Lecture
6:
DIRECTIONAL
DRILLINGDirectional Drilling Fundamentals &Directional Trajectories
Arun S Chandel
Assistant [email protected]
09997200339
1
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
2/31
Segments of Deviated Well
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
3/31
Major Directional Well Profiles
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
4/31
Directional Drilling Terminologies
KICK-OFF POINTThe kick off point is defined as the point below the surface locationwhere the well is deflected from the vertical. The osition of the kick
off depends on several parameters including: geologicalconsiderations, geometry of well and proximity of other wells.
The maximum permissible build up /drop off rate is normally
determined by one or more of the following: The total depth of the well Maximum torque and drag limitations Mechanical limitations of the drill string or casing Mechanical limitations of logging tools and production strings.
T h e o p t i m u m b u i l d u p a n d d r o p o f f r a t e s i n c o n v e n t i o n a l
d i r e c t i o n a l w e l l s a r e i n t h e r a n g e o f 1 . 5 0 t o 30 p e r 1 0 0 f t ,
a l t h o u g h m u c h h i g h e r b u i l d u p r a t e s a r e u s e d f o r h o r i z o n t a l a n d
m u l t i l a t e r a l w e l l s .
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
5/31
INCLINATION ANGLE
The inclination angle of a well at any point is the angle the wellboreforms between its axis and the vertical, see Figure 11.11.
MEASURED DEPTH
from one reference point to the survey point. Measured depth isalso known as Along Hole Depth and is measured with the pipetally or by a wireline.
True vertical depth (TVD) is the vertical distance measured from
a reference point to the survey point. TVD is usually referenced to
Northing: Horizontal distance between one survey point and theRKB, measured to the North. A distance to the South is generally
eno e as e ng nega ve.
Easting: Horizontal distance between one survey point and theRKB measured to the East. A distance to the West is eneralldenoted as being negative.
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
6/31
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
7/31
Azimuth & Departure
The azimuth of a wellbore at any point is defined as the direction of thewellbore on a horizontal plane measured clockwise form a northreference. Azimuths are usually expressed in angles from 0-360 ,measure rom zero nor .
Azimuths can also be expressed in a quadrant system from 0-90measured from north in the northern quadrants and from south in thesouthern quadrants. The azimuth reading of 135 equates to S45 E inquadrant readings.
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
8/31
Azimuth and departure
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
9/31
Azimuth and departure
N
AB
C OEW
84
tD
n
D
1852
S
AZIMUTH = 272.6 de rees
0
.
eD
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
10/31
HorizontalDeparture:
2 2
t e nD D D= +
Azimuthof
the
well ( )= 1tan eD
n
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
11/31
Azimuth and departure
Given the following grid coordinates, determine the departureand azimuth of the target from the surface location.
Grid Coordinates: Target6,334,400.00 N (m)200 600.00 E m
Grid Coordinates: Surface
6,335,000.00 N (m), .
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
12/31
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
13/31
Circular Functions
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
14/31
Circular Functions
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
15/31
Radius of curvature
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
16/31
Radius of curvature
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
17/31
Build-up Rate Formula
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
18/31
Determining End of Build
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
19/31
J-Profile (departure >R)
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
20/31
J-Profile (departure < R)
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
21/31
S-Profile (R1+R2 < total target displacement)
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
22/31
S-Profile (R1+R2 > total target displacement)
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
23/31
Whats Best?
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
24/31
ManualDesign:Build&HoldTrajectory(JProfile)
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
25/31
ManualDesign:Build&HoldTrajectory(JProfile)
To carry out the geometric planning for a Type Iwell, Figure 11.13, the following information isrequired:
-
Target Co-ordinates
TVD of target
TVD to KOP
Build-u rate
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
26/31
Base Equations
Using the detailed trigonometry shown in Figure 11.13, themaximum inclination angle max for type I trajectory can becalculated for two cases:
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
27/31
Base Equations
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
28/31
Base Equations
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
29/31
Problem:Build&HoldTrajectory(JProfile)
Following data is given for a directional offshore
we r e as -pro e:
Kick-off point (K) = 1000
Build Rate BUR = 2.50 100
Target data
True vertical depth (V3) = 9500Northings (Dn) = +3507
Eastings De = -1752
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
30/31
Find the following:
1.Horizontal Departure (D2)
2.Azimuth of the well ( )
.
4.End of build at TVD (V2)
5.End of build at departure (D1)
6.Measured depth at end of build (OE)
.
-
7/28/2019 L6-DD Fundamentals and Directional Well Planning
31/31
O
CK
A
v1
R
B
Rv2
E
v3
xy
T
D2
1