Transcript
Page 1: Power Plant Gannt Chart

ID Task Name Duration Start Finish PredecessorsNotes

1 8 MW Dendro Power Project Development 376 days Oct 16 Oct 25

2 Project Progress Report Submission 1 day Oct 16 Oct 16

3 Approval Phase 31 days Oct 17 Nov 16

4 Approvals from SLSEA 13 days Oct 17 Oct 29 2

5 PPA Extension From CEB 13 days Oct 30 Nov 11 4

6 Generation Licence Extension from PUCSL 5 days Nov 12 Nov 16 5

7 Project Financing 60 days Oct 17 Dec 15

8 Bankable Feasibility report 30 days Oct 17 Nov 15 2

9 Loan Appraisal 15 days Nov 16 Nov 30 8

10 Loan Approval 15 days Dec 1 Dec 15 9

11 Procurement 60 days Dec 16 Feb 13 7

12 Finalysing detailed design and suppliers 14 days Dec 16 Dec 29 7

13 Plant Machineries 45 days Dec 30 Feb 12 12

14 Building Materfials 45 days Dec 30 Feb 12 12

15 Fuel Supply Contracts 60 days Dec 16 Feb 13 7

16 Civil Construction 120 days Dec 16 Apr 13

17 Land preparation 60 days Dec 16 Feb 13 10

18 Access roads 30 days Feb 14 Mar 14 17

19 Plant house 30 days Mar 15 Apr 13 18

20 Fuel wood storage 30 days Dec 16 Jan 14 10

21 Machine Installation 90 days Apr 14 Jul 12

22 Boiler and accessories 14 days Apr 14 Apr 27 16

23 Turbine and Alternator 30 days Apr 14 May 13 16

24 Other accessories 60 days May 14 Jul 12 23

25 Electrical Evacuation 135 days Apr 14 Aug 26

26 Inplant electrical works 60 days Apr 14 Jun 12 16

27 Power line to SGS 75 days Jun 13 Aug 26 26

28 Commissioning 60 days Aug 27 Oct 25

29 Civil Structure 30 days Aug 27 Sep 25 25

30 Machine Commissioning 30 days Aug 27 Sep 25 25

31 Eelctrical Commissioning 30 days Aug 27 Sep 25 25

32 Grid Connection 30 days Sep 26 Oct 25 31

10/16

10/25

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 1

Project: MSProj11Date: Oct 14

Top Related