PAUL L. SHANK P.E., C.M.CHIEF ENGINEER BWI MARSHALL AIRPORT
MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION
WHERE WE ARE – WHERE WE ARE GOINGNOVEMBER 20,
2013
![Page 2: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/2.jpg)
RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM
![Page 3: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/3.jpg)
PROGRAM YEAR 2013TASK CONTRACT VALUE MBE
1Runway 15R-33L Standards Compliance Earthwork Project
$21,800,000 25%
2Runway 15R Deicing Pad Pavement Rehab. And Stnds. Compliance
$14,169,000 30%
3 Low Maintenance Grassing Test Plots
$133,000 25%
4 General Aviation Pavement Rehabilitation
$994,000 20%
5RSA Program Environmental Stream Restoration Project
$2,079,000 26%
6Runway 15L-33R Runway Safety Area Improvements
$4,960,000 20%
7Runway 15R-33L RSA, PMP and Standards Compliance Project
$83,235,000 20%
8Runway 10-28 and 15R-33L Obstruction Clearing Project
$413,000 4%
9* Runway 15R-33L NAVAIDS Project
$5,409,000 13%
*Graphic location same as Task 7
![Page 4: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/4.jpg)
15R 33L EARTHWORK
CONTRACT VALUE: $ 21,756,470
Contract Completes – Summer 2014
MBE: 25%
PROJECT OVERVIEW:
Clearing and grubbing. Storm drain installation. Box culvert installation. Sanitary sewer and underground fire hydrant relocation. Mass earthwork, grading and retaining wall.
![Page 5: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/5.jpg)
RUNWAY 15R DEICINGCONTRACT VALUE: $ 14,168,409
Contract Completes – November 2013
MBE: 30%
PROJECT OVERVIEW:
Removal of existing pavement. Installation of new glycol drainage infrastructure, lighting, diversion vaults. New concrete pavement and pavement markings.
![Page 6: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/6.jpg)
ENVIRONMENTAL STREAM RESTORATION
CONTRACT VALUE: $ 2,078,771
Contract Completes – July 2014
MBE: 26%
PROJECT OVERVIEW:
Grading of stream channels and placement of fill.
Construction of in-stream structures. Removal of invasive vegetation and plantings.
![Page 7: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/7.jpg)
RUNWAY 15L 33R RSA
CONTRACT VALUE: $ 4,959,398
Contract Completes – Spring 2014
MBE – 14%
PROJECT OVERVIEW:
New vehicle service road and airfield equipment access road. Drainage pipe, box culvert and structure installation. Preparation of site and infrastructure for future relocation of existing NAVAIDS.
![Page 8: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/8.jpg)
CONTRACT VALUE: $ 83,235,000
Proposed Schedule – September 2013 to April 2015
PROJECT OVERVIEW:
Comprehensive Pavement Rehabilitation. Runway Safety Area Grading and Improvements. NAVAID Relocations and Infrastructure Improvements. Runway and Taxiway Lighting Improvements. Taxiway Realignments. Runway Incursion Prevention Elements.
RUNWAY 15R 33L RSA
![Page 9: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/9.jpg)
PROGRAM YEAR 2014-2015
2014-2015 PROGRAM ELEMENTS
6Runway 10-28 Navaids & Runway 28 Displacement
15A
New T/W “Uniform” & T/W “Uniform 1” And South Portion De-ice Pad
15BRunway 4-22 Conversion To Taxiway “Papa”
15CNew Taxiway Construction (EB-75)
15DOld Taxiway “Delta” Demolition
PROGRAM VALUE 75-100M
15D
15B
15C
15A
6
![Page 10: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/10.jpg)
10
EXISTING TERMINAL - 2012
SECURITY CHECKPOINTS IN THE
THROAT OF THE CONCOURSES
RESTRICT EGRESS/ EVACUATION CAPACITY
CORRIDOR WIDTH IN ORIGINAL
PORTIONS OF CONCOURSES INADEQUATE
![Page 11: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/11.jpg)
11
LONG TERM TERMINAL PLAN UPPER LEVEL PLAN
NEW CHECKPOINTS
BETWEEN CONCOURSES BEHIND SECURITY
CONNECTORS ALLOW FOR LOAD BALANCING
AND CONNECTING FLIGHTS
![Page 12: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/12.jpg)
12
LONG TERM TERMINAL PLAN PHASING PLAN
CONCOURSE D ORIGINALLY FIRST
BECAUSE DEFICIENCIES WERE
GREATER DUE TO THE NUMBER OF GATES
SERVED.
SWA / AIRTRAN MERGER AND CONSOLIDATION ON
CONCOURSES A/B/C SHIFTED PRIORITIES TO
BC CONNECTOR
A B
C
E
![Page 13: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/13.jpg)
13
CONCOURSE C WIDENING
B/C CONNECTOR
BC CONNECTOR PROGRAM TWO CONSTRUCTION PROJECTS
![Page 14: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/14.jpg)
14
BC CONNECTOR FINAL UPPER LEVEL PLAN
9 LANE CHECKPOIN
T
![Page 15: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/15.jpg)
BC CONNECTORCONTRACT VALUE: $ 43,937,000
MBE: 20%
PROJECT OVERVIEW:
Secure passenger corridor connecting Concourse B and C. Nine (9) Lane Security Checkpoint. Observation Deck improvements. Concessions and Office Spaces.
![Page 16: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/16.jpg)
BC CONNECTOR
![Page 17: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/17.jpg)
NEW BC SECURITY CHECKPOINT
![Page 18: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/18.jpg)
NEW BC CONNECTOR
![Page 19: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/19.jpg)
CONCOURSE C WIDENING
CONTRACT VALUE: $ 28,799,512
Completion Date – January 2013
MBE: 31%
PROJECT OVERVIEW:
Renovate Concourse C to include larger passenger hold rooms and a wider corridor and exit.
New passenger boarding bridges. New baggage handling system. New public restrooms. Modify mechanical & electrical systems.
![Page 20: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/20.jpg)
DE CONNECTOR
CONTRACT VALUE: $ 75-100M
Proposed Design Schedule: September 2013- September 2014
Proposed Construction Schedule: January 2015- November 2016
![Page 21: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/21.jpg)
DE CONNECTOR
![Page 22: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/22.jpg)
DE CONNECTOR ARRIVAL LEVEL PLAN
![Page 23: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/23.jpg)
DE CONNECTOR DEPATURE LEVEL PLAN
![Page 24: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/24.jpg)
NEW DE SECURITY CHECKPOINT
![Page 25: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/25.jpg)
DE SECURITY CHECKPOINT VIEW FROM TERMINAL D
![Page 26: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/26.jpg)
DE SECURITY CHECKPOINT VIEW FROM TERMINAL E
![Page 27: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/27.jpg)
DE CONNECTOR
![Page 28: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/28.jpg)
DE CONNECTOR
VIDEO OF PROJECT OVERVIEW:
BWI CONFORM.wmv
![Page 29: PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING](https://reader036.vdocuments.net/reader036/viewer/2022081602/551a2b06550346cb358b4e27/html5/thumbnails/29.jpg)
*Program
**Advertised
***BidsDue
****Bid Opening
Contract Number & Title Proposed Date Project Value
MAA-CO-13-020Parking Access and Revenue Control System (PARCS)
***May 2013 $8M-$11M
MAA-CO-14-0012015 Airfield Capacity Enhancement Project
**April 2014 $80M
MAA-CO-14-005International Building Expansion
**December 2013 $7M
MAA-CO-14-007Comprehensive Interior/Exterior Modification 2014
**November 2013 $25M
MAA-CO-14-008Long Term Parking Lot B Pavement Rehabilitation
**November 2013 $1.7M
MAA-CO-14-009Pedestrian Walkway from CRCF to the East Tenant Lot *October 2013 $.5M
MAA-CO-14-010Public Parking Area Pavement Rehabilitation **November 2013 $1M
MAA-CO-14-011Central Terminal Third Floor Elevator Upgrades **November 2013 $.5M
MAA-CO-14-012Air Cargo Drive Pavement Rehabilitation *February 2014 $1.7M