It will test your

knowledge as a Process Engineer

acquisition of the contents of Chapter 3 Process of The Guide1

1 ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015

Process Engineer knowledge test

Page 2: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which revision of the P&IDs includes Company comments?

• IFR

• IFD

• IFC

Project Engineer knowledge test

Page 3: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which revision of the P&IDs includes Company comments?

• IFR

• IFD

• IFC

Project Engineer knowledge test

”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015

Page 4: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which of the following equipment does the Process Engineer specify and which ones does the Process Engineer design?

- Heat exchangers

- Rotating equipment

- Packages

- Columns

- Boilers

- Fired Equipment

- Reactors

Project Engineer knowledge test

Page 5: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which of the following equipment does the Process Engineer specify and which ones does the Process Engineer design?

- Heat exchangers - specify

- Rotating equipment - specify

- Packages - specify

- Columns - design

- Boilers - specify

- Fired Equipment - specify

- Reactors - design

Page 6: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

What do Process Flow Diagrams (PFD) show?

- Process Lines

- Utility lines

- Line diameters

- Instruments

- Main process lines

- Controllers

- Control valves

- Emergency ShutDown valves

Project Engineer knowledge test

Page 7: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

What do Process Flow Diagrams (PFD) show?

- Process Lines

- Utility lines

- Line diameters

- Instruments

- Main process lines

- Controllers

- Control valves

- Emergency ShutDown valves

Project Engineer knowledge test

Page 8: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Process simulation softwares calculates:

• The surface area of heat exchangers

• The power consumption of pumps

• The equipment duty

Project Engineer knowledge test

Page 9: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Process simulation software calculates:

• The surface area of heat exchangers

• The power consumption of pumps

• The equipment duty

Project Engineer knowledge test

”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015

Page 10: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which revision of the P&IDs includes HAZOP actions?

• IFR

• IFD

• IFC

Project Engineer knowledge test

Page 11: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which revision of the P&IDs includes HAZOP actions?

• IFR

• IFD

• IFC

Project Engineer knowledge test

Page 12: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which of the following is defined by Process, hence indicated on the Process data sheet, for a heat exchanger

• Equipment design conditions

• Inlet/outlet fluid conditions and properties

• Heat exchange area

• Size

• Duty

• Weight

• Dimensions

• Material of construction

• Corrosion allowance

• Fouling factor

• Allowable pressure drop

• Equipment overdesign

Project Engineer knowledge test

Page 13: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which of the following is defined by Process, hence indicated on the Process data sheet, for a heat exchanger

• Equipment design conditions

• Inlet/outlet fluid conditions and properties

• Heat exchange area

• Size

• Duty

• Weight

• Dimensions

• Material of construction

• Corrosion allowance

• Fouling factor

• Allowable pressure drop

• Equipment overdesign

Project Engineer knowledge test

Page 14: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which Process document(s) is(are) used to estimate the CAPEX of the facility?

• Process Flow Diagrams (PFDs)

• Process Equipment data sheets

• Process Equipment list

• Piping & Instrumentation Diagrams (P&IDs)

Project Engineer knowledge test

Page 15: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which Process document is used to estimate the CAPEX of the facility?

• Process Flow Diagrams (PFDs)

• Equipment data sheets

• Process Equipment list

• P&IDs

Project Engineer knowledge test

Page 16: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which Process document(s) is (are) needed to develop the Plant Equipment Layout (Plot Plan)

• Process Flow Diagrams (PFDs)

• Process Equipment data sheets

• Process Equipment list

• Piping & Instrumentation Diagrams (P&IDs)

Project Engineer knowledge test

Page 17: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which Process document(s) is (are) needed to develop the Plant Equipment Layout (Plot Plan)

• Process Flow Diagrams (PFDs)

• Process Equipment data sheets

• Process Equipment list

• Piping & Instrumentation Diagrams (P&IDs)

Project Engineer knowledge test

Page 18: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

For which arrangements are typical P&IDs prepared?

• Filters

• Drains

• Control valves

• Sample connection

• Equipment isolation

• Battery limits

• PSVs

• Flare

Project Engineer knowledge test

Page 19: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

For which arrangements are typical P&IDs prepared?

• Filters

• Drains

• Control valves

• Sample connection

• Equipment isolation

• Battery limits

• PSVs

• Flare

Project Engineer knowledge test

”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015

Page 20: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Level Transmitter and shutdown valve shown here in red are part of which instrumented system?

- Process Control System (DCS)

- Emergency Shutdown System (ESD)

- Process Shutdown System (PSS)

Page 21: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Level Transmitter and shutdown valve shown here in red are part of which instrumented system?

- Process Control System (DCS)

- Emergency Shutdown System (ESD)

- Process Shutdown System (PSS)

Page 22: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which revision of the P&IDs indicates the size of control valves and PSVs?

• IFR

• IFD

• IFC

Project Engineer knowledge test

Page 23: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Which revision of the P&IDs indicates the size of control valves and PSVs?

• IFR

• IFD

• IFC

Project Engineer knowledge test

Page 24: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which of the following does Process define for lines?

• Design conditions

• Material of construction

• Generic material of construction

• Corrosion allowance

• Diameter

• Wall thickness

• Rating

• Insulation

• Routing

• Piping class

• Non Destructive Examination

• Test pressure

• One phase / 2 phase flow

Page 25: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which of the following does Process define for lines?

• Design conditions

• Material of construction

• Generic material of construction

• Corrosion allowance

• Diameter

• Wall thickness

• Rating

• Insulation

• Routing

• Piping class

• Non Destructive Examination

• Test pressure

• One phase / 2 phase flow

Page 26: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The isometric drawing of which of the following lines are checked by Process?

• 2 phase flow

• Inlet lines to control valves

• Lines with flow instrument

• Pump suction lines

• Impulse lines to PSVs

Page 27: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The isometric drawing of which of the following lines are checked by Process?

• 2 phase flow

• Inlet lines to control valves

• Lines with flow instrument

• Pump suction lines

• Impulse lines to PSVs

Page 28: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The isometric drawing of which of the following lines are checked by Process?

• 2 phase flow

• Inlet lines to control valves

• Lines with flow instrument

• Pump suction lines

• Impulse lines to PSVs

What kind of check is done by Process for these lines?

• Routing

• Hydraulics

• No pocket

Page 29: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The isometric drawing of which of the following lines are checked by Process?

• 2 phase flow

• Inlet lines to control valves

• Lines with flow instrument

• Pump suction lines

• Impulse lines to PSVs

What kind of check is done by Process for these lines?

• Routing

• Hydraulics

• No pocket

Page 30: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Process Emergency isolation and Shutdown system is designed by

• Process discipline

• Safety discipline

• Process & Safety disciplines together

Page 31: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Process Emergency isolation and Shutdown system is designed by

• Process discipline

• Safety discipline

• Process & Safety disciplines together

Page 32: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

What does the P&ID review consist of (select all correct answers)?

• checking that the needed alarms and trips are provided

• checking that the required equipment and control valves isolations and bypasses are provided

• checking that the drains, vents are provided

• checking versus similar equipment/unit P&ID

• checking the adequacy of the equipment design pressure and temperature

• checking the allocation of piping class and insulation type

Page 33: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

What does the P&ID review consist of (select all correct answers)?

• checking that the needed alarms and trips are provided – done in HAZOP

• checking that the required equipment and control valves isolations and bypasses are provided

• checking that the drains, vents are provided

• checking versus similar equipment/unit P&ID

• checking the adequacy of the equipment design pressure and temperature

• checking the allocation of piping class and insulation type

Page 34: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Heat & Mass balance shows the flowrate, conditions and composition of:

• process and utility streams

• process streams

Page 35: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Heat & Mass balance shows the flowrate, conditions and composition of:

• process and utility streams

• process streams

Page 36: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which of the following is necessary to produce the Utility consumption list?

• Heat & Material balance

• Equipment duty

• Equipment sizing

• Utility Flow Diagrams

• Operating manual

Page 37: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which of the following is necessary to produce the Utility consumption list?

• Heat & Material balance

• Equipment duty. The utilities consumption is based on the equipment duty, e.g., cooling fluid flow = mCpΔT for heat exchanger. Equipment sizing is not required.

• Equipment sizing

• Utility Flow Diagrams

• Operating manual

Page 38: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Process data sheet of a control valve specifies

• The valve type (globe, butterfly, etc.)

• The min/max flow and pressure conditions

• The valve diameter

• The valve Cv

• Requirement for hand wheel

• Type of positioner

• Fail position

Page 39: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

The Process data sheet of a control valve specifies

• The valve type (globe, butterfly, etc.)

• The min/max flow and pressure conditions

• The valve diameter

• The valve Cv

• Requirement for hand wheel

• Type of positioner

• Fail position

Page 40: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which Process documents are used for programming the Process Control System?

• PFDs

• P&IDs

• Process description

• Operating manual

• Operating & Control philosophy

Page 41: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

Which Process documents are used for programming the Process Control System?

• PFDs

• P&IDs

• Process description

• Operating manual

• Operating & Control philosophy

Page 42: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Project Engineer knowledge test

That’s all for now folks, but I won’t be long with tests on knowledge acquisition for the next chapters of the guide…

Page 43: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Page 44: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide - 2nd edition

Discipline presentation: activities and deliverables

Table of Contents

The overall process

Methods & tools

Page 45: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Discipline presentation: activities and deliverables

Page 46: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The work of each Engineering discipline is described

Page 47: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Design activities are explained, e.g., Plant

Equipment layout

Page 48: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Complex activities, such as QRA, are explained through a

practical example.

Page 49: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

How are materials of construction selected ?

Page 50: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

How and when are Piping Materials ordered?

Page 51: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

A sample of all common Engineering documents is

included

Page 52: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

A sample of all common Engineering documents is

included

Use this to specify what you want to your Engineering

supplier !

Page 53: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Verify the contents of engineering documents

with check lists.

Page 54: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Difference between Engineering and Shop

drawings

Page 55: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Understand the main technical aspects, e.g., DCS

vs ESD

Page 56: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The common 2 types of package control

Page 57: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The different Plant drainage systems

Page 58: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The dynamic forces to which an Off-Shore

Plant is subject

Page 59: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

The overall process

Page 60: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Use this as standard, question deviations.

Page 61: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Understand the new 3D-model centered engineering process

Page 62: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Know the interfaces between disciplines...

and with Vendors

Page 63: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Understand what drives the Project schedule

Page 64: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Methods & tools

Page 65: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Use these methods as standard, question

deviations.

Page 66: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Implement powerful procedures

Page 67: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Request meaningful progress reports

Page 68: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

Implement effective Project Control

Page 69: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide - 2nd edition

This book is destined to both:

Oil & Gas companies Project execution personnel

Oil & Gas contractors Project execution personnel

Date of publication: March, 2015.

Page 70: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide

2nd edition

If your are on the Client side, i.e., contracting Engineering services, this book will help you to:

Specify to an Engineering supplier what you want: what deliverables and with what contents,

Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.

Specify the progress report you want, with the meaningful indicators,

Ask the right questions to assess the true progress,

Page 71: Process engineering test

HERVE

BARON

© 2

01

5 – H

ervé Baro

n

The Oil & Gas Engineering Guide

2nd edition

If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:

Understand the work of each discipline and the overall picture,

Challenge what one discipline tells you,

Understand the critical areas,

Put in place the right methods to be successful,


Top Related