Download - Monaco Engineering Solutions - Subsea UK
Monaco Engineering Solutions
1
Overview
• Subsea Reliability Challenges
• Reliability, Availability and Maintainability Definitions
• Subsea Reliability Strategy using PLASMA – Based on API RP 17N
• Reliability Strategy Summary
2
3
• Maximise Oil and Gas production
• Minimise environmental impact
• Minimise risk to assets and personnel
• Maximise profit
These can be accomplished by improving reliability of subsea systems and
optimising maintenance costs and thus:
Maximising Subsea Production Availability
Subsea Reliability Challenges
System Production Availability
4
Production Availability
Reliability Maintainability Reliability
0.9986
0.9988
0.999
0.9992
0.9994
0.9996
0.9998
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Failu
re R
ate
Time
5
Reliability – Bathtub Curve
Early Life Useful Life Wear out
The main focus of Reliability is understanding the failure patterns of
equipment/components throughout life of field.
Wear out
0.9986
0.9988
0.999
0.9992
0.9994
0.9996
0.9998
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Failu
re R
ate
Time
6
Reliability – Bathtub Curve
Early Life Useful Life
Early life failures are also known as infant mortality and burn-in failures.
Manufacturing defects: Welding flaws, cracks, defective parts, contaminations,
poor workmanship and poor quality control.
Minimised by good design, fabrication and testing philosophy and
implementing a Reliability Strategy.
Wear out
7
• Aiming to reduce early life failures
Reliability – Bathtub Curve
0.9986
0.9988
0.999
0.9992
0.9994
0.9996
0.9998
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Failu
re R
ate
Time
Early Life Useful Life
Uncertainty
Wear out
8
• Aiming to reduce early life failures
Reliability – Bathtub Curve
0.9986
0.9988
0.999
0.9992
0.9994
0.9996
0.9998
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Failu
re R
ate
Time
Early Life Useful Life
Uncertainty
• What are the uncertainties in the equipment failure
rates
– Environmental conditions
– Operating conditions
– Suitability for Service (e.g. Is it operated within design
conditions?, Is it designed to appropriate standards? Is
it being used beyond its capability?)
– Lack of dependable subsea reliability data
System Production Availability
9
Production Availability
Reliability Maintainability Maintainability
• Maintenance downtime profile for a single failure
10
Full Production
Maintainability
• Maintenance downtime profile for a single failure
11
Partial Production loss
Supply Delay and
Mobilisation Delay
Maintainability
• Maintenance downtime profile for a single failure
12
Repair Time (No Production)
Repair Time comprises:
• Access
• Diagnosis
• Replacement/Repair
• Verification and Alignment
Maintainability
13
Restart or Ramp-up
Maintainability
• Maintenance downtime profile for a single failure
Maintainability
14
1. Corrective Maintenance (CM) i.e. repair or replace when failure occurs.
2. Planned Preventive Maintenance (PPM) i.e. time based maintenance or
replacement.
3. Condition based maintenance (CBM) i.e. monitoring the performance and
perform maintenance/replacement when condition deteriorates.
For ultra-deepwater, the preferred strategy is Corrective Maintenance (CM) i.e.
repair or replace when failure occurs.
However, the CM strategy itself when implemented is still not
cost-effective. There’s a need to eliminate potential failures when possible.
• Reducing frequency of failures = Improving Reliability
• Reducing repair or downtime i= Improving Maintainability
• How do we quantify production availability?
15
Typical Production Output
Failures
Assuming a constant production profile
10 failures
6 weeks downtime
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝑨𝒗𝒂𝒊𝒍𝒂𝒃𝒊𝒍𝒕𝒚 = 𝑨𝒄𝒕𝒖𝒂𝒍 𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝑽𝒐𝒍
𝑷𝒐𝒕𝒆𝒏𝒕𝒊𝒂𝒍 𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝑽𝒐𝒍
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝑨𝒗𝒂𝒊𝒍𝒂𝒃𝒊𝒍𝒕𝒚 = 𝑨𝒄𝒕𝒖𝒂𝒍 𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝑽𝒐𝒍
𝑷𝒐𝒕𝒆𝒏𝒕𝒊𝒂𝒍 𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝑽𝒐𝒍
16
Production Availability Definition
Assuming a constant production profile
17
How can we optimise the production
availability?
• Optimise reliability and maintainability and adopt the asset management
strategy based on API RP 17N.
• Use specialised tools that implement Subsea Reliability Strategy into design:
– The tool should be designed to conform with API RP 17N and ISO 20815.
– Platform for Operators, Contractors and Vendors to understand and review R&M
as an iterative and continuous process
– Allow all parties to work together to meet R&M goals and remain up-to-date on
Reliability targets
– Ensure R&M goals are carefully considered throughout all life-cycle phases
– Formulate a Reliability Assurance Document (RAD) which summarises the
findings from various analyses from the Reliability Strategy program such as RAM,
FTA, FMECA, TRC and TRL and demonstrate whether production availability
targets have been met.
• This paper investigates the implementation of Subsea Reliability Strategy
using PLASMA software.
18
• API RP 17N provides a structured
approach which organisations can
adopt to manage uncertainties
throughout the life of a project.
19
Reliability Strategy Flowchart
• The reliability activities have been
arranged into a cycle of four basic steps.
• Based on 12 key reliability processes as
defined by ISO 20815 for production
assurance and reliability management
20
The changes to the
Goals can be tracked
through each iteration.
21
Goals and Requirements
• Define project specific goals, strategies
and requirements
• Define high level reliability and
maintainability goals
– Overall Production Availability
– Probability of achieving a
maintenance free operating period
– Probability of achieving a minimum
failure free operating period
(non-maintainable items)
22
Goals and Requirements
• Allocation of availability
– Topside system
– Subsea system
• Define project strategy
– Minimise time to restore failed
equipment to an operable state
(Maintainability Strategy)
– Extend equipment life before failure
(Reliability Strategy)
– Combination of both
23
Technical Risk Categorisation
• Define project requirements
– A high level technical review using
Technical Risk Categorisation
24
Technical Risk Categorisation
24
Reliability Technology Architecture /
Configuration Environment Organisation
Key Words
Reliability Requirements
Maintainability
Availability
Failure modes
Risk
Uncertainty
Materials
Dimensions
Design life
Stress limits
Corrosion
Equipment
Layout
Interfaces
Complexity
Field location
Water depth
Sealed conditions
Reservoir conditions
Environmental
loadings
Test location
Storage
Location
Company
Supply chain
Design
Manufacture
Install
Operate
Maintain
Very High
(A)
Significant Reliability
Improvements
(technology change)
Novel technology or
new design concepts Novel application New environment
Whole new
team
High
(B)
Significant Reliability
Improvements
(design change)
Major modifications Orientation and
capacity changes
Significant
environmental
changes
Significant team
changes
Medium
(C) Minor Reliability improvements Minor modifications Interface changes
Similar
environmental
conditions
Minor team
changes
Low
(D) Unchanged Reliability Unchanged Technology Unchanged
Same
environmental
conditions
Same team as
previous
25
Reliability Activities
• Allocate leadership and resources to the
required reliability activities
– resources (people, software/hardware,
etc.);
– roles and responsibilities;
– deliverables for each activity;
– schedules and milestones.
26
Reliability Activities
• Planning philosophies and tasks
– Operators should initiate reliability plans
as early as possible in feasibility and
concept selection stage
– Plans should be adopted by contractors in
consultation with the operators
Reliability Activities
27
Reliability Activity Task Notes Responsibility Timing Output
Reliability Data Establish data for RAM Model - initially
use OREDA RAM Specialist Ongoing PLASMA Database
Define/update/monitor
R&M Goals
Achieve availability of Ai% within
CAPEX of Ci and OPEX of Oi Project Manager Before ITT Update Basis of Design
Update qualification plan
& schedule
Update and manage Reliability Plan
and schedule for qualification Reliability Lead Ongoing - Quarterly
Qualification plan and
schedule
System functional FMECA Identify unacceptable system failure
modes
Reliability Lead /
RAM Specialist Before ITT
HAZOP report and
actions; input into the
RAM model
Fault Tree Analysis
Identify the causes of failure and failure modes. Applicable to Unrevealed Failure
Modes
Reliability Lead /
RAM Specialist Ongoing
Quantify the Probability of
Failure on Demand for the
TOP Events
System RAM Analysis
Use PLASMA to examine Production
Availability and look at impact of
design change
RAM Specialist
Ongoing – Final
completion in X
months
RAM Model
Lessons Learned Verify lessons learned have been
considered in the design Project Manager Ongoing Design review report
Reliability Assurance
(RAD)
Ongoing collection of evidence for
assurance Reliability Lead
Ongoing – Final
completion in Y
months
Subsea RAD
28
• Project implementation should keep
R&M at it’s core:
– potential failure modes that could
affect system performance have
been analysed and managed
– all design decisions are consistent
with the R&M goals
– the qualification of equipment has
addressed the R&M required by the
project
– all documented lessons learnt from
previous projects have been
incorporated
– the supply chain is fully integrated
into the reliability and technical risk
management program
29
Feedback
• Lesson learnt from operations
regarding reliability performance of
equipment should be included as an
input into projects.
30
Reliability Assurance Document (RAD)
• The purpose of Reliability Assurance is to
demonstrate that the Availability requirements
have been met and the extent to which the
availability goals will be achieved.
• This contains statements on:
– Goals, requirements and strategy
– Project technical risk category
– Description of work carried out and findings
– Recommendations for the project
– Lessons learnt
31
Process Flow Diagram (PFD)
Reliability Block Diagram (RBD)
32
Fault Tree Analysis (FTA)
33
Probability of Failure on Demand
34
Top event frequency
0
35
Failure Mode Effects and Criticality Analysis (FMECA)
0
36
Failure rate data is dynamically linked with other
Reliability Activities to ensure consistent use of data.
37
1. The subsea system has an average production availability of 97.4% ± 1.4% over it’s 30 year design life.
2. This is equivalent to an average production rate of 10,700,000 sm3 per year and average production loss of 270,000 sm3 per year.
3. The estimated production volume over the design life is 321,000,000 sm3 per year.
4. The average production availability does not meet the production availability target of 98.5%.
5. A breakdown of the contributor to overall unavailability.
38
Production Availability Probability Distribution (PAPD)
1. The PAPD is based upon 500 simulation runs.
2. There is a 6.8% probability that the production availability
target of 98.5% shall be achieved over its 30 year design
life.
3. There is a 50% probability that the system shall achieve
an average production availability of 97.4% or above over
its 30 year design life.
39
Relative Contribution to System Unavailability
1. The main system relative contributors to overall
unavailability are Production (36.9%), MEG DS (22.4%)
and HIPPS (17.1%).
Overall System
40
Relative Contribution to Production Unavailability
1. The main system relative contributors to overall
unavailability are Production (36.9%), MEG DS (22.4%)
and HIPPS (17.1%).
2. The main Production relative contributors to system
unavailability are Pipelines (54.7%), Wells (37.5%) and
Hydrate (7.8%) respectively.
Overall System > Production
41
Relative Contribution to Wells Unavailability
Overall System > Production > Wells
1. The main system relative contributors to overall
unavailability are Production (36.9%), MEG DS (22.4%)
and HIPPS (17.1%).
2. The main Production relative contributors to system
unavailability are Pipelines (54.7%), Wells (37.5%) and
Hydrate (7.8%) respectively.
3. The main Wells relative contributors to system
unavailability are X-Tree (37.6%), Tubing (24.4%) and
SCSSV (18.0%) respectively.
Cost Benefit Curve - Reliability
42
Reliability
Co
st
• How much Reliability and Maintainability should be designed into a product?
• Acquisition cost includes cost of implementing and operating a reliability
program in addition to the overall development and production costs
associated with the product (Material, labour, taxes, insurance, admin,
marketing etc.)
• Failure Cost includes warranty costs, liability costs, replacement or repair
costs and loss of market share.
Total Cost (t) = Acquisition cost (t) + Failure Cost (t)
Minimum
Required
Reliability Minimum Cost
Cost Benefit Curve - Maintainability
43
Maintenance Frequency
Co
st
• Planned Maintenance (PM) Cost includes labour and equipment required.
This will capture any incipient failures.
• Corrective Maintenance Cost includes costs associated with downtime,
repair crews, equipment required and parts required.
Total Cost (t) = CM cost (t) + PM cost (t)
Optimum
PM
44
Reliability Assurance Document (RAD)
Reliability Assurance Document (RAD)
Contents
• Executive Summary
• Introduction
• Process Description
• Availability Requirements and Strategy
• Reliability Activities
• RAM Analysis
• Fault Tree Analysis (FTA)
• Failure Mode Effects and Criticality Analysis (FMECA)
• Technical Risk Categorisation (TRC)
• Technology Readiness Level (TRL)
• Availability Evidence
• Availability Claims
• Conclusions & Recommendation
45
46
47
Reliability Strategy Summary
• API RP 17N is a structured approach which can be used to optimise R&M
goals.
• Reliability Strategy is an iterative process which is used throughout all project
phases.
• Reliability Assurance Document (RAD) records the findings from various
reliability activities (RAM, FTA, FMECA, TRC, TRL etc.) and demonstrates
whether the production availability targets have been met.
• PLASMA is an integrated reliability tool which provides a live platform for
Operators, Contractors and Vendors to understand and demonstrate that
R&M goals have been met.
48
Any Questions?
49
UK Office
Contact: Dr. Mehran Pourzand
Address: Monaco Engineering Solutions Ltd., Randalls Road, Leatherhead, Surrey,
KT22 7RY
Telephone: +44(0) 1372 227 997
Fax: +44(0) 1372 227 998
Website: www.mes-international.com
Enquiries: [email protected]
Contact Us