Transcript
Page 1: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

REHABILITATION OF THE HONORÉ MERCIER BRIDGE

FEDERAL SECTION

WORK PLAN

2014

Page 2: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

FOLLOW UP ON THE PROJECT

Page 3: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

3

Pier 14

Ramp 4139 SLABSINSTALLED

Ramp 2188 SLABSINSTALLED

Ramp 3120 SLABSINSTALLED+ 73 FOR THE BIKE PATH

FEDERAL SECTIONWORK COMPLETED

Pier 32

Maline Island East Side Montréal Direction116 SLABSINSTALLED

Page 4: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

FEDERAL SECTION2/3 OF THE WORK COMPLETED BEFORE 2014

SUMMARY OF THE WORK BEFORE 2014

636 SLABS REPLACED

346 SLABSTO BE INSTALLED

Page 5: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

WORK PLANNED IN 2014

Page 6: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

6

XX

X

Pier 14

Pier 27

2014 WORK120 SLABS TO INSTALL+ 73 SLABSFOR THE BIKE PATH

X

ONE LANE / DIRECTION

Work zone

WORKDAY AND NIGHTSEVEN WEEKSSUMMER 2014

Page 7: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

7

MALINE ISLAND SECTION

SEAWAY SECTION

CONVERGENCE SECTION

2014

Page 8: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

8

LASALLElSOUTH-SHOREl

MALINE ISLAND SECTIONTOWARDS THE SOUTH-SHORE

ONE LANE OPEN PER DIRECTION

Page 9: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

WORK SCHEDULE

Page 10: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

Honoré Mercier Bridge

2014 WORK SCHEDULESEVEN CONSECUTIVE WEEKS

APRIL MAY JUNE

JULY AUGUST SEPTEMBER

Page 11: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

OVERVIEW OF WORK TO COME

Page 12: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

SLABS CUT AND REMOVED

Page 13: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF THE NEW CONCRETE DECK SLABS

Page 14: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF THE NEW CONCRETE DECK SLABS

Page 15: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

NEW VS OLD DECK

NEW

OLD

Page 16: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

SLABS ANCHORERD TO STEEL STRUCTURE

Page 17: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

HIGH LEVEL OF PRECISION DURING THE INSTALLATION

Page 18: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF NEW BEARING DEVICES

Page 19: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF NEW EXPANSION JOINTS

Page 20: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

POST-TENSIONING OF THE DECK SLABS (INSTALLATION OF STEEL CABLES)

Page 21: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSPECTION AND FINAL PAVING OF THE BRIDGE

Page 22: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

22

MERCIERBRIDGE.CA


Top Related