Project requirements Utility scale PV plant for electricity supply of 12.000 households

Plant implementation in a hilly and complex 66ha landscape

Attractive IRR

Installation time within 10 month

Reliable long term performance

Siemens answer Turnkey EPC solution for an installed capacity of 31 MWp

BOP optimized plant design

Reliable and best in class in-house products (e.g. SINVERT inverter, MV switchgear, GEAFOL transformer)

Qualified 112.000 Suntech photovoltaic modules

Sustainable operation and maintenance agreement over 18 years

Strong performance ratio contracting

Customer: EDD Delta Solar

Country: FranceProject: Les MéesDate: 2010 / 11Size: 31 MWp

Page 2: Project Le Mées - utility scale EPC solution
Page 3: Project Le Mées - utility scale EPC solution
Page 4: Project Le Mées - utility scale EPC solution
Page 5: Project Le Mées - utility scale EPC solution
Page 6: Project Le Mées - utility scale EPC solution
Page 7: Project Le Mées - utility scale EPC solution

Top Related