PERENCANAAN LINE BALANCING DENGAN METODE RANK
POSITION WEIGHT (RPW) DAN METODE REGION APPROACH
(RA) GUNA MENINGKATKAN OUTPUT PRODUKSI
Fakultas Teknik Universitas Muhammadiyah Malang
Untuk Memenuhi Salah Satu Persyaratan
Akademik Dalam Menyelesaikan
UNIVERSITAS MUHAMMADIYAH MALANG
PERENCANAAN LINE BALANCING DENGAN METODE RANK
POSITION WEIGHT (RPW) DAN METODE REGION APPROACH
(RA) GUNA MENINGKATKAN OUTPUT PRODUKSI
SKRIPSI
Diajukan Kepada :
Fakultas Teknik Universitas Muhammadiyah Malang
Untuk Memenuhi Salah Satu Persyaratan
Akademik Dalam Menyelesaikan
Program Sarjana Teknik
Disusun Oleh :
ABDUL ARIJAL TAUFIQ
( 02540018 )
JURUSAN INDUSTRI
FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH MALANG
2008
PERENCANAAN LINE BALANCING DENGAN METODE RANK
POSITION WEIGHT (RPW) DAN METODE REGION APPROACH
(RA) GUNA MENINGKATKAN OUTPUT PRODUKSI
Fakultas Teknik Universitas Muhammadiyah Malang
UNIVERSITAS MUHAMMADIYAH MALANG
ABSTRAKSI
ABDUL ARIJAL TAUFIQ, 2008, NIM.02540018, PERENCANAAN LINE BALANCING
DENGAN METODE RANK POSITION WEIGHT ( RPW ) DAN METODE REGION
APPROACH ( RA ) GUNA MENINGKATKAN OUTPUT PRODUKSI DI KOPERASI
INTAKO TANGGULANGIN SIDOARJO, Skripsi Jurusan Teknik Industri Fakultas Teknik
Universitas Muhammadiyah Malang. Pembimbing I : Ir. H. M. LUKMAN, MT. Pembimbing
II : ANNISA KESSY, G. ST. MT.
Permasalahan line balancing dalam aliran produksi terkadang masih diabaikan oleh
perusahaan, meskipun pada kenyataannya masalah line balancing merupakan salah satu yang
memegang peranan penting dalam pemenuhan target produksi yang telah direncanakan.
Koperasi INTAKO pada divisi pabrik yang terletak di tanggulangin sidoarjo merupakan
koprasi yang menghasilkan beraneka ragam jenis tas perempuan. Permasalahan yang
dihadapi koperasi INTAKO adalah sering kali adanya penambahan jam kerja (lembur) hal ini
diakibatkan tidak dapat memenuhi permintaan pasar yang disebabkan karena rendahnya
jumlah produksi akibat kurang seimbangnya lintasan produksi.
Dalam upaya menyelesaikan masalah tersebut digunakan metode rank position weight
dan region approach yang merupakan metode heuristic dengan pendekatan trial and error
untuk membandingkan kondisi awal dengan kondisi setelah perencanaan metode line
balancing pada koperasi INTAKO. Yang meliputi balance delay, efisiensi lintasan, dan
output produksi.
Berdasarkan hasil analisa ternyata dari kedua metode didapatkan hasil perhitungan
balance delay awal 23% berkurang menjadi 21% dengan metode rank position weight. Dan
17% dengan metode region approach. Sedangkan efisiensi lintasan dari kondisi awal sebesar
77% meningkat menjadi 79% dengan metode rank position wight, dan 83% dengan metode
region approach. Output produksi tas perempuan meningkat dari kondisi awal 1848
unit/bulan menjadi 2662 unit/bulan dengan metode rank position weight, dan 2464 unit/bulan
dengan metode region approach. Karena pada kasus ini yang lebih ditekankan adalah output
produksinya maka perencanaan line balancing dengan metode rank positional weight dapat
digunakan dalam pemecahan masalah pada koperasi INTAKO Tanggulangin Sidoarjo.
Kata Kunci : Line Balancing, Efisiensi Lintasan, Balance Delay, Output Produksi, RPW, RA.
ABSTRACT
ABDUL ARIJAL TAUFIQ, 2008, NIM.02540018, PLANNING OF LINE of BALANCING
WITH METHOD of RANK POSITION WEIGHT (RPW) AND METHOD of REGION
APPROACH (RA) UTILIZE TO IMPROVE OUTPUT PRODUCE IN CO-OPERATION of
INTAKO TANGGULANGIN SIDOARJO, Industrial Skripsi Majors Technique [of] Faculty
Of Technique University of Muhammadiyah Unlucky. Counsellor Of I : Ir. H. M. LUKMAN,
MT. Counsellor Of II : ANNISA KESSY, G. ST. MT.
Problems of line of balancing in stream of productions sometimes still disregarded by
company, though practically the problem of line of balancing represent one other playing a
part important in accomplishment of goals produce which have been planned. Co-operation
of INTAKO at factory division which located in sidoarjo tanggulangin represent co-operation
yielding is multifarious of woman bag type manner. Problems faced by co-operation of
INTAKO is frequently the existence of addition of office hours this matter overtime is
resulted cannot fulfill request of caused by market to lower him is amount of production
effect of less as well-balanced as production trajectory.
In the effort finishing the problem used by method of rank weight position and of
region approach representing method of heuristic with approach of error and trial for
comparing is condition of early with condition of after planning of line method of balancing
at co-operation of INTAKO. covering delay balance, trajectory efficiency, and production
output.
Pursuant to result of analysis in the reality from both method got by result of
calculation of delay balance early 23% decreasing to become 21% with method of rank
weight position. And 17% with method of region approach. While trajectory efficiency from
condition of early equal to 77% mounting to become 79% with method of rank wight
position, and 83% with method of region approach. Output produce woman bag mount from
condition of early 1848 unit / month become 2662 unit / month with method of rank weight
position, and 2464 unit / month with method of region approach. Because [at] this case which
more emphasized its production output hence planning of line of balancing with method of
rank weight positional can be used in trouble-shooting at co-operation of INTAKO
Tanggulangin Sidoarjo.
Keyword : Line of Balancing, Efficiency Trajectory, Balance Delay, Output Production,
RPW, RA.
KATA PENGANTAR
Syukur Alhamdulillah penulis ucapkan kehadirat Allah SWT yang maha dari segala
maha sehingga laporan tugas akhir dengan judul “PERENCANAAN LINE BALANCING
DENGAN METODE RANK POSITION WEIGHT (RPW) DAN METODE REGION
APPROACH (RA) GUNA MENINGKATKAN OUTPUT PRODUKSI” ini dapat
terselesaikan lewat pada waktu yang telah penulis rencanakan.
Teriring do’a sholawat serta salam semoga senantiasa melimpah kehariban nabi besar
MUHAMMAD SAW rosul akhir zaman, penutup para nabi yang membawa kesempurnaan
ajaran tauhid dan keutamaan budi pekerti. Dan semoga ditumpahkan do’a sholawat menetes
segenap keluarga sahabat dan seluruh ummatnya yang dengan tulus mencintai dan
menjunjung sunnahnya.
Skripsi ini merupakan salah satu persyaratan untuk menyelesaikan pendidikan di
Fakultas Teknik Jurusan Industri Universitas Muhammadiyah Malang. Skripsi ini dapat
terselesaikan karena banyak pihak yang telah membantu baik doa, maupun dengan tenaga.
Oleh karena itu pada kesempatan ini penulis ingin mengucapkan banyak terima kasih kepada
:
1 Keluargaku (emmak, bapak, alek anis, dan alek vera). Terutama emmakku ”bapak
kedua” yang tidak akan pernah kering akan do’a – do’anya yang tulus yang slalu
mendukung lahir maupun batin. Dan keluarga besar H.SATIMAN.
2. Ibu Dyah Retno P, MT, selaku Ketua Jurusan Teknik Industri.
3. Ir.M.Lukman, MT selaku dosen pembimbing I, yang telah meluangkan waktunya
untuk memberikan bimbingan hingga terselesaikannya Skripsi ini.
4. Annisa Kesy, G. ST. MT selaku dosen pembimbing II terima kasih atas kesabaran,
arahan dan bimbingannya hingga terselesaikannya Skripsi ini.
5. TU jurusan, terima kasih atas bantuannya.
6. Seluruh staf dan karyawan Koperasi INTAKO Tanggulangin Sidoarjo, yang telah
membantu selama penelitian.
7. Yang kusayangi dan aku hargai ”hanunah”.
8. Seluruh teman jurusan industri yang sudah maupun yang tertunda.
Penulis hanya bisa memberi ungkapan terima kasih dan doa tulus yang dapat
dipersembahkan, semoga segala yang mereka berikan kepada saya tercatat diperjalanan hidup
saya dan tercatat dalam catatan sang Roqib sebagai sebuah ibadah yang tiada ternilai, amiiiin.
Ya Allah terima kasih atas segalanya, terutama nikmat hidup yang engkau berikan,
dan ampuni hambamu ini yang sering melupakanmu dalam keseharianku. Hamba mohon
padamu untuk engkau, bawa hambamu kemanapun engkau ridhoi agar hambamu kelak bisa
menemukan kedamaian hidup dan hati yang sebenarnya dalam pelukan cinta sesungguhnya
dariMu.
Akhirnya penulis berharap semoga Skripsi ini dapat bermanfaat. Terima kasih.
Billahittaufiq wal hidayah
Malang, 29 November 2008
Penulis
DAFTAR ISI
Halaman Judul HALAMAN
Berita Acara Ujian Tugas Akhir
Lembar Pengesahan
Lembar Asistensi
Abstaraksi
Kata Pengantar
Daftar Isi
Daftar Tabel
Lampiran
BAB I : PENDAHULUAN
1.1. Latar Belakang............................................................................................................1
1.2. Rumusan Masalah.......................................................................................................2
1.3. Tujuan Penelitian........................................................................................................2
1.4. Manfaat Penelitian......................................................................................................3
1.5. Batasan Masalah.........................................................................................................3
1.6. Asumsi-Asumsi...........................................................................................................4
1.7. Sistematika Penulisan.................................................................................................4
BAB II : LANTASAN TEORI
2.1. Line Balancing.............................................................................................................6
2.1.1 Faktor Faktor Yang Mempengarihi Line Balancing...............................................7
2.1.2 Tipe Tipe Line Balancing.......................................................................................8
2.1.3 Tujuan Line Balancing……………………………………………….………...…9
2.1.4 Metode Dalam Penyeimbangan Lintasan Perakitan………………….…………..9
2.1.5 Metode Rank Position Weight…..……………………………………………....10
2.1.6 Metode Region Approach.....................................................................................11
2.2. Peta Proses Operasi....................................................................................................12
2.3 Precedence Diagram..................................................................................................14
2.4. Menentukan Waktu Siklus.........................................................................................27
2.5 Menentukan Jumlah Stasiun Kerja………………….……………………………….16
2.6 Menghitung Balance Delay…………………..………………………………………17
2.7 Menghitung Efisiensi Lintasan…………….……………………………………...…18
2.8 Menentukan Output Produksi………………………..………………………………18
2.9 Pengukuran Waktu Kerja Dengan Jam Henti………………………………………..19
2.9.1 Uji Kecukupan Dan Keseragaman Data…………………………………...…….22
2.9.2 Performance Rating……………………..……………………………………….23
2.9.3 Menentukan Allowance Time……………………….…………………………...32
2.9.4 Waktu Normal………………………...………………………………………….37
2.9.5 Waktu Baku…………………..………………………………………………….38
BAB III : METODOLOGI PENELITIAN
3.1 Diagram Alir Penelitian............................................................................................39
3.2 Diskripsi Diagram Alir Penelitian............................................................................40
3.2.1. Survey Perusahaan...............................................................................................40
3.2.2. Identifikasi Masalah.............................................................................................40
3.2.3. Study Literatur.....................................................................................................41
3.2.4. Pengumpulan Data…………………………………………………………...…41
3.2.5. Tes Keseragaman Data…………………………………………………………42
3.2.6 Tes Kecukupan Data............................................................................................43
3.2.7. Menghitung Waktu Normal.................................................................................44
3.2.8. Menghitung Waktu Baku.....................................................................................44
3.2.9. Pembuatan Precedence Diagram..........................................................................45
3.2.10. Perencanaan Keseimbangan Lintasan.................................................................45
3.2.11. Analisa Hasil.......................................................................................................49
3.2.12 Kesimpulan Dan Saran.......................................................................................49
BAB IV : PENGUMPULAN DAN PENGOLAHAN DATA
4.1. Sejarah Umum Perusahaan.........................................................................................50
4.2. Produk Koperasi Intako..............................................................................................51
4.3. Outlet Intako...............................................................................................................52
4.4. Layout Produksi..........................................................................................................53
4.5. Pengumpulan Data......................................................................................................53
4.5.1. Cara Mendapatkan Data........................................................................................53
4.5.2. Bahan Baku Yang Digunakan...............................................................................54
4.5.3. Mesin Dan Alat Yang Digunakan.........................................................................54
4.5.4. Proses Pembuatan Tas Perempuan........................................................................56
4.5.5. Peta Proses Operasi...............................................................................................59
4.5.6. Waktu Operasi Tiap Proses...................................................................................62
4.5.7. Jam Kerja Efektif..................................................................................................65
4.6. Pengolahan Data.........................................................................................................65
4.6.1. Uji Keseragaman Data………………………………………………….……….65
4.6.2. Uji Kecukupan Data …………………………….………………………………70
4.6.3. Menghitung Waktu Baku Tiap Proses…………………………………………..73
4.6.4. Pengelompokan Elemen Kerja Kedalam Stasiun Kerja Awal……………..........85
4.6.5. Perhitungan Tenaga Kerja Dan Output Sebelum Perencanaan……………...…..87
4.7. Perencanaan Keseimbangan Lintasan Dengan Metode RPW……………………...92
4.7.1. Precedence Diagram.............................................................................................93
4.7.2. Penentuan Bobot Posisi Masing-masing Operasi.................................................95
4.7.3. Penyusunan Ranking Bobot Posisi.......................................................................96
4.7.4. Penentuan Rank Waktu Siklus..............................................................................98
4.7.5.Pengelompokan Operasi Kedalam Stasiun Kerja..................................................99
4.7.5.1. Perencanaan I Dengan Waktu Siklus 226.42 detik.........................................99
4.7.5.2. Perencanaan II Dengan Waktu Siklus 244.81 detik......................................103
4.7.5.3. Perencanaan III Dengan Waktu Siklus 263.21 detik....................................106
4.7.5.4. Perencanaan IV Dengan Waktu Siklus 281.60 detik....................................109
4.8. Perencanaan Keseimbangan Lintasan Dengan Metode RA.....................................112
4.8.1. Precedence Diagram ..........................................................................................112
4.8.2 Pembagian Operasi Kedalam Beberapa Region.................................................112
4.8.3 Pengelompokan Operasi Kedalam Stasiun Kerja...............................................114
4.8.3.1. Perencanaan I Dengan Waktu Siklus 226.42 detik.......................................114
4.8.3.2. Perencanaan II Dengan Waktu Siklus 244.81 detik......................................118
4.8.3.3. Perencanaan III Dengan Waktu Siklus 263.21 detik....................................121
4.8.3.4. Perencanaan IV Dengan Waktu Siklus 281.60 detik....................................124
4.9. Analisa Perencanaan Line Balancing Dengan Metode RPW Dan RA....................127
4.10. Perhitungan Biaya Tenaga Kerja Sesudah Perencanaan.........................................128
4.10.1. Perhitungan Biaya Tenaga Kerja Dengan Metode RPW..................................128
4.10.2. Perhitungan Biaya Tenaga Kerja Dengan Metode RA.....................................131
4.12. Pemilihan Perencanaan Line Balancing Terbaik Berdasarkan Output Maksimal
Dengan Metode RPW dan RA.............................................................................133
BAB V : ANALISA PEMBAHASAN
5.1. Perbandingan Output Produksi Dan Biaya Tenaga Kerja, Sebelum Dan Sesudah
Perencanaan............................................................................................................139
5.1.1. Sebelum Perencanaan.........................................................................................139
5.1.2. Sesudah Perencanaan Keseimbangan Lintasan Dengan Menggunakan Metode RPW
dan RA........................................................................................................141
5.2. Perbandingan Perubahan Elemen Kerja Antara Stasiun Kerja Awal Dengan Stasiun
Kerja Usulan............................................................................................................143
BAB VI : KESIMPULAN
6.1. Kesimpulan..............................................................................................................149
6.2. Saran........................................................................................................................151
DAFTAR TABEL
Tabel 2.1 Westing House Performance Rating................................................................24
Tabel 2.2 Beasarnya Kelonggaran Faktortenaga yang dikeluarkan……………........ 33
Tabel 2.3 Besarnya Kelonggaran Berdasarkan Faktor Sikap Kerja................................33
Tabel 2.4 Besarnya Kelonggaran Berdasarkan Faktor Gerakan Kerja............................34
Tabel 2.5 Besarnya Kelonggaran Berdasarkan Faktor Kelelahan Mata..........................34
Tabel 2.6 Besarnya Kelonggaran Berdasarkan Faktor Keadaan Tempratur ….....……..35
Tabel 2.7 Besarnya Kelonggaran Berdasarkan Faktor Kadaan Atmosfer …………..…36
Tabel 2.8 Besarnya Kelonggaran Berdasarkan Faktor Kadaan Lingkungan...................36
Tabel 3.1 Tes Keseragaman Data....................................................................................42
Tabel 3.2 Tes Kecukupan Data........................................................................................43
Tabel 3.3 Perhitungan Waktu Normal.............................................................................44
Tabel 3.4 Perhitungan Waktu Baku.................................................................................44
Tabel 3.5 Pengelompokan Elemen Kerja Kedalam Stasiun Kerja..................................47
Tabel 4.1 Proses Pembuatan Tas Perempuan..................................................................56
Tabel 4.2 Data Waktu Pengamatan Pembuatan Tas Perempuan.....................................63
Tabel 4.3 Data Pengamatan Untuk Proses Operasi 1 (0-01)...........................................66
Tabel 4.4 Uji Keseragaman Data.....................................................................................68
Tabel 4.5 Uji Kecukupan Data........................................................................................72
Tabel 4.6 Waktu Siklus Tiap Operasi .............................................................................74
Tabel 4.7 Westinghause Performance Rating..................................................................75
Tabel 4.8 Performance Rating Operasi 1(0-01)………………………………………...76
Tabel 4.9 Penentuan Performace Rating..........................................................................77
Tabel 4.10 Waktu Normal Tiap Proses..............................................................................79
Tabel 4.11 Allowance Time Tiap Operasi.........................................................................81
Tabel 4.12 Waktu Normal Tiap Proses..............................................................................83
Tabel 4.13 Stasiun Kerja Awal………………………………………………………….85
Tabel 4.14 Data Permintaan………..……………... …………………………….....…..88
Tabel 4.15 Keterangan Stasiun Kerja Kondisi Awal..............……………………...…...91
Tabel 4.16 Penentuan Bobot Posisi Pada Tiap Opersi.....................................................95
Tabel 4.17 Penyusunan Ranking Bobot Opersi ...............................................................97
Tabel 4.18 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 226.42 detik...............99
Tabel 4.19 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 244.81 detik.............103
Tabel 4.20 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 263.21 detik.............106
Tabel 4.21 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 281.60 detik.............109
Tabel 4.22 Pembagian Operasi Kedalam Beberapa Region...........................................113
Tabel 4.23 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 226.42 detik.............115
Tabel 4.24 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 244.81 detik ............118
Tabel 4.25 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 263.21 detik.............121
Tabel 4.26 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 281.60 detik.............124
Tabel 4.27 Hasil Perencanaan Line Balancing Dengan Metode RPW dan RA..............127
Tabel 4.28 Perbandingan Hasil Line Balancing Dengan Metode RPW dan RA............134
Tabel 4.29 Keterangan Pengelompokan Elemen Kerja Waktu Siklus 207.46 Detik......136
Tabel 5.1 Data Historis Permintaan Tas Perempuan Perbulan......................................119
Tabel 5.2 Perbandingan Metode RPW dan RA.............................................................141
Tabel 5.3 Perbandingan Kriteria Sebelum Dan Sesudah Perencanaan .........................143
Tabel 5.4 Perbandingan Elemen Kerja Sebelum Dan Sesudah Perencanaan ...............144
Tabel 6.1 Perbandingan Sebelum dan Sesudah Perencanaan .....................................149
Tabel 6.2 Pengelompokan Elemen Kerja Dengan Metode RPW Dan RA Dengan Waktu
Siklus 207.46 Detik..........................................................................................................150
DAFTAR GAMBAR
Gambar 2.1 Sketsa Pembuatan Peta Proses Operasi ........................................................14
Gambar 2.2 Precedence Diagram ....................................................................................15
Gambar 2.3 Langkah Langkah Sistematis Dalam Kegiatan Pengukuran Kerja Dengan Jam
Henti...........................................................................................................................21
Gambar 2.4 Precedence Diagram.....................................................................................34
Gambar 3.1 Diagram Alir Penelitian................................................................................39
Gambar 3.2 Precedence Diagram.....................................................................................45
Gambar 4.1 Layout Lantai Produksi.................................................................................53
Gambar 4.2 Peta Proses Operasi.......................................................................................61
Gambar 4.3 Pengelompokan Stasiun Kerja Kondisi Awal...............................................90
Gambar 4.4 Precedence Diagram Pembuatan Tas Perempuan.........................................94
Gambar 4.5 Pengelompokan Stasiun Kerja Menggunakan metode RPW Dengan Waktu
Siklus 207.46 detik.....................................................................................135
Gambar 5.1 Pembagian Stasiun Kerja Sebelum Perencanaan........................................147
Gambar 5.2 Pembagian Stasiun Kerja Setelah Perencanaan..........................................148
DAFTAR PUSTAKA
Baroto, Teguh, 2002, Pengantar Teknik Industri, Cetakan Pertama, UMM Press, Malang.
Sutalaksana, Iftikar Z. dkk, 1979, Teknik Tata Cara Kerja, Departemen Teknik Industri,
ITB, Bandung.
Purnomo, Hari Pengantar Teknik Industri, Graha Ilmu, Yogyakarta.
Wignjosoebroto, Sritomo, 2003, Ergonomi Studi Gerak dan Waktu, Edisi Pertama,
Cetakan Ketiga, PT. Guna Widya, Jakarta.
Wignjosoebroto, Sritomo, 1992, Teknik Tata Cara dan pengukuran Kerja, Edisi Kedua,
PT. Guna Widya, Jakarta.