Download - November 12, 2007 7:00 pm
![Page 1: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/1.jpg)
November 12, 2007
7:00 pm
_________ P r e s e n t a t i o n
Matthews Board of Commissioners
Matthews Sportsplex
![Page 2: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/2.jpg)
Woolpert, Inc.
Town & County StaffElected Officials Park and Recreation Commission Members
Citizens of the Mecklenburg County & Town of Matthews
•
•
• Mecklenburg County Park and Recreation & Town of Matthews
Project Team
“C o l l a b o r a t i v e” Team Approach___
![Page 3: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/3.jpg)
- Project Timeline
- Project Study Area / Site Analysis
- Planning Process/ Workshops
- Master Plan Presentation
- Questions / Answers
Agenda
P r e s e n t a t i o n A g e n d a________
![Page 4: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/4.jpg)
Project Timeline
D a t e_________________ A s s o c i a t e d T a s k_________________
• July - August 2007
• September 6, 2007
• September 27, 2007
• October 30, 2007
• November / December 2007
• Early 2008 (6-8 months)
• Late 2008 to Early 2009
Project Team Site Analysis
Community Workshop No. 3(Matthews Community Center)
Presentation of Master Plan to Town, P&R Commission / County Commission(Nov. 12th, 13th and tentatively Dec. 18th)
Community Workshop No. 2(Matthews Community Center)
Anticipated Phase 1 Construction to Begin
Design Phase
Community Workshop No. 1(Matthews Community Center)
![Page 5: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/5.jpg)
• 11 Sportsplexes
Matthews
Sportsplex
• Matthews Sportsplex Site
County’s Proposed Sportsplexes
![Page 6: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/6.jpg)
Study Area / Site Analysis
![Page 7: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/7.jpg)
• +/-160 AC study area
• North
• NC - 74
• CSX Rail Line
• Matthews Township Pkwy
• I - 485
• Four Mile Creek
• Adjacent Town Project
• Adjacent Neighborhood
• Adjacent Institutional
Preformed analysis of natural and cultural factors which lead to a suitability map
CPCC – Levine Campus
Crestdale Neighborhood
Town Maintenance
A e r i a l P h o t o _______ Downtown Matthews
Matthews Small Area Plan
485
Study Area
![Page 8: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/8.jpg)
Planning Process / Workshops
![Page 9: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/9.jpg)
September 6, 2007 – 42 attendees Summary of Comments
Program Elements:
• Multi-purpose fields - soccer/football/rugby/lacrosse– Synthetic turf on portion of fields
• One championship field / stadium–seating for 1,500 / berm / room for expansion
• Family amenities – playgrounds, volleyball, horseshoes, etc.• Greenway connectivity/ walking / hiking trails• Indoor programming space
•Other Comments:
• Consider CATS relocating to perimeter • Multi vehicular access points into park• Stormwater considerations / maintain natural creek• Traffic on Tank Town Road
Workshop Exercise
(5) groups suggested ideas/ comments on the sportsplex design
__________
Community Workshop #1
![Page 10: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/10.jpg)
Concept 1
Concept 2
Community Workshop #2
![Page 11: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/11.jpg)
Community Workshop #2September 27, 2007 – 31 attendees Summary of Comments
Program Ideas & Preferences:
• Stadium capacity– allow for expansion
• Family amenities – playgrounds, volleyball, horseshoes, etc.• Greenway connectivity/ walking / hiking trails• Indoor programming space
•Other Comments:
• Security• Parking Issues • Equestrian Facilities• Indoor Swimming Center
Workshop Exercise
(3) groups suggested ideas/ comments on the sportsplex design
___________
![Page 12: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/12.jpg)
Master Plan
![Page 13: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/13.jpg)
Master Plan
![Page 14: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/14.jpg)
Overall Plan
![Page 15: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/15.jpg)
Master Plan
![Page 16: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/16.jpg)
CATS Transit Alignment
Shared Maintenance Facility (expansion)
Indoor Meeting Facility(patio, volleyball, open field, playground)
Four Mile Creek Greenway
Wetlands (Typ.)
Main Park Entrance
80 Car Parking Lot
80 Car Parking Lot
Connection to Levine Campus & Park and Ride(tunnel under I 485)
(2) Natural Turf Sports Fields 1
2
Master Plan
![Page 17: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/17.jpg)
Master Plan
![Page 18: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/18.jpg)
(3) Natural Turf Sports Fields
Perimeter Walking Trails
Boardwalks (Typ.)
Restroom/ Concession
Playground
250 Car Parking Lot
Park Road (landscaped median)
Retaining Wall (Typ.)
(2) Synthetic Turf Sports Fields
1 2
3 4 5
Master Plan
![Page 19: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/19.jpg)
Master Plan
![Page 20: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/20.jpg)
900 Car Parking Lot
Potential Stadium Expansion to 5000 seats
Natural Turf Stadium Field
Pedestrian Connections to Future Development (typ.)
Fieldhouse
2700 Person Stadium
Park Entrance From Future Development
Best Management Practice (BMP)
Master Plan
![Page 21: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/21.jpg)
Master Plan
![Page 22: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/22.jpg)
Playground
200 Car Parking Lot
Spectator Bleachers (Typ.)
Restroom/ Concession
(4) Synthetic Turf Sports Fields
1 2
3 4
Shelters (Typ.)(volleyball / horseshoe/ grills)
Perimeter Walking Trails
Cross Country (5 K)
Start
Finish
Master Plan
![Page 23: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/23.jpg)
Potential Phase One Area
![Page 24: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/24.jpg)
Parking Fields
Entrance / Road
Potential Phase One Area$ 7 Million Budget Allocation
![Page 25: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/25.jpg)
Future development to be determined based upon program preferences and future funding allocation
Potential Phase One
Future Phasing
![Page 26: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/26.jpg)
Project Timeline - Next Steps in the Planning Process
D a t e_________________ A s s o c i a t e d T a s k_________________
• July - August 2007
• September 6, 2007
• September 27, 2007
• October 30, 2007
• November / December 2007
• Early 2008 (6-8 months)
• Late 2008 to Early 2009
Project Team Site Analysis
Community Workshop No. 3(Matthews Community Center)
Presentation of Master Plan to Town, P&R Commission / County Commission(Nov. 12th, 13th and tentatively Dec. 18th)
Community Workshop No. 2(Matthews Community Center)
Anticipated Phase 1 Construction to Begin
Design Phase
Community Workshop No. 1(Matthews Community Center)
![Page 27: November 12, 2007 7:00 pm](https://reader037.vdocuments.net/reader037/viewer/2022110103/56814ebe550346895dbc5e3e/html5/thumbnails/27.jpg)
Questions