LCLS-II Bypass Line Design GoalsP. Emma, July 7, 2010
Provide 14-GeV (?) electron bypass line from sector-20 around LCLS-I, feeding new undulators south of LCLS-I at 2 to 4-deg angleUse existing PEP-II 9-GeV line on linac ceiling (2’ above & 2’ south of linac)Sneak line around crowded BSY and BTHWBore new hole in 17-m thick iron m-plug wallPreserve 0.6-mm emittance with up to 3 kA at 14 GeVInclude diagnostics and corrections in design
![Page 2: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/2.jpg)
Bypass-Line ComponentsExtract beam out at 20-5 (use half of sec-20 RF)Rolled x/y bends to existing 9-GeV PEP-II line(Existing PEP-II extraction bends blow up LCLS emittance by factor of 4 – redesigned here)Use 1-km of existing FODO cells (bmax = 400 m)
Also use long FODO as emittance diagnosticRemove 4.6-mrad pitch of linac (as in LCLS-I)Bend south with LCLS bend-cells (four 1-deg cells)Keep beamline at bypass line height (25.5” up)Bore new tunnel in hill 25.5” higher than LCLS-IAdd final wire scanner section & undulator matching (+ room for ECHO seeding)
![Page 3: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/3.jpg)
47”
66”
Inside Linac Vault - Looking Down-Beam
120”
132”
LINAC
25.512”
25.512”
9-GeV17” 3-GeV
(ID-344-013-30)
![Page 4: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/4.jpg)
LCLS-II Bypass Layout
Dx = 25.5”
PLAN VIEW
ELEVATION VIEW
N
Sector 20-517-m thick m-plug wall
17-m thick m-plug wall
Dy = 25.5”
![Page 5: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/5.jpg)
Sector-20(20-5)
m-plug wall
2324 26 28 30
25 27 29existing quads on ceiling
![Page 6: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/6.jpg)
m-plug walleight 0.5-deg bends
![Page 7: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/7.jpg)
LCLS-I Head-House Layout(R. M. Boyce)
![Page 8: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/8.jpg)
South-Side Head-House Port
~5 m
![Page 9: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/9.jpg)
Linac Tunnel Approaching BSY
Bypass Line will pass through
most congested area in BSY
Bypass Line will pass through
most congested area in BSY
LINAC
SIT Lineto PEP-II
![Page 10: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/10.jpg)
Quadrupole magnet here?
![Page 11: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/11.jpg)
![Page 12: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/12.jpg)
![Page 13: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/13.jpg)
![Page 14: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/14.jpg)
problem area
![Page 15: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/15.jpg)
Twiss functions in Elegant
![Page 16: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/16.jpg)
With CSR (uniform temporal dist.) – note that ISR is no problem
gex,y = 0.6 mm
![Page 17: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/17.jpg)
Longitudinal phase space at 13.6 GeV, 3 kA, with CSR(uniform temporal dist.)
![Page 18: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/18.jpg)
Energy spread (green) & bunch length (red) vs. z
![Page 19: LCLS-II Bypass Line Design Goals P. Emma, July 7, 2010](https://reader035.vdocuments.net/reader035/viewer/2022062322/56815201550346895dc0416e/html5/thumbnails/19.jpg)
QuestionsIs this 2-4-deg option the choice (2 other options exist, but all need a bypass line)?Will we run at 7 GeV/360 Hz, or 14 GeV/120 Hz, or both (assuming both for now)?Can a new hole be bored in the 17-m thick m-plug wall ?Can we tunnel the new undulator hall 25.5” higher in elevation than LCLS-I ?Do we need a jumper line from LCLS-I to LCLS-II, and the reverse?Do we want a horizontal spreader to someday feed 2 undulators in the new hall ?