Projects Status
Current Projects
•5086.3A – Phase 1 - Health and Training Center – 98% Complete
•5086.4 – Phase 2 - Main Addition (New construction)– Substantially Complete
•5086.4 – Phase 2 - Summer 2020 Renovations – Complete
•5086.5 – Phase 3 - 400/500 Connector – Substantially Complete
•5086.5 – Phase 3 – Summer 2021 Renovations – 60% Complete
•5086.6 – Phase 4 - HVAC Renovations – Complete
•5086.7 – Partial Reroofing –Substantially Complete
•5086.8 – Greenhouse – 80% Complete
•5086.9 – Parking Lot / Old Building Demo –
40% Complete
2
![Page 3: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/3.jpg)
Projects Status
Current Projects
• Construction Progress Meetings are held every other Thursday morning and are held in
the new Media Center
• All personnel on site have been instructed to wear masks whenever in proximity to
District Staff
3
![Page 4: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/4.jpg)
Project Summary
Project 5086.3A – Health and Training Center(Five Prime Contractors)
General Construction – Arthur Ogren
HVAC - Driscoll Mechanical
Structural Steel – Southern New Jersey Steel
Plumbing – Annese Mechanical
Electrical – QPI Electric
• Project is 98% complete – Waiting for wood doors and terrazzo
patching (currently underway)
• Interior renovations that are part of this contract are nearly
complete (Classroom renovations and restrooms)
4
![Page 5: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/5.jpg)
Project Photo
Project 5086.3A – Health and Training Center
Exterior View from Baseball Field
5
![Page 6: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/6.jpg)
Project Photo
Project 5086.3A – Health and Training Center
Inside View – Cleaning in Progress
6
![Page 7: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/7.jpg)
Project Summary
Project 5086.4 – Main Connector Addition/Renovations(Five Prime Contractors)
General Construction – Arthur Ogren
Structural Steel – Southern New Jersey Steel
Plumbing – Annese Mechanical
HVAC – Preferred Mechanical
Electric – QPI Electric
• Project is Substantially Complete
• Remaining new construction work to be complete this month (Site, Roof
Metal, Millwork)
7
![Page 8: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/8.jpg)
Project Summary
Project 5086.4 – Main Connector Additions
West Cafeteria Expansion Complete
8
![Page 9: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/9.jpg)
Project Summary
Project 5086.4 – Main Connector Addition
West Cafeteria Expansion
9
![Page 10: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/10.jpg)
Project Summary
Project 5086.4 – Main Connector Addition
West Cafeteria Expansion
10
![Page 11: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/11.jpg)
Project Summary
Project 5086.4 – Main Connector Addition
West Kitchen Expansion
11
![Page 12: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/12.jpg)
Project Photos
Front Entrance of Main Addition Final Metal Work
12
![Page 13: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/13.jpg)
Project Photos
New Media Center
13
![Page 14: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/14.jpg)
Project Photo
North Side of New Media Center
14
![Page 15: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/15.jpg)
Project Photos
Loading Dock at Rear of Main Addition
15
![Page 16: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/16.jpg)
Project Summary
Project 5086.5 – 400/500 Connector Addition(Five Prime Contractors)
General Construction – Arthur Ogren
Structural Steel – Mastercraft Iron
Plumbing – Three G’s Plumbing
Electric – QPI Electric
HVAC - Preferred Mechanical
• Addition is Substantially Complete with minor issues to address
16
![Page 17: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/17.jpg)
Project Summary
Project 5086.5 – Phase 3 (400/500 Connector) Addition
View from West Parking Lot
17
![Page 18: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/18.jpg)
Project Photo
Project 5086.5 – Phase 3 (400/500 Connector) Addition
Finished Choral Room
18
![Page 19: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/19.jpg)
Project Photo
Project 5086.5 – Phase 3 (400/500 Connector) Addition
Early Childhood Development Room
19
![Page 20: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/20.jpg)
Project Summary
Project 5086.5 – Phase 3 – Summer 2021 Renovations
• June 21, 2021 - Summer Renovation Work Began
• August 27, 2021 – Substantial Completion
Scope of Renovations
• Rooms 203, 205, 306, 307, and 308 are complete and have been
turned over to District
• New Guidance Offices have been turned over to the District
20
![Page 21: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/21.jpg)
Project Summary
Project 5086.5 – Phase 3 – Summer 2021 Renovations
• Extensive renovations continue in 100, 200, 300 and 700 Corridor
Classrooms
• 600 Corridor Restrooms (new) are 80% Complete
• HVAC renovations continue in East Cafeteria, Art Room and 700
Classrooms
21
![Page 22: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/22.jpg)
Project Scope
Project 5086.5 – Phase 3 – Summer 2021 Renovations
22
![Page 23: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/23.jpg)
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
700 Wing Renovation
23
![Page 24: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/24.jpg)
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
24
![Page 25: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/25.jpg)
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
25
![Page 26: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/26.jpg)
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
26
![Page 27: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/27.jpg)
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
27
![Page 28: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/28.jpg)
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
600 Wing Restroom Tile (Old Faculty Room)
28
![Page 29: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/29.jpg)
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
Old Media Center Conversion to Board Offices
29
![Page 30: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/30.jpg)
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
New Air Handler Unit in 500 Building
30
![Page 31: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/31.jpg)
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
Floor Trenches for Science Lab Utilities
31
![Page 32: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/32.jpg)
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
New Casework in Room 203
32
![Page 33: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/33.jpg)
Project Summary
Project 5086.6 – HVAC Renovations
HVAC - Preferred Mechanical
• Project is in close-out phase
• Systems are operating well
• Preferred Mechanical has responded quickly to a minimal number of issues
33
![Page 34: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/34.jpg)
Project Summary
Project 5086.7 – Partial Roof Replacement
Contractor - Winchester Roofing
• Project is Substantially Complete
• Contractor has some punch list items to complete and is working with the
HVAC Contractor flashing curbs for new roof top units
34
![Page 35: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/35.jpg)
Project Summary
Project 5086.8 – Greenhouse Project
Contractor – Aliano Brothers
• New Greenhouse is 80% - anticipated completion 9/1/2021
35
![Page 36: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/36.jpg)
Project Summary
Project 5086.8 – Greenhouse Project
36
![Page 37: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/37.jpg)
Project Summary
Project 5086.8 – Greenhouse Project
• Building concrete, masonry, framing and roofing are complete
• Exterior wall glazing is 85% complete
• Mechanical, Plumbing and Electrical rough-in are 50% complete
• Energy curtains are on site for installation
37
![Page 38: Northern Burlington County Regional School District Board](https://reader034.vdocuments.net/reader034/viewer/2022042320/625d11b658dfe72b8a5e8624/html5/thumbnails/38.jpg)
Project Summary
Project 5086.9 – Parking Lot and Demolition of Old
Buildings
• Underground gas, sanitary and water lines are complete
• Rainwater piping is being installed
• Concrete curbs are being formed and poured
• Final paving and finishes may be completed
After the start of school
38