Download - October 1 , 2009

Transcript
Page 1: October 1 ,  2009

Hydrokinetic TurbineFeaturing Variable Flux Generation

October 1, 2009

Sean CurranVanessa Kohler

Erik MinnisMichael Perry

C. Taylor PetersonAlex Quintal

Page 2: October 1 ,  2009

Introduction• Direct drive power generation at low flow velocities• Magnets engage with coils • Axial displacement is relative to drag on the rotors

Page 3: October 1 ,  2009

Objectives

Design and construct a hydrokinetic turbine to utilize low velocity tidal currents for power generation.

VFG Wind Turbine:4.7m diameter

Page 4: October 1 ,  2009

Approach• Water is 830 times denser than air

– Turbine blades will encounter higher forces• Model tested in tow tank • Demonstration model turbine to be deployed under

General Sullivan Bridge

Page 5: October 1 ,  2009

Major Tasks• Stator Development

– Includes coils specified to generate a certain amount of electricity at certain frequency

• Rotor Design– Formed by turbine blade assembly– Turns magnetic ring assembly in generator

• Blade Selection– Shape, angle of attack & material

Page 6: October 1 ,  2009

Major Tasks (cont.)• Water Proofing and Corrosion Resistance

– Salt water application– Component isolation from water

• Generator Actuation– Magnetic rotor– Fixed coils– Magnetic rotor can move axially

• Deployment Structure– Based from barge– Based from pier– Based from platform in Tow Tank

Page 7: October 1 ,  2009

TimelinePLAN OF ATTACK

September Proposal, Conceptual design analysisOctober Create parts in CADNovember Analyze CAD parts using FEA

December

Analyze CAD parts using FEA, and consider parts procurement /manufacturing

Break Begins Order Parts, rough draft of final report

Break Ends Prototype partially assembled

FebruaryPrototype fully assembled- testing in Tow Tank

March Testing in tow tank and in salt water

April Review Progress- finish report

MayPresent Report, poster, and final product

Page 8: October 1 ,  2009

Write Proposal

Compile Gantt Chart

Conceptual Designs

Conceptual Design Report

Pro/ENGINEER Drawings

Pro/ENGINEER Report

Analysis

FEA Report

Price Report

Parts & Materials Ordered

Build Report I

Tank Testing

Build Report II

Prototype Conmplete

Build Report III

Ocean Testing

Testing Report

Final Report/Poster/URC

9/1/2009 10/21/2009 12/10/2009 1/29/2010 3/20/2010 5/9/2010

Start Date 4/3/2010

VFG Project Timeline

Page 9: October 1 ,  2009

Fiberglass Resin Magnets Generator

Seals Housing Bearings

Shafts Steel

Budget