Maynard Jackson High School Weekly Photo Report
This Week’s Activities
May 6 – May 10
• Site Wall C complete
• Stair 2 pan slabs pouring complete
• South elevation brick complete
• Built up roofing at pop up structure complete
• South courtyard curtainwall glazing complete
• Core drilling for underground feeds to new riser room complete
• Main gym demolition currently underway
• Main gym shoring currently being erected and roof soil being removed
• Curb and gutter and parking lot grading currently underway at North parking lot
• Roofing at mezzanine, high roof and pop up roof ongoing
• Preparation for painting existing structure ongoing
• Preparation for glazing at North courtyard curtainwall ongoing
• Flashing and backfilling at green roof parapet ongoing
• Horizontal WSHP installation ongoing
• Main level in�wall electrical rough�in ongoing
• Saw cutting for new electrical feeds ongoing
• Drywall hang and finish on Upper Level ongoing
• MEP wall inspections on Main Level underway
Date: May 10, 2013
Client: Atlanta Public Schools
Project Name: Maynard Jackson High School Renovation
Project #: #12-034
Prepared By: Logan Crutchfield
Distribution: Steven Brown Josh Flannigan Matt Loveless
Carrie Campbell Meghan Frydrych Bobby Mote
Natalia Cardelino Jimmy Haralson Jeff Schafer
Barbara Crum Alvah Hardy Brint Smith
Logan Crutchfield Bill Hill Jere Smith
Rebecca Dean John Hutton Barry Spurlock
Jamie Dye Lin Kelley Brian Thomas
Comments: May 6th to May 10th, 2013 Photo Report
� 2 �
Maynard Jackson High School Weekly Photo Report
Tower 2 Steel Erection East Elevation
South Expansion South Courtyard Glazing
� 3 �
Maynard Jackson High School Weekly Photo Report
Site Wall C North Parking Lot Curb and Gutter
Stair 2 Gym Exterior Wall Demolition
� 4 �
Maynard Jackson High School Weekly Photo Report
Gym Shoring Cooling Tower
North Courtyard Glazing Corridor Adjacent to Cafeteria
� 5 �
Maynard Jackson High School Weekly Photo Report
Next Week’s Activities
May 6 – May 10
• Stair 2 blocking to begin
• Stair 6 brick work to begin
• Glazing at North courtyard to begin
• Continue main gym demolition
• Continue shoring erection and roof soil removal
• Continue roofing at mezzanine, high roof and pop up roof
• Continue existing structure paint preparation
• Tower 2 Steel to be completed
• Waterproofing of the 3 remaining V�Notch infills to be completed
• Field measuring for Tower 2 curtainwall to be completed
• Elastomeric coating on West Mezzanine CMU to be completed
• Waterproofing and Backfilling of retaining wall C to be completed