montanatu.org/
Demonstrate financial impacts
![Page 30: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/30.jpg)
In 17 Case studies EPA comparing conventional stormwater to green infrastructure practices, costs for green infrastructure were generally 15-80% cheaper
Reducing Costs through LID Strategies and Practices – http://www.epa.gov/nps/lid
Try calculating expenses yourself: Green Values Stormwater Toolbox -
http://greenvalues.cnt.org/
Demonstrate financial impacts
![Page 31: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/31.jpg)
Evaluate public works contracts
Require post-construction controls in public works contracts
Public works areas can receive grant funding for green infrastructure
Ensure that contracts have a line item for budgeting post-construction BMP costs
![Page 32: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/32.jpg)
Track BMP maintenance and specifications
Requires submission of final plans/ ownership/ and maintenance specs.
Use an NOT form or performance bond
Provide a 1-year warranty in bonds
![Page 33: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/33.jpg)
Track BMP maintenance and specifications
Use existing systems and speak the same language as implementing staff
Georeference using GIS/ CAD system employed for storm sewer system mapping
Inspect using current inspector systems (e.g., Maximo)
![Page 34: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/34.jpg)
Evaluate local land use planning
Imperviousness can be driven by:
Zoning Subdivision Codes Street and Road Standards Parking and Setback Requirements
![Page 35: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/35.jpg)
Designate new MS4s
40 CFR 122.26(f)(4) Any person may petition the Director for the designation of a large, medium, or small municipal separate storm sewer system
Probable new MS4s include resort cities, high growth areas, and dischargers to pristine waters
![Page 36: Implementing Post-Construction Stormwater Controls Greg Davis, EPA Region 8](https://reader035.vdocuments.net/reader035/viewer/2022062423/56649f0c5503460f94c1f6e4/html5/thumbnails/36.jpg)
Communicate, communicate,
communicate, communicate, communicate, communicate, communicate,…
Using other people’s terms (financial, engineering, environmental)