ID Task Name Duration Start Finish PredecessorsNotes
1 8 MW Dendro Power Project Development 376 days Oct 16 Oct 25
2 Project Progress Report Submission 1 day Oct 16 Oct 16
3 Approval Phase 31 days Oct 17 Nov 16
4 Approvals from SLSEA 13 days Oct 17 Oct 29 2
5 PPA Extension From CEB 13 days Oct 30 Nov 11 4
6 Generation Licence Extension from PUCSL 5 days Nov 12 Nov 16 5
7 Project Financing 60 days Oct 17 Dec 15
8 Bankable Feasibility report 30 days Oct 17 Nov 15 2
9 Loan Appraisal 15 days Nov 16 Nov 30 8
10 Loan Approval 15 days Dec 1 Dec 15 9
11 Procurement 60 days Dec 16 Feb 13 7
12 Finalysing detailed design and suppliers 14 days Dec 16 Dec 29 7
13 Plant Machineries 45 days Dec 30 Feb 12 12
14 Building Materfials 45 days Dec 30 Feb 12 12
15 Fuel Supply Contracts 60 days Dec 16 Feb 13 7
16 Civil Construction 120 days Dec 16 Apr 13
17 Land preparation 60 days Dec 16 Feb 13 10
18 Access roads 30 days Feb 14 Mar 14 17
19 Plant house 30 days Mar 15 Apr 13 18
20 Fuel wood storage 30 days Dec 16 Jan 14 10
21 Machine Installation 90 days Apr 14 Jul 12
22 Boiler and accessories 14 days Apr 14 Apr 27 16
23 Turbine and Alternator 30 days Apr 14 May 13 16
24 Other accessories 60 days May 14 Jul 12 23
25 Electrical Evacuation 135 days Apr 14 Aug 26
26 Inplant electrical works 60 days Apr 14 Jun 12 16
27 Power line to SGS 75 days Jun 13 Aug 26 26
28 Commissioning 60 days Aug 27 Oct 25
29 Civil Structure 30 days Aug 27 Sep 25 25
30 Machine Commissioning 30 days Aug 27 Sep 25 25
31 Eelctrical Commissioning 30 days Aug 27 Sep 25 25
32 Grid Connection 30 days Sep 26 Oct 25 31
10/16
10/25
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: MSProj11Date: Oct 14