GDE - Status
• GDE has successfully completer Phase 1 of the Technical Design Phase
• Publication of comprehensive interim report: International Linear Collider: A Technical Progress Report– ILC-HiGrade-Report-2011-001
• Phase 2 now underway, shifts emphasis away from risk-mitigating R&D towards preparation for the final Technical Design Report (TDR end 2012):– Consolidation and review of final design baseline and
associated documentation– Preparation of updated Cost Estimate– Industrialisation of SCRF and global mass production
studies
12-10-2011
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 3
Coordinating with the GDE
12-10-2011
• ILC-HiGrade has remained tightly coordinated with GDE activities– Via key European
management
• No fundamental change during TDP– exception:
Steinar Stapnes (CERN) replaces Jean-Pierre Delahaye in GDE Exec. Committee
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 4
TDR CostEngineers
ILC-GDE Organisation
E. Elsen (DESY)
B. Foster (OXU)S. Stapnes (CERN)N. Walker (DESY)
W. Bialowons (DESY)
Primary coordination between ILC-HiGrade and GDE
12-10-2011
B. Warmbein (CERN/DESY)P. Royole-Degieux (IN2P3)M. Illenseer (DESY)
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 5
GDE, ILC-HiGrade Timelines
Reference Design Report (RDR)
GDE
TDP 2
2005 2006 2007 2008 20122009 2010 2011 2013 2014
TDR publication.Ready for Project Submission.
Tech. Design Phase (TDP) 1
ILC-HiGrade
LHC physics
12-10-2011
TDR international review
Transition to new LC org.
XFEL, ILC-HiGrade & GDE
12-10-2011
ILC-HiGrade participants reflect strong GDE-XFEL synergy (European strength), and are also active participants in the ILC-GDE
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay)
◉DESY
LAL,Saclay INFN Milan
CERN◉
OXUN
6
◉◉◉
ILC-HiGrade
ILC-HiGrade to provide QA/QC for XFEL cavity production- Focus on achieving consistent ILC gradient
performance
Now focused on XFEL input into- Cavity and Cryomodule Mass production- Costs (XFEL → ILC production levels)
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 7
SCRF Cryomodule Mass Production Studies
• ILC-HiGrade will coordinate European industrial studies on ILC-level production of cavities and cryomodules.– 18,000 cavities– 17,00 cryomodules
• Build on two sources of input– XFEL production of ~100 cryomodules (800 cavities)– TESLA industrial studies for 20,000 cavities (year 2000)
• Currently updating TESLA studies– Research Instruments (cavity)– Zanon (cavity)– Babcock Noell (string assembly)
• CERN-based model of string assembly– similar to LHC experience
• Studies to be complete mid-2012– Provide European input into GDE TDR cost estimate
12-10-2011
XFEL experience
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 8
The GDE Technical Design Report
• Primary TD Phase deliverables:– Updated design of the machine– Updated VALUE estimate– Project Implementation Plan– Results and conclusions from worldwide Risk-mitigating
R&D
• TDR will be three volumes*– Executive Summary– Part I: Results of Risk-Mitigating R&D– Part II: ILC Baseline Design, including
• Comprehensive design document• Cost and schedule• Project Implementation Planning
• ILC-HiGrade has already provide input at many levels12-10-2011
*Not including Physics and Detector volumes
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 9
Coordination requires Communication
• GDE (and ILC-HiGrade) is a worldwide (European) distributed collaboration
• Face-to-face meetings (workshops) remain critical for progress– And team building!
• However, primary (weekly) contact remains via remote conferencing
12-10-2011
N. Walker (DESY) - ILC-HiGrade Annual Meeting (LAL, Orsay) 10
Relevant European Workshops• TESLA Technology Collaboration meeting
– INFN Milan, 28.02-03.03.11
• ILC Damping Ring Baseline Technical Review– INFN Frascati, 06-08.07.11
• 1st European SRF Industrialisation Meeting– CERN, 14.04.11
• 3rd European SRF Industrialisation Meeting– CERN, 16.09.11
• LCWS ‘11– Granada, 26-30.09.11 – together with Physics & Detector community
• ILC central region Baseline Technical Review– DESY, 24-27.10.11
• ILC CFS meeting– DESY 28.10.11
• ILC cost management meeting– DESY 29.10.11
12-10-2011
11
Summary
• ILC-HiGrade integration into the GDE remains at the highest level and is essentially unchanged
• GDE is now shifting focus to the preparation of the TDR, including updated cost estimate
• ILC-HiGrade co-coordinating European industrial study effort for SRF– As part of the GDE global effort
• Other key areas of TDR input now quite mature– Governance (Project Implementation Planning)– Siting (CERN and Dubna sites)