REHABILITATION OF THE HONORÉ MERCIER BRIDGE
FEDERAL SECTION
WORK PLAN
2014
FOLLOW UP ON THE PROJECT
3
Pier 14
Ramp 4139 SLABSINSTALLED
Ramp 2188 SLABSINSTALLED
Ramp 3120 SLABSINSTALLED+ 73 FOR THE BIKE PATH
FEDERAL SECTIONWORK COMPLETED
Pier 32
Maline Island East Side Montréal Direction116 SLABSINSTALLED
FEDERAL SECTION2/3 OF THE WORK COMPLETED BEFORE 2014
SUMMARY OF THE WORK BEFORE 2014
636 SLABS REPLACED
346 SLABSTO BE INSTALLED
WORK PLANNED IN 2014
6
XX
X
Pier 14
Pier 27
2014 WORK120 SLABS TO INSTALL+ 73 SLABSFOR THE BIKE PATH
X
ONE LANE / DIRECTION
Work zone
WORKDAY AND NIGHTSEVEN WEEKSSUMMER 2014
7
MALINE ISLAND SECTION
SEAWAY SECTION
CONVERGENCE SECTION
2014
8
LASALLElSOUTH-SHOREl
MALINE ISLAND SECTIONTOWARDS THE SOUTH-SHORE
ONE LANE OPEN PER DIRECTION
WORK SCHEDULE
Honoré Mercier Bridge
2014 WORK SCHEDULESEVEN CONSECUTIVE WEEKS
APRIL MAY JUNE
JULY AUGUST SEPTEMBER
OVERVIEW OF WORK TO COME
SLABS CUT AND REMOVED
INSTALLATION OF THE NEW CONCRETE DECK SLABS
INSTALLATION OF THE NEW CONCRETE DECK SLABS
NEW VS OLD DECK
NEW
OLD
SLABS ANCHORERD TO STEEL STRUCTURE
HIGH LEVEL OF PRECISION DURING THE INSTALLATION
INSTALLATION OF NEW BEARING DEVICES
INSTALLATION OF NEW EXPANSION JOINTS
POST-TENSIONING OF THE DECK SLABS (INSTALLATION OF STEEL CABLES)
INSPECTION AND FINAL PAVING OF THE BRIDGE
22