Archdiocese of AtlantaOffice of Planning and Research
Archdiocese of AtlantaArchdiocese of Atlanta
Large Capital Process – What is it?
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research
2
The sixty-nine county area that comprises the Archdiocese of Atlanta continues to experience significant population growth. This growth creates a strain on existing Archdiocesan facilities and also highlights the need for new facilities. Therefore, one of the key challenges facing pastors* is the maintenance, renovation, and expansion of parish facilities. Pastors and parishes need to know what steps they need to take when a parish believes it needs to expand.
The planning and construction of facilities is an exciting but long effort for a parish. We have developed a series of presentations that contain the key information that a pastor and parish will need to begin the process, as well as an overview of the entire process. We hope that by providing information and tools, parishes will be able to more quickly and effectively identify the key projects that are both important and feasible for their future growth and understand how to obtain required approvals for them.
BALDWIN
BANKS
BARROW
BARTOW
CARROLL
CATOOSA
CHATTOOGA
CHEROKEE
CLARKECOBB
COWETA
DADE
DAWSON
DeKALBDOUGLAS
ELBERT
FANNIN
FLOYD FORSYTHFRANKLIN
FULTON
GILMER
GORDON
GREENE
GWINNETT
HABERSHAM
HALL
HANCOCK
HARALSON
HART
HEARD
JACKSON
LINCOLN
LUMPKIN
MCDUFFIE
MADISON
MERIWETHER
MORGAN
MURRAY
OCONEE
OGLETHORPEPAULDING
PICKENS
PIKE
POLK
PUTNAM
RABUN
STEPHENS
TALIAFERRO
TOWNS
TROUP
UNION
UPSON
WALKER
WARREN
WHITE
WHITFIELD
WILKES
NEWTON
SPALDINGJASPER
MONROELAMAR
BUTTS
HENRY
WALTON
CLAYTON
FAYETTE
ROCKDALE
Why do We Need a Large Capital Project Process?
To help and protect Parishes, Schools and other Archdiocesan
entities when they expand, renovate or maintain their
current facilities or properties.
*Anytime the word “Pastor” is used, it is meant to include Pastors, Principals, Administrators, etc.*Anytime the word “Parish” is used, it is meant to include Parishes, Schools, Missions, etc.
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research
3
Large Capital Projects may involve significant risk for Archdiocesan entities. Therefore, projects that will cost over a certain amount must obtain the Archbishop’s approval before proceeding with major capital improvements to the facilities and properties.
Photo by Michael Alexander, The Georgia Bulletin
Key Thresholds
When should we use the Large Capital Project Process?
What size project requires the sign off of the Archbishop?
If your project cost is equal to or below the value listed above, then you may proceed without obtaining the Archbishop’s approval. If you plan on using volunteer labor for these projects, then please be especially cautious in dealing with legal and liability issues of volunteers doing facility work without meeting proper codes and licensing. Catholic Construction Services, Inc. is available to help you plan and execute these projects.
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research
4
If your project cost exceeds the limits on the preceding slide, then you will need to follow the steps in the Archdiocesan Large Capital Process:
1. Define and review project2. Request First Approval (Initial Conceptual Approval) from the Archbishop3. Develop preliminary design4. Request Second Approval (for capital campaign and detailed drawings)5. Secure funding (includes capital campaign)6. Finalize design7. Request Final Approval (to begin construction)8. Begin Construction management9. Accept and dedicate
You will need to follow this process whether your project involves new construction, renovation, maintenance of facilities or land acquisition.
Key Steps in the Large Capital Project Process
Please note: these presentations are not inclusive of all project exceptions. The process presented is a general overview and may not account for every experience possible while undergoing construction. Rather, these websites will give you the language and background needed to confidently embark on your large capital project under CCSI’s guidance.
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research
5
PLEASE NOTE: Before being approved for any Large Capital Project, you will need to ensure that your parish is in compliance with Archdiocesan Procedures
• Accounts current (e.g. loans, assessments, etc.)? If not, contact the Controller, Finance Office• Using the LOGOS system? If not, contact the Parish Systems Manager, Finance Office• Using ParishSoft system? If not, contact the Training Coordinator, Finance Office• Using the HR portal? If not, contact the Parish Systems Manager, Finance Office• Safe Environment compliance is current? If not, contact the Director of Safe Environment• Parish facilities master plan in place? If not, contact the Director of Planning and Research
For current contact information, please open our contacts page.
If you suspect you are not in compliance, please go ahead through the initial steps of the process to request First Approval and, concurrently, work with the appropriate Chancery contact to be in compliance before requesting Second Approval.
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research 6
• Capital Campaign Guidance
• Offertory Best Practices
• Master Planning• Overview of Large
Capital Project process• Steps 1 and 2 of LCP
• Review current financial capacity
• Capital campaign exemption from assessment
• Loan terms and rate• Review final application with
Project Review Committee of Finance Council
• Provides a preliminary budget and monitors cost estimates and change order proposals
• Oversight of design• Contract administration and risk
protection• Inspections throughout construction
Customer Centric View of the Large Capital Process
Please note that through the entire Large Capital
Process, Chancery departments are here to serve you and help you
through your construction projects!
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research
Acceptance and Dedication
Overview of Large Capital Project Process Overview of Large Capital Project Process
Define and Review Project Request First Approval: Initial Conceptual Approval
• Review letter and forms• Grant initial conceptual approval to
engage design professionals and/or a capital campaign consultant
Develop Preliminary DesignRequest Second Approval: Approval for Capital Campaign andDetailed Drawings
• Review letter and forms• Grant approval to:
• Kick-off capital campaign• Obtain detailed drawings and
cost estimate
Request Final Approval: Build Approval
• Review letter and forms• Grant approval to begin construction
Construction Management
Step 1 Step 2
Step 3
Step 5
Step 6
Step 7
Step 8
Step 9
Step 4
• CCSI to present Preliminary Drawings to the Archbishop
Secure Financing
Finalize Design
Lar
ge
Cap
ital
Pro
cess
– W
hat
is
it?
Archdiocese of AtlantaOffice of Planning and Research
8
Who Do You Call?
• Peter Faletti, Director of Planning and Facilities• Work phone
o (680): 404-885-7279 o (Lake Park): 404-920-7855
• Cell phone: 404-915-3785• Email: [email protected]