FOURTH AFRICA CENTERS OF EXCELLENCE (ACE) PROJECT WORKSHOP
FIDUCIARY COMPLIANCE – PROCUREMENT November 17-19, 2015
Cotonou Presented by : Wole Afuye & Mathias Gogohounga.
![Page 2: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/2.jpg)
Overriding Objectives of Procurement
The overriding objective is to deliver procurement activities with due considerations to efficiency and value for money in the use of public funds, while adhering to agreed World Bank procedures and national procurement regulations.Other Objectives are : Effectiveness Transparency Accountability
![Page 3: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/3.jpg)
Procurement Progress/update:
• To discuss on the procurement progress made so far in relation to the agreed procurement plans.
• To discuss the challenges in procurement since implementation commenced.
• To emphasize that procurement procedures are based on the Institution’s procurement manuals which are subject to the national procurement systems. (Govt. thresholds, policies and regulations).
![Page 4: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/4.jpg)
Responsibilities:
• ACE:• The responsibility for implementation of the project,
award and administration of contracts, rests with the ACEs.
• World Bank:• The Bank, for its part, is required by its Articles of
Agreement to “ensure that the proceeds of any loan are used only for the purposes for which the loan was granted, with due attention to considerations of economy and efficiency and without regard to political or other noneconomic influences or considerations.”
![Page 5: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/5.jpg)
Main Considerations Guiding the World Bank’s Procurement Policies on Goods
and Works.
(a) economy and efficiency in the implementation of the project;(b) giving all eligible bidders from developed and developing countries the same information and equal opportunity to compete;(c) encouraging the development of domestic contracting and manufacturing industries in the borrowing country; and(d) transparency in the procurement process.
![Page 6: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/6.jpg)
Main Considerations Guiding the World Bank’s Procurement Policies on
Consultancy Services.
• (a) high-quality services,• (b) economy and efficiency,• (c) give all eligible consultants an opportunity
to compete in providing the services financed by the Bank,
• (d) encouraging the development and use of national consultants in its developing member countries, and
• (e) transparency in the selection process.
![Page 7: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/7.jpg)
Reminder : Component 1 - DLI approach
• That all expenditures be reimbursed under
the project will be part of the Eligible Expenditure Program . This would be verified during procurement audits and Bank’s Post Procurement Reviews (PPRs).
• All expenditures for procurable items in the EEP will follow the World Bank “Guidelines for Procurement of Goods, Works and Non-Consulting Services", dated January 2011 and "Guidelines: Selection and Employment of Consultants", dated January 2011.
![Page 8: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/8.jpg)
Component 2
• Regional Facilitation Unit at AAU, the National Universities Commission, Nigeria and the implementation team in The Gambia.
• Make use of World Bank “Guidelines: Procurement of Goods, Works and Non-Consulting Services", dated January 2011 or the World Bank.
• "Guidelines: Selection and Employment of Consultants", dated January 2011, with procurement plans acceptable to IDA.
![Page 9: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/9.jpg)
Component 2.
The RFU at AAU and National Universities Commission, Nigeria’s Eligible Procurement Activities :
• Goods : Computer equipment and related office equipment.
• Consultancy Services : Simple consultancy contracts
• Works : Not Applicable
The Gambia:
• will procure consultant services only from the other participating ACEs.
• Procure goods when justified.
• Works contracts : only when cleared by the Bank.
![Page 10: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/10.jpg)
Goods & Works
DLI 2: Excellence in education and research capacity and Development impact.DLR 2.8: Meeting milestones for improved learning and research environment specified in the Performance and Funding contracts.
Procurement Activities :
Development of Web Portal
Renovation & Construction of Office Blocks
Procurement of Vehicles.
Procurement of Laboratory Equipment.
![Page 11: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/11.jpg)
Consultancy Services
DLI#4. Timely and audited Procurement.Procurement Activity: • DLR# 4.1 Timely procurement audit• Procurement Auditing report to be submitted to World
Bank latest by June 30 – USD 50,000 per year • DLR#4.2: Timely and Satisfactory Procurement
Progress. – USD50,000 per year.• Hiring of relevant Technical Assistance. • Consultants for Preparation of manuals. • Consultants for specialized reports etc.
![Page 12: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/12.jpg)
Two Procurement DLI Performance criteria :
• (a) Third-party procurement process verification (audit). Deadline before June 30, 2016.
• (b) Timeliness of procurement progress: • 25% of all procurement contracts signed by
year 1 (Amount);• 55% of all procurement contracts by year 2
(amount), and • 100% by year 3 (amount), • Verification of installation by year 4).
![Page 13: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/13.jpg)
Result Based Procurement Planning
• Effective Planning requires:• By December 2015, all centers should be
revising the current procurement plans in preparation for Year 16, Annual work plan and procurement plans.• Goods , Works, consulting services and
Non-Consulting services, Operating Cost, workshop and training.
• Annual Disbursement Plan/Cashflow plan
![Page 14: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/14.jpg)
The Annual Procurement Plan
Work Plan and procurement plan should be linked to the annual budget.
Activities not completed during the year should be rolled to the new year procurement plans Workplans.
All revised Procurement plans would be submitted to the World Bank for review and No Objection.
![Page 15: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/15.jpg)
The Annual Procurement Plan
Procurement plans reflect a schedule of activities in order of need/priority.
Workplan and Procurement plan reflect all transactions to be implemented by the Center.
Both the Workplan and procurement plan can be revised during the year. All revisions should be cleared with the WB.
![Page 16: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/16.jpg)
Procurement Methods (Goods & Works)
• ICB - International Competitive Bidding (Large works and Equipment)
• NCB – National Competitive Bidding (National Procurement Document).
• IS – International Shopping• SH – Shopping• DC – Direct Contracting
![Page 17: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/17.jpg)
Consultancy Services Methods
• QCBS – Quality and Cost Based Selection (Firms).
• CQ- Consultants Qualification (Firms)• IC – Individual Consultants• SS – Sole Source (Firms/Individuals)
![Page 18: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/18.jpg)
Checklists - NCB
• Bidding Process: • Technical Specifications drawn by technical experts -
No brand names.• Bidding Documents prepared and issued with Invitation
for Bids (IFB). First package can be shared with WB for necessary guidance.
• IFB publicly launched in at least one national newspaper.
• Bids are publicly opened and announced. (copy of Bids, minutes of bids opening and attendance records are well kept)
![Page 19: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/19.jpg)
Checklist - NCB
Bid Evaluation Process:• Bid Evaluation Committee.• Bid Evaluation Report should consist of :
• Preliminary Examination: checking the completeness of the bid e.g Bid Securities.)
• Technical Evaluation – Checking compliance with required specifications.
• Post Qualification of Bidders.• Technical Capacity of Bidders (Specified relevant
general and similar experience• Financial Capacity: Average annual turnover.
![Page 20: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/20.jpg)
Works Evaluation
• Emphasis is giving to the following:• Cash flow requirement • Access to credit facilities. • Required Equipment• Required technical personnel
![Page 21: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/21.jpg)
Contract Award Checklist: NCB
• Recommendation & Award:• Notification of awards.• Acceptance Letter of Offer.• Performance Security (PG)• Advance payment Guarantee (APG)• Contract Agreement with clear conditions.
![Page 22: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/22.jpg)
Implementation Checklist:
• Copies of Delivery/Waybill• Copies of Payment Invoices• Payment approvals.• Payment Vouchers• Copies of Receipts for payments
![Page 23: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/23.jpg)
Contract Management /Records.
Contract Amendments (if any) Goods Inspection Certificate Acceptance Certificate Delivery Papers /Waybills /Stores Receipt Payment Certificates Copies of Performance Guarantee and Bid
Securities Claims and disputes (liquidated damages if any)
![Page 24: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/24.jpg)
National Shopping : Goods and Works / Checklist
Solicitation letters with technical specification sent to minimum of three bidders
Quotations received from Contractors/Suppliers Quotations are opened same day. Evaluation Committee evaluates the quotations. Recommended bidder signed contract or Purchase
Order Record of Inspection /Delivery of goods, Receipt,
waybills. Store Receipt Completion Certificates are issued.
![Page 25: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/25.jpg)
Individual Consultants – Checklist/filing.
• Terms of Reference• Request for Expression of Interest/ Invitation
of CVs.• Committee evaluate CVs.• Interview and Contract Negotiations.• Contract Agreement.• Reports/ Deliverables.• Payment Documents.
![Page 26: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/26.jpg)
World Bank Procurement Supervision Roles.
(a) Continuous Project Implementation Supervision Missions. (b) Post Procurement Reviews (PPR).(c ) Continuous Procurement Trainings.(d) Hands Holding procurement supports.
![Page 27: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/27.jpg)
Procurement Filling/Documentation.
• All procurement documents should be filed accordingly for : • Procurement Audit • World Bank’s Post Procurement
Reviews• External Financial Audit.• References.
![Page 28: Procurement presentation Ace workshop - Cotonou](https://reader036.vdocuments.net/reader036/viewer/2022081605/58ec81801a28abcc188b472b/html5/thumbnails/28.jpg)
THANK YOU.
Comments & Clarifications